cost sheets (road construction) dupa

Upload: neb-bie

Post on 02-Jun-2018

332 views

Category:

Documents


35 download

TRANSCRIPT

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    1/547

    Item No./Description : 100(1) Clearing & Grubbing (with Stripping)

    Unit of Measurement : sq.m.

    Output per hour : 500.00

    A. Labor

    1 1 109.19

    2 1 61.44

    B. Equipment

    a. Dump Truck (10 cu.m.) 2 1 1,352.00

    b. Payloader (1.50 cu.m.) 1 1 1,733.00

    c. Bulldozer (155 Hp), D65A-8 1 1 2,299.00

    (Hauling Distance - within three (3) km.)

    Assumed 150mm cut

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Output per hour = 500.00 sq.m.

    Name and Specification Unit Quantity Unit Cost

    a. Construction Foreman

    b. Laborer

    Sub - Total for A

    Sub - Total for F

    Sub - Total for B

    Name and Capacity No of Units No. of Hours Hourly Rate

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Designation No. of Person No. of Hours Hourly Rate

    Total (A + B)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    2/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    3/547

    Item No./Description : 100(2)b

    Unit of Measurement : ea.

    Output per hour : 1.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    1 1 79.70

    2 1 61.44

    B. Equipment

    a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00

    b. Dump Truck (10 cu.m.) 1 0.50 1,352.00

    c. Chain Saw 1 0.50 121.50

    Minor Tools (5% of labor)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Rope, 1" dia. m. 20.00 3.50

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Unit Cost

    Sub - Total for F

    Total (A + B)

    Output per hour = 1.00 ea.

    Name and Specification Unit Quantity

    c. Laborer

    * Boom Truck - if necessary for trimming in Urban

    Areas

    Sub - Total for A

    Name and Capacity No of Units No. of Hours Hourly Rate

    Individual Removal of Trees (small b, 301-500mm )

    Sub - Total for B

    b. Skilled Laborer

    Designation No. of Person No. of Hours Hourly Rate

    DETAILED UNIT PRICE ANALYSIS (DUPA)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    4/547

    Item No./Description : 100(3)a

    Unit of Measurement : ea.

    Output per hour : 0.25

    A. Labor

    a. Construction Foreman 1 1 109.19

    1 1 79.70

    2 1 61.44

    B. Equipment

    a. Backhoe (0.80 cu.m.) 1 1 1,537.00

    b. Dump Truck (10 cu.m.) 1 1 1,352.00

    c. Chain Saw 1 1 121.50

    Minor Tools (5% of labor)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Rope, 1" dia. m. 20.00 3.50

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Output per hour = 0.25 ea.

    Name and Specification Unit Quantity Unit Cost

    b. Skilled Laborer

    c. Laborer

    * Boom Truck - if necessary for trimming in Urban

    Areas

    Sub - Total for BTotal (A + B)

    Sub - Total for A

    Name and Capacity No of Units No. of Hours Hourly Rate

    Sub - Total for F

    Hourly Rate

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Individual Removal of Trees (large a, 501-750mm )

    Designation No. of Person No. of Hours

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    5/547

    Item No./Description : 100(3)b

    Unit of Measurement : ea.

    Output per hour : 0.125

    A. Labor

    a. Construction Foreman 1 1 109.19

    1 1 79.70

    2 1 61.44

    B. Equipment

    a. Backhoe (0.80 cu.m.) 1 1 1,537.00

    b. Dump Truck (10 cu.m.) 1 1 1,352.00

    c. Chain Saw 1 1 121.50

    Minor Tools (5% of labor)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Rope, 1" dia. m. 20.00 3.50

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Total (A + B)

    Output per hour = 0.125 ea.

    Name and Specification Unit Quantity Unit Cost

    Sub - Total for F

    * Boom Truck - if necessary for trimming in Urban

    Areas

    Sub - Total for A

    Name and Capacity No of Units No. of Hours Hourly Rate

    Sub - Total for B

    b. Skilled Laborer

    c. Laborer

    Designation No. of Person No. of Hours Hourly Rate

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Individual Removal of Trees (large b, 751-900mm )

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    6/547

    Item No./Description : 101(1)

    Unit of Measurement : cu.m.

    Output per hour : 10.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Skilled Laborer 1 1 79.70

    c. Laborer 2 1 61.44

    B. Equipment

    a. Backhoe (0.80 cu.m.) 1 1 1,537.00

    b. Dump Truck (10 cu.m.) 1 1 1,352.00

    Minor Tools (10% of Labor)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Sub - Total for F

    Total (A + B)

    Output per hour = 10.00 cu.m.

    Name and Specification Unit Quantity

    No of Units No. of Hours Hourly Rate

    Unit Cost

    Sub - Total for B

    Sub - Total for A

    Removal of Structures and Obstruction (other than concrete)

    Name and Capacity

    Designation No. of Person No. of Hours Hourly Rate

    DETAILED UNIT PRICE ANALYSIS (DUPA)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    7/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    8/547

    Item No./Description : 101(2)

    Unit of Measurement : cu.m.

    Output per hour : 1.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    2 1 79.70

    4 1 61.44

    B. Equipment

    a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95

    b. Jackhammer 2 1 514.31

    c. Air Compressor (103 Hp) 1 1 675.00

    d. Dump Truck (10 cu.m.) 1 0.125 1,352.00

    e. Payloader (1.50 cu.m.) 1 0.125 1,733.00

    f. Truck Mounted Crane (35 T) 1 0.25 1,553.00

    g. Cutting Outfit 1 1 45.00

    * Disposal area (within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Oxy/Acytelene set 0.10 2,500.00

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Output per hour = 1.00 cu.m.

    Name and Specification Unit

    Name and Capacity No of Units

    Sub - Total for F

    Total (A + B)

    Quantity Unit Cost

    Sub - Total for B

    b. Skilled Laborer

    c. Laborer

    No. of Person No. of Hours Hourly Rate

    No. of Hours Hourly Rate

    Designation

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Removal of Concrete Bridge Structures

    Sub - Total for A

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    9/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    10/547

    Item No./Description : 101(2)

    Unit of Measurement : kg.

    Output per hour : 1,000.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    2 1 79.70

    4 1 61.44

    B. Equipment

    a. Service Truck/Cargo Truck 1 1 712.00

    b. Welding Machine 1 1 391.00

    c. Truck Mounted Crane (35 T) 1 1 1,553.00

    d. Cutting Outfit 1 1 45.00

    Minor Tools (10% of Labor)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Oxy/Acytelene set 0.00025 2,500.00

    b. Welding Rod kg. 0.002 90.00

    c. Rope 1" dia. m. 0.05 3.50

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    * Include shoring materials if needed based on

    actual field condition

    Sub - Total for F

    Total (A + B)

    Output per hour = 1000.00 kg.

    Name and Specification Unit Quantity Unit Cost

    Sub - Total for B

    Sub - Total for A

    Name and Capacity No of Units No. of Hours

    Hourly Rate

    Hourly Rate

    b. Skilled Laborer

    c. Laborer

    Removal of Steel Bridge Structures

    Designation No. of Person No. of Hours

    DETAILED UNIT PRICE ANALYSIS (DUPA)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    11/547

    K. Total Unit Cost (G + H + I + J)

    Item No./Description : 101(2) Removal of Stone Masonry Lined Drainage Structures

    Unit of Measurement : cu.m.

