cost mgmt

69
Paulo Faroleiro Project Management Topic 4 Cost Management Cost Management

Upload: bollone

Post on 13-Nov-2015

6 views

Category:

Documents


2 download

DESCRIPTION

Analysis of cost management performance in Project management

TRANSCRIPT

  • Paulo Faroleiro

    Project Management

    Topic 4

    Cost Management

    Cost Management

  • 1. Price Estimation

    2. Cost Control

    Part IV

    Cost Management Cost Management

    Parts Copyright 2014 Wiley

  • PRICING AND ESTIMATING

    Many managers regard this as an art !

    Information available to one bidder is generally available to others.

    This is an essential part of the planning process.Forms the basis for establishing standards for budgets, man-hours, material costs, contingencies, etc.Specific pricing strategies must be developed for each situation.

  • TWO TYPES OF ACQUISITION

    POLICIES

    Type I acquisition: One-of-a-kind contract with little or no follow-on potential Objective:-Win the contract-Execute it profitably

    Type II Acquisition: One of many contractsAn entry point to larger follow-up project contractsObjective:-Win the contract-Perform with excellence

  • TYPES OF ESTIMATES

    Order of magnitude estimates Made without any detailed engineering data May use past experience Accuracy +- 35% within the scope of the project

    Approximate (rule of thumb) estimates Made without any detailed engineering data May use previous similar projects -- Accuracy +- 15%

    Definitive (or detailed) estimates Prepared from well-defined engineering data, vendor quotes, unit

    prices, etc. Accuracy +- 5%Estimating manual

    Developed over time Use to price out effort. Accuracy +-10%

  • ADDITIONAL ESTIMATING

    METHODS

    Direct Estimate Estimate/experienced person Requires judgement

    Estimate by analogy Compare with similar activities Requires judgement

    Factored method Based on historical data Requires equipment lists, sizes Starts with equipment quotes

    Gross proration method Based on historical data Near duplicate information

  • Detailed estimate- Uses the WBS- Takes the WBS down several levels

    Quotation method- Compare three quotations- Select the best quotation

    Handbook manualsLearning curves

  • Construction Cost Estimates

  • COST FOUNDATIONS

    Actual costs to date and estimates to completion Proposal data Marketing intelligence Management goals Past performance and trends

  • Establishing The Project Budget

  • PRICING OUT A PROJECT

    1. Provide a complete definition of the work to be done.2. Develop/construct a Logic Network Diagram. 3. Construct the WBS and estimate the activities (time/cost).4. Review these (time/cost) with the respective functional

    managers.5. Decide on a course of action .6. Establish acceptable costs for each WBS-activity.7. Review the base costs with your sponsor.8. Develop the pricing cost report. 9. Document this in the project file.

  • PRICING METHOD

    Work is priced out at the department average, and all work performed is charged to the project at the department average salary, regardless of who accomplished the work.

    Work is priced out at the department average, but all work performed is billed back to the project at the actual salary of those employees who perform the work.

    The work is priced out at the salary of those employees who will perform the work, and the cost is billed back the same way.!!

  • Do Project Managers Control

    Costs, Monitor Costs Or Both?

  • COST MANAGEMENT

    Cost estimatingCost accountingProject cash flowCompany cash flowDirect labor costingOverhead rate costingOthers, such as incentives, penalties, and profit-sharing

  • COST AND CONTROL SYSTEM

    PLANNINGWORK

    AUTHORIZATIONAND RELEASE

    DATA

    COLLECTIONAND REPORTING

    COSTACCOUNTING

    CUSTOMER ANDMANAGEMENT

    REPORTING

    PHASE I PHASE II PHASE III PHASE IV PHASE V

    OPERATING CYCLECYCLEPLANNING

  • COST CONTROL REQUIREMENTS

    Measure resources consumedMeasure status and accomplishmentsCompare measurements to projections and standardsProvide the basis for diagnosis and re-planning!!

  • COST CONTROL REQUIREMENTS

    Thorough planning of the work to be performed to complete the projectGood estimating of time, labor, and costsClear communication of the scope of required tasksA disciplined budget and authorizations of expendituresTimely accounting of physical progress and cost expendituresPeriodic re-estimation of time and cost to complete remaining workFrequent, periodic comparison of actual progress and expenditures to schedules and budgets, both at the time of comparison and at project completion!!

  • WHEN TO IMPLEMENT A COST

    MANAGEMENT SYSTEM

    CONCLUSION

    A cost management system should be implemented right at the beginning of the life cycle of the project.

