cost effectiveness of dsm programmes case studies of...
TRANSCRIPT
Cost Effectiveness of DSM Programmes – Case Studies of
EESL
Presentation to 5th Meeting of Utility CEO Forum on DSM
Date: 11th April, 2014
Venue: Delhi
Energy Efficiency Services Limited 1
Cost Effectiveness Assessment of DSM programme -The Regulatory framework
• Model DSM Regulations provide for cost effectiveness assessment of DSM programme. A DSM programme may be categorized as under:-
Type of programme
Distribution of DSM programme Cost Regulatory Approval criteria
Type-1
Distribution Licensee -All the Cost of DSM programme borne by licensee
Cost Effectiveness Index (B/C) > 1
Type-2
Distribution Licensee -The Costs of DSM programme borne by licensee
Consumer-Partial Costs are shared with Consumers
Cost Effectiveness Index (B/C) >1 Cost of Conserved Energy < Avg Tariff
Type-3
Distribution Licensee -The Costs of DSM programme borne by licensee
Consumer- Partial Costs are shared with Consumers
Government -Subsidy Scheme
Cost Effectiveness Index (B/C) >1 Cost of Conserved Energy < Avg Tariff
• Cost effectiveness Index (i.e. Present Value of benefits/Present Value of Cost ) assess the viability from the perspective of distribution licensee.
• Cost of Conserved Energy assess the cost effectiveness from the point of view of participating investing consumers as under:- (i.e. [(Present Value of costs of efficient option X cost recovery factor (CRF) of efficient option - Present Value of costs of inefficient option X CRF of inefficient)/ Annual Energy Saved in kWh]
Energy Efficiency Services Limited
DSM based Efficient Lighting Programme
Energy Efficiency Services Limited
DELP – Ex-Counter Distribution
Energy Efficiency Services Limited 4
DELP SOP-A Case Study
Puducherry-Power Scenario
Total Domestics consumers : 299772
CAGR : 8.77%
Total Sales to domestic Consumers : 564.33 MUs (2013-14)
Projected Sales to domestic Consumers : 613.8 MUs (2014-15)
Increase in Sales : 49.5 MUs
Additional Power Procurement : 59.16 MUs
AT&C Losses : 19%
Targeted consumers : 245000 Nos of residential households
Energy Saving from DELP (at utility end) : 48.33 MUs
Energy Efficiency Services Limited
COST 1 2 3 4 5 6 7 8 9 10
Initial Investment (Equiity) 6.84
Debt Repayment 1.59 1.59 1.59 1.59 1.59 1.59 1.59 1.59 1.59 1.59
O&M Cost 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 Interest Cost @ 12.5% 1.99 1.79 1.59 1.40 1.20 1.00 0.80 0.60 0.40 0.20
Total 10.99 3.96 3.76 3.56 3.36 3.16 2.96 2.76 2.56 2.36
Present Value of Cost @ 15% 10.99 2.99 2.84 2.69 2.54 2.39 2.24 2.09 1.94 1.79 33
BENEFITS
Profits 5.90 5.60 5.29 4.99 4.68 4.37 4.07 3.76 3.46 3.15 Taxes 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0
Total 5.90 5.60 5.29 4.99 4.68 4.37 4.07 3.76 3.46 3.15
Present Value of Benefits @ 15% 5.90 4.23 4.00 3.77 3.54 3.31 3.08 2.85 2.62 2.38 36
Cost Effectiveness Index 1.10
Cost Effectiveness of DELP SOP…..
• Cost of conserved energy is 0.12 and Cost Effective Index greater than one means programme is feasible in the area of distribution licensee.
• JERC approved the project on 5.2.2014 based on the above • Benefit to consumer: Savings of INR 96.45 Crs due to reduction in demand and LEDs at the cost of ICLs • Benefit to DISCOM: Reduction in power procurement of about 47.96 MU per annum equivalent to a savings of INR 30.72 Cr
Amount in Rs. (Cr)
Energy Efficiency Services Limited
Pump Replacement- (HESCOM & EESL Team ) Pump Replacement- Pump & Panel
Farmers Awareness campaign First Pump Replacement
Agriculture DSM
Energy Efficiency Services Limited 7
AgDSM project at HESCOM
Region : Nippani and Byadgi circles
Total Inefficient Pumps : 590 Pumps
Total Savings : 2,991,628 kWh per annuam
Commission Determined Tariff (CDT) : 4.42 per unit
Energy Saving Shared with Utility : 5%
Business Model: Replacement of inefficient pumps of farmers free of cost and the reduction in subsidy used to service EESL investment. Project commissioned on 31.12.2013
Energy Efficiency Services Limited
BEE- EESL Ag DSM Business Model
Energy Efficiency Services Limited 9
EESL: Hubli AgDSM Project
1. No. of pumps replaced – 590
2. Annual energy savings achieved (MUs) – 2.9
3. Energy Savings (%) – 37%
4. Investment by third party – 2.6 Cr.
5. Contract Period – 6 years
6. Annual Reduction of subsidy – 1.01 cr
7. 60% investment by private sector partner
8. Equal sharing of savings
9. EESL taken over revenue risk – technical risk by private partner
Amount in Rs. Cost Effectiveness of AgDSM Project with HESCOM, Hubli………..
