HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Welcome to this presentation. It explains how the investment cost for an Oil & Gas facility is
estimated. After a short introduction, the 3 common methods of cost
estimate are shown. Common ratios, such as $/kg for equipment, pipe etc. are given. Please download this file so that you can see my trainers notes in
the top left corner latest Acrobat Pro feature. Herv
Cost estimate of Oil & gas facilities
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Cost estimate of Oil & gas facilities
Place your mouse over here
Please download this file to access my notes in the top left corner
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Please download this file to access my notes in the top left corner
Cost estimate of Oil & gas facilities
Place your mouse over here
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Agenda Introduction The different estimation methods: Capacity factored Equipment factored Analytical
Cost estimate of Oil & gas facilities
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
What will be the overall cost of this facility?
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Cost = Quantities * item costs
How would you determine quantities?
All items
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Quantities estimates:
Ratio from past projects
Material Take-Off
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Cost = Quantities * item costs
How would you determine quantities?
What is an item cost made of?
All items
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Item cost = Supply cost + installation cost
How would you each one?
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Item cost estimates:
Supply + installation
In-house data from past projects
Inquiries
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Item cost estimates:
Supply + installation
In-house data from past projects
Inquiries
Sensitivity to:
Raw materials
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Item cost estimates:
Supply + installation
In-house data from past projects
Inquiries
Sensitivity to:
Raw materials
Steel, alloy steel, copper, cement, iron
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Item cost estimates:
Supply + installation
In-house data from past projects
Inquiries
Sensitivity to:
Raw materials
Construction market
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Sensitivity to:
Raw materials
Construction market
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Purpose of estimate: Concept screening Study of feasibility Decision to invest Estimate type: Capacity factored Equipment factored Analytical
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Purpose of estimate: Concept screening Study of feasibility Decision to invest Estimate type: Capacity factored Equipment factored Analytical
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Capacity factored C1/C2 = (P1/P2)e e ~ 0.6 Ci: Cost of facility with production capacity Pi
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Capacity factored C1/C2 = (P1/P2)e e ~ 0.6 Ci: Cost of facility with production capacity Pi
Exercise: what is the increase in cost for +50% capacity increase?
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Exercise: what is the increase in cost for +50% capacity increase? In your opinion, what is the limit of such estimate?
Capacity factored C1/C2 = (P1/P2)e e ~ 0.6 Ci: Cost of facility with production capacity Pi
PrsentateurCommentaires de prsentationDoes not take into account market conditions
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Exercise: what is the increase in cost for +50% capacity increase? In your opinion, what is the limit of such estimate? It takes into account neither market conditions nor plant location (labour cost)
Capacity factored C1/C2 = (P1/P2)e e ~ 0.6 Ci: Cost of facility with production capacity Pi
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Equipment factored C = f M C: total installed cost of facility M: cost of main equipment f: factor
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Equipment factored C = f M C: total installed cost of facility M: cost of main equipment f: factor Note: Typical figures for Petrochemical Plant
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Whats the main equipment?
Equipment factored C = f M C: total installed cost of facility M: cost of main equipment f: factor
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
How is the cost of main equipment evaluated?
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Process design
PFDs
H&M balance
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Equipment factored C = f M f: factor f depends on
type of facility (petrochemical, refining, LNG, off-shore) Size
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Equipment factored C = f M f: factor f depends on
type of facility (petrochemical, refining, LNG, off-shore) Size
Typical figures for a chemical plant
In your opinion, how can we refine the estimate?
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Equipment factored C = fi Mi Mi Cost of all type i Main equipment fi: factor
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Equipment factored C = fi Mi Mi Cost of all type i Main equipment fi: factor Why do you think justifies such an approach?
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Equipment factored C = fi Mi Mi Cost of all type i Main equipment fi: factor Why do you think justifies such an approach?
PrsentateurCommentaires de prsentationStandard arrengements
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Equipment factored C = fi Mi Mi Cost of all type I Main equipment fi: factor
In your opinion, what is the limit of such estimate?
