county of allegheny city of pittsburgh · pittsburgh, pa 15219. include one (1) original and one...

36
County of Allegheny City of Pittsburgh DAN ONORATO LUKE RAVENSTAHL COUNTY EXECUTIVE MAYOR On behalf of the City of Pittsburgh DEPARTMENT OF ADMINISTRATIVE SERVICES DIVISION OF PURCHASING AND SUPPLIES REQUEST FOR QUALIFIED VENDORS for PRE-QUALIFIED CONTRACT FOR TREE PLANTING SERVICES SPECIFICATION NO. 6682 DUE DATE: Friday, September 28, 2012, 3:00PM SUBMIT TO: Division of Purchasing and Supplies Allegheny County Courthouse 436 Grant Street, Room 206 Pittsburgh, PA 15219 Include one (1) original and one (1) identical photocopy of agreement. Both documents must be in one sealed envelope clearly stating the Specification Number. Jennifer McCaffrey Purchasing Agent 412-350-4482 [email protected]

Upload: others

Post on 21-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

County of Allegheny City of Pittsburgh DAN ONORATO LUKE RAVENSTAHL

COUNTY EXECUTIVE MAYOR

On behalf of the City of Pittsburgh

DEPARTMENT OF ADMINISTRATIVE SERVICES DIVISION OF PURCHASING AND SUPPLIES

REQUEST FOR QUALIFIED VENDORS

for

PRE-QUALIFIED CONTRACT FOR TREE PLANTING SERVICES

SPECIFICATION NO. 6682

DUE DATE: Friday, September 28, 2012, 3:00PM

SUBMIT TO: Division of Purchasing and Supplies Allegheny County Courthouse 436 Grant Street, Room 206 Pittsburgh, PA 15219

Include one (1) original and one (1) identical photocopy of agreement. Both documents must be in one sealed envelope clearly stating the Specification Number.

Jennifer McCaffrey Purchasing Agent

412-350-4482 [email protected]

Page 2: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

DAN ONORATO COUNTY EXECUTIVE

DEPARTMENT OF ADMINISTRATIVE SERVICES DIVISION OF PURCHASING AND SUPPLIES

County of Allegheny 206 COURTHOUSE ♦ 436 GRANT STREET

PITTSBURGH, PA 15219 PHONE (412) 350-4495 ♦ FAX (412) 350-5883

TIMOTHY H. JOHNSON DIRECTOR

JOHN DEIGHAN, CPCP CHIEF PURCHASING OFFICER

Dear Bidder:

Allegheny County on behalf of the City of Pittsburgh invites you to participate in a new prequalified contract for PRE-QUALIFIED CONTRACT FOR TREE PLANTING SERVICES.

In order to qualify as a bidder for said contract you must review and execute the enclosed forms and forward to the Allegheny County Purchasing Department no later than 3:00 PM on September 28, 2012, Please carefully review, sign and return the related documents which must be submitted.

1. One (1) original and one (1) photocopy of the enclosed Agreement, returned to Allegheny

County Purchasing Department properly executed and attested to by the appropriate company officers (signature of President and Vice-President; attestation by Secretary, Treasurer, or Secretary/Treasurer).

2. Notarized Affidavit of Contractor.

Affidavit must be executed by an officer of the company as designated by the contract signature sheet as listed below or an individual authorized to execute contracts on the company's behalf. (Form enclosed as Attachment B)

3. Financial Security (Performance Bond) in the amount of $5,000.00, completed on the enclosed

form. (See Item #XI of this Agreement)

4. One (1) signature sheet enclosed, properly executed and attested to by the appropriate company officers (signature of President or Vice-President; attestation by Secretary, Treasurer, Secretary/Treasurer). Please include your Federal Identification Number or Social Security Number. (Page 31)

5. Copy of Pre-printed Internal Revenue label from Tax forms.

6. One (1) original Insurance Certificate, covering general liability and property damage, workers'

compensation and automotive liability, see Item #19 of the Articles of Agreement for limits. The City of Pittsburgh must be named as "additional insured".

7. Statement of Affiliations. Contractor must file a Statement of Affiliations with the City of

Pittsburgh, attached hereto as Attachment A, in compliance with Section 197.08 ( c ) of the Pittsburgh Code.

Page 3: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

2

8. Anti-Sweatshop Provision. Contractor will be required to submit an executed statement of compliance attached hereto as Attachment C, required by the Allegheny County Administrative Code which certifies that any of the goods and/or products provided herein were not made under sweatshop conditions, as defined by Part 9, § 5-903.02 as amended, of Article 903 of the County’s Administrative Code (Ordinance Number 08-07-OR)

The subject Agreement will only afford your company the opportunity to bid on PRE-QUALIFIED CONTRACT FOR TREE PLANTING SERVICES and neither guarantees any award of such bids, nor that will any minimum amount of PRE-QUALIFIED CONTRACT FOR TREE PLANTING SERVICES be requested. Bids will be solicited for PRE-QUALIFIED CONTRACT FOR TREE PLANTING SERVICES, made on an as- needed basis, with award of estimates to the lowest responsible bidder on any given day that bids are solicited by the City of Pittsburgh.

Upon return of the properly executed documents to the address below, the City of Pittsburgh will contact you for a contract review meeting to discuss the operational procedures for this Agreement.

Should you have questions, please call Ed Pikula, Purchasing Agent, City of Pittsburgh at 412-255-2485

Sincerely,

Jennifer McCaffrey Purchasing Agent Allegheny County Purchasing Department Room 206 Courthouse 436 Grant Street Pittsburgh, Pennsylvania 15219

Page 4: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

3

TREE PLANTING SERVICES

MADE THIS DAY OF , 20

BY AND BETWEEN CITY OF PITTSBURGH, a municipal corporation of the COMMONWEALTH OF PENNSYLVANIA, hereinafter referred to as "CITY".

A N D

VENDOR'S NAME:

VENDOR'S ADDRESS:

Hereinafter referred to as "Vendor" or "Contractor"

WITNESSETH:

WHEREAS, Vendors are providers of tree planting services

WHEREAS, the "City" desires the above-mentioned services to be available for use by the "City"

WHEREAS, the "Vendor" agrees to provide pricing for the services listed herein at the times, also, listed herein, together with several other vendors participating as specified herein;

NOW, THEREFORE, in consideration of the mutual premises and intending to be legally bound hereby,

the parties hereto agree as follows:

Page 5: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

4

1. SCOPE The scope of work for projects contemplated by the Department of Public Works, City of Pittsburgh, includes the furnishing and installation of trees at various locations within the limits of the public rights-of-way of the City of Pittsburgh, and/or within the confines of parks and playgrounds, maintenance and guarantee of plants, and all related work thereof. “Related work” shall include, but is not limited to: saw-cutting and removal of sidewalk surfaces, removal and replacement of tree grates and/or tree guards, installation of block stone and/or brick surfaces within the tree pit area, removal of existing dead trees that fall within the planting areas, spoil removal, placement of topsoil mixture and soil amendments, tree stakes and all site protection, clean-up and maintenance requirements (i.e. watering, re-mulching, pruning, tightening of guys, removal of guys, weeding and settlement correction, etc.)

It is anticipated that the total expenditures for any one new construction project shall not exceed $25,000.00, but there is no limit to the dollar amount for maintenance work that may be undertaken.

2 PURPOSE The purpose of this contract is to provide the City of Pittsburgh with services described and specified herein upon Vendor's receipt of an order from the City.

This agreement will pre-qualify vendors and permit them to submit quotations for work.

3. CONTRACT PERIOD a) The initial contract period shall commence upon the execution of this contract and shall terminate at

midnight on September 30, 2012. The City shall have the option to renew the contract for four (4) additional one-year periods, exercisable at the sole discretion of the City, which additional periods shall expire at midnight on September 30 of the next succeeding year.

b) In the event the City exercises its option to renew this contract as stated above, written confirmation will

be provided by the City to the Vendor within thirty (30) days prior to the termination date.

c) The City reserves the right to terminate the contract at any time in accordance with the provision of Paragraph 66 of the “Articles of Agreement”, which is made part of this proposal.

4. GENERAL SPECIFICATIONS a) The appropriate City Department shall provide documentation consisting of the written scope of work,

drawings and specifications describing the work of each intended project as well as provide construction observation for each project initiated. The contractor shall provide all tools, equipment, materials (when directed), and services, including construction management necessary to perform the work of each project in an efficient, cost effective, and timely manner.

Properties. An Information Sheet for each location with applicable Tree Planting Specifications, detailing specific requirement of each job site will be provided with each job request.

b) The City of Pittsburgh will pay only those charges which are specifically detailed and included in the “Job

Quote”. c) All contractors shall comply with all Federal, State and Local Codes, Regulations and Standards as

appropriate including those in regard to the environmental protection of the public and property. d) All Provisions of General Conditions for Maintenance and Repairs, (attached) will apply, unless otherwise

specified.

Page 6: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

5

5. BID PROCESS a) The job site visitation will be coordinated by the Director of the User Department, or his designee.

b) Vendor agrees to submit a sealed bid, for each site bid, returned in the addressed envelope (supplied with

each job site specification sheet), to the Office of City Controller no later than 9:00 AM on the date indicated in the proposal specifications.

c) Pricing shall be inclusive of all costs necessary to complete the work described at the time of visitation.

d) The prices provided shall be free of all Federal, State and Local taxes; the City will provide State sales tax

exemption form upon request. e) Orders for services at the job site will be placed by the City to the lowest responsible vendor providing pricing within the time period as specified in item (b) above.

f) All services performed shall be invoiced at prices quoted, in accordance with this contract, on the day following the completion of the service with the authorization of the Director of the User Department, or his assignee.

