country-wide distributed emergency control systems of the

20
© 2021 SEL Country-Wide Distributed Emergency Control Systems of the Transmission Network in the Republic of Georgia Alexander Didbaridze and Vladimer Korganashvili Georgian State Electrosystem (GSE) Eduardo S. Palma Schweitzer Engineering Laboratories, Inc. (SEL) May 20, 2021

Upload: others

Post on 26-Nov-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

© 2021 SEL

Country-Wide Distributed Emergency Control Systems of the Transmission Network in the Republic of Georgia

Alexander Didbaridze and Vladimer Korganashvili

Georgian State Electrosystem (GSE)

Eduardo S. Palma

Schweitzer Engineering Laboratories, Inc. (SEL)

May 20, 2021

▪ System background

▪ Emergency Control System requirements

▪ Contingencies considered

▪ Distributed vs Centralized

▪ Reliable Communications

▪ The future of GSE’s Emergency Control System

Introduction

Ksani

Akhaltsikhe

Centralnaia

Turkey AzerbaijanArmenia

Russia

500 kV220 kV

Stepantsminda

110 kV

110 kV

330 kV

400 kV

Zestaponi

Marneuli

Georgia

Black

Sea

Enguri

hydro

powerplant

Jvari

BorhkhaAlaverdi

Kartli-2

Imereti

Zekari

Vardzia

Kartli-1

Asureti

Gachiani

Mukhranis Veli

Samukhi

Tbilisi

System Background

“... is the ability of an electric power system, for a given initial operating condition, to regain a state of operating equilibrium after being subjected to a physical disturbance, with most system variables bounded so that practically the entire system remains intact.”

—lEEE / CIGRE Task Force

Power System Stability

Power System Stability

Loads

Demand

Generation

Supply

P

X

VS VR

GSE Power System Instability

X500

VS VR

State 0

PVS VR

X220State 1

P

X500

X220

t

P State 0

180

0 0

State 1

P0

Emergency Control System BenefitsSystem Installed in 2011

*As of April 2021

• Economic and social

• Power system stability

Year Blackouts Brownouts Total

2014 14 11 25

2015 2 16 18

2016 9 15 24

2017 10 8 18

2018 9 15 24

2019 5 13 18

2020 6 34 40

2021* 4 5 9

• N-1 criterion

• Highly probable contingencies (e.g., loss of line)

• Power system studies performed

• Angular instability and overloads

• Coordination with neighboring countries

• Emergency control actions (balancing generation and loadafter contingency)

• Validation through accurate simulation models

Contingencies Considered

Distributed vs. Centralized ArchitectureDistributed

Contingency 1

Logic / Rules

Contingency 2

Logic / Rules

Action

Equipment

Original Emergency Control System

C2C1

Ethernet

Switches

GSC1

LSC1

LSC7

PIme PKr2

Enguri

Zestaponi Ksani

Imereti

To Russia

Kartli-2

Distributed Architecture Details

Component No. Possible Actions

500 kV line 8• Load and generator shedding

HVdc control

500 / 400 / 330 kV

interconnection

lines

5

• Load shedding

• Generator shedding if exporting

• HVdc control

Disconnection of other interconnecting lines

220 kV lines 1 • Load and generator shedding

Autotransformers 2 • Load and generator shedding

HVdc converters 2• Load shedding if importing

• Generator shedding if exporting

Generators 6 • Load shedding and HVdc control

Distributed vs. Centralized ArchitectureCentralized

Central Controller

Contingency 1 Logic / Rules

Contingency 2 Logic / Rules

Contingency 2

Detection Equipment

Action Equipment

Contingency 1

Detection Equipment

GSE operates

both schemes

Load Shedding Controller Logic

HMI

Trip Feeder

Trip Level

A B

A

B

Trip Level

Based on

Precontingency

Power Flow Subscribed to Contingency

Detection Controller

▪ System overview (SCADA complement)

▪ Thresholds and settings

▪ Alarms and status

HMI

Generator Shedding Logic

MW to Shed

Based on State of

Power System

and Contingency

ECS Contingency

Detected

Detection Controller

Subscribed to Contingency

Measured MW

in HVdc

+

Select Combination of

Generators to Trip

START

S

Communications Network Considerations

▪ Use Optical Ground Wire (OPGW) infrastructure

▪ Cybersecurity

– Use of firewalls

– Secure login

– Secure, complex device passwords

▪ Careful traffic engineering

▪ Traffic segregation

▪ Time distribution

ECS Communication Network

▪ Synchronous Multiplexers allow separate Ethernet bandwidth:

– One bandwidth routes critical GOOSE messages

– Second network bandwidth routes TCP/IP traffic

▪ Multiplexers distribute precise time synchronization

▪ Ring networks provide redundancy

Work planned for the future of the ECSECS system will become completely independent of SCADA.

Connection to GSE SCADA will be removed.

SEL-451 Contingency

Detection Equipment

CT

VT

Breacker

SEL-2440

Action Equipment

Trip Load

Trip Load

Trip Load

Clock

Antenna

SEL-1102 Central ControllerContingency Logic / Rules

SCADA

Measurement

SEL-2240 Contingency

Detection Equipment

CT

VT

Generators

Clock

Antenna

Existing

SEL-451 Contingency

Detection Equipment

CT

VT

Breacker

SEL-2440

Action Equipment

Trip Load

Trip Load

Trip Load

Clock

Antenna

SEL-1102 Central ControllerContingency Logic / Rules

SCADA

Measurement

SEL-2240 Contingency

Detection Equipment

CT

VT

Generators

Clock

Antenna

Future

SEL-2240Axion

VT

CT CT CT

BreackerDetection Detection Detection

Detection

Action ActionCentral

Controller

Central

Controller

Measure

Work planned for the future of the ECS

The Synchrophasor Metering System

(SPM) project

Wide Area Monitoring System

(WAMS)

Questions?

https://selinc.com/Solutions/Success-Stories/Republic-of-Georgia/

[email protected]