    Output per hour : 5.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    2 1 79.70

    4 1 61.44

    B. Equipment

    a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95

    b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00

    c. Dump Truck (10 cu.m.) 1 0.25 1,352.00

    * Disposal area (within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    No. of Hours Hourly Rate

    Sub - Total for B

    Name and Specification Unit Quantity

    Output per hour = 5.00 cu.m.

    Sub - Total for F

    Designation No. of Person No. of Hours

    Total (A + B)

    Name and Capacity No of Units

    b. Skilled Laborer

    c. Laborer

    Sub - Total for A

    Unit Cost

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Hourly Rate

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    12/547

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    13/547

    Item No./Description : 101(2) Removal of Concrete Drainage Structures

    Unit of Measurement : cu.m.

    Output per hour : 2.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    2 1 79.70

    4 1 61.44

    B. Equipment

    a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95

    b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00

    d. Dump Truck (10 cu.m.) 1 0.125 1,352.00

    e. Cutting Outfit 1 1 45.00

    * Disposal area (within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Oxy/Acetylene set 0.10 2,500.00

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Name and Capacity No of Units No. of Hours Hourly Rate

    Sub - Total for B

    Sub - Total for F

    Name and Specification Unit Quantity Unit Cost

    Sub - Total for A

    Output per hour = 2.00 cu.m.

    Total (A + B)

    Hourly Rate

    b. Skilled Laborer

    c. Laborer

    Designation No. of Person No. of Hours

    DETAILED UNIT PRICE ANALYSIS (DUPA)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    14/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    15/547

    Item No./Description : 101(2)a Removal of RCPC (24" dia.) - 610mm

    Unit of Measurement : l.m.

    Output per hour : 6.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    2 1 61.44

    B. Equipment

    a. Backhoe (0.80 cu.m.) 1 1 1,537.00

    b. Boom Truck 1 0.50 961.20

    Minor Tools (10 % of Labor)

    Note: Exclude Excavation Works

    * Disposal area (within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Sub - Total for BTotal (A + B)

    Output per hour = 6.00 l.m.

    Sub - Total for F

    Name and Specification Unit

    Sub - Total for A

    No. of Person No. of Hours Hourly Rate

    b. Laborer

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Name and Capacity

    Quantity

    No of Units No. of Hours Hourly Rate

    Unit Cost

    Designation

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    16/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    17/547

    Item No./Description : 101(2)b

    Unit of Measurement : l.m.

    Output per hour : 5.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    2 1 61.44

    B. Equipment

    a. Backhoe (0.80 cu.m.) 1 1 1,537.00

    b. Boom Truck 1 0.50 961.20

    Minor Tools (10 % of Labor)

    Note: Exclude Excavation Works

    * Disposal area (within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Hourly Rate

    Sub - Total for F

    Sub - Total for BTotal (A + B)

    Output per hour = 5.00 l.m.

    Sub - Total for A

    Name and Specification Unit Cost

    b. Laborer

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Removal of RCPC (30" dia.) - 760mm

    Designation No. of Person No. of Hours Hourly Rate

    Unit Quantity

    Name and Capacity No of Units No. of Hours

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    18/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    19/547

    Item No./Description : 101(2)c

    Unit of Measurement : l.m.

    Output per hour : 4.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    2 1 61.44

    B. Equipment

    a. Backhoe (0.80 cu.m.) 1 1 1,537.00

    b. Boom Truck 1 0.50 961.20

    Minor Tools (10 % of Labor)

    Note: Exclude Excavation Works

    * Disposal area (within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Sub - Total for BTotal (A + B)

    Quantity

    Sub - Total for F

    Unit Cost

    b. Laborer

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Removal of RCPC (36" dia.) - 910mm

    Sub - Total for A

    Designation No. of Person

    Hourly Rate

    No. of Hours Hourly Rate

    Name and Specification Unit

    No. of Hours

    Output per hour = 4.00 l.m.

    Name and Capacity No of Units

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    20/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    21/547

    Item No./Description : 101(2)d

    Unit of Measurement : l.m.

    Output per hour : 4.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    2 1 61.44

    B. Equipment

    a. Backhoe (0.80 cu.m.) 1 1 1,537.00

    b. Boom Truck 1 0.50 961.20

    Minor Tools (10 % of Labor)

    Note: Exclude Excavation Works

    * Disposal area (within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Sub - Total for F

    Name and Specification Unit Quantity Unit Cost

    Designation No. of Person No. of Hours

    Name and Capacity No of Units No. of Hours

    Output per hour = 4.00 l.m.

    Sub - Total for BTotal (A + B)

    Hourly Rate

    Hourly Rate

    Sub - Total for A

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    b. Laborer

    Removal of RCPC (42" dia.) - 1070mm

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    22/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    23/547

    Item No./Description : 101(2)e

    Unit of Measurement : l.m.

    Output per hour : 3.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    2 1 61.44

    B. Equipment

    a. Backhoe (0.80 cu.m.) 1 1 1,537.00

    b. Boom Truck 1 0.50 961.20

    Minor Tools (10 % of Labor)

    Note: Exclude Excavation Works

    * Disposal area (within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Name and Capacity No of Units No. of Hours Hourly Rate

    Sub - Total for F

    Sub - Total for BTotal (A + B)

    Output per hour = 3.00 l.m.

    b. Laborer

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Removal of RCPC (48" dia.) - 1220mm

    Name and Specification Unit Quantity Unit Cost

    Designation No. of Person No. of Hours Hourly Rate

    Sub - Total for A

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    24/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    25/547

    Item No./Description : 101(2)f

    Unit of Measurement : l.m.

    Output per hour : 2.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    2 1 61.44

    B. Equipment

    a. Backhoe (0.80 cu.m.) 1 1 1,537.00

    b. Boom Truck 1 0.50 961.20

    Minor Tools (10 % of Labor)

    Note: Exclude Excavation Works

    * Disposal area (within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    No of Units No. of Hours Hourly Rate

    Sub - Total for BTotal (A + B)

    Output per hour = 2.00 l.m.

    Name and Specification Unit

    Designation No. of Person No. of Hours Hourly Rate

    Sub - Total for F

    Sub - Total for A

    Name and Capacity

    b. Laborer

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Removal of RCPC (60" dia.) - 1520mm

    Quantity Unit Cost

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    26/547

    Item No./Description : 101(2)g Removal of Pipes other than Pipe Culverts (PVC/GI/Asbestos, up to 200m

    Unit of Measurement : ea.

    Output per hour : 2.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    1 1 79.70

    2 1 61.44

    B. Equipment

    a. Cargo Truck (10 T) 1 0.25 1,102.00

    Minor Tools (10% of Labor)

    Note: Exclude Excavation Works

    * Disposal area (within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Sub - Total for F

    Sub - Total for B

    Name and Specification Unit Quantity Unit Cost

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Designation

    Sub - Total for A

    Output per hour = 2.00 ea.

    No of Units No. of Hours Hourly Rate

    No. of Person No. of Hours Hourly Rate

    c. Laborer

    Total (A + B)

    Name and Capacity

    b. Skilled Laborer

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    27/547

    Item No./Description : 101(3)a.1

    Unit of Measurement : sq.m.

    Output per hour : 40.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    2 1 61.44

    B. Equipment

    a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 1 2,074.95

    b. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00

    c. Dump Truck (10 cu.m.) 1 0.50 1,352.00

    Minor Tools (10% of Labor)

    * Disposal area (within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Sub - Total for F

    Name and Capacity No of Units No. of Hours Hourly Rate

    Sub - Total for B

    Name and Specification Unit Quantity Unit Cost

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Removal of Existing Concrete Pavement (0.23m thk.)