BIDDER'S NOTE: All bids for individual projects covered under this contract shall be signed in ink by an officer or authorized representative of the company, or said bid may be subject to rejection.

6. SERVICE SCHEDULE a) It is the intention of the City, under these specifications, to require the Vendor to furnish such services, as

may be ordered by properly authorized representatives of the City within the prescribed time frame (reference paragraph “a)” of General Specifications). If Vendor cannot furnish or deliver such services within said time period after the order has been given, City reserves the right to purchase the needed services in the open market, and Vendor may be declared in default of the contract and contract may be cancelled.

b) Vendor will not be penalized for delays in furnishing services which have been ordered when such delays

are due to peril of navigation, acts of Providence, fires, strikes and similar causes over which Vendor has no control, provided that in the event of such delay, Vendor immediately notifies City by the most expeditious means, and confirms said notice in writing, so that City may makes other arrangements for procuring the services ordered (a facsimile is acceptable for this notice).

c) Vendor will comply with any special requirements necessary and peculiar to the specific job site, as

described by the City at the time of the site visitation or contained within the Job Specification Sheet, and quote accordingly.

d) All services must be performed in a professional and business-like manner. Vendor is responsible for

clean-up of site at Vendor’s expense and to the satisfaction of the City. In case of dispute, the City may remove debris and charge the cost to Vendor, including setting off the cost against future payments due to Vendor.

7. EMERGENCY WORK Throughout the term of the contract it may be necessary for Vendors to assist the City in providing emergency tree planting services. All Awarded Vendors of this contract shall provide a list of telephone numbers at which a representative can be reached on a 24-hour emergency basis.

Page 7: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

6

The City reserves the right to award emergency services to more than one Vendor as necessary to insure access to the required quantity of equipment and labor.

Please note: the City will use Vendor’s emergency crews in such a manner as to insure the availability of sufficient resources to meet the needs of the city.

8. WITHHOLDING PAYMENT City may withhold payment in whole or in part of this contract to such extent as may be necessary to protect City from loss. When grounds are removed, a payment shall be made for amounts withheld because of them.

9. METHOD OF SERVICE ORDER a) Order releases will be issued to Vendor from time to time, for such services as may be required, by City using fax machines or e-mail. Vendor must accept as official the faxed service request from the City with authorized signature, or an e-mailed service request.

b) All Service Requests against this contact shall be coordinated, consolidated, and made via telephone by the Director of the User Department, or his designee, or by the Director of Finance, or his designee.

10. BILLING AND PAYMENT Payment shall be made after satisfactory performance of service (job signoff by an Inspector from the using Department), in accordance with all of the provisions herein, and upon receipt of a properly completed invoice in duplicate by City. The City will endeavor to process payment promptly. However, Vendor shall not assess late payment charges of any kind, for any reason. Vendor shall, following acceptance of performance of service by City, submit an invoice to the City of Pittsburgh (Requesting Department). Each invoice shall include the following information: 1) Site Location 2) Service Order Number (if applicable) and/or Project Number 3) Date Order was Placed and Completed 4) Job Signoff by an Inspector of using Department

11. INDEMNITY Vendor shall: indemnify, save, hold harmless, defend City its officers, agents, and employees from and against any and all: liens, charges, claims, demands, losses, costs, judgments, liabilities, and damages of every kind and nature whatsoever, including court costs and attorney's fees, arising by reason of: Vendor's performance of any services hereunder; Vendor's failure to perform any services hereunder; and Vendor's breach of any of the terms or conditions of this contract.

Any products or equipment to be provided by Vendor under this contract will remain at Vendor's expense, all property or work damaged or destroyed by any cause whatsoever.

12. INSURANCE Prior to execution of this contract by City, Vendor shall cause to be attached hereto a certificate of insurance duly executed by the officers or authorized representatives of a responsible and non-assessable insurance company, evidencing the following minimum coverage and specifically identifying the City of Pittsburgh as an additional insured, which insurance shall be non-cancelable, except upon thirty (30) days prior to written notice to City.

Occurrence Aggregate General Liability

Bodily injury, including death $500,000.00 $1,000,000.00 Property Damage $250,000.00 $ 500,000.00

Automobile Liability Property damage $250,000.00 $ 500,000.00

Page 8: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

7

All premiums shall be at the expense of the Vendor, and all such insurance coverage’s shall be on an occurrence, not a "claims-made" basis, and shall be indicated as such.

In the event that the term of said insurance shall expire prior to the expiration of the term of this contract, or any renewal or extension thereof, Vendor shall renew said insurance in a timely manner and shall promptly cause a certificate of insurance evidencing such renewal, and also identifying the City of Pittsburgh as an "additional insured", to be forwarded to the Director of the Department of Finance (hereinafter, "the Director"). All insurance coverage originally requested are to be included in this renewal.

Failure to provide and renew such insurance, as required above, shall be deemed a material breach of the contract, and may be the basis for immediate termination thereof.

13. PERFORMANCE BOND To insure the faithful performance of its duties under this contract, Vendor shall provide City with a Performance Bond in the amount of $5,000.00 with a corporate surety acceptable to City, prior to execution of this contract by City. Said performance bond shall be maintained by Vendor throughout the term of this contract, or, any renewal or extension thereof. The City reserves the right to increase the requirement amount of the Performance Bond dependent upon the individual TREE PLANTING project.

14. CONTRACT NOT AWARDED TO PERSONS DISQUALIFIED Vendor must complete a signed "Affidavit of Contractor under Section 161.00(f)". In signing this affidavit, Vendor affirms, under penalty of perjury, that neither Vendor nor any of its affiliates have been debarred or disqualified from participating in a City of Pittsburgh contract under Section 161.22(b) of the Pittsburgh Code.

15. WORKER'S COMPENSATION Vendor hereby certifies that it has accepted the provisions of the Pennsylvania Worker's Compensation and Occupational Disease Acts, as amended and supplemented, insofar as the services covered by this contract are concerned, and that it has insured its liability thereunder in accordance with the terms of said Acts, as evidenced by the certificate of insurance it has caused to be attached hereto.

16. COMPLIANCE WITH LAWS Vendor shall fully obey and comply with all Federal, State and Local laws, statutes, ordinances, resolutions and administrative regulations, which are or shall become applicable to the services performed under this contract.

Vendor agrees to maintain throughout duration of the contract, all necessary city, county and state licenses and approvals as applicable, and to immediately notify the City of Pittsburgh Department of Finance, Bureau of Procurement, Fleet and Asset Services of any loss or changes of licenses and approvals.

17. ANTI-DISCRIMINATION Vendor shall not discriminate in its employment on the basis of race, color, religion, ancestry, national origin, place of birth, sex, age, disability, non-job related handicap, or sexual orientation. Vendor shall comply with the applicable provisions of Title I and Title II of the Americans with Disabilities Act, any amendments thereto, and any regulations issued thereunder. Vendor shall incorporate in any sub-contracts, which may be permitted under the terms of the agreement, a requirement that said sub-contractors also comply with the provisions of this paragraph.

18. SUB-CONTRACTING None of the work or services covered by this contract shall be sub-contracted without the prior approval of the Director of Finance, or his authorized designee.

Page 9: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

8

19. ASSIGNMENT Vendor shall not assign this contract or any right for monies to be paid hereunder, without the prior written consent of the Director of Finance.

20. AMENDMENT This contract may be amended only by formal written agreement of the parties, duly executed by the authorized officers or officials of said parties.

21. INTEGRATION These contract documents and subsequent service orders to Vendor contain the entire understanding between the parties, and any additions or modifications hereto may only be made in writing properly executed by both parties.

22. TERMINATION City may terminate this contract at any time, with cause, at its sole discretion or liability, by giving Vendor ten (10) days advance, written notice of its intention to terminate. In the event that City exercises its right of termination hereunder, City shall reimburse Vendor for any services performed prior to the effective date of said termination.

The City shall have the right to terminate a contract or any part thereof before work is completed under certain circumstances, to include but not be limited to the following: a) Discovery of previously unknown circumstances that make it desirable and in the public interest to void

the contract. b) The Vendor is not adequately complying with the specifications c) The Vendor refuses, neglects, or fails to supply a properly trained workforce and/or skilled supervisory

personnel; or the equipment supplied is of the wrong type, of inferior quality, or of insufficient quantity to meet specifications

d) The Vendor refuses to proceed with work when and as directed by City e) The Vendor abandons the work. f) The Vendor fails to respond to emergency work within the time set forth in the specifications

23. MBE/WBE SOLICITATION AND COMMITMENT It is the City's current goal to encourage increased minority and women's participation in all City contracts. It is believed that it is reasonable to expect that within five (5) years, minority participation will constitute twenty-five percent (25%), and women's participation will constitute ten percent (10%) of the total dollar of city contracts. The City, therefore, requires that Vendor demonstrate a good faith effort to obtain the participation of certified minority and women's business enterprises in work to be performed under this contract. In order to demonstrate this good faith commitment, Vendor is required to complete and submit a MBE/WBE Solicitation and Commitment Statement, which details the efforts made by Vendor to obtain such participation, and includes an MBE/WBE Commitment Waiver Request.

Contracts for $10,000.00 or more must be accompanied by either an MBE/WBE Solicitation and Commitment Statement or an MBE/WBE Commitment Waver Request.

24. MBE/WBE REPORT By entering into a contract with City, Vendor agrees to submit a final report within thirty (30) days of the City's request, detailing the actual levels of MBE and WBE participation in the contract. Any disparity between actual participation levels and the participation levels projected in the MBE/WBE Solicitation and Commitment Statement will be explained in the final report. Failure to make a good faith effort to meet the goals stated in the MBE/WBE Solicitation and Commitment Statement may be considered a material breach of the contract resulting in debarment from participation in future City contracts.

