cost planning rics

Upload: mohit-sharma

Post on 07-Jul-2018

243 views

Category:

Documents


3 download

TRANSCRIPT

  • 8/18/2019 Cost Planning Rics

    1/15

    6/24/2013

    1

    Qonqests Technical Solutions Pvt. Ltd

    COST MANAGEMENT

    Cost Planning Concepts

    Qonqests Technical Solutions Pvt. Ltd

    COST PLANNING

    What is Cost Planning?

    • Work involved in Controlling the Design of a

    Building within the Set Parameters of Cost, Areaand Quality

    • Cost Planning is Proactive - Working with PM/DMteam during the Needs Study & Design Phases ofthe Project. It Precedes the issue of that stagedocument

    http://www.pdfcomplete.com/cms/dpl/tabid/111/Default.aspx?r=du2vH8r

  • 8/18/2019 Cost Planning Rics

    2/15

    6/24/2013

    2

    Qonqests Technical Solutions Pvt. Ltd

    COST PLAN

    What is a Cost Plan?

    • A written description of Cost broken in toElements, Levels & Areas, subject to constantupdating and reconciliation as the design evolves

    • Cost Plan is NOT an Estimate

    • Cost Plan facilitates “ Designing to a Cost ”

    Qonqests Technical Solutions Pvt. Ltd

    ESTIMATE

    What is an Estimate?

    • A Cost applicable to a design at a Set FreezePoint

    • Different levels of Estimate - Indicative, Budget,Contract

    • Usually an Indicative Estimate forms the InitialCost Plan

    http://www.pdfcomplete.com/cms/dpl/tabid/111/Default.aspx?r=du2vH8r

  • 8/18/2019 Cost Planning Rics

    3/15

    6/24/2013

    3

    Qonqests Technical Solutions Pvt. Ltd

    ESTIMATION

    What is Estimation?

    • The actual process of Quantifying and Pricing theEstimate for a Set Design at a particular point intime

    Qonqests Technical Solutions Pvt. Ltd

    RELATIONSHIP OF COSTPLANNING TO ESTIMATING

    • The original Cost Plan can be extracted from an indicativeestimate for a set design at a particular point in time

    • The budget and contract estimates should be

    confirmation of the Cost Planning that has taken place asthe design has progressed i.e. management cost checks

    • Cost Planning requires a working knowledge of alldisciplines, and the ability not to just cost what is on thedrawings - to allow for the real effects when workingdocuments are finalised - ability to see in the future

    http://www.pdfcomplete.com/cms/dpl/tabid/111/Default.aspx?r=du2vH8r

  • 8/18/2019 Cost Planning Rics

    4/15

    6/24/2013

    4

    Qonqests Technical Solutions Pvt. Ltd

    USE OF COST PLANNING

    1. Control of Cost

    2. Early Commitment

    3. Client ’s Confidence

    4. Advantages for the Design Team

    5. Maximise Construction / Design Overlap

    Qonqests Technical Solutions Pvt. Ltd

    CONTROL OF COST

    • The costs and profitability of the project are largelydetermined at the design stage. As the project proceedsfurther in to construction stage, risk of losses remainpresent, but opportunities for cost reduction or profitimprovement diminish.

    • Cost Planning enables the PM to observe and control theinteraction of design and cost during the design process,and maintain the overall scheme within the budgetlimitations.

    • Cost Planning ensures a direct relationship betweeninitial and final project cost

    http://www.pdfcomplete.com/cms/dpl/tabid/111/Default.aspx?r=du2vH8r

  • 8/18/2019 Cost Planning Rics

    5/15

    6/24/2013

    5

    Qonqests Technical Solutions Pvt. Ltd

    ADVANTAGES FOR THE DESIGN TEAM

    • Cost Planning provides a basis for “ value ” judgement ofdesign alternatives in a clear and concise form

    • Looking at alternatives and checking costs at the earliestpossible stage prior to detail drawings commencing,means less abortive design

    • An experienced Cost Planner should be able to questionearly design solutions for inadequacy - savingembarrassment later