    Output per hour = 40.00 sq.m.

    Hourly Rate

    b. Laborer

    Total (A + B)

    Sub - Total for A

    No. of HoursNo. of PersonDesignation

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    28/547

    Item No./Description : 101(3)a.2

    Unit of Measurement : sq.m.

    Output per hour : 30.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    2 1 61.44

    B. Equipment

    a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 1 2,074.95

    b. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00

    c. Dump Truck (10 cu.m.) 1 0.50 1,352.00

    d. Concrete Saw, Blade 14" (7.5 Hp) 1 0.50 167.38

    Minor Tools (10% of Labor)

    * Disposal area (within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Sub - Total for F

    Name and Capacity No of Units No. of Hours Hourly Rate

    Sub - Total for BTotal (A + B)

    Name and Specification Unit Quantity Unit Cost

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Removal of Existing PCC Pavement, 0.23m thk. (for Reblocking at intermitt

    Sub - Total for A

    Output per hour = 30.00 sq.m.

    Designation No. of Person

    b. Laborer

    No. of Hours Hourly Rate

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    29/547

    Item No./Description : 101(3)b

    Unit of Measurement : sq.m.

    Output per hour : 60.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    2 1 61.44

    B. Equipment

    a. Motorized Road Grader w/ Scarifier, G710A 1 1 2,173.00

    b. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00

    c. Dump Truck (10 cu.m.) 1 0.50 1,352.00

    Minor Tools (10% of Labor)

    * Disposal area (within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Name and Capacity No of Units No. of Hours Hourly Rate

    Sub - Total for F

    Quantity Unit Cost

    Sub - Total for BTotal (A + B)

    Output per hour = 60.00 sq.m.

    Hourly Rate

    b. Laborer

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Removal of Existing Asphalt Pavement (100mm thk.)

    Sub - Total for A

    Name and Specification Unit

    Designation No. of Person No. of Hours

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    30/547

    Item No./Description : 101(3)c

    Unit of Measurement : sq.m.

    Output per hour : 60.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 2 1 61.44

    B. Equipment

    a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 0.50 2,074.95

    b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00

    c. Dump Truck (10 cu.m.) 1 0.50 1,352.00

    * Disposal area (within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Total (A + B)

    Output per hour = 60.00 sq.m.

    Hourly Rate

    Sub - Total for F

    Name and Specification Unit Quantity Unit Cost

    Sub - Total for A

    Name and Capacity No of Units No. of Hours

    Sub - Total for B

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Removal of Sidewalk

    Designation No. of Person No. of Hours Hourly Rate

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    31/547

    Item No./Description : 101(4)a

    Unit of Measurement : l.m.

    Output per hour : 50.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 2 1 61.44

    B. Equipment

    a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95

    b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00

    c. Dump Truck (10 cu.m.) 1 0.50 1,352.00

    * Disposal area (within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Sub - Total for B

    Name and Capacity No of Units No. of Hours Hourly Rate

    Sub - Total for F

    Name and Specification Unit Quantity Unit Cost

    Designation No. of Person No. of Hours Hourly Rate

    Sub - Total for A

    Total (A + B)

    Output per hour = 50.00 l.m.

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Removal of Curb

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    32/547

    Item No./Description : 101(4)b

    Unit of Measurement : l.m.

    Output per hour : 30.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 2 1 61.44

    B. Equipment

    a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95

    b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00

    c. Dump Truck (10 cu.m.) 1 0.50 1,352.00

    * Disposal area (within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Sub - Total for F

    Name and Capacity No of Units No. of Hours Hourly Rate

    Sub - Total for BTotal (A + B)

    Output per hour = 30.00 l.m.

    Name and Specification Unit Quantity Unit Cost

    Removal of Curb & Gutter

    Sub - Total for A

    No. of Person No. of Hours Hourly RateDesignation

    DETAILED UNIT PRICE ANALYSIS (DUPA)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    33/547

    Item No./Description : 102(1)

    Unit of Measurement : cu.m.

    Output per hour : 20.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 3 1 61.44

    B. Equipment

    a. Dump Truck (10 cu.m.) 2 1 1,352.00

    b. Backhoe (0.80 cu.m.) 1 1 1,537.00

    c. Payloader (1.50 cu.m.) at disposal site 1 0.10 1,733.00

    Minor Tools (10% of Labor)

    * Disposal area (within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Sub - Total for F

    Name and Specification

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Roadway Excavation (Unsuitable)

    Designation No. of Person No. of Hours Hourly Rate

    Unit CostUnit Quantity

    Sub - Total for A

    Name and Capacity No of Units No. of Hours Hourly Rate

    Sub - Total for BTotal (A + B)

    Output per hour = 20.00 cu.m.

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    34/547

    Item No./Description : 102(2)a

    Unit of Measurement : cu.m.

    Output per hour : 60.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 2 1 61.44

    B. Equipment

    a. Bulldozer (155 Hp), D65A-8 1 1 2,299.00

    b. Payloader (1.50 cu.m.) 1 1 1,733.00

    c. Payloader (1.50 cu.m.) - at disposal area 1 0.25 1,733.00

    d. Dump Truck (10 cu.m.) 2 1 1,352.00

    (Hauling Distance - within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Unit Cost

    Sub - Total for F

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Roadway Excavation (Surplus Common)

    Designation No. of Person No. of Hours Hourly Rate

    Sub - Total for A

    Name and Capacity No of Units No. of Hours Hourly Rate

    Sub - Total for BTotal (A + B)

    Output per hour = 60.00 cu.m.