Page 10: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

9

25. GOVERNING LAW This contract shall in all respects, be governed by the laws of the Commonwealth of Pennsylvania.

26. AUTHORIZING RESOLUTION This contract is entered in the City pursuant to Section 161.2(b) of the Pittsburgh Code and Resolution No. 646, approved November 06, 2009 and effective November 13, 2009. 27. STATEMENT OF AFFILIATIONS All vendors entering into contracts with the City are required to provide a "Statement of Affiliations". The Vendor shall provide in the "Statement of Affiliations", a description of his or her qualifications and experience, a description of any contractual or business relationship with the City over the past three (3) years, and a listing of the contractor's owners, principals, partners, or shareholders holding more than three percent (3%) of the corporate stock. This statement shall be provided by the successful bidder prior to the signing of the agreement.

28. LIQUIDATED DAMAGES Substantial and unreasonable delays in response times, estimated time, or non-adherence thereto shall constitute cause for the assessment of liquidated damages. Such damages shall be assessed at the rate of $100.00 per day for the first five (5) days and $200 per day for each additional day until completion of contract. Liquidated damages shall be deducted from payments due under this contract. (Also see Initiating the Work on page 12)

29. CONTACT NAME:

Phone Number:

Emergency Number:

Fax Number:

Pager Number:

E-mail Address:

30. The bidder does hereby propose and agree to furnish all materials, equipment, tools and labor required to the City of Pittsburgh and its Authorities, the City of Pittsburgh School Board, and Allegheny County and its Authorities at the prices quoted.

31. Bidders must submit five (5) references for whom you have performed TREE PLANTING SERVICES. Form entitled “References”, on page 9, must be completed and submitted with agreement.

32. Please indicate with an (x) how you were informed of this proposal:

Post Gazette Pgh Courier Direct Mail Letter City Web Site Word of Mouth (Please List)

Construction News Pgh Builders Exchange Accu Copy Dodge Report

City Posting or other agencies (Please List) Other Publication (Please List)

Page 11: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

10

33. REFERENCES

Please state five (5) references for whom you have performed the type of work required in this agreement: 1. Company/Individual Address Telephone Number of people served Type of event Contact Person

2. Company/Individual Address Telephone Number of people served Type of event Contact Person

3. Company/Individual Address Telephone Number of people served Type of event Contact Person

4. Company/Individual Address Telephone Number of people served Type of event Contact Person

5. Company/Individual Address Telephone Number of people served Type of event Contact Person

Page 12: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

11

1.1 GENERAL CONTRACT CONDITIONS 1.2 EXCLUSIVITY 1.3 AUTHORIZATION 1.4 INITIATING THE WORK 1.5 INVOICING 1.6 COORDINATION WITH OTHERS 1.7 PERMITS 1.8 BONDING AND INSURANCE 1.9 SAFETY AND CODE REQUIREMENTS 1.10 EMERGENCY WORK 1.11 CONSTRUCTION DOCUMENTS: DRAWINGS AND TECHNICAL

SPECIFICATIONS 1.12 USE AND POSSESSION PRIOR TO COMPLETION 1.13 INSPECTIONS AND PROJECT CLOSEOUT 1.14 LIQUIDATED DAMAGES 1.15 GUARANTEE 1.16 CLARIFICATION OF OWNERSHIP

2.1 GENERAL INSTALLATION REQUIREMENTS 2.2 TESTING 2.3 STORAGE OF MATERIALS AND EQUIPMENT 2.4 PROTECTION OF WORK 2.5 RESTORATION AND MAINTENANCE OF SURFACES 2.6 CUTTING, FITTING, AND PATCHING 2.7 CLEANUP OF PREMISES AND EQUIPMENT

3.1 BASIS OF ACCEPTANCE

3.2 UNIT PRICES, PERSONNEL, MARKUP, EQUIPMENT 4.0 REFERENCES, ETC.

Page 13: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

12

1.0 GENERAL CONTRACT CONDITIONS

A. The City of Pittsburgh Bid and General Contract Conditions (1984) revised June, 2002.

B. The following Sections are to be excluded from the General Contract Conditions except as noted below:

1) a.

TITLE II

Article 3, Sec. 2.31

EXAM. OF WORKSITE b. Article 4, Sec. 2.41-2.44 BONDS shall be modified as

stated in the attached specifications

c. Article 4, Section 2.46 INSURANCE shall be modified as stated in the attached specifications

d. Art. 5, Sec. 2.53 COMMENCEMENT OF WORK e. Art. 6, Sec. 2.61-2.68 M/WBE (MBE/WBE language

shall be modified as stated in “Articles of Agreement”)

2) TITLE III

a. Art. 1, Sec. 3.14 MAINTENANCE& GUARANTY b. Article 4, Section 3.43 COMPENSATION FOR

ALTERATIONS/EXTRA WORK c. Art. 5, Sec. 3.51 MAX. UNIT PRICE d. Art. 5, Sec. 3.53 RETAINAGE e. Art. 6, Sec. 3.66 PREVAILING WAGE AND

WORKER’S COMPENSATION shall be deleted in its entirety and the following paragraph inserted in its place: “3.66 WORKER’S COMPENSATION. Contractor hereby certifies that it has complied with the provisions of the Pennsylvania Worker’s Compensation and Occupational Disease Acts.”

PLEASE NOTE THAT THE PROPOSAL TERMS, CONDITIONS, AND SPECIFICATIONS ARE PRIMARY; UNLESS OTHERWISE SPECIFIED, THEY SUPERCEDE THESE CONDITIONS, AS THESE SUPERCEDE THE BID AND GENERAL CONTRACT CONDITIONS WHERESOEVER A CONFLICT MAY APPEAR.

1.1 EXCLUSIVITY

This contract shall be non-exclusive. The City reserves the right to do work of the type covered by this contract with City forces or with other contracts.

1.2 AUTHORIZATION

The award of this contract shall be such that any City Department may make use of it under the terms stipulated. However, all work (i.e., trees planted on City-owned properties) must have prior authorization of the City Forester and the Department Director(s), or their designee.

Page 14: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

13

1.3 INITIATING THE WORK

The procedure for initiating the work shall be as follows:

A. The Department Director or his representative shall, by Request For Quote (RFQ) letter, describe the work for each intended project and request this Contractor to submit a not-to-exceed cost proposal based upon the rates and unit prices established in this bid as well as any other costs associated with the completion of the work. The Contractor shall follow the requested format for the submission of each proposal as enumerated in the RFQ. Each proposal must include a written estimate on City forms and shall be submitted as per the time frame indicated in the proposal specifications, unless otherwise specified by the city.

B. Such estimates must be in a format acceptable to the City of Pittsburgh and should include approximate start

and finish dates, cost breakdowns for labor, material and equipment, (including truck time, when applicable), a schedule of values with a total cost for the project as per City supplied construction documents, a list of shop drawings (to be supplied as required by the project), a list of subcontractors and/or suppliers (when value of work is > $1000.) together with a copy of their proposal(s) including breakdowns, and any other data which may be pertinent and requested. On projects estimated to cost-over $10,000. a minimum of two (2) sub- contractor and supplier proposals may be requested for review and approval. On large projects, a construction schedule with periodic updates may be required to be provided at no additional cost.

C. Non-adherence to the stipulated start and completion dates or failure to supply requested documentation in a

timely manner for the proper progress of the work may be cause for immediate cancellation of an individual project or of a bidder’s entire contract. Liquidated damages may also apply (see pages 8 and 16).

D. The Department Director may notify the Contractor by a Letter Of Acceptance (LOA) of his cost proposal

accepting the Not-To-Exceed-Amount (NTEA) for each project. Final cost of each completed project may not exceed the NTEA as accepted by the LOA.

E. Unless otherwise directed, the Contractor must begin work within the time frame indicated in the proposal

specifications and shall perform the work in accordance with the Department Director's orders and instructions.

1.4 INVOICING

A. The Contractor shall prepare his invoices based on the aggregate of those items computed from the project quote as accepted and enumerated in the LOA. Detailed breakdowns consistent with the initial price proposals are required with each invoice. Each invoice page must also show contract number, project number, company name and contact person, etc. The Contractor will also be responsible for submitting a complete breakdown of subcontracting costs together with all subcontractors documentation (i.e., labor invoices, material invoices, equipment rental, etc.). Invoices shall be submitted directly to the Department initiating the project and should be submitted not more than once a month, or at project completion, whichever comes first. Contractor will be responsible to follow the user Department's invoicing procedures. Payment to the Contractor shall be consistent with the City Inspector's daily labor and material logs. Itemized payroll records must be available, when, and as, required.

B. City Business Privilege Tax is the Contractor's and Sub-Contractor’s responsibility and as such is not a

reimbursable item on Contractor's or Sub-Contractor’s billing.

C. PA State Sales taxes paid by the Contractor on material purchases or equipment rentals are reimbursable if included on third party invoices submitted.

Page 15: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

14

D. Off-site fabrication time may be allowed, if approved by the Department Director and is included in the proposal. City Inspector shall be permitted to verify off-site fabrication as deemed appropriate.

E. A Final project invoice MUST be submitted within 45 days after the completion of the work on each project.

Failure to submit the required product warranties, operation manuals, and maintenance manuals may delay final payment. When submitting the Final project invoice, the Contractor shall state therein that payment of said invoice constitutes full and complete payment of all monies owed and billable on said project. Any exception to this should be so noted and tallied on the Final invoice. After receipt and processing of the Final project invoice, the City will not entertain any additional cost for that particular project and will consider the project closed.