    Qonqests Technical Solutions Pvt. Ltd

    MAXIMISE CONSTRUCTION / DESIGN OVERLAP

    • Early Construction Commencement

    • Care is required to ensure that the gains in starting early,are not lost in the haste required to complete design

    • Where design is just ahead of site requirements, anintense cost checking process is important

    http://www.pdfcomplete.com/cms/dpl/tabid/111/Default.aspx?r=du2vH8r

  • 8/18/2019 Cost Planning Rics

    6/15

    6/24/2013

    6

    Qonqests Technical Solutions Pvt. Ltd

    STAGES OF COST PLANNING

    • Initial Cost Plan can be produced from a welldefined user needs brief, giving areas and qualityrequirements, prior to any drawing being produced

    • Once outline sketch plans, sections & elevations aredrawn, options comparison and elemental checksagainst client budget can take place

    Concept to Completion: Cost Plan evolves throughout theduration of project

    Qonqests Technical Solutions Pvt. Ltd

    Inception/ Appraisal Establishing theneed for the projectFormation of in-

    house workgroupIdentification of

    Client’srequirements

    O pti on App rai sal In itia l C os ti ng

    Feasibility/ DesignBrief

    Appoint PM &Design Team CDM Co-ordinator

    Surveys &exploratory works

    Development ofStrategic Brief Feasibility Study

    Outline BusinessCase

    EstablishCritical

    timescales

    Concept Design/Outline Proposals

    Develop Outlineproposals &

    preliminary Design

    Preparation of InitialCost Plan & master

    programmeRisk Assessments Health & SafetyIssues (CDM)

    Set sustainability &Green Targets

    Assessment ofProcurement routes

    Consultations &

    Approvals

    Detailproposal/Design

    DevelopmentDetailed DesignDevelopment

    Room Data collation& documentation

    PlanningPermissions

    Review programme,risks & procurement

    options

    Elemental Cost plan,Project Cost Plan &

    Budget ConfirmationConsultations &

    ApprovalsScheme is

    “ Frozen”

    Final Proposal/Technical Design

    Development ofFinal Proposal

    Detailed Room DataSheets

    Incorporation ofSpecialist Reqmt, IT,

    AV etc.

    Review ProcurementStrategy, Cost Plan

    & programme

    InternalConsultations i.e.security, fire, IT

    Sign-off proposal bythe Client

    Production

    Information

    Preparation ofDetailed Co-

    ordinateddrawings

    Final Confirmation ofmaterials & finishes

    CompleteSpecifications,components

    drawings, BoQs

    Building Warrant Application

    Review ProcurementStrategy, Cost Plan

    & programme

    Review of GreenBldg

    TenderDocumentation

    Preparation ofTender

    DocumentationComplete Pre-tender

    EH&S planFinal ProcurementStrategy, Cost Plan

    & programme

    Tender Action Identification ofpotential contractor Tender ReportContractorsInterviews

    Approval of Client toappoint Contractor

    MobilisationBuilding contractor

    prepares tocommence on site

    Main contractorappoints sub-contractors

    Onsite Construction Works Monitoring of worksat siteChange ControlManagement

    Cost Control Duringworks

    Snagging, Testing &Commissioning

    Handover of theproject to the Clients

    Fit-out &Furnishings

    Occupation Removals Occupation Utilization of thebuildingDefects Liability

    PeriodSettlement of Final

    AccountsPost Contract

    Review & ClientFeeback

    A

    B

    C

    D

    E

    FG

    H

    J

    K

    L

    ConstructionLife Cycle

    http://www.pdfcomplete.com/cms/dpl/tabid/111/Default.aspx?r=du2vH8r

  • 8/18/2019 Cost Planning Rics

    7/15

    6/24/2013

    7

    Qonqests Technical Solutions Pvt. Ltd

    Indigenizing RIBA …!Stage Level of Cost Plan

    InformationNeeded

    Info Neededfrom Remarks for the Information Needed for Cost Plan

    ProjectDefinition

    Indicative CostPlan

    User Brief/VisionDocument

    ClientA wri tten statement including need brief, spat ialrequirements, capacity etc. along with a visiondocument or reference benchmark needed