PrsentateurCommentaires de prsentationIncorporates market conditions for supply only, not for labour no localization
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Analytical Main equipment supply + install Piping supply + install Electrical supply + install Instrumentation & Control system supply + install Civil Works Steel structures Painting, Insulation Temporary construction facilities Engineering & Project Management Miscellaneous
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Analytical Establish the bill of quantities (BOQ) in each trade: equipment,
civil, piping, structural steel etc. BOQ = Material Take-Off (what is measured from available
drawings at this stage) + allowances for design development + allowances for what is not yet on drawings + contingencies
Apply ratios to get supply + installation cost Installation cost = qty * manhours/ton ratio * labour cost Labour cost is all in, i.e., includes construction equipment (crane,
scaffolding) The ratio is based on standard manhours, i.e., home country, Localization factor (productivity) to be applied, i.e., actual
installation manhours = ratio * productivity Example: piping installation cost, ratio: 250 std h / ton
Western Europe, labour cost $100/hr yields $20k/ton Middle East, labour cost $18/hr, productivity 2.5 yeilds $16k/ton
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Analytical Main equipment supply + install Piping supply + install Electrical supply + install Instrumentation & Control system supply + install Civil Works Steel structures Painting, Insulation Temporary construction facilities Engineering & Project Management Miscellaneous
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Main equipment supply + install Supply
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Main equipment supply + install Supply: eqt list (dimensions) => weight
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Process design
PFDs
H&M balance
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Main equipment supply + install Supply: eqt list (dimensions) => weight Rate?
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Main equipment supply + install Supply: eqt list (dimensions) => weight Rate:
USD 4/kg for CS depends on eqt size: 4 (large) 10 (small) USD12/kg for SS USD 300-500 /m2 for Shell&Tube / Air-coolers USD 1000/kW for pumps
Important note: the above ratios and the following ones - are the ones obtained by large EPC Contractors ordering large quantities (USD 1bln jobs). Higher ratios must be used on smaller jobs!
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Main equipment supply + install Supply: eqt list, dimensions/capacity/weight Installation
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Main equipment supply + install Supply: eqt list, dimensions/capacity/weight Installation ratios: % supply cost, typ. 8%
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Main equipment supply + install Supply: eqt list, dimensions/capacity/weight Installation ratios: % supply cost, typ. 8%
30 std manhours/ton (includes labour and equipment)
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Analytical Main equipment supply + install Piping supply + install Electrical supply + install Instrumentation & Control system supply + install Civil Works Steel structures Painting, Insulation Temporary construction facilities Engineering & Project Management Miscellaneous
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Piping supply + install Qty: ratio (eqt weight), typ. 40%
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Piping supply + install Qty: ratio f (eqt number)
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Piping supply + install Qty: ratio f (eqt number)
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Piping supply + install Qty: ratio f (eqt number)
Remark: Unit vs Interconnection
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Piping supply + install Qty: ratio (eqt number, eqt weight)
MTO
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Process design
PFDs
H&M balance
P&IDs
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
PFDs
H&M balance P&IDs
Process design
Plot Plan
Equipment list
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
P&IDs
Plot Plan
Piping Layout
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
A unique synthesis for the busy Project professional 270 pages 300 illustrations
For more information on Engineering, refer to:
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
For more information on Engineering, refer to:
Table of Contents
-
HERVE BARON
The Oil & Gas Engineering Guide 2nd edition
Order direct on the publisher website:
http://www.editionstechnip.com/en/catalogue-detail/1111/oil-gas-engineering-guide-the.html
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Piping supply + install Qty: MTO
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Piping supply + install Qty: MTO
Item count: P&IDs Lengths: Piping Layout
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Piping supply + install Qty: MTO
Item count: P&IDs Lengths: Piping Layout Both Process & Utility lines Both Above Ground & Underground lines, Fire water
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Piping supply + install Qty: MTO
Item count: P&IDs Lengths: Piping Layout Both Process & Utility lines Both Above Ground & Underground lines, Fire water Allowances added for:
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Piping supply + install Qty: MTO
Item count: P&IDs Lengths: Piping Layout Both Process & Utility lines Both Above Ground & Underground lines Allowances added for: what is not taken-off, e.g., small diameter and design
development (P&ID completion) to obtain quantities to erect
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Piping supply + install Qty: MTO
Item count: P&IDs Lengths: Piping Layout Both Process & Utility lines Both Above Ground & Underground lines Allowances added for: what is not taken-off, e.g., small diameter and design
development (P&ID completion) to obtain quantities to erect
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Piping supply + install Qty: MTO
Item count: P&IDs Lengths: Piping Layout Both Process & Utility lines Both Above Ground & Underground lines Allowances added for: what is not taken-off, e.g., small diameter and design
development (P&ID completion) to obtain quantities to erect
cut and losses to obtain quantities to be supplied
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Piping supply + install Qty: ratio (eqt number, eqt weight) MTO Rate Supply
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Piping supply + install Qty: ratio (eqt number, eqt weight) MTO Rate Supply $ /kg, typ. USD 3 /kg for CS
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Piping supply + install Qty: ratio (eqt number, eqt weight) MTO Rate Supply $ /kg, typ. USD 3 /kg for CS
Install
PrsentateurCommentaires de prsentationAnswer: 200*2.5*16 = $ 8000 / ton
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Piping supply + install Qty: ratio (eqt number, eqt weight) MTO Rate Supply $ /kg, typ. USD 3 /kg for CS
Install std mhrs/ton, typ. 200-250 in unit, 100 on interconnecting pipe-racks, applied to the total piping weight, including fittings & valves.