1.5 COORDINATION WITH OTHERS

This Contractor shall cooperate with all other entities involved in the project including the Owner in the scheduling of the work so that he does not delay or interfere with the others' work. It will be this Contractor's responsibility to coordinate the schedule for the work with other primes and subcontractors and provide input to General Contractor for preparation, periodical update, and distribution of a master schedule for each project, if required, at no additional cost. The master schedule shall include the work of all other primes and subcontractors participating in the work.

1.6 PERMITS

A. The Contractor shall secure all necessary permits and licenses required for the performance of the contract and shall pay all legal fees and charges thereof. The City shall waive any fees and charges normally associated with issuance of City permits. All other fees for Non-City permits shall be included by the Contractor in the proposal.

B. The Contractor shall legally dispose of all waste associated with the work, off site, unless otherwise indicated

by the Department Director. In such disposal cases, the Contractor shall secure all permits, pay all fees and produce documentation attesting to the legal disposal of such waste. Special disposal of toxic materials, debris or equipment must be specifically addressed in the proposal for each project.

1.7 BONDING AND INSURANCE

IMPORTANT: BONDING AS DESCRIBED BELOW SHALL PREVAIL OVER THAT SPECIFIED IN “BID AND GENERAL CONTRACT CONDITIONS”.

A. No Bid Bond is required

B. The Performance Bond amount shall be as indicated in the Proposal specifications. C. Insurance requirements shall be as indicated in the Proposal/ project specifications.

1.8 SAFETY AND CODE REQUIREMENTS

A. All Contractors shall comply with standards and regulations of Public Law 91-596, "Safety and Health Regulations for Construction", latest edition, Occupational Safety and Health Act of 1970.

B. All Contractors will comply with Act No. 287 of the General Assembly, approved December 10, 1974, which

defines the procedures for notification to public utilities prior to excavation, drilling or demolition work by use of powered equipment or explosives. For confirmation of utilities call 800-242-1776.

Page 16: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

15

C. All Contractors shall comply with all federal, state and local codes, regulations and standards as appropriate including those in regard to environmental protection, of the public, and property, etc. Where codes, regulations, and standards are referred to herein, it shall be understood that such reference is to the current issue in effect at the date of the contract including all revisions and addenda, if any, and are hereby made part of this contract and at no additional expense to the City.

1.9 EMERGENCY WORK

A. Unless otherwise specified within the proposal, the Contractor must perform emergency work within the following time frames, based on situation, and must verify that their work forces can be dispatched accordingly:

4 hours EMERGENCY 48 hours URGENT

B. The Contractor must have twenty-four (24) hours a day accessibility (Answering service, or Machine and paging capability). The Contractor must also have a FAX machine in operation by time of contract commencement.

C. The Contractor must also have the ability to complete emergency work as requested by the City within a 24

hour period from initiation of repair, unless other arrangements are approved. Non-adherence to this clause may be cause for cancellation of contract.

1.10 CONSTRUCTION DOCUMENTS: DRAWINGS AND TECHNICAL SPECIFICATIONS

A. The Contractor will be required to comply with all drawings and technical specifications, which may be associated with each particular project. Failure to comply may result in delay of payments, backcharging for corrective remedial work, and/or cancellation of the contract.

B. On certain large and/or complex projects, the contractor may be required to provide shop drawings and

catalogue cuts of the proposed equipment and/or assemblies. Submittals of these types shall be furnished in a timely manner for the progress of the work and at the Department Director's request and the cost thereof will be considered as Overhead.

C. Where standards, specifications, and codes are referred to herein, it shall be understood

that such reference is to the issue in effect as of the date of the proposal, including all revisions and addenda, if any.

D. The material, equipment, and installation shall conform to all applicable regulations,

and codes and as such are hereby made a part of the proposal specifications. They shall take precedence over these proposal specifications and shall be satisfied by the contractor at no additional expense to the City.

1.11 USE AND POSSESSION PRIOR TO COMPLETION

A. The City shall have the right to take possession of or use any completed, or partially completed part of the work. Before taking possession of, or using any part of the work, the Department Director shall furnish the Contractor with a Certificate of Substantial Completion containing a list of items of work remaining to be completed or corrected for those portions of the work that the City intends to take possession of, or use. However, failure of the Director to list any item of work shall not relieve the Contractor of responsibility for complying with the terms of the Contract. The City's possession or use of some of the work shall not be deemed an acceptance of all of the work under the Contract.

Page 17: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

16

B. For those portions of the work which the City has such possession or use, the Contractor shall be relieved of the responsibility of loss or damage to the work resulting from the City's possession or use, notwithstanding the terms of any warranties, maintenance responsibilities, protection requirements, or other specified duties which remain the Contractor's responsibility beyond the Date of Substantial Completion.

1.12 INSPECTIONS AND CLOSEOUT

A. During the course of the project, the City will designate an employee to this site to monitor the work. The Designee shall act as the Director's Representative on all matters in the field. The Contractor shall fully cooperate with the Designee. The Contractor's Field Representative may be requested to sign the Designee's daily log as verification of hours worked by the Contractor. Only the actual hours that workers are productively engaged in the progress of the work will be logged by the Designee. It is in the Contractor's best interest to efficiently and effectively manage each project.

B. When the work is substantially complete, the Contractor may request a Pre-Final Inspection. At that time a

punch-list of deficiencies and/or incomplete work will be compiled and sent to the Contractor(s) for completion. All punch-list items must be completed within 30 days unless otherwise arranged. If there are no discrepancies found at the Pre-Final, this inspection may be considered a Final Inspection and as such Final Acceptance of the work.

C. One (1) Initial Project Meeting, and one (1) Pre-Final and/or Final Inspection shall be a requirement for

every project. Only line items submitted as part of the original project estimate as awarded, will be considered pay items.

1.13 LIQUIDATED DAMAGES

A.S Substantial and unreasonable delays in response times, estimated time, or non-adherence thereto shall constitute cause for the assessment of liquidated damages. Such damages shall be assessed at the rate of $300.00 per day for every day of such substantial delay, unless otherwise specified. Liquidated damages shall be deducted from payments due under this contract.

1.14 GUARANTEE

A.T The Contractor shall, at his cost, replace any work, materials or equipment furnished and installed by him under this contract which develops defects, except from vandalism or unusual wear and tear, within one (1) year from the date of the Final Acceptance of the work for each project. Additional warranties of specific materials and systems may be required of the Contractor on a per project basis and will be so noted in the Department Director’s requesting (RFQ) letter.

1.15 CLARIFICATION OF OWNERSHIP

A. Providing false or insufficient information may result in the successful Bidder being subjected to civil and/or criminal liabilities.

2.1 GENERAL INSTALLATION REQUIREMENTS

A. Installation shall be of a quality not less than is accepted as industry standard for any trade covered herein.

B. All materials furnished under this contract shall be determined safe by nationally recognized testing laboratory, such as underwriter’s laboratories inc., or factory mutual engineering corporation. All material shall be labeled, certified, or listed by such laboratory.

Page 18: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

17

2.2 TESTING

A. Testing of materials or of the installation of same may be required by the Department Director. If the materials and installation are found to be in accordance with the contract documents, the cost of testing and replacement of the installation shall be paid by the City. If the work is found not in accordance with the Contract Documents, the Contractor shall pay the costs of testing and replacement of that installation in order to meet current specifications.

B. Any material or equipment, which is found to be defective during the tests, shall be removed and replaced

with new by this Contractor at no additional cost to the City unless it is found that this condition was caused by the City of Pittsburgh or a separate prime contractor in which event the City shall be responsible for the payment of said costs and will pursue reimbursement from the contractor(s) responsible.

2.3 STORAGE OF MATERIALS AND EQUIPMENT

A. The Contractor will be required to store his material and equipment in a location, which will not interfere with the normal operations of other contractors or employees of the City, and in a manner which will afford them maximum protection. The City will not guaranty the security nor be responsible for loss, damage or theft of stored materials or equipment in a City facility. Security of materials and equipment is the Contractor's responsibility. The Contractor shall replace such items, as required, at his own expense.

B. When City-owned equipment is removed from any part of the building systems it shall be taken down

with due care in a workman-like manner, the parts shall be marked for identification, and the whole shall be stored in the City stock in the contractor premises. Subject to further orders of the City, the contractor may be directed to transport the material directly to a City storage area.

C. At the end of each project, a list of all City-owned equipment in the possession of the Contractor shall be sent

to the Director of Finance. Said equipment shall be returned, at the Contractor’s expense, to the City yard or as directed by the Department Director.

2.4 PROTECTION OF WORK

A. This Contractor shall be held responsible for the protection of the General Public as well as City personnel during construction. This to include but not be limited to erection of barricades, screens, or other such enclosures/precautions to protect other portions of the site or building from dust, fumes and all other construction debris within the construction area.

B. Protection of his work prior to the final acceptance of same shall be the Contractor’s responsibility. He shall repair or replace work damaged before final acceptance at his own expense.

2.5 RESTORATION AND MAINTENANCE OF SURFACES

A. The Contractor shall adequately protect adjacent work, existing or new. He shall restore all materials including site paving, other site improvements, landscaping, exterior building components and surfaces, interior building components, equipment and surfaces which may have been damaged through his activities to a condition equal to that before work began, furnishing all labor and material required at his own cost.

Page 19: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

18

B. During the installation, removal, repair, or maintenance of equipment under this contract, it may be necessary for this contractor to move, remove, or relocated signs, fences, barriers, or other objects in order to gain access to existing equipment or to the proposed equipment site. The Contractor shall perform such duties, within reason, at no additional charge and shall restore the site to its original condition.