    Name and Specification Unit Quantity

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    35/547

    109.19

    122.88

    232.07

    2,704.00

    1,733.00

    2,299.00

    6,736.00

    6,968.07

    13.94

    0.00

    13.94

    1.25

    1.11

    1.96

    18.26

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    36/547

    109.19

    79.70

    122.88

    311.77

    768.50

    676.00

    60.75

    15.59

    1,520.84

    1,832.61

    610.87

    70.00

    70.00

    680.87

    61.28

    54.47

    95.59

    892.21

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    37/547

    109.19

    79.70

    122.88

    311.77

    768.50

    676.00

    60.75

    15.59

    1,520.84

    1,832.61

    1,832.61

    70.00

    70.00

    1,902.61

    171.23

    152.21

    267.13

    2,493.18

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    38/547

    109.19

    79.70

    122.88

    311.77

    1,537.00

    1,352.00

    121.50

    15.59

    3,026.09

    3,337.86

    13,351.43

    70.00

    70.00

    13,421.43

    1,207.93

    1,073.71

    1,884.37

    17,587.45

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    39/547

    109.19

    79.70

    122.88

    311.77

    1,537.00

    1,352.00

    121.50

    15.59

    3,026.09

    3,337.86

    26,702.87

    70.00

    70.00

    26,772.87

    2,409.56

    2,141.83

    3,758.91

    35,083.17

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    40/547

    109.19

    79.7

    122.88

    311.77

    1,537.00

    1,352.00

    31.18

    2,920.18

    3,231.95

    323.19

    0.00

    323.19

    29.09

    25.86

    45.38

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    41/547

    423.51

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    42/547

    109.19

    159.40

    245.76

    514.35

    1,037.48

    1,028.62

    675.00

    169.00

    216.63

    388.25

    45.00

    3,559.97

    4,074.32

    4,074.32

    250.00

    250.00

    4,324.32

    389.19

    345.95

    607.13

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    43/547

    5,666.59

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    44/547

    109.19

    159.40

    245.76

    514.35

    712.00

    391.00

    1,553.00

    45.00

    51.44

    2,752.44

    3,266.79

    3.27

    0.63

    0.18

    0.18

    0.98

    4.25

    0.38

    0.34

    0.60

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    45/547

    5.56

    109.19

    159.40

    245.76

    514.35

    1,037.48

    768.50

    338.00

    2,143.982,658.33

    531.67

    0.00

    531.67

    47.85

    42.53

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    46/547

    74.65

    696.69

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    47/547

    109.19

    159.40

    245.76

    514.35

    1,037.48

    768.50

    169.00

    45.00

    2,019.98

    2,534.33

    1,267.16

    250.00

    250.00

    1,517.16

    136.54

    121.37

    213.01

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    48/547

    1,988.09

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    49/547

    109.19

    122.88

    232.07

    1,537.00

    480.60

    23.21

    2,040.81

    2,272.88

    378.81

    0.00

    378.81

    34.09

    30.31

    53.19

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    50/547

    496.40

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    51/547

    109.19

    122.88

    232.07

    1,537.00

    480.60

    23.21

    2,040.81

    2,272.88

    454.58

    0.00

    454.58

    40.91

    36.37

    63.82

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    52/547

    595.68

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    53/547

    109.19

    122.88

    232.07

    1,537.00

    480.60

    23.21

    2,040.81

    2,272.88

    568.22

    0.00

    568.22

    51.14

    45.46

    79.78

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    54/547

    744.59

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    55/547

    109.19

    122.88

    232.07

    1,537.00

    480.60

    23.21

    2,040.81

    2,272.88

    568.22

    0.00

    568.22

    51.14

    45.46

    79.78

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    56/547

    744.59

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    57/547

    109.19

    122.88

    232.07

    1,537.00

    480.60

    23.21

    2,040.81

    2,272.88

    757.63

    0.00

    757.63

    68.19

    60.61

    106.37

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    58/547

    992.79

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    59/547

    109.19

    122.88

    232.07

    1,537.00

    480.60

    23.21

    2,040.81

    2,272.88

    1,136.44

    0.00

    1,136.44

    102.28

    90.92

    159.56

    1,489.19

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    60/547

    ), L=10 ft.

    109.19

    79.70

    122.88

    311.77

    275.50

    31.18

    306.68

    618.45

    309.22

    0.00

    309.22

    27.83

    24.74

    43.41

    405.21

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    61/547

    109.19

    122.88

    232.07

    2,074.95

    1,733.00

    676.00

    23.21

    4,507.16

    4,739.23

    118.48

    0.00

    118.48

    10.66

    9.48

    16.63

    155.26

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    62/547

    109.19

    122.88

    232.07

    2,074.95

    1,733.00

    676.00

    83.69

    23.21

    4,590.85

    4,822.92

    160.76

    1.20

    1.20

    161.96

    14.58

    12.96

    22.74

    212.24

    Amount

    Amount

    ent section)

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    63/547

    109.19

    122.88

    232.07

    2,173.00

    1,733.00

    676.00

    23.21

    4,605.21

    4,837.28

    80.62

    0.00

    80.62

    7.26

    6.45

    11.32

    105.65

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    64/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    65/547

    109.19

    122.88

    232.07

    1,037.48

    768.50

    676.00

    2,481.98

    2,714.05

    54.28

    0.00

    54.28

    4.89

    4.34

    7.62

    71.13

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    66/547

    109.19

    122.88

    232.07

    1,037.48

    768.50

    676.00

    2,481.98

    2,714.05

    90.47

    0.00

    90.47

    8.14

    7.24

    12.70

    118.55

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    67/547

    109.19

    184.32

    293.51

    2,704.00

    1,537.00

    173.30

    29.35

    4,443.65

    4,737.16

    236.86

    0.00

    236.86

    21.32

    18.95

    33.25

    310.38

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    68/547

    109.19

    122.88

    232.07

    2,299.00

    1,733.00

    433.25

    2,704.00

    7,169.25

    7,401.32

    123.36

    0.00

    123.36

    11.10

    9.87

    17.32

    161.64

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    69/547

    Item No./Description : 102(2)b

    Unit of Measurement : cu.m.

    Output per hour : 80.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 2 1 61.44

    B. Equipment

    a. Bulldozer (155 Hp), D65A-8 1 1 2,299.00

    b. Payloader (1.50 cu.m.) 1 1 1,733.00

    c. Payloader (1.50 cu.m.) - at disposal area 1 0.30 1,733.00

    d. Dump Truck (10 cu.m.) 3 1 1,352.00

    e. Backhoe (0.80 cu.m.) 1 1 1,537.00

    (Hauling Distance - within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Unit Cost

    Sub - Total for F

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Roadway Excavation (Surplus Common)

    Designation No. of Person No. of Hours Hourly Rate

    Sub - Total for A

    Name and Capacity No of Units No. of Hours Hourly Rate

    Sub - Total for BTotal (A + B)

    Output per hour = 80.00 cu.m.

    Name and Specification Unit Quantity

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    70/547

    Item No./Description : 102(3)a

    Unit of Measurement : cu.m.

    Output per hour : 56.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 2 1 61.44

    B. Equipment

    a. Bulldozer w/ Ripper (155 Hp), D65A-8 1 1 2,758.80

    b. Payloader (1.50 cu.m.) 1 1 1,733.00

    c. Payloader (1.50 cu.m.) at disposal area 1 0.25 1,733.00

    d. Dump Truck (10 cu.m.) 2 1 1,352.00

    e. Backhoe (0.80 cu.m.) w/ attachment 1 1 2,074.95

    (Hauling Distance - within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Unit Cost

    Sub - Total for F

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Roadway Excavation (Surplus Soft Rock)

    Designation No. of Person No. of Hours Hourly Rate

    Sub - Total for A

    Name and Capacity No of Units No. of Hours Hourly Rate

    Sub - Total for BTotal (A + B)

    Output per hour = 56.00 cu.m.

    Name and Specification Unit Quantity

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    71/547

    Item No./Description : 102(3)b

    Unit of Measurement : cu.m.

    Output per hour : 42.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 2 1 61.44

    B. Equipment

    a. Bulldozer w/ Ripper (155 Hp), D65A-8 1 1 2,758.80

    b. Payloader (1.50 cu.m.) 1 1 1,733.00

    c. Payloader (1.50 cu.m.) at disposal area 1 0.20 1,733.00

    d. Dump Truck (10 cu.m.) 2 1 1,352.00

    (Hauling Distance - within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Roadway Excavation (Surplus Soft Rock)

    Designation No. of Person No. of Hours Hourly Rate

    Sub - Total for A

    Name and Capacity No of Units No. of Hours Hourly Rate

    Unit Cost

    Sub - Total for F

    Sub - Total for BTotal (A + B)

    Output per hour = 42.00 cu.m.

    Name and Specification Unit Quantity

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    72/547

    Item No./Description : 102(3)c

    Unit of Measurement : cu.m.