    Possible costreductions

    Cost of change

    PROJECTCOSTS

    PROJECT LIFE CYCLE PHASES

  • CAPACITY PLANNING

  • The Work Authorization Form

  • WORK AUTHORIZATION FORM

    Description - Test Material 2400 150 R4500 1 Aug 15 Sept - Processing 2610 160 R7500- Final inspection 2621 140 R3500- Packaging 2623 46 R 750- Delivery 2624 R 350

    Project office authorization signature:________________

    WBS: 31.03.02 Work order no: D1385

    Date of original release: 03 Feb 01Date of revision: 18 March 01Revision number: C

  • PLANNING AND BUDGETING

    Work packages

    WBS Element

    MGR

    OrgOrgOrg

    Work PackageWP______ORG_______Description of task_________________________

    Sched: Start____Stop__Budget:______________

  • CACN No. _____________ Revision to Cost Account No. ____________ Date ___________

    DESCRIPTION OF CHANGE:____________________________________________________________________________________

    ____________________________________________________________________________________

    ____________________________________________________________________________________

    ____________________________________________________________________________________

    REASON FOR CHANGE:____________________________________________________________________________________

    ____________________________________________________________________________________

    ____________________________________________________________________________________

    __________________________________________________________________________________

    Requested Budget Authorized BudgetLabor Hours _________________ _________________ Period of performanceMaterials _________________ _________________ From _____________ODCS _________________ _________________ To _____________

    BUDGET SOURCE:Funded Contract ChangeManagement ReserveUndistributed BudgetOther _________________

    INITIATED BY: ____________________________ APPROVALS: Program Mgr. ________Prog. Control ________

    COST ACCOUNT CHANGE NOTICE (CACN)

  • LaborMaterialOther direct chargesOverhead

    Distributed budgetManagement budgetUndistributed budgetContract changes

    TYPES OF BUDGETS COST DATA

  • VARIANCE ANALYSES

  • Actuals

    Labor

    ACWP

    InventoryAccounts

    BCWP

    Computer

    BCWS

    Monthly TotalProgram Effort

    Weekly LaborReports

    MCCS Comparisonreports To All Execs

    Variance Report

    COST DATA COLLATION AND

    REPORTING FLOW CHART

  • VARIANCES

    The cost variance compares deviations only from the budget and does not provide a measure of comparison between work scheduled and work accomplished.The scheduling variance provides a comparison between planned and actual performance but does not include costs.

  • VARIABLES FOR VARIANCE

    ANALYSIS

    BUDGETED COST FOR WORKED SCHEDULED (BCWS) IS THE BUDGETED AMOUNT OF COST FOR WORD SCHEDULED TO BE ACCOMPLISHED PLUS THE AMOUNT OF LEVEL OF EFFORT OR APPORTIONED EFFORT SCHEDULED TO BE ACCOMPLISHED IN A GIVEN TIME PERIOD.

    BUDGETED COST FOR WORK PERFORMED (BCWP) IS THE BUDGETED AMOUNT OF COST FOR COMPLETED WORD, PLUS BUDGETED FOR LEVEL OF EFFORT OR APPORTIONED EFFORT ACTIVITY COMPLETED WITHIN A GIVEN TIME PERIOD. THIS IS SOMETIMES REFERRED TO AS AN EARNED VALUE.

    ACTUAL COST FOR WORK PERFORMED (ACWP) IS THE AMOUNT REPORTED AS ACTUALLY EXPENDED IN COMPLETING THE WORK ACCOMPLISHED WITHIN A GIVEN TIME PERIOD.

    COST VARIANCE = BCWP ACWP

    SCHEDULE/PERFORMANCE VARIANCE = BCWP - BCWS

  • ACWP: ACTUAL COST OF WORK PERFORMEDACTUAL COST INCURRED FOR THE WORK PERFORMED IN A GIVEN PERIOD, INCLUDING ALL LABOR, MATERIALS, OTHER DIRECT COSTS, OVERHEADS, ETC.

    BCWP: BUDGETED COST OF WORK PERFORMEDMEASURE OF THE AMOUNT OF MONEY BUDGETED TO COMPLETE THE ACTUAL WORK PERFORMED AS OF THE DATA DATE.REPRESENTS THE VALUE OF WORK PERFORMED, RATHER THAN THE COST OF THE ACTUAL WORK PERFORMED. IN CURRENT EARNED VALUE MANAGEMENT SYSTEM USAGE, IT IS REFERRED TO AS "EARNED VALUE" OR EV.

    BCWS: BUDGETED COST OF WORK SCHEDULEDTHE SUM OF THE BUDGETED COSTS FOR ALL PLANNED WORK SCHEDULED TO BE COMPLETED TO-DATE, OR ON ANY GIVEN DATE.