C. The Contractor shall not injure trees. Trimming of trees in connection with the work or access to the

work site shall be done only under the supervision of a City Forester. However, the Contract shall not be required to trim trees except at the time of the installation of new work or repair and maintenance of existing work.

2.6 CUTTING, FITTING AND PATCHING

A. This Contractor shall do all cutting and fitting of all work that may be required to make the related parts come together properly to receive or be received by other parts of the work. He shall also do such patching of related parts and assemblies that may be required as a result of cutting and fitting work.

B. He shall not endanger the stability of existing structures or any part thereof by cutting, digging or other

operations. He shall not cut or alter any structural components in any way save with the written consent and under direction of the Department Director.

C. All patching shall be done by mechanics skilled in the trade which originally erected the work and in such manner as to restore such parts to their original (prior to the work) construction, finish, and to the satisfaction of the Owner.

2.7 CLEANUP OF PREMISES AND EQUIPMENT

A. The Contractor shall not allow waste material or rubbish caused by work under this contract to accumulate in or about the premises, but shall promptly and thoroughly remove rubbish and excess tools daily from the site including immediate work area, equipment and scaffolding. Stockpile of stored material must be maintained in an orderly condition. Upon Final Completion, he shall leave the site thoroughly cleaned and ready for use. In case of a dispute, the City of Pittsburgh may remove the rubbish and do such cleanup as required and charge the cost thereof back to the Contractor responsible.

B. The Contractor shall take legal responsibility for the environmentally safe disposal of construction debris,

rubbish, and waste material. Special disposal of toxic materials and/or equipment should be specifically addressed in the Contractor's proposal.

C. Demolished material with salvage value shall be disposed of as instructed by the director. Salvaged

payments to the contractor shall be returned to the city by way of a credit.

3.0 BASIS OF ACCEPTANCE

A. The basis for acceptance of the contractors pre-qualified hereunder shall be Experience and References. The basis for award on each of the subsequent project estimates shall be the low bid price and timely completion dates as viewed in light of the following requirements

(NOTE THAT ALL REFERENCES TO REIMBURSEMENTS, RATE OF PAY, OR PRICING OF ANY SORT, IS INTENDED AS A GUIDELINE FOR BIDDING AND ESTIMATING. THE CITY WILL PAY ONLY THOSE CHARGES WHICH HAVE BEEN INCLUDED IN THE ORIGINAL PROJECT ESTIMATE AS AWARDED):

Page 20: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

19

3.1 Where applicable, all Unit Prices, Personnel, Markup, and Equipment must be provided for each project bid, or, such bid may be subject to rejection.

A. Principals, project managers, estimators, expeditors, clerical and all other office personnel shall be considered Overhead. Time spent in preparation of an estimate for each project shall be considered Overhead. Time spent preparing and securing permits, drawings required thereof, shop drawings, submittals, schedules, reports and invoices shall also be considered Overhead costs.

B. Hauling or delivery of personnel, materials, supplies, or equipment to/from/within the job site(s) is not to be considered as billable. Travel time for personnel to/from/within the job site(s) is also not to be considered as billable hours. These costs incurred by the Contractor are to be included in project bid price.

C. Use of subcontractors must be identified on each project estimate and approved by the Department Director. Such usage shall be permitted only where the subcontracted work is minor, a specialty trade, incidental to the total project, and/or more cost/time effective than other means available.

4.0 REFERENCES, ETC.

Inability to provide references or determination by the City of Pittsburgh that references are invalid or irrelevant may remove a bidder from consideration in pre-qualifying for this contract.

A. The City of Pittsburgh reserves the right to inspect the facilities and available equipment to perform work under this contract of all bidders to determine the bidders’ abilities to perform the services required. If, in the opinion of the user Department that may recommend award, the lowest responsible bidder does not have adequate facilities and/or proper equipment to service this contract, bidder may be subject to rejection.

Page 21: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

20

PERFORMANCE BOND

Know All Persons by these Presents THAT

As principal, and as surety are held and firmly bound unto the City of Pittsburgh, in the sum of $ as a Performance Bond. Performance Bond required is as stipulated within the contract of the contract amount to be paid to said City of Pittsburgh, aforesaid, their certain attorney, successors or assigns. To which payment, well and truly to be made, we do not bind ourselves, our successors and assign, jointly and generally, firmly by these presents.

WITNESS our hands and seals, the day of in the year of our Lord, Two thousand

WHEREAS, the above bound has filed with the Controller of the City of Pittsburgh proposals for

to be done under and in pursuance of the Acts of Assembly and Ordinances of Council relating thereto; now THE CONDITIONS OF THE ABOVE OBLIGATION ARE SUCH That the said

shall enter into a written contract, as required by said laws and ordinances in case the same shall be awarded to and well and faithfully perform and fulfill in all its parts, the contract to be made and entered into by and between the said City of Pittsburgh and the said

for

in accordance with the above mentioned contract, and shall indemnify and save harmless said City of Pittsburgh from all liens, and shall otherwise indemnify, save and hold harmless said City of Pittsburgh from all liens, charges, claims, loss, costs, and damages of every kind and nature whatsoever, then this obligation to be void, otherwise to be and remained in full force and virtue.

It is further agreed that any alterations which may be made in the terms of the contract or in the work to be done and materials to be furnished or labor to be supplied or performed under it, or the giving by the City of Pittsburgh or any extension of time for the performance of the contract or any forbearance of the part of either the City of Pittsburgh or the principal to the other, shall not in any way release principal and the surety of sureties, or either or any of them, their heirs, executors, administrators, successors, or assigns, from their liability hereunder, notice to the sureties of any such alteration, extension or forbearance being hereby waived.

Attest:

(Seal) For Bidder (Seal) Secretary-Treasurer President – Vice President

Sealed and Delivered in Presence of (Seal) For Surety Company

Page 22: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

21

ARTICLES OF AGREEMENT MADE AND ENTERED INTO, this day of , 20 , by and between Allegheny County and the City of Pittsburgh, a municipal corporation of the Commonwealth of Pennsylvania acting in this behalf through THE DIRECTOR OF THE DEPARTMENT OF FINANCE of said City, having been duly authorized thereto by Ordinance of Council of said City (hereafter “City”)

AND

(“Contractor”)

incorporated in the Commonwealth/State of

Page 23: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

22

NOW, THEREFORE, THIS AGREEMENT WITNESSETH:

That the Contractor agrees, and by these presents does/do agree with the County and City under the conditions set forth in a bond which is annexed hereto and made a part hereof, to furnish all necessary materials, labor, plant, machinery and appliances, and at its own risk and expense and to do such work and/or perform such services, and/or furnish such materials required in connection therewith as may be contemplated and described herein, the specifications and such instructions as may be issued by the Director during the term of this Contract, for the prices as shown on the attached proposal.

The City of Pittsburgh reserves the right, during the period while this contract is in force, to take bids and award separate contracts for individual jobs where it may be in the best interest of the City to do so, such determination to be made at the City’s sole discretion.

For the purpose of this Agreement, and any Exhibits attached hereto, the following terms, phrases, and their derivations shall have the meanings given below unless the context clearly mandates a different interpretation. Where the context so indicates, the present tense shall imply the future tense, words in plural include the singular, and words in the singular include the plural. The word "will" is always mandatory and not merely directory. The definitions are applicable regardless of whether the term is capitalized.

1.DEFINITION OF DIRECTOR - It is agreed by the parties to this contract, that wherever the word “Director” occurs in the contract, it will be considered as referring to the City.

2. DEFINITION OF CITY - The City of Pittsburgh, a municipal corporation of the Commonwealth of Pennsylvania. It is to be understood “City” shall also include Allegheny County for the

3.DEFINITION OF CONTRACTOR - It is agreed by the parties hereto that wherever the word “Contractor,” or the pronoun(s) in place thereof are used in this contract, they are to be considered as referring to and meaning the contracting party or parties, or such party or parties seeking to enter into a contract with the City of Pittsburgh, as the case may be, or the legal representatives of such party or parties.

4.DEFINITION OF COUNCIL - Council of the City of Pittsburgh, Pennsylvania.

5.DEFINITION OF STANDARD FOR CONSTRUCTION - It is agreed by the parties to this contract that wherever the words "Standard for Construction" or the pronouns in place thereof are used in this contract, they are to be considered as referring to and reading "Part 3" of the "Contract for Construction," of the Department of Public Works, Bureau of Engineering & Construction, as contained in a separate pamphlet and as revised to date of advertisement of this contract.

6.COMPONENTS OF CONTRACT - The following documents are part of this contract and supplement one another:

A. ADVERTISEMENT for proposals as published in newspapers of general circulation (for contracts with an estimated value above $10,000.00);

B. PROPOSAL made by the prospective Contractor on the separate form provided by the City; C. Particular SPECIFICATIONS special to this contract (if applicable); D. STANDARD(S) FOR CONSTRUCTION (if applicable); E. ARTICLES OF AGREEMENT;

The contract shall become binding upon the formal acceptance of the prospective Contractor’s bid by the City as evidenced by the City's execution of the Articles of Agreement.

F. FINANCIAL SECURITIES executed by the prospective Contractor (if applicable); G. AFFIDAVIT OF CONTRACTOR; H. STATEMENT OF AFFILIATIONS; I. SWEATSHOP CONDITIONS

Page 24: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

23

The contract sets forth all the promises, agreements, conditions and understandings between City and Contractor(s), and there shall be no promises, agreements, conditions, or understandings, either oral or written, between them other than those that are set forth in the contract. Unless provided for in the contract, no subsequent alteration, amendment, charge or addition to the contract shall be binding upon City or Contractor(s), unless expressly agreed upon and reduced to writing by the City to the Contractor(s).