    Output per hour : 10.00

    A. Labor

    a. Construction Foreman (Drilling) 1 1 109.19

    b. Skilled Laborer 2 1 79.70

    c. Laborer 4 1 61.44

    a. Construction Foreman (Blasting) 1 1 109.19

    b. Skilled Laborer 1 1 79.70

    c. Laborer 2 1 61.44

    a. Construction Foreman (Disposal) 1 1 109.19

    b Laborer 2 1 61.44

    B. Equipment

    a. Backhoe (0.80 cu.m.) 1 0.25 1,537.00

    b. Payloader (1.50 cu.m.) 1 0.25 1,733.00

    c. Payloader (1.50 cu.m.) - at disposal area 1 0.05 1,733.00

    d. Dump Truck (10 cu.m.) 1 0.50 1,352.00

    e. Pneumatic Drilling Machine 2 1 514.31

    f. Compressor 1 1 358.00

    (Hauling Distance - within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Dynamite kg. 0.40 280.00

    b. Detonation Cord m. 2.00 80.00

    c. Detonator pc. 0.15 260.00

    d. Ammonium Sulfate kg. 0.20 75.00

    e. Blasting Cap pc. 0.30 45.00

    f. Safety Fuse m. 0.10 40.00

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Unit Quantity Unit Cost

    Sub - Total for F

    Name and Specification

    Total (A + B)

    Output per hour = 10.00 cu.m.

    No of Units No. of Hours Hourly Rate

    Hourly RateNo. of Person

    Sub - Total for B

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Roadway Excavation (Surplus Hard Rock) - Blasting

    Name and Capacity

    Designation

    Sub - Total for A

    No. of Hours

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    73/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    74/547

    Item No./Description : 102(4)

    Unit of Measurement : cu.m.

    Output per hour : 50.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 2 1 61.44

    B. Equipment

    a. Bulldozer (155 Hp), D65A-8 1 1 2,299.00

    b. Payloader (1.50 cu.m.) 1 1 1,733.00

    c. Payloader (1.50 cu.m.) - at disposal area 1 0.20 1,733.00

    d. Dump Truck (10 cu.m.) 2 1 1,352.00

    (Hauling Distance - within three (3) km.)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Name and Capacity

    No. of Person No. of Hours Hourly Rate

    Name and Specification

    Sub - Total for F

    Total (A + B)

    Output per hour = 50.00 cu.m.

    Sub - Total for B

    No of Units No. of Hours Hourly Rate

    Unit Quantity Unit Cost

    Sub - Total for A

    Designation

    Roadway Excavation (Unclassified)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    75/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    76/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    77/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    78/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    79/547

    K. Total Unit Cost (G + H + I + J)

    Item No./Description : 103(1)c

    Unit of Measurement : cu.m.

    Output per hour : 4.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 3 1 61.44

    B. Equipment

    a. Dump Truck (10 cu.m.) 1 1 1,352.00

    b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00

    c. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95

    Minor Tools (10% of Labor)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    No. of Person

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Unit CostName and Specification

    No. of Hours Hourly RateNo of Units

    Sub - Total for F

    Unit Quantity

    Total (A + B)

    Output per hour = 4.00 cu.m.

    Sub - Total for B

    Name and Capacity

    Sub - Total for A

    No. of Hours Hourly RateDesignation

    Structure Excavation (Solid Rock)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    80/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    81/547

    Item No./Description : 103(2)a Bridge Excavation (Common Soi l)

    Unit of Measurement : cu.m.

    Output per hour : 20.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    1 1 79.70

    2 1 61.44

    B. Equipment

    b. Backhoe (0.80 cu.m.) 1 1 1,537.00

    b. Dump Truck (10 cu.m.) 2 1 1,352.00

    Minor Tools (10% of Labor)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Unit

    Sub - Total for A

    No. of Hours

    No of UnitsName and Capacity

    Unit Cost

    Sub - Total for F

    Name and Specification Quantity

    No. of Hours

    Output per hour = 20.00 cu.m.

    Sub - Total for B

    Hourly Rate

    Total (A + B)

    Hourly RateNo. of Person

    b. Skilled Laborer

    c. Laborer

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Designation

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    82/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    83/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    84/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    85/547

    Item No./Description : 103(2)c Bridge Excavation (Sol id Rock)

    Unit of Measurement : cu.m.

    Output per hour : 4.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    1 1 79.70

    2 1 61.44

    B. Equipment

    a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00

    b. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95

    c. Dump Truck (10 cu.m.) 1 1 1,352.00

    Minor Tools (10% of Labor)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Output per hour = 4.00 cu.m.

    Designation

    Hourly Rate

    Total (A + B)

    Sub - Total for F

    Unit Quantity Unit Cost

    Sub - Total for B

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    b. Skilled Laborer

    No of UnitsName and Capacity

    Name and Specification

    c. Laborer

    Sub - Total for A

    No. of Person No. of Hours Hourly Rate

    No. of Hours

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    86/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    87/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    88/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    89/547

    Item No./Description : 103(4) Excavation ordered below Plan Elevation

    Unit of Measurement : cu.m.

    Output per hour : 20.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    3 1 61.44

    B. Equipment

    a. Dump Truck (10 cu.m.) 2 1 1,352.00

    b. Backhoe (0.80 cu.m.) 1 1 1,537.00

    Minor Tools (10% of Labor)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Total (A + B)

    No. of Person

    Sub - Total for A

    Output per hour = 20.00 cu.m.

    No. of Hours

    Unit Quantity

    Sub - Total for B

    No. of Hours

    Name and Specification

    Sub - Total for F

    Hourly Rate

    Hourly Rate

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Designation

    Unit Cost

    Name and Capacity No of Units

    b. Laborer

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    90/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    91/547

    Item No./Description : 103(5)a Shoring

    Unit of Measurement : l.s.

    Output : 1.00

    A. Labor

    Note:

    B. Equipment

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials/Processed Component Pay Item

    a. 404 - Reinforcing Steel Bar kg. *

    b. 405 - Structural Concrete cu.m. *

    c. 509 - Steel Sheet Pile l.m. *

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    **) Costing of this item shall be based on the standard Detailed Unit Price Analysis (DUPA) of item 404/405

    as processed component pay item.

    Direct Unit

    Cost

    Output = 1.00 l.s.

    Sub - Total for A

    Sub - Total for BTotal (A + B)

    Hourly Rate

    *) The component quantity of items of work involved such as item 404/405/509 shall be based on the

    Sub - Total for F

    actual design of the shoring.

    Name and Specification Unit Quantity

    Hourly RateNo. of Hours

    No. of Person No. of Hours

    Name and Capacity

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Designation

    No of Units

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    92/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    93/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    94/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    95/547

    Item No./Description : 104(1)a

    Unit of Measurement : cu.m.

    Output per hour : 50.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 2 1 61.44

    B. Equipment

    a. Motorized Road Grader, G710A 1 1 2,173.00

    b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00

    c. Water Truck (1000 gal.) 1 0.25 1,065.00

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Common Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 400.00

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    No. of Hours

    Output per hour = 50.00 cu.m.

    Sub - Total for F

    Total (A + B)

    Sub - Total for A

    Name and Specification Unit Quantity Unit Cost

    Sub - Total for B

    No. of Hours

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Name and Capacity No of Units

    Designation No. of Person

    Embankment (from Borrow)

    Hourly Rate

    Hourly Rate

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    96/547

    Item No./Description : 104(1)b Embankment from Roadway Excavation

    Unit of Measurement : cu.m.