PrsentateurCommentaires de prsentationAnswer: 200*2.5*16 = $ 8000 / ton
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Electrical supply + install Price ratio % Main equipment, typ. 15-20%
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Electrical supply + install Price ratio % Main equipment, typ. 15-20% Quantities: Consumers list Rate (supply+install): USD 50k / consumer (w/o
generation) USD 520 / installed kW
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Plot Plan
Single Line Diagram Consumers list
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Plot Plan
Single Line Diagram Consumers list
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Instrumentation & Control system supply + install Price ratio % Main equipment, range: 40-120%
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Instrumentation & Control system supply + install Price ratio % Main equipment, range: 40-120% Qties
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Instrumentation & Control system supply + install Price ratio % Main equipment, range: 40-120% Qties nb equiv. loops (CV, 0.5 ON/OFF, Analyser)
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Instrumentation & Control system supply + install Price ratio % Main equipment, range: 40-120% Qties nb equiv. loops (CV, 0.5 ON/OFF, Analyser) Rate
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Instrumentation & Control system supply + install Price ratio % Main equipment, range: 40-120% Qties nb equiv. loops (CV, 0.5 ON/OFF, Analyser) Rate supply: $ /equivalent control loops, typ. 90k
install: hrs / equivalent control loops, typ. 750
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Instrumentation & Control system supply + install Price ratio % Main equipment, range: 40-120% Qties Instrument list
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Instrumentation & Control system supply + install Price ratio % Main equipment, range: 40-120% Qties Instrument list Rate Supply+install: $ / I/O, typ. 1000
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Civil Works Price Ratio % Main equipment cost, typ. 15-20%
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Civil Works Price Ratio % Main equipment cost, typ. 15-20% Qty
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Civil Works Price Ratio % Main equipment cost, typ. 15-20% Qty Dimensions/Weight of equipment &
structure => size of foundations (m3)
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Civil Works Price Ratio % Main equipment cost, typ. 15-20% Qty Dimensions/Weight of equipment &
structure => size of foundations (m3) Rate
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Civil Works Price Ratio % Main equipment cost, typ. 15-20% Qty Dimensions/Weight of equipment &
structure => size of foundations (m3) Rate all-in (materials & labour) rate $/m3, typ. 1000
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Civil Works Price Ratio % Main equipment cost, typ. 15-20% Qty MTO: excavation, formwork, rebar, etc.
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Civil Works Price Ratio % Main equipment cost, typ. 15-20% Qty MTO: excavation, formwork, rebar, etc. Rate Mhrs/operation + labour cost
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Steel structures Price Ratio % Main equipment cost, typ. 10-30%
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Steel structures Price Ratio % Main equipment cost, typ. 10-30% Qty Ratio
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Steel structures Price Ratio % Main equipment cost, typ. 10-30% Qty Ratio pipe-racks: 90% of piping weight
platforms: 10% of equipment weight
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Steel structures Price Ratio % Main equipment cost, typ. 10-30% Qty Ratio pipe-racks: 90% of piping weight
platforms: 10% of equipment weight Rate
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Steel structures Price Ratio % Main equipment cost, typ. 10-30% Qty Ratio pipe-racks: 90% of piping weight
platforms: 10% of equipment weight Rate Supply USD 2/kg
Erection 20 std manhours/t
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Analytical Main equipment supply + install Piping supply + install Electrical supply + install Instrumentation & Control system supply + install Civil Works Steel structures Painting, Insulation
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Painting, Insulation Price ratio % eqt, piping, str cost, typ. 5% each
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Painting, Insulation Price ratio % eqt, piping, str cost, typ. 5% each Qty MTO
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Painting, Insulation Price ratio % eqt, piping, str cost, typ. 5% each Qty MTO Rate supply + install h / m2
typ. 0,5 for painting 1,5 for (hot) insul.