7.LENGTH OF AGREEMENT - It is agreed that this contract shall be in effect for the initial contract period shall commence upon the execution of this contract and shall terminate at midnight on September 30, 2012. The City shall have the option to renew the contract for four (4) additional one-year periods, exercisable at the sole discretion of the City, which additional periods shall expire at midnight on September 30 of the next succeeding year.

WHEN AND WHERE TO COMMENCE - The Contractor further agrees to commence the work described or contemplated herein at such point(s), and at such time(s) as the Director may request.

9.TIME OF BID OPENING - The separate and sealed bids or proposals will be received upon the City's blank proposal forms at the Office of the City Controller, First Floor, City-County Building, Pittsburgh, Pennsylvania, until the date and time stated in the advertisement for bids for the above, and will be opened and read upon the same date, in the place and at the time designated in said advertisement.

10. BLANK FORM OF PROPOSAL - All bids shall be made on the blank form of proposal provided for that purpose, shall give the price of each item or service to be furnished, shall be signed, in ink, by the prospective Contractors with the prospective Contractors business address or addresses, and shall also contain the full name of all persons interested with the prospective Contractors. In signing the proposal, the Contractor shall give the individual, as well as the firm or corporate name. Copies of the printed form of proposal may be obtained from the Bureau of Procurement, Fleet and Asset Services of the Department of Finance, Room 502, City- County Building, Pittsburgh, Pennsylvania. Please do not redesign the attached sheets of this proposal. All should be returned as single sized sheets.

11. ALTERATIONS/CORRECTIONS. Any alteration, erasure, addition to or omission of required information, change of the specifications or bidding schedule, is made at the risk of the prospective contractor and may result in the rejection of the bid, unless such changes are authorized by the specifications.

12. EXECUTION OF BIDS - Bids are to be executed, by the following persons:

I.CORPORATION - The President or Vice President, and one of the following:

Secretary, Treasurer, Assistant Secretary or Assistant Treasurer.

If a bid is executed by any other person, a power of attorney, a copy of the bylaws, or a resolution of the Board of Directors documenting the authority of that person to sign the bid must be accompanied by the bid. The power of attorney, bylaw, or resolution must be certified by the Corporate Secretary as a true and correct copy, still in force as of the date of the execution of the contract.

II. PARTNERSHIP - At least one (1) of the partners.

III. SOLE PROPRIETORSHIP - The individual owner.

IV. BUSINESS OPERATING UNDER A FICTITIOUS NAME - Entities operating a business under a Fictitious Name must

execute the contract in the name of the entity trading and doing business as the Fictitious Name.

13. FINANCIAL SECURITY FOR BIDS (BID BONDS) - Prospective Contractors on contracts with a value of Two Hundred Thousand ($200,000) Dollars or more are required to file with their proposals financial security equal to Ten to Fifty percent (10% - 50%) of the total bid. This financial security shall be in the form of a bid bond, certified check or letter of credit. In order to be acceptable as financial security, a bid bond must be issued by one or more surety companies legally authorized to do business in Pennsylvania which retain as capital no less than the amount of the issued bond and said bond must be in form approved by the City of Pittsburgh. If the bonding company executes the bond through an attorney-in-fact, a Power of Attorney showing authority to act must accompany the bond.

14. PERFORMANCE BOND - Financial security shall be further required to insure faithful performance of the work provided for in the contract and to indemnify and save harmless the City from all liens, charges, claims, demands, losses, costs and damages of every kind and nature, whatsoever, except as is otherwise provided in said contract.

Page 25: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

24

15. SERVICE CONTRACTS; REDUCTION IN PERFORMANCE SECURITY - In the case of service contracts where the City holds certified checks or a letter of credit as security for performance, the Director of the Department of Finance may approve reduction in the amount of the security over the term of the contract; provided, however, that at no time shall the amount of the security for performance be less than ten percent (10%) of the cost of the contract.

16. FINANCIAL SECURITY FOR PERFORMANCE AND LABOR AND MATERIAL INDEMNITY - For public works contracts exceeding Five Thousand ($5,000.00) Dollars, the successful Contractor shall furnish financial security equal to One Hundred Percent (100%) of the contract amount conditioned upon the faithful performance of the contract. The successful Contractor shall further provide financial security equal to One Hundred Percent (100%) of the contract amount for the protection of claimants supplying labor or materials to either the prime contractor or any subcontractor for work performed in furtherance of the contract. These financial securities must be in forms acceptable to the city.

17. EXECUTION OF FINANCE SECURITY - Any financial security furnished shall be an original, fully executed by both the prospective Contractor and the surety or sureties in ink and shall be in a form acceptable to the City. Where the prospective Contractor is a corporation, the security shall be signed by two officers of the corporation who have been duly authorized to do so by appropriate action of the corporation, and the seal of the corporation shall be affixed. Where the prospective Contractor is an individual or individuals, the security shall be signed by the individual or individuals affixing the signature to the bid. Changes or additions to bid security or to the signatures thereon may not be permitted after the opening of bids.

18. CONTENTS OF BID AND PERFORMANCE SECURITY -

A. The financial security submitted to the City must be the originally issued document, signed in ink.

B. Both the name of the contractor and the name of the issuing financial institution must appear on the financial

security.

C. The name of the insured and the name of the contractor must be the same.

D. The bid's title, contract number or description must appear in the financial security.

19. INSURANCE (SERVICE CONTRACTS ONLY) - For all contracts in which insurance is required, a certificate evidencing the following minimum insurance must be provided when award is made, unless otherwise specified:

A. GENERAL LIABILITY Single limit of Bodily Injury and Property Damage Combined: $500,000.00 each

occurrence. $1,000,000.00 aggregate.

B. CITY OF PITTSBURGH must be listed as "Additional Insured' on the insurance certificate. NOTE: The name(s) of the insured on the certificate must be the same as the name(s) of the Contractor listed on the bid document.

C. Insurance coverage must be an “OCCURRENCE POLICY". "Claims made” policies are unacceptable.

D. WORKERS’ COMPENSATION STATUTORY LIMITS.

E. AUTOMOTIVE LIABILITY INSURANCE – MINIMUM REQUIREMENTS: $500,000 for each individual

occurrence and $1,000,000 in aggregate coverage.

Insurance must be maintained in full force and effect throughout the term of the contract. If insurance must be renewed during the term of the contract, the new certificate of insurance must be forwarded to:

Bureau of Procurement, Fleet and Asset Services

Department of Finance

Room 502, City-County Building

414 Grant Street

Pittsburgh, PA 15219

Page 26: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

25

Failure to provide and renew such insurance as required shall be deemed a material breach of contract and shall be a basis for immediate termination of the contract. The insurance requirements of this provision shall be in addition to any other insurance requirements of the contract.

20.FICTITIOUS NAME REGISTRATION - Where a fictitious name is use certificate must be attached showing that the fictitious name is duly registered with the state.

21. TAX STATUS OF CITY - The City of Pittsburgh is exempt from all Federal Excise and Transportation Taxes, and the Pennsylvania Sales and Use Tax for purchase of tangible personal property. Therefore, a prospective Contractor should not include any such taxes in its calculations, or in the prices bid. A Pennsylvania Sales Tax Blanket Exemption Certificate is available, upon written request, from the Bureau of Procurement, Fleet and Asset Services of the Department of Finance. Only a Sales Tax Blanket Exemption Certificate will be issued by the City. Thus, if necessary to claim and secure exemption, a Sales Tax License issued by the Commonwealth of Pennsylvania, Department of Revenue will be required of the successful contractor. However, if the prospective Contractor determines that certain taxes are properly payable by, the City, the contractor must include such costs in its calculations of bid prices. The City will not be responsible or liable for the payment of any of the aforesaid taxes, or any other tax paid or payable by the contractor, unless specifically stated in bid. Nothing in this paragraph is meant to exempt a construction contractor from the payment of Sales Tax or Use Tax required to be paid by law with respect to its purchase or use of tangible personal property used or transferred in connection with the performance of a construction contract.

22. BUSINESS PRIVILEGE TAX - By entering into this agreement with the City of Pittsburgh, contractor agrees that all gross receipts generated through the provision of services hereunder shall be subject either to the City of Pittsburgh’s gross receipts taxes (i.e., business privilege tax, institution and service privilege tax) or to a payment in lieu of taxes (PILOT) as described hereafter, whichever is applicable. In the event that contractor is not subject to one of the two gross receipts taxes identified above, contractor shall nevertheless make a PILOT payment to the City Treasurer equal to the amount of tax which would be due and owing if contractor were subject to one of said gross receipts taxes. Any such PILOT payment shall be made annually, in the same manner as the gross receipts taxes, and interest and penalty shall accrue on any balance not paid when due at the rate in effect for said taxes. No deductions from gross receipts may be taken with respect to any amounts paid to subcontractor(s) or material suppliers. No deductions can be made for taxes paid to other localities for services performed under this contract or any sub-contract(s).

When the performance of a contract requires the hiring of subcontractor(s), such contract(s) with all subcontractors must incorporate a requirement that the subcontractor(s) pay the business privilege tax, the institution and service privilege tax or a PILOT, whichever is applicable, regardless as to whether the subcontract was initiated by the contractor or the City. Failure to include such provision shall subject the contractor to the amount of gross receipt tax, or PILOT payment, which would have been due from the subcontractor(s) if this provision had been included.