    Output per hour : 50.00

    A. Labor

    For Excavation Work:

    a. Construction Foreman 1 0.83 109.19

    2 0.83 61.44

    Spreading and Compaction:

    a. Construction Foreman 1 1 109.19

    b. Laborer 2 1 61.44

    B. Equipment

    For Excavation Work:a. Bulldozer (155 Hp), D65A-8 1 0.83 2,299.00

    b. Payloader (1.50 cu.m.) 1 0.83 1,733.00

    c. Dump Truck (10 cu.m.) 2 0.83 1,352.00

    Spreading and Compaction:

    a. Motorized Road Grader, G710A 1 1 2,173.00

    b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00

    c. Water Truck (1000 gal.) 1 0.25 1,065.00

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Name and Specification

    Sub - Total for F

    Sub - Total for BTotal (A + B)

    Output per hour = 50.00 cu.m.

    Hourly Rate

    Unit CostUnit Quantity

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Designation No. of Person No. of Hours Hourly Rate

    Sub - Total for A

    Name and Capacity No of Units No. of Hours

    b. Laborer

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    97/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    98/547

    Item No./Description : 104(3) Selected Borrow for topping , case 2

    Unit of Measurement : cu.m.

    Output per hour : 50.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    2 1 61.44

    B. Equipment

    a. Motorized Road Grader, G710A 1 1 2,173.00

    b. Vibratory Roller (10 m.t.) 1 1 1,507.00

    c. Water Truck (1000 gal.) 1 0.25 1,065.00

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Selected Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 420.00

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Sub - Total for F

    No of Units

    Sub - Total for BTotal (A + B)

    Name and Specification Unit Quantity Unit Cost

    No. of Hours Hourly Rate

    No. of Hours Hourly Rate

    Output per hour = 50.00 cu.m.

    Sub - Total for A

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Name and Capacity

    b. Laborer

    No. of PersonDesignation

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    99/547

    Item No./Description : 104(4) Earth Berm

    Unit of Measurement : cu.m.

    Output per hour : 1.25

    A. Labor

    a. Construction Foreman 1 1 109.19

    4 1 61.44

    B. Equipment

    a. Plate Compactor (5 Hp) 1 1 123.00

    b. Water Truck (1000 gal.) 1 0.01 1,065.00

    Minor Tools (10% of Labor)

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Filling Materials cu.m. 1.25 420.00

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    No of Units No. of Hours Hourly Rate

    Sub - Total for B

    Sub - Total for F

    No. of Hours Hourly Rate

    Name and Specification Unit Quantity Unit Cost

    Total (A + B)

    Output per hour = 1.25 cu.m.

    b. Laborer

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Designation

    Sub - Total for A

    Name and Capacity

    No. of Person

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    100/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    101/547

    Item No./Description : 105(2)

    Unit of Measurement : sq.m.

    Output per hour : 300.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 2 1 61.44

    B. Equipment

    a. Motorized Road Grader, G710A 1 1 2,173.00

    b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00

    c. Water Truck (1000 gal.) 1 0.25 1,065.00

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Sub - Total for F

    Sub - Total for BTotal (A + B)

    Output per hour = 300.00 sq.m.

    No of Units No. of Hours

    Name and Specification Unit Quantity

    Sub - Total for A

    Name and Capacity

    Unit Cost

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Subgrade Preparation (Existing Pavement)

    Hourly Rate

    Designation No. of Person No. of Hours Hourly Rate

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    102/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    103/547

    109.19

    122.88

    232.07

    2,299.00

    1,733.00

    519.90

    4,056.00

    1,537.00

    10,144.90

    10,376.97

    129.71

    0.00

    129.71

    11.67

    10.38

    18.21

    169.97

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    104/547

    109.19

    122.88

    232.07

    2,758.80

    1,733.00

    433.25

    2,704.00

    2,074.95

    9,704.009,936.07

    177.43

    0.00

    177.43

    15.97

    14.19

    24.91

    232.50

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    105/547

    109.19

    122.88

    232.07

    2,758.80

    1,733.00

    346.60

    2,704.00

    7,542.40

    7,774.47

    185.11

    0.00

    185.11

    16.66

    14.81

    25.99

    242.56

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    106/547

    109.19

    159.4

    245.76

    109.19

    79.7

    122.88

    109.19

    122.88

    1,058.19

    384.25

    433.25

    86.65

    676.00

    1,028.62

    358.00

    2,966.77

    4,024.96

    402.50

    112.00

    160.00

    39.00

    15.00

    13.50

    4.00

    343.50

    746.00

    67.14

    59.68

    104.74

    977.55

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    107/547

    436.76

    318.8

    491.52

    163.785

    119.55

    184.32

    109.19

    61.44

    1,885.37

    768.50

    405.60

    4,114.48

    1,432.00

    259.95

    51.99

    7,032.52

    8,917.89

    1,371.98

    868.00

    184.00

    806.00

    112.50

    22.50

    6.00

    1,999.00

    3,370.98

    303.39

    269.68

    473.29

    4,417.34

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    108/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    109/547

    191.70

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    110/547

    109.19

    184.32

    293.51

    2,704.00

    1,537.00

    29.35

    4,270.35

    4,563.86

    228.19

    0.00

    228.19

    20.54

    18.26

    32.04

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    111/547

    299.02

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    112/547

    109.19

    184.32

    293.51

    2,704.00

    768.50

    1,037.48

    29.35

    4,539.33

    4,832.84

    345.20

    0.00

    345.20

    31.07

    27.62

    48.47

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    113/547

    452.35

    109.19

    184.32

    293.51

    1,352.00

    768.50

    1,037.48

    29.35

    3,187.333,480.84

    870.21

    0.00

    870.21

    78.32

    69.62

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    114/547

    122.18

    1,140.32

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    115/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    116/547

    300.34

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    117/547

    109.19

    79.70

    122.88

    311.77

    768.50

    1,037.48

    2,704.00

    31.18

    4,541.15

    4,852.92

    346.64

    0.00

    346.64

    31.20

    27.73

    48.67

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    118/547

    454.23

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    119/547

    109.19

    79.70

    122.88

    311.77

    768.50

    1,037.48

    1,352.00

    31.18

    3,189.15

    3,500.92

    875.23

    0.00

    875.23

    78.77

    70.02

    122.88

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    120/547

    1,146.90

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    121/547

    109.19

    245.76

    354.95

    123.00

    10.65

    35.50

    169.15

    524.10

    419.28

    534.75

    534.75

    954.03

    85.86

    76.32

    133.95

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    122/547

    1,250.16

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    123/547

    109.19

    184.32

    293.51

    2,704.00

    1,537.00

    29.35

    4,270.35

    4,563.86

    228.19

    0.00

    228.19

    20.54

    18.26

    32.04

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    124/547

    299.02

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    125/547

    /509

    Amount

    Amount

    Direct Cost

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    126/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    127/547