    Concept Cost Plan Design Concept Consultants

    A concept design with possibly a design brief/ designconsiderations to be furnished along with dimensioneddrawings for plans, elevations, sections etc. & materialchart

    SchematicBudgetoryCosting based onElementary BoQ

    SchematicDesign Consultants

    Complete schematic designs including architectural,structural, MEP drawings, schedule of finishes andmaterial specifications

    DesignDevelopment

    Tender BoQ DetailedDesigns

    ConsultantsAll drawings, specifications and Consultants BoQsrequired as per agreed programme and details.

    Qonqests Technical Solutions Pvt. Ltd

    PLEASE NOTE:

    Cost Planning is of greatest use in Design & Constructionprojects. It is less relevant when we have limited control over

    the design (i.e. construction management projects)

    http://www.pdfcomplete.com/cms/dpl/tabid/111/Default.aspx?r=du2vH8r

  • 8/18/2019 Cost Planning Rics

    8/15

    6/24/2013

    8

    Qonqests Technical Solutions Pvt. Ltd

    OVERALL PRINCIPLES OF COST PLANNING

    1. Logical set out

    2. Balancing savings and overruns

    3. Project Engineering

    4. Rates & Pricing

    5. Level of detail

    Qonqests Technical Solutions Pvt. Ltd

    LOGICAL SET OUT

    • The cost plan is a statement of space, quality and cost forthe project, and requires acceptance by the design team

    • The dominant factor can vary from project to project

    • The cost plan should be set out in a logical way to facilitate

    understanding and flexibility in use, therefore it is dividedin to levels, areas and elements/trades as applicable to aparticular project (proprietary software?)

    • The initial cost plan should allow for undesigned butnecessary items

    • An elemental analysis check with historical data

    http://www.pdfcomplete.com/cms/dpl/tabid/111/Default.aspx?r=du2vH8r

  • 8/18/2019 Cost Planning Rics

    9/15

    6/24/2013

    9

    Qonqests Technical Solutions Pvt. Ltd

    BALANCING SAVINGS AND OVERRUNS

    • Cost overruns in one area can be balanced by costsavings in another

    • If a saving requires a change to the specification tobalance an overrun - agree with the client

    • If a saving is generated, and the project team wish toapply this to another project element, i.e. anupgrade to the contractual requirement - agree withsenior management

    Cost Planning is NOT an EXACT SCIENCE. It is an overall totalpackage.

    Qonqests Technical Solutions Pvt. Ltd

    PROJECT ENGINEERING

    • Design options evaluation - project engineering skills arerequired - Why not try? Can it be built? Etc.

    • Various options should be compared to see which is theOPTIMUM SOLUTION - this is not purely a ?? of price

    • It is important when considering different options to takein to account other items that may be effected

    • All details should be queried where a complicatedsolution has been proposed. These small details can costus a great deal when we get to actual construction on site.

    http://www.pdfcomplete.com/cms/dpl/tabid/111/Default.aspx?r=du2vH8r

  • 8/18/2019 Cost Planning Rics

    10/15

    6/24/2013

    10

    Qonqests Technical Solutions Pvt. Ltd

    RATES & PRICING

    • current market rates

    • historical estimating / cost planning records

    • cost feed back from sites

    • local consultants

    The cost information used in cost planning would come from,in order of importance

    Qonqests Technical Solutions Pvt. Ltd

    LEVEL OF DETAIL

    1. Project definition stage

    2. Concept design stage

    3. Schematic plan stage

    4. Design Development

    5. Final Design

    Depends on information and time available

    http://www.pdfcomplete.com/cms/dpl/tabid/111/Default.aspx?r=du2vH8r

  • 8/18/2019 Cost Planning Rics

    11/15

    6/24/2013

    11

    Qonqests Technical Solutions Pvt. Ltd

    PROJECT DEFINITION STAGE

    • an all-up cost per m2 of gross building area for indicative

    budgets only (Note: this is an extremely unreliable basisupon which to start)

    • from experience and historical records build up anelemental cost. This should also include parameters forsketch outline - plans and an indication of quality

    What is available at this stage?