The City Treasurer shall provide a method of registration and applicable forms for filing. Contractor shall provide a list of all subcontractors to the City Treasurer. The list shall include (1) Legal Name; (2) Business Name; (3) Federal Identification Number; (4) Mailing Address; (5) E-mail address; (6) Local Address, if any; (7) Business Phone Number; (8) Name of Officer or Owner Signing the Contract; (9) Monetary Value of the Contract. When (a) subcontractor(s), in turn, employ (a) subcontractor(s), they shall be bound by the same rules as a general contractor.

23. MERCANTILE TAX RETURN - For successful Contractors selling goods, wares or merchandise under the terms of this contract, whose place of business is located inside the City: receipts generated by this contract should be included as part of gross income and reported on the Mercantile tax return.

24. FIRM PRICE BIDS - The City cannot allow escalation of prices during the contract term. All contracts are for fixed prices. Such statements as "interest charges applied on accounts 30 days or older" or "prices subject to revision" are considered escalation clauses. Any reference in documents submitted with the bid which indicates that the prices are not firm may be cause for rejection of the bid.

25. PAYMENT DISCOUNTS - In determining the low bid, the City will not consider payment discounts quoted by the prospective contractors. However, the City will apply payment discounts offered by the successful bidder in the proposal to payments made in relation to the contract when appropriate. The terms of payment discounts offered by the successful contractor must be clearly stated on each invoice submitted to the City in regard to this contract.

26. ANTI-DISCRIMINATION - Contractor shall not discriminate in its employment on the basis of race, color, religion, ancestry, national origin, place of birth, sex, age, disability, non-job related handicap, or sexual orientation. Contractor shall comply with the applicable provisions of the PITTSBURGH CODE OF ORDINANCES, Title Six - Conduct Article V Discrimination, and any amendments thereto. Contractor also shall comply with the applicable provisions of Title I and Title II of the Americans with Disabilities Act, any amendments thereto and any regulations issued thereunder. Contractor shall incorporate in any subcontracts which may be permitted under the terms of the contract, a requirement that said subcontractors also comply with the provisions of this section.

Page 27: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

26

27. MBE/WBE SOLICITATION AND COMMITMENT - It is the City's goal to encourage increased participation of women and minority groups in all City contracts. The City, therefore, requires that all prospective Contractors demonstrate good faith efforts to obtain the participation of minority-owned business enterprises (“MBEs”) and women-owned business enterprises (“WBEs”) in work to be performed under City contracts. In order to demonstrate this good faith commitment, all prospective Contractors are required to complete and submit with their bids either an MBE/WBE Solicitation and Commitment Statement, which details the efforts made by the prospective Contractor to obtain such participation, or an MBE/WBE Commitment Waiver Request which details why no MBE/WBE participation could be obtained. Failure to submit either an MBE/WBE Solicitation and Commitment statement or an MBE/WBE Commitment Waiver Request will result in rejection of the bid.

A. Bids for $10,000.00 or more must be accompanied by either an MBE/WBE Solicitation and Commitment statement,

or, an MBE/WBE Commitment Waiver Request.

B. On contracts over $75,000.00, final payment will be retained by the City at least until all work is performed under the contract and the contractor submits a final report to the City detailing the actual levels of MBE and WBE participation, as well as explaining any failure to meet MBE and WBE goals which had been stated in the previously submitted MBE/WBE Solicitation and Commitment Statement. The report must be submitted within thirty (30) days after the City's request.

C. On contracts for $75,000.00 or more, the performance security will be retained by the City at least until all work is

performed under the contract and the contractor submits a final report to the City detailing the actual levels of MBE and WBE participation as well as explaining any failure to meet MBE and WBE goals which had been stated in the contractor’s previously submitted MBE/WBE Solicitation and Commitment Statement. The report must be submitted within thirty (30) days after the City's request.

D. On construction contracts over $250,000.00, the contractor may comply with stated MBE/WBE goals through the

employment of twenty-five percent (25%) minority and ten percent (10%) women employees in construction related jobs.

28. MBE/WBE REPORT - By entering into a contract with the City, the prospective Contractor shall be required to submit a final report, within thirty (30) days of the City's request, detailing the actual levels of MBE and WBE participation in the contract. Any disparity between actual participation levels and the participation levels projected in the MBE/WBE Solicitation and Commitment Statement will be explained in the final report. Failure to make a good faith effort to meet the goals stated in the MBE/WBE Solicitation and Commitment Statement may be considered a material breach of the contract resulting in debarment from participation in future City contracts. Please note that final payment under the contract can be withheld for failure to submit a MBE/WBE report.

29. PAYMENT OF TAXES AND SET-OFF - Contractor warrants that any and all taxes or municipal claims that may be payable to the City of Pittsburgh by Contractor are current and not delinquent. If the City determined that there is an outstanding delinquency, that delinquency must be satisfied before a contract will be awarded to the delinquent Contractor. If any taxes or municipal claims become delinquent or owing during the term of this agreement or prior to final payment by City, Contractor hereby grants City the right to set-off that indebtedness against any amounts owing to contractor under the terms of this Agreement. If, at any time, the Contractor fails (or has failed) to enter into any contract awarded by the City, the City expressly reserves the right to recoup any and all costs associated with rebidding or reawarding of any contract awarded to this Contractor to another vendor. City reserves the right to apply set-off payments in whatever manner it deems appropriate.

30. CONTRACT NOT TO BE AWARDED TO PERSONS IN ARREARS TO CITY - No contract will be awarded to any corporation, firm or individual who is, for any reason, in arrears to the City or who has failed, in any former contract with the City, to perform work satisfactorily, either as to the character of the work or the time consumed in its completion.

31. CONTRACTOR TO BE QUALIFIED AND RESPONSIBLE - Before the Contract is awarded, prospective Contractors must satisfy the City that they have the requisite organization, capital, plant, ability and experience to satisfactorily perform the work under this contract in accordance with the terms and conditions of the contract and in conformity with the best modern practices and industry standards.

32. COLLUSION BETWEEN BIDDERS - If the City forms a reasonable belief that a prospective Contractor is interested in more than one proposal for the same item, that is sufficient cause for rejection of all proposals in which collusion between bidders is suspected.

Page 28: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

27

34. REJECTION OF BIDS - The City reserves the right to reject, for any reason, any or all bids if it is in the best interest(s) of the City to do so.

35. PAYMENT - It is the intent of the City to pay all invoices resulting from purchases under this contract in forty-five (45) calendar days from invoicing. The City CANNOT pay any INTEREST CHARGES or LATE PAYMENT CHARGES. Any inclusion of such charges may disqualify the proposal from award consideration and/or will be disregarded by the City.

36. AWARD - Award shall be made to the lowest responsible bidder on an item by item or low total basis as the City determines is in its best interests. Bidders should be mindful that the lowest-priced bidder may not be the lowest responsible bidder.

37. CITYWIDE PURCHASES - The award of this contract shall be such that any County or City department may purchase from it at the prices stipulated. The successful Contractor will be required to follow any or all Departmental invoicing procedures. Also, the successful Contractor will be required upon request, if the contract is formulated by the hourly rate and cost plus method, to submit information with its invoice(s) that will substantiate the charges indicated on the invoice(s) in regard to the contract.

38. NON-EXCLUSIVITY - The City reserves the right at its sole discretion to utilize other contracts (such as Commonwealth of Pennsylvania or County of Allegheny contracts) for the services or commodities as described herein. The City also reserves, at its sole discretion, the right to bid separately any service or commodity that may be included in this contract.

39. NOTICE OF AWARD - Regardless of any notification of award to any prospective Contractor, all bids remain open and acceptable by the City for sixty (60) days from the bid opening date. Nothing in this paragraph is to be considered a waiver of the City's rights against a prospective Contractor who fails to execute a contract once it is awarded.

40. COMPLIANCE WITH PENNSYLVANIA "RIGHT TO KNOW" LAW; SUPERFUND - The City of Pittsburgh is obligated to comply with the Pennsylvania Worker and Community Right to Know and Superfund Amendments and Reauthorization Act (“SARA”) Title III laws. Successful Contractors, where applicable, must submit a Material Safety Data Sheet (“MSDS”) for all chemicals that the City purchases from this contract.

Submit all Material Safety Data Sheets to:

Department of Finance Bureau of Procurement, Fleet and Asset Services Room 502, City-County Building

414 Grant Street Pittsburgh, PA 15219

41. PRICE LISTS AND CATALOGUES - When price lists are required for a proposal, price lists are submitted with the bid for the sole purpose of providing an audit reference for the various items on the price list and the manufacturer's price for each item. Price list pricing, as the price list and pricing is stated in the contract, will remain firm for the duration of the contract regardless of manufacturers’ price list changes that may occur during the term of the contract, unless otherwise agreed in the contract. Any reference, which may appear on any price list, to any terms and conditions, such as F.O.B. shipping point or prices subject to change, will not be part of any contract with successful bidders and will be disregarded by the City of Pittsburgh. Any attempts to enforce such terms and conditions will be considered a material breach of the contract and may result in termination of the contract. Contractors agree to supply the using Departments of the City of Pittsburgh with copies of additional catalogues and price lists as requested.

42. LOCATION OF WORK - Service and commodities may be required or deliverable anywhere in the City of Pittsburgh. In the case of Allegheny County’s use of this contract services/commodities may be required or deliverable anywhere in Allegheny County. Prospective Contractors are to understand that work may be required anywhere in the City of Pittsburgh, and shall bid accordingly.