    14,740.65

    21,519.00

    33,177.60

    69,437.25

    233,415.00

    243,000.00

    13,196.25

    1,533.94

    35,943.75

    527,088.94

    596,526.19

    596,526.19

    2,488,320.00

    351,540.96

    28,398.61

    2,868,259.57

    3,464,785.76

    311,830.72

    277,182.86

    486,455.92

    4,540,255.26

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    128/547

    109.19

    184.32

    293.51

    2,704.00

    1,537.00

    29.35

    4,270.35

    4,563.86

    228.19

    0.00

    228.19

    20.54

    18.26

    32.04

    299.02

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    129/547

    109.19

    122.88

    232.07

    2,173.00

    1,507.00

    266.25

    3,946.25

    4,178.32

    83.57

    500.00

    500.00

    583.57

    52.52

    46.69

    81.93

    764.71

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    130/547

    90.63

    101.99

    109.19

    122.88

    424.69

    1,908.17

    1,438.39

    2,244.32

    2,173.00

    1,507.00

    266.25

    9,537.13

    9,961.82

    199.24

    0.00

    199.24

    17.93

    15.94

    27.97

    261.08

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    131/547

    109.19

    122.88

    232.07

    2,173.00

    1,507.00

    266.25

    3,946.25

    4,178.32

    83.57

    525.00

    525.00

    608.57

    54.77

    48.69

    85.44

    797.47

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    132/547

    109.19

    122.88

    232.07

    2,173.00

    1,507.00

    266.25

    3,946.25

    4,178.32

    83.57

    525.00

    525.00

    608.57

    54.77

    48.69

    85.44

    797.47

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    133/547

    109.19

    245.76

    354.95

    123.00

    10.65

    35.50

    169.15

    524.10

    419.28

    525.00

    525.00

    944.28

    84.98

    75.54

    132.58

    1,237.38

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    134/547

    109.19

    122.88

    232.07

    2,173.00

    1,507.00

    266.25

    3,946.25

    4,178.32

    13.93

    0.00

    13.93

    1.25

    1.11

    1.96

    18.25

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    135/547

    109.19

    122.88

    232.07

    2,173.00

    1,507.00

    266.25

    3,946.25

    4,178.32

    13.93

    0.00

    13.93

    1.25

    1.11

    1.96

    18.25

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    136/547

    109.19

    122.88

    232.07

    2,173.00

    1,507.00

    266.25

    3,946.25

    4,178.32

    13.93

    0.00

    13.93

    1.25

    1.11

    1.96

    18.25

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    137/547

    Item No./Description : 200

    Unit of Measurement : cu.m

    Output per hour : 50.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborers 2 1 61.44

    B. Equipment

    a. Motorized Road Grader, G710A 1 1 2,173.00

    b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00

    c. Water Truck (1000 gal.) 1 0.25 1,065.00

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Aggregate Subbase Course cu.m. 1.15 580.00

    (w/ 15% Shrinkage Factor)

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    Output per hour = 50.00 cu.m.

    Name and Specification

    No. of Hours

    Total (A + B)

    No. of Person

    Sub - Total for A

    Hourly Rate

    Unit Cost

    Sub - Total for F

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Aggregate Subbase Course

    Designation

    Quantity

    Sub - Total for B

    Name and Capacity No of Units No. of Hours Hourly Rate

    Unit

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    138/547

    I tem No./Description : 200(1) Aggregate Subbase Course (for Intermittent Reblocking)

    Unit of Measurement : cu.m

    Output per hour : 40.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborers 2 1 61.44

    B. Equipment

    a. Motorized Road Grader, G710A 1 1 2,173.00

    b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00

    c. Plate Compactor (5 Hp) 1 0.25 123.00

    d. Water Truck (1000 gal.) 1 0.25 1,065.00

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Aggregate Subbase Course cu.m. 1.15 580.00

    (w/ 15% Shrinkage Factor)

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Total (A + B)

    Output per hour = 40.00 cu.m.

    Name and Specification

    Sub - Total for F

    Sub - Total for B

    Unit Quantity Unit Cost

    Hourly RateName and Capacity No of Units No. of Hours

    Sub - Total for A

    Designation No. of Person No. of Hours

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Hourly Rate

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    139/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    140/547

    Item No./Description : 201

    Unit of Measurement : cu.m

    Output per hour : 50.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborers 2 1 61.44

    B. Equipment

    a. Motorized Road Grader, G710A 1 1 2,173.00

    b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00

    c. Water Truck (1000 gal.) 1 0.25 1,065.00

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Aggregate Base Course cu.m. 1.15 650.00

    (w/ 15% Shrinkage Factor)

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Sub - Total for F

    Sub - Total for BTotal (A + B)

    Output per hour = 50.00 cu.m.

    Designation No. of Person No. of Hours Hourly Rate

    Sub - Total for A

    Name and Capacity No of Units No. of Hours

    Aggregate Base Course

    Name and Specification Unit Quantity Unit Cost

    Hourly Rate

    DETAILED UNIT PRICE ANALYSIS (DUPA)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    141/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    142/547

    Item No./Description : 201(1)

    Unit of Measurement : cu.m

    Output per hour : 40.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborers 2 1 61.44

    B. Equipment

    a. Motorized Road Grader, G710A 1 1 2,173.00

    b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00

    c. Plate Compactor (5 Hp) 1 0.25 123.00

    d. Water Truck (1000 gal.) 1 0.25 1,065.00

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Aggregate Base Course cu.m. 1.15 650.00

    (w/ 15% Shrinkage Factor)

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Total (A + B)

    Unit Cost

    Sub - Total for F

    Output per hour = 40.00 cu.m.

    Name and Specification Unit Quantity

    Name and Capacity No of Units No. of Hours

    No. of Hours Hourly Rate

    Sub - Total for A

    Hourly Rate

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Aggregate Base Course (for Reblocking)

    Sub - Total for B

    Designation No. of Person

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    143/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    144/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    145/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    146/547

    109.19

    122.88

    232.07

    2,173.00

    1,507.00

    266.25

    3,946.25

    4,178.32

    83.57

    667.00

    667.00

    750.57

    67.55

    60.05

    105.38

    983.54

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    147/547

    109.19

    122.88

    232.07

    2,173.00

    1,507.00

    30.75

    266.25

    3,977.00

    4,209.07

    105.23

    667.00

    667.00

    772.23

    69.50

    61.78

    108.42

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    148/547

    1,011.93

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    149/547

    109.19

    122.88

    232.07

    2,173.00

    1,507.00

    266.25

    3,946.25

    4,178.32

    83.57

    747.50

    747.50

    831.07

    74.80

    66.49

    116.68

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    150/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    151/547

    109.19

    122.88

    232.07

    2,173.00

    1,507.00

    30.75

    266.25

    3,977.00

    4,209.07

    105.23

    747.50

    747.50

    852.73

    76.75

    68.22

    119.72

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    152/547

    1,117.41

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    153/547

    109.19

    122.88

    232.07

    2,173.00

    1,507.00

    266.25

    3,946.25

    4,178.32

    83.57

    805.00

    805.00

    888.57

    79.97

    71.09

    124.75

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    154/547

    1,164.38

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    155/547

    Item No./Description : 203

    Unit of Measurement : cu.m.

    Output per hour : 15.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 10 1 61.44

    B. Equipment

    a. Motorized Road Grader (140 Hp) 1 1 2,173.00

    b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00

    c. Water Truck (1000 gal.) 1 0.25 1,065.00

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Hydrated Lime, Type N (Normal) bag 2.80 180.00

    b. Aggregate Base Course cu.m. 1.15 650.00

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    K. Total Unit Cost (G + H + I + J)

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Lime Stabilized Road Mix Base Course

    Designation No. of Person No. of Hours Hourly Rate

    Hourly Rate

    Sub - Total for BTotal (A + B)

    Output per hour = 15.00 cu.m.

    Name and Specification

    Sub - Total for F

    Unit Quantity Unit Cost

    Sub - Total for A

    No of Units No. of HoursName and Capacity

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    156/547

    Item No./Description : 204

    Unit of Measurement : cu.m.