COST 0 1 yr 2yr 3yr 4yr 5yr 6yr
Initial Investment 26069782
R&M & Miscellaneous cost (5%) 1303489.1 1303489.1 1303489.1 1303489.1 1303489.1 1303489.1
Total 26069782 1303489.1 1303489.1 1303489.1 1303489.
1 1303489.1 1303489.1
Present Value of Cost @ 15% 26958968.6
BENEFITS
Energy Saving 11,157,071 10,555,871 9,673,184 8,388,431 6,529,434 3,850,321
Total Revenue 11157071.3 10555871.3 9673183.68 8388431.
433 6529433.813 3850321.475
Present Value of Benefits @ 15% 33750827.4
Cost Effectiveness Index 1.25
Based on the success – EESL has been asked to replace about 1.15 lakh pumpsets in Karnataka
Energy Efficiency Services Limited
Mu- DSM: LED Street Lighting at Naya Raipur, Chhattisgarh
EESL Street Lighting Methodology
• MoU to be signed between Municipalities & EESL MoU
• Detailed walk through energy audit for data validation of existing DPR and Joint Verification
DPR/ Re Validation Of DPR
• To assess actual energy savings and determination of annuity payments and finalising technical specifications
Technology Demonstration
• Agreement to be signed between Municipalities & EESL for implementation.
Agreement
• The Payment security mechanism to be finalized. Payment Mechanism
• EESL will implement the project based on own resources Implementation
• Deemed saving approach used M & V
Overall cost (energy and O&M) savings to Municipalities Energy Efficiency Services Limited
Street Light Demo at JIPMER Road Puducherry
HPSV 250W Installation LED 130W Installation
250 W SV Lamp Average Lux: 22.18 130 W LED Lamp Average Lux: 33.49
Energy Efficiency Services Limited
EESL Demo Projects - Ludhiana Road Category B1 As per NLC (6 M road width) Left side Image 70W HPSV 30M span and Right side image 30W LED on same road
Power Saving more than 55% . Lux level is much more than existing lux level. Illumination > 91.71%. Power factor improvement leading to additional savings of about 25% at DISCOM end.
Energy Efficiency Services Limited
Street Light Demo at Mohali MC, Punjab
150 W SV Lamp 60 W LED Lamp
Road Category B1 As per NLC (12 M road width) Left side Image 150W HPSV 28M span and Right side image 60W LED on same road
Energy Efficiency Services Limited
Cost Effectiveness of MuDSM Project at Puducherry………..
Energy Efficiency Services Limited
COST 0 1 2 3 4 5 6 7
Initial Investment 2,888,524,800
866,557,440
288,852,480
288,852,480
288,852,480
288,852,480
288,852,480
288,852,480
288,852,480
Interest Cost on Loan
234,692,640
198,586,080
162,479,520
126,372,960
90,266,400
54,159,840
18,053,280
PMC cost (2%) 57,770,496 -
8,252,928
8,500,516
8,755,531
9,018,197
9,288,743
9,567,405
9,854,428
Total 2,946,295,296
866,557,440
531,798,048
495,939,076
460,087,531
424,243,637
388,407,623
352,579,725
316,760,188
Present Value of Cost @ 15% 2,359,729,113
BENEFITS
Energy Saving 741,011,651
763,242,001
786,139,261
809,723,438
834,015,142
859,035,596
884,806,664
Other Benefits 194,386,000
200,217,580
206,224,107
212,410,831
218,783,156
225,346,650
232,107,050
TOTAL REVENUE 935,397,651
963,459,581
992,363,368
1,022,134,269
1,052,798,297
1,084,382,246
1,116,913,713
Present Value of Benefits @ 15% 4,190,931,156
Cost Effectiveness Index
1.78
BEE-DSM – MoU signed with BEE – DSM plan for 30 states to be
prepared by EESL – total allocation Rs. 26.2 crores
Utility DSM - Project for MSEDCL and BEST under submission to
MERC
SME Projects – GEF proposal prepared for implementation of
demonstration projects in MSME clusters – total value $ 4.5 m (Rs.
27 crores). Similar project of BEE likely to be given to EESL
DISCOM Audit– Audit for all 3 DISCOMs in Rajasthan started – total
value Rs. 80 lakhs – inquiries from 3 other DISCOMs
MOEF – BUR – Work being awarded to EESL for updating SNC –
total value Rs. 80 lakhs
Consultancy Work
Energy Efficiency Services Limited
Thank You
Energy Efficiency Services Limited 18