    • Needs Brief

    Costing Method?

    Qonqests Technical Solutions Pvt. Ltd

    CONCEPT DESIGN STAGE

    • Build up on a level basis an elemental cost on alternativedesign schemes to assist with the choice

    • from experience and historical records build up anelemental cost. This should also include parameters forsketch outline - plans and an indication of quality

    What is available at this stage?

    • Needs Brief

    • Plan outlines

    Costing Method?

    http://www.pdfcomplete.com/cms/dpl/tabid/111/Default.aspx?r=du2vH8r

  • 8/18/2019 Cost Planning Rics

    12/15

    6/24/2013

    12

    Qonqests Technical Solutions Pvt. Ltd

    SCHEMATIC DESIGN STAGE

    • Build quantities taken off in levels and / or areas in anelemental format

    What is available at this stage?• Needs Brief

    • Schematic Plan, Elevations and Sections

    • Schematic Structural Plans

    • Outline Finishing Plans

    Costing Method?

    Qonqests Technical Solutions Pvt. Ltd

    DESIGN DEVELOPMENT

    • Bulk quantity take-offs to compare design alternatives

    • Check all preliminary drawings conform to cost plan parameters

    • Check all detailing

    What is available at this stage?

    • Alternative design options

    • Preliminary drawings

    • Preliminary specifications, finishes schedule, doorschedules etc.

    • Detailing

    Costing Method?

    http://www.pdfcomplete.com/cms/dpl/tabid/111/Default.aspx?r=du2vH8r

  • 8/18/2019 Cost Planning Rics

    13/15

    6/24/2013

    13

    Qonqests Technical Solutions Pvt. Ltd

    FINAL DESIGN

    • Examine to ensure that all corrections have beenincorporated and that there are no last minuteinclusions

    What is available at this stage?• All final AFC drawings, specifications etc.

    Costing Method?

    Qonqests Technical Solutions Pvt. Ltd

    Elements of Checking a Bldg EstimateScope v/s Provision (Plot Area/ FAR/ GFA etc.)

    Area, Perimeter, Height Statements

    Provided Area v/s Needs Brief

    Adequacy of Elements/ Trades Items

    Abnormal elemental qty variations thru floors

    Soffit of slab ~ Ceiling Finishes ~ Floor Finishes ~ GFA

    Reinforcement densities ranges

    Formwork / Concrete Ratios

    Walls/ Façade/ Wall Finishes corresponds to Area/ Perimeter

    http://www.pdfcomplete.com/cms/dpl/tabid/111/Default.aspx?r=du2vH8r

  • 8/18/2019 Cost Planning Rics

    14/15

    6/24/2013

    14

    Qonqests Technical Solutions Pvt. Ltd

    Elements of Checking a Bldg EstimateAir, Water (all types), Electricity – Path in/ Path out

    Defined P&IDs/ SLDs

    Services Provision v/s Need

    Risers Lengths ~ Building Heights

    Horizontal Reticulation ~ Approx runs on the floor plate

    External Services around the building ~ Perimeter statementAir-conditioning tonnage v/s area covered

    Fixtures per unit area

    Qonqests Technical Solutions Pvt. Ltd

    Important Factors

    Formulation of Cost Plan based on design information level.

    Identification of Cost Parameters and Elements.

    Identification of Cost Heads for each Element.

    Estimation of Cost Heads based on preliminary concept

    drawings and established database of market prices.

    Comparison of Alternative Designs on costs.

    Identification and estimation of cost for ongoing design

    changes.

    http://www.pdfcomplete.com/cms/dpl/tabid/111/Default.aspx?r=du2vH8r

  • 8/18/2019 Cost Planning Rics

    15/15

    6/24/2013

    15

    Qonqests Technical Solutions Pvt. Ltd

    QUESTIONS

    http://www.pdfcomplete.com/cms/dpl/tabid/111/Default.aspx?r=du2vH8r