    COST DATA COLLATION AND REPORTING FLOW

    CHART

  • COST VARIANCE CALCULATION

    A NEGATIVE VARIANCE INDICATES A COST OVERRUN

    CV = BCWP - ACWP

  • SCHEDULE VARIANCE

    CALCULATION

    SV = BCWP - BCWS

    A NEGATIVE VARIANCE INDICATESA BEHIND SCHEDULE CONDITION

  • MANAGEMENT RESERVE

    CONTRACTED COST

    RELEASED BUDGET

    ACTUAL COST

    TIME

    MANAGEMENTRESERVE

    $

  • PROJECT VARIANCE ANALYSIS

    R&D QUALIFICATION DEVELOPMENTPHASE I PHASE II PHASE III

    VARIANCE LOWER BOUNDARY

    ACTUAL COST VARIANCE

    PROJECTED COST

    VARIANCE UPPER BOUNDARY

    TIME

    $

  • VARIANCE PERCENTS

    SCHEDULE VARIANCE % =(SVP)

    COST VARIANCE % =(CVP)

    SVBCWS X 100

    CVBCWP X 100

  • Trend Analyses

  • INFORMATION REQUIREMENTS

    Budgeted cost for work scheduled (BCWS) Budgeted cost for work performed (BCWP) Actual cost for work performed (ACWP) Estimated cost at completion Budgeted cost at completion Cost and schedule variances/explanations Traceability

  • VARIANCE ANALYSIS QUESTIONS

    What is the problem causing the variance? What is the impact on time, cost, and performance? What is the impact on other efforts, if any? What corrective action is planned or under way? What are the expected results of the corrective action?

  • VARIANCE REPORTING

    Variance reporting is accomplished at each reporting interval. However, the variance threshold reports are exception reports and occur only when the variances exceed the upper and lower boundaries of the project variances envelope.

  • REPORTING INTERVALS

    Depends on the type of organization and characteristics of the projects.Project-driven organization - weekly.Non-project-driven organization - monthly

  • Cost account no/camWBS/Description

    Cost performance data Variance

    Reporting levelAs of

    At completionBudget EAC Var.BCWS BCWP ACWP SCHED COST

    Month to date ($)Contract todate ($k)

    Problem cause and impact

    Corrective action (including expected recovery date)

    Cost account Date Cost center Date WBS element Date DateMgr. Mgr. Mgr.

  • The 50/50 Rule

  • THE 50/50 RULE

    HALF OF THE BUDGET FOR EACH ELEMENT IS RECORDED AT THE TIME THAT THE WORK IS SCHEDULED TO BEGIN AND THE OTHER HALF AT THE TIME THE WORK IS SCHEDULED TO BE COMPLETED.

    FOR A PROJECT WITH A LARGE NUMBER OF ELEMENTS THE AMOUNT OF DISTORTION FROM SUCH A PROCEDURE IS MINIMAL.

  • J F M A M J J A S O N D

    Scheduled (BCWS)Performed (BCWP)

    Budget - 6

    814

    12

    10

    12

    812

    10

    8

    Work packages

    Cost account budget = 100(thousands)

    BCWS = 38BCWP = 49SCHED. VARIANCE = +11

    50-50 rule used for work in process

    ANALYSIS

    BUDGETED COST FOR WORK

  • USING THE 50-50 RULE

    4,000

    10,000

    12,000

    4,000

    6,000

    6,000

    10,000

    TIME

    TIME LINE

    COMPLETED

    NOT COMPLETED

    LEGEND

    BCWS = 34,000BCWP = 33,000BAC = 52,000

  • EARNED VALUE STATUS

    REPORTING

    SV

    CV

    BCWS

    BCWP

    ACWP

    TIME LINE

    C

    U

    M

    M

    U

    L

    A

    T

    I

    V

    E

    C

    O

    S

    T

    ,

    $

    TIME

  • Estimated Cost At Completion

  • ESTIMATE AT COMPLETION (EAC)

    EAC = ACWPBCWP X Budget at completion

    The estimate at completion is the best estimate of the total cost at the completion of the project.

    The EAC is a periodic evaluation of the status of the project - usually on a monthly basis or until a significant change has been identified.

    (BAC)

  • STATUS REPORTING IS MORE THAN

    JUST A COMPUTER PRINTOUT.

  • INTRANET STATUS

    REPORTING

  • REPORTING FAVORABLE

    STATUS

  • REPORTING UNFAVORABLE

    STATUS

  • PROGRESS REPORTING

    Progress reporting needs to answer four fundamental questions:

    1. Where are we today (time and cost)?2. Where will we end up (time and cost)?3. What are the present and future risks?4. Are there any special problems that need to be

    addressed and what can management do to help?