    Output per hour : 15.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 10 1 61.44

    B. Equipment

    a. Motorized Road Grader (140 Hp) 1 1 2,173.00

    b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00

    c. Water Truck (1000 gal.) 1 0.25 1,065.00

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Cement bag 3 220.00

    b. Aggregate Base Course cu.m. 1.15 650.00

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Name and Specification Unit Unit Cost

    Sub - Total for F

    Quantity

    Output per hour = 15.00 cu.m.

    Sub - Total for B

    No. of Hours Hourly Rate

    Hourly RateNo. of Person

    No of Units

    Total (A + B)

    No. of Hours

    Sub - Total for A

    Designation

    Name and Capacity

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Portland Cement Stabilized Road Mix Base Course

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    157/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    158/547

    Item No./Description : 205

    Unit of Measurement : cu.m.

    Output per hour : 15.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 10 1 61.44

    B. Equipment

    a. Motorized Road Grader (140 Hp) 1 1 2,173.00

    b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00

    c. Water Truck (1000 gal.) 1 0.25 1,065.00

    d. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Emulsified Asphalt SS-1 m.t. 0.07 44,000.00

    b. Aggregate Base Course cu.m. 1.15 650.00

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Unit Cost

    Sub - Total for F

    Total (A + B)

    Output per hour = 15.00 cu.m.

    Unit QuantityName and Specification

    No. of Hours

    Sub - Total for B

    No. of Hours Hourly Rate

    Sub - Total for A

    Hourly Rate

    No. of Person

    Name and Capacity No of Units

    Designation

    Asphalt Stabilized Road Mix Base Course

    DETAILED UNIT PRICE ANALYSIS (DUPA)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    159/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    160/547

    Item No./Description : 206

    Unit of Measurement : cu.m.

    Output per hour : 15.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    2 1 79.70

    4 1 61.44

    B. Equipment

    a. Batching Plant (30 cu.m.) 1 0.50 1,208.03

    b. Dump Truck (10 cu.m.) 3 0.50 1,352.00

    c. Motorized Road Grader, G710A 1 0.50 2,173.00

    d. Vibratory Roller (10 m.t.), SP56 1 0.50 1,507.00

    e. Payloader (1.50 cu.m.), LX80-2C 1 0.50 1,733.00

    f. Water Truck (1000 gal.) 1 0.25 1,065.00

    g. Asphalt Distributor, 10 ft. wide (5 tons) 1 0.10 936.00

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Cement bag 3 220.00

    b. Aggregate Base Course cu.m. 1.15 650.00

    c. MC 70 Cut-back Asphalt m.t. 0.0075 40,300.00

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Name and Specification

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    No. of Person No. of Hours Hourly Rate

    Unit Quantity Unit Cost

    Sub - Total for F

    Total (A + B)

    Output per hour = 15.00 cu.m.

    No of Units No. of Hours Hourly Rate

    Sub - Total for B

    Sub - Total for A

    Name and Capacity

    Portland Cement Treated Plant Mix Base Course

    b. Skilled Laborer

    c. Laborer

    Designation

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    161/547

    K. Total Unit Cost (G + H + I + J)

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    162/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    163/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    164/547

    109.19

    614.40

    723.59

    2,173.00

    1,507.00

    266.25

    3,946.25

    4,669.84

    311.32

    504.00

    747.50

    1,251.50

    1,562.82

    140.65

    125.03

    219.42

    2,047.92

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    165/547

    109.19

    614.40

    723.59

    2,173.00

    1,507.00

    266.25

    3,946.25

    4,669.84

    311.32

    660.00

    747.50

    1,407.50

    1,718.82

    154.69

    137.51

    241.32

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    166/547

    2,252.35

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    167/547

    109.19

    614.40

    723.59

    2,173.00

    1,507.00

    266.25

    936.00

    4,882.25

    5,605.84

    373.72

    3,080.00

    747.50

    3,827.50

    4,201.22

    378.11

    336.10

    589.85

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    168/547

    5,505.28

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    169/547

    109.19

    159.40

    245.76

    514.35

    604.02

    2,028.00

    1,086.50

    753.50

    866.50

    266.25

    93.60

    5,698.37

    6,212.72

    414.18

    660.00

    747.50

    302.25

    1,709.75

    2,123.93

    191.15

    169.91

    298.20

    Amount

    Amount

    Amount

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    170/547

    2,783.20

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    171/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    172/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    173/547

    Item No./Description : 300(1)

    Unit of Measurement : cu.m

    Output per hour : 50.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 2 1 61.44

    B. Equipment

    a. Motorized Road Grader, G710A 1 1 2,173.00

    b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00

    c. Water Truck (1000 gal.), All Make 1 0.25 1,065.00

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Uncrushed Aggregate Surface Course cu.m. 1.15 700.00

    (w/ 15% Shrinkage Factor)

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Sub - Total for B

    Unit CostQuantityName and Specification

    Sub - Total for A

    Sub - Total for F

    Total (A + B)

    Output per hour = 50.00 cu.m.

    Designation No. of Person No. of Hours Hourly Rate

    No of Units No. of Hours Hourly Rate

    Unit

    Name and Capacity

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Gravel Surface Course (Uncrushed)

    1762

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    174/547

    K. Total Unit Cost (G + H + I + J)

    5485

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    175/547

    Item No./Description : 300(2)

    Unit of Measurement : cu.m

    Output per hour : 50.00

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 2 1 61.44

    B. Equipment

    a. Motorized Road Grader, G710A 1 1 2,173.00

    b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00

    c. Water Truck (1000 gal.), All Make 1 0.25 1,065.00

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. Crushed Aggregate Surface Course cu.m. 1.15 750.00

    (w/ 15% Shrinkage Factor)

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Hourly Rate

    Sub - Total for A

    No of Units No. of Hours

    Sub - Total for F

    Unit Cost

    Name and Capacity

    Total (A + B)

    Output per hour = 50.00 cu.m.

    Name and Specification Unit Quantity

    Sub - Total for B

    Designation No. of Person No. of Hours Hourly Rate

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Crushed Aggregate Surface Course

    1782

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    176/547

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    177/547

    Item No./Description : 301(1)

    Unit of Measurement : m.t.

    Output per hour : 0.30

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 3 1 61.44

    B. Equipment

    a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00

    b. Power Broom (20 m. wide) 1 1 130.54

    C.

    D.

    E. Direct Unit Cost (C D)

    F. Materials

    a. MC 70 Cut-back Asphalt m.t. 1.05 40,300.00

    (w/ 5% wastage)

    G. Direct Unit Cost (E + F)

    H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G

    I. Contractor's Profit (CP) 8% of G

    J. Value Added Tax (VAT) 12% of (G + H + I)

    Unit

    Sub - Total for F

    Total (A + B)

    Name and Specification Quantity

    Sub - Total for A

    Sub - Total for B

    No. of Hours Hourly Rate

    Name and Capacity No of Units No. of Hours Hourly Rate

    DETAILED UNIT PRICE ANALYSIS (DUPA)

    Designation No. of Person

    Bituminous Prime Coat (MC Cut-back Asphalt)

    Unit Cost

    Output per hour = 0.30 m.t.

    1802

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    178/547

    K. Total Unit Cost (G + H + I + J)

    5485

  • 8/11/2019 Cost Sheets (Road Construction) DUPA

    179/547

    Item No./Description : 301(2)

    Unit of Measurement : m.t.

    Output per hour : 0.30

    A. Labor

    a. Construction Foreman 1 1 109.19

    b. Laborer 3 1 61.44

    B. Equipment

    a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00

    b. Power Broo