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Analytical Main equipment supply + install Piping supply + install Electrical supply + install Instrumentation & Control system supply + install Civil Works Steel structures Painting, Insulation Temporary construction facilities Engineering & Project Management Miscellaneous
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Temporary Construction facilities Ratio % total cost, typ. 5% for new site Detailed
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Analytical Main equipment supply + install Piping supply + install Electrical supply + install Instrumentation & Control system supply + install Civil Works Steel structures Painting, Insulation Temporary construction facilities Engineering & Project Management Miscellaneous
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Engineering & Project Management = all Project services Price ratio % total cost, typ. 15%
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Engineering & Project Management = all Project services
Price ratio % total cost, typ. 15% Qty ratio
PrsentateurCommentaires de prsentationEqt item PA/B counts for 2Hrs exclude field supervision
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Engineering & Project Management = all Project services
Price ratio % total cost, typ. 15% Qty ratio hrs / eqt item, typ. 1800 for Refining,
2500 for gas, 4000 for LNG
PrsentateurCommentaires de prsentationEqt item PA/B counts for 2Hrs exclude field supervision
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Engineering & Project Management = all Project services
Price ratio % total cost, typ. 15% Qty
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Engineering & Project Management = all Project services
Price ratio % total cost, typ. 15% Qty home office: tasks list + std manhours
field supervision: ratio to labour, typ. 1/7
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Analytical Main equipment supply + install Piping supply + install Electrical supply + install Instrumentation & Control system supply + install Civil Works Steel structures Painting, Insulation Temporary construction facilities Engineering & Project Management Miscellaneous Contractors cost
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Miscellaneous Earthworks: always specific Special foundations Infrastructures: roads, buildings Spare parts, typ. 5% main equipment cost First fill (catalyst, lubes, chemicals)
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Analytical Main equipment supply + install Piping supply + install Electrical supply + install Instrumentation & Control system supply + install Civil Works Steel structures Painting, Insulation Temporary construction facilities Engineering & Project Management Miscellaneous Contractors cost
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Contractors cost profit, risks, sales cost,
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Contractors cost profit, typ. 7% risks, sales cost, typ. 10-15%
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Main equipment supply + install Piping supply + install Electrical supply + install Instrumentation & Control system
supply + install Civil Works Steel structures Painting, Insulation Temporary construction facilities Engineering & Project Management Miscellaneous: catalysts etc. Contractors cost
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Main features: Different level of Cost estimate accuracy
Feasibility study +/-30% accuracy Final Investment Decision (FID) +/- 10%
Which of the methods we have seen would you use for each case?
PrsentateurCommentaires de prsentationRatio for +/-30% and detailed (MTO) for +/-10%
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Main concepts: Different level of Cost estimate accuracy Factored / Detailed Qty estimate: allowances for design development Rates:
In-house historical data similar Plant Cost estimate: Contingencies for cost escalation Inquiries + provisions for cost adders (supplies),
additional works/re-works (construction) Direct costs / Indirect costs
PrsentateurCommentaires de prsentationEqt item PA/B counts for 2
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
Historical evolution: + Increased instrumentation & control costs - Engineering low cost centers - Low cost sourcing 20% cheaper - Increase in productivity (3D model) + Additional requirements: safety, environment
-
HERVE BARON Cost estimate of Oil & gas facilities
2013 Herv Baron
A unique synthesis for the busy Project professional 270 pages 300 illustrations
For more information on Engineering, refer to:
-
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition
Discipline presentation: activities and deliverables
Table of Contents
The overall process
Methods & tools
-
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
Discipline presentation: activities and deliverables
-
HERVE BARON
The work of each
Engineering discipline is described
-
HERVE BARON
Design activities are explained, e.g., Plant
Equipment layout
-
HERVE BARON
Complex activities, such as
QRA, are explained through a practical
example.
-
HERVE BARON
How are materials of
construction selected ?
-
HERVE BARON
How and when are Piping
Materials ordered?
-
HERVE BARON
A sample of all common Engineering documents is
included
-
HERVE BARON
A sample of all common Engineering documents is
included
Use this to specify what
you want to your Engineering supplier !
-
HERVE BARON
Verify the contents of
engineering documents with check lists.
-
HERVE BARON
Difference between
Engineering and Shop drawings
-
HERVE BARON
Understand the main
technical aspects, e.g., DCS vs ESD
-
HERVE BARON
The common 2 types of
package control
-
HERVE BARON
The different Plant drainage systems
-
HERVE BARON
The dynamic forces to
which an Off-Shore Plant is subject
-
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
The overall process
-
HERVE BARON
Use this as standard, question deviations.
-
HERVE BARON
Understand the new 3D-model centered engineering process
-
HERVE BARON
Know the interfaces
between disciplines... and with Vendors
-
HERVE BARON
Understand what drives the Project
schedule
-
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
Methods & tools
-
HERVE BARON
Use these methods as
standard, question deviations.