  • 2. ESTIMATE AT COMPLETION (EAC)EAC = (360/340) X 579,000 = $613,059Overrun = 613,059 - 579,000 = $34,059

    3. COST SUMMARYCosts are running approximately 5.9% over budget due to higher salaried labor.4. SCHEDULE SUMMARYThe 24.4% behind schedule condition is due to subtasks 4 and 6 which have not yet begun due to lack of raw materials and the 50/50 method for booking costs. Overtime will get us back on schedule but at an additional cost of 2.5% of direct labor costs.

  • DATA ACCUMULATION

    WBS

    O

    r

    g

    a

    n

    i

    z

    a

    t

    i

    o

    n

    BCWS

    BCWP

    ACWP

    BudgetSCHED

    VAR

    COSTVAR

  • FINANCIAL CLOSE-OUT

  • COST PROBLEMS

    Poor estimating techniques and/or standards, resulting in unrealistic budgets

    Out-of-sequence starting and completion of activities and events

    Inadequate work breakdown structure No management policy on reporting and control practices Poor work definition at the lower levels of the

    organization!

  • COST PROBLEMS (CONTINUED)

    Management reducing budgets or bids to be competitive or to eliminate fat

    Inadequate formal planning that results in unnoticed, or often uncontrolled, increases in scope of effort

    Poor comparison of actual and planned costs Comparison of actual and planned costs at the wrong

    level of management Unforeseen technical problems Schedule delays that require overtime or idle time costing Material escalation factors that are unrealistic!!

  • PROBLEM AREAS IN COST

    CONTROL

    Organization: Inadequate Work Breakdown Structure Poor work definition at working levels Lack of formal system procedures

    Planning and budgeting: Inadequate forward planning Over-allocation of budget Poor integration of budget, schedule, work authorization

    Accounting: Inability to account for cost of material on applied basis

    Analysis: Determination of status not based on work package completion Comparison of actual vs. planned costs at improper level

    Revisions:

    Failure to maintain valid measurement baseline!!

  • COST PROBLEMS PER PHASE

    Proposal Phase Failure to understand customer requirements Unrealistic appraisal of in-house capabilities Underestimating time requirements

    Planning phase Omissions Inaccuracy of the work breakdown structure Misinterpretation of information Use of wrong estimating techniques Failure to identify and concentrate on major cost elements Failure to assess and provide for risks!!

  • COST PROBLEMS PER PHASE

    Negotiation phase Forcing a speedy compromise Procurement ceiling costs Negotiation team that must win this one

    Contractual phase Contractual discrepancies SOW different from RFP requirements Proposal team different from project team!!

  • COST PROBLEMS PER PHASE

    Design phase Accepting customer requests without management approval Problems in customer communications channels and data

    items Problems in design review meetings

    Production phase Excessive material costs Specifications that are not acceptable Manufacturing and engineering disagreement

  • SUMMARY

    1. A cost estimate is prepared As a basis for control To assess the projects

    viability To obtain funding To allocate resources To estimate durations To prepare tenders for

    bespoke contracts

    2. There are four types of estimate of increasing accuracy requiring proportionately more work to prepare: Proposal estimate Budget estimate Sanction estimate Control estimate!!

  • SUMMARY

    3. The proposal estimate is prepared at the concept stage to commit resources to the feasibility. The budget estimate is prepared during feasibility to initiate the project, and commit resources to design. The sanction estimate is prepared during design to gain funding for the project, or approval from the project sponsor. The control estimate is prepared during implementation planning.

    4. There are several types of cost to be estimated, including:LabourMaterials, plant, and equipmentSubcontractManagement, overhead and administrationFees and taxation, inflation, and other contingency!!

  • SUMMARY

    5. The cost control cube, a three-dimensional matrix of the WBS OBS CBS provides a structure for estimating and controlling costs. The estimate is prepared by breaking the work down to an appropriate level of WBS, and then estimating the cost of each element in the cost control cube. Effectively we estimate each type of cost for each cell in the responsibility chart at that level. Spreadsheets can be used to support this process.

    6. There are five techniques for estimating cost:Detailed or bottom upComputer supportedComparativeFunctionalParametric!!

  • SUMMARY

    7. Cost is most easily controlled by forecasting cost at completion, by adding the actual work to date to the estimated cost of work remaining, and comparing that to the original estimate.

    8. Cost can also be controlled by comparing the earned value, a measure of the amount of work performed to date, to the actual expenditure to date. A comparison of earned value to the originally planned cash flow helps to control elapsed time. S-curves provide a visual representation.

  • 1. Topic 5 and 6

    Quality and Risk Management

    Part IV

    Cost Management