-
HERVE BARON
Implement powerful
procedures
-
HERVE BARON
Request meaningful
progress reports
-
HERVE BARON
Implement effective
Project Control
-
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition
This book is destined to both:
Oil & Gas companies Project execution personnel
Oil & Gas contractors Project execution personnel
-
HERVE BARON
The Oil & Gas Engineering Guide 2nd edition
If your are on the Client side, i.e., contracting Engineering services, this book will help you to:
Specify to an Engineering supplier what you want: what deliverables and with what contents,
Set a standard in Engineering execution that you and your supplier can adhere to: design stages/gates, methods to be used, etc.
Specify the progress report you want, with the meaningful indicators,
Ask the right questions to assess the true progress,
-
HERVE BARON
The Oil & Gas Engineering Guide 2nd edition
If your are on the Contractor side, i.e., performing Engineering activities, this book will help you to:
Understand the work of each discipline and the overall picture,
Challenge what one discipline tells you,
Understand the critical areas,
Put in place the right methods to be successful,
-
HERVE BARON
The Oil & Gas Engineering Guide 2nd edition
Order direct on the publisher website:
http://www.editionstechnip.com/en/catalogue-detail/1111/oil-gas-engineering-guide-the.html
Diapositive numro 1Diapositive numro 2Diapositive numro 3Diapositive numro 4Diapositive numro 5Diapositive numro 6Diapositive numro 7Diapositive numro 8Diapositive numro 9Diapositive numro 10Diapositive numro 11Diapositive numro 12Diapositive numro 13Diapositive numro 14Diapositive numro 15Diapositive numro 16Diapositive numro 17Diapositive numro 18Diapositive numro 19Diapositive numro 20Diapositive numro 21Diapositive numro 22Diapositive numro 23Diapositive numro 24Diapositive numro 25Diapositive numro 26Diapositive numro 27Diapositive numro 28Diapositive numro 29Diapositive numro 30Diapositive numro 31Diapositive numro 32Diapositive numro 33Diapositive numro 34Diapositive numro 35Diapositive numro 36Diapositive numro 37Diapositive numro 38Diapositive numro 39Diapositive numro 40Diapositive numro 41Diapositive numro 42Diapositive numro 43Diapositive numro 44Diapositive numro 45Diapositive numro 46Diapositive numro 47Diapositive numro 48Diapositive numro 49Diapositive numro 50Diapositive numro 51Diapositive numro 52Diapositive numro 53Diapositive numro 54The Oil & Gas Engineering Guide2nd editionDiapositive numro 56Diapositive numro 57Diapositive numro 58Diapositive numro 59Diapositive numro 60Diapositive numro 61Diapositive numro 62Diapositive numro 63Diapositive numro 64Diapositive numro 65Diapositive numro 66Diapositive numro 67Diapositive numro 68Diapositive numro 69Diapositive numro 70Diapositive numro 71Diapositive numro 72Diapositive numro 73Diapositive numro 74Diapositive numro 75Diapositive numro 76Diapositive numro 77Diapositive numro 78Diapositive numro 79Diapositive numro 80Diapositive numro 81Diapositive numro 82Diapositive numro 83Diapositive numro 84Diapositive numro 85Diapositive numro 86Diapositive numro 87Diapositive numro 88Diapositive numro 89Diapositive numro 90Diapositive numro 91Diapositive numro 92Diapositive numro 93Diapositive numro 94Diapositive numro 95Diapositive numro 96Diapositive numro 97Diapositive numro 98Diapositive numro 99Diapositive numro 100Diapositive numro 101Diapositive numro 102Diapositive numro 103Diapositive numro 104Diapositive numro 105Diapositive numro 106Diapositive numro 107Diapositive numro 108Diapositive numro 109Diapositive numro 110Diapositive numro 111The Oil & Gas Engineering Guide - 2nd editionThe Oil & Gas Engineering Guide - 2nd editionDiapositive numro 114Diapositive numro 115Diapositive numro 116Diapositive numro 117Diapositive numro 118Diapositive numro 119Diapositive numro 120Diapositive numro 121Diapositive numro 122Diapositive numro 123Diapositive numro 124Diapositive numro 125Diapositive numro 126The Oil & Gas Engineering Guide - 2nd editionDiapositive numro 128Diapositive numro 129Diapositive numro 130Diapositive numro 131The Oil & Gas Engineering Guide - 2nd editionDiapositive numro 133Diapositive numro 134Diapositive numro 135Diapositive numro 136The Oil & Gas Engineering Guide - 2nd editionThe Oil & Gas Engineering Guide2nd editionThe Oil & Gas Engineering Guide2nd editionThe Oil & Gas Engineering Guide2nd edition