43.SCOPE OF CONTRACT - This contract will include all necessary repair, maintenance, and minor extension work as described elsewhere herein, which cannot be properly estimated or planned in advance, or which may be of any emergency nature. The Director of the Department authorizing the work to be done under this contract shall be the sole judge of repair or maintenance or minor extension work to be carried out under this contract, and shall direct same, and the successful Contractor agrees to accept such

33. AGREEMENT - WHEN TO BE SIGNED - The corporation, firm, or individual to whom the contract is awarded will be required by the Director of the Department of Finance to sign the Articles of Agreement (page 15), prior to the submission of the completed bid package. Failure to sign the Articles of Agreement will render the bid non-responsive. All other required documents must be signed and submitted within fifteen (15) days of the bid opening.

Page 29: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

28

decisions as final and binding and further agrees that nothing in this contract binds the City to carry out all work of this nature under the terms of this contract, but agrees that exceptions may be made and that the City may enter into other contracts for specific work for which plans and/or specifications are separately provided.

44. QUANTITY OF ITEMS/WORK CONTINGENT UPON NEEDS - It is hereby agreed that the City of Pittsburgh does not in any way guarantee or imply the amount of work, services, or commodities which may be required under this agreement. It is also mutually understood between the parties to this agreement that needs cannot be forecast. The intent of this proposal, and the subsequently awarded contract (if any be entered into), is to determine the lowest responsible bidder who will be able, willing, and ready to furnish proper materials, qualified persons, and/or efficient service(s) as required under this contract. No liability shall attach to the City for any decision: (a) to limit the work under the contract; (b) to decline to award the contract; or (c) to decline to order any work to be performed under an awarded contract.

45. SUPERVISION AND INSPECTION - The Contractor further agrees that the work shall be at all times under the immediate supervision of the Director, who shall at all times have free access to all parts of the work and all places where materials for the same are prepared, and shall have every facility made available for the proper inspection of (a) all materials used in, and (b) workmanship executed for the work under this contract. It is expressly understood and agreed that the inspection of the work and materials by the Director will in no way diminish the responsibility of the Contractor, or release him/her from the Contractor’s obligation to perform and deliver to the City sound and satisfactory work. It is further agreed that the Contractor shall obey orders of the Director and by all persons employed on the work.

46. WORK UNNECESSARILY DELAYED - Contractor agrees that, if at any time the Director shall be of the opinion that the work or any part of it is unnecessarily delayed, or that the Contractor is willfully violating any of the conditions or covenants of this contract, or is executing the contract in bad faith, the Director shall have the power to notify Contractor to discontinue all or any part of the work under this contract. Contractor shall then cease work as notified, and will not be entitled to further compensation. The Director shall have the power to place such and as many persons as s/he may deem necessary, the same to be employed by contract or otherwise, to work at and complete the work, and to use such materials as s/he may find upon the work site, or to procure other materials for the completion of the work and to charge the expense of said labor and materials to the Contractor. Any expense so charged shall be deducted from and paid by the City, out of such moneys as may then be due or at any time there after may become due to the Contractor under and by virtue of this agreement. In case such expense shall exceed the sum which would have been payable under this contract, if Contractor had satisfactorily completed the work, the Contractor, their executors, administrators, or assigns shall pay the amount of such excess to the City, on notice of Director of the excess due.

47. FAILURE TO PERFORM CONTRACT - If the contractor fails to perform any of the elements of the contract, the City shall have the right to purchase such materials or supplies from other sources, and to charge to the contractor or the contractor’s sureties any and all expenses arising from the necessity of purchasing materials or supplies, including any excess in price over the prices fixed in the contract. Contractors must remove rejected deliveries within the time specified on a written notification of rejection from the Director of the Department of Finance and/or the Controller. Rejected material left longer than 30 days will be deemed abandoned and the City shall have the right to dispose of such rejected materials as it alone deems appropriate. For perishable foodstuffs, no written notice of rejection will be given; it will be incumbent on the contractor immediately to remove or replace rejected merchandise on verbal notice from the City.

48. CONTRACTOR TO SUSTAIN ALL LOSSES - It is agreed that all loss or damage arising out of the nature of the work to be performed under this contract, or any damages to the work itself, for any unforeseen obstruction or difficulties which may be encountered in the performance of the work or from the action of the elements, or from any cause whatsoever, shall be sustained and paid for by the Contractor until the same shall have been finally accepted and final payment made.

49. CONTRACTOR RESPONSIBLE UNTIL WORK IS COMPLETED - The Contractor further agrees to assume charge of and be responsible for the entire work until completed and accepted by final payment; and that s/he will personally supervise the faithful performance of the work, and that s/he will keep it under Contractor’s exclusive control. In case of absence, the Contractor will designate a competent representative to continue such supervision of the work uninterrupted, and such representative shall receive orders and instruction as appropriate from the Director, and enjoy full authority to execute any such Director’s orders and to supply materials, tools and labor without delay.

Page 30: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

29

50.COMPENSATION - Contractor hereby further agrees that his/her full compensation for furnishing all the required materials, labor, tools, equipment, etc., for the proper execution and completion of the whole of the work, and/or service to be performed under this agreement, will be the amount(s), as set forth in this agreement.

51. TRAVEL TIME - It is understood and agreed that time spent in travel between the Contractor's shop, or, headquarters and the job site, time spent in travel from job to job, or any other travel time shall not be included as a direct charge under the terms of this contract. The Contractor shall claim compensation to be due and payable only for such time Contractor’s employees are actively performing the work, and no other charge(s) for time will be considered.

52. USE OF TRADE NAMES - The use of a name of a manufacturer, or of any special brand, model or make in describing an item or the use of detailed descriptive specifications pertinent thereto, does not restrict bidders to that manufacture or specific article of such detailed descriptive specifications. This means or method being used is simply to indicate the character or quality of the article desired; but the article on which bids are submitted must be of such character, quality and design as will serve the purpose which it is to be used for equally as well as that specified, and must be the equal of the article described and equally suitable to the needs of the City. If bidding on other than the make, model or brand specified or such detailed descriptive specifications therefore, the manufacturer’s name and catalogue reference, together with specifications therefore, must be given or other information given (CLEARLY STATED ON THE PROPOSAL OR BID SHEET IN EVERY INSTANCE) to enable the Director to determine its suitability, or otherwise. The City reserves the right, through the Director of the Department of Finance to be the sole judge in such determinations. WHEN NO REFERENCE IS MADE BY THE BIDDER TO THE MAKE OR GRADE PROPOSED TO BE FURNISHED, IT IS UNDERSTOOD THAT THE SPECIFIC ARTICLE NAMED IN THE PROPOSAL OR BID SHEET WILL BE FURNISHED.

53. INDEMNIFICATION - CONTRACTOR - hereby agrees to indemnify, save and hold harmless, and defend COUNTY/CITY, its officers, agents and employees from and against all liens, charges, claims, demands, losses costs, judgements liabilities, and damages of every kind and nature whatsoever, including court costs and attorney’s fees arising by reason of: the performance by CONTRACTOR of any services under this Agreement; any act, error or omission of CONTRACTOR or of an agent, employee or licensee of CONTRACTOR or subcontractor of CONTRACTOR; and any breach by CONTRACTOR of any of the terms conditions or provisions of this Agreement.

54. MONITORING AND EVALUATION - All services provided under this agreement shall be subject to monitoring and evaluation by City or its authorized representatives. Contractor shall supply City with written reports on program activity, in a form approved by City, as City may, from time to time, require. Contractor shall provide City with such additional information and data as may be periodically required by federal or state authorities, or by City itself. Authorized representatives of City shall have access to the books and records maintained by Contractor with respect to any services or materials provided to City pursuant to this Agreement at all reasonable times and for all reasonable purposes, including, but not limited to, inspecting and copying any books, records, computer disks, memoranda, checks, correspondence or other relevant documents. All such aforementioned records shall be preserved by Contractor for a period of three (3) years after the termination of this Agreement.

55. CONTRACTOR THOROUGHLY INFORMED AS TO WORK - Contractor hereby affirms that s/he has read each and every clause in the advertisement, Information to Prospective Contractors, specifications and agreements relating to this work and fully understands the meaning of each, and hereby agrees that s/he will comply with all the terms, covenants and agreements herein set forth; and that s/he fully understands the character of the work to be performed under this contract.

56. SETTLEMENT OF DISPUTES - It is expressly covenanted and agreed that in the event of a disagreement or controversy arising between the Contractor and the Director as to the interpretation, specifications, or proper execution of this contract, or as to settlement thereunder, or in the event any disagreement, as to any dispute under this contract or the work involved, such dispute shall be brought immediately to the Director’s attention in writing. The Director shall decide upon the dispute and such decision shall be final and conclusive, as to all matters in controversy, without exception or appeal, and all right(s) of action at law, in equity or otherwise, under and by virtue of this contract are hereby expressly waived.

57. ASSIGNMENT; SUBCONTRACTING - Contractor shall not assign this contract or any right to monies to be paid hereunder without the written consent of City. None of the services covered by this contract shall be subcontracted without the prior written approval of City. It is further agreed that no subcontract, if consented to, shall under any circumstances relieve the Contractor of any liabilities and obligations under this Contract, and should any subcontractor fail to perform the work undertaken in a satisfactory manner, such subcontract must be terminated immediately and ended by the Contractor upon notice of the Director so to do.

Page 31: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

30

58. HOME RULE CHARTER: LIABILITY OF CITY - This contract is subject to the provisions of the Pittsburgh Home Rule Charter; and the liability of CITY thereunder is limited to amounts authorized by Resolutions of Pittsburgh City Council.

59. PREVAILING WAGE ORDINANCE - The Contractor agrees that section 161.16(e) of the PITTSBURGH CODE OF ORDINANCES, stating that the Contractor shall pay at least the applicable prevailing wages as shall have been determined by the Secretary of Labor and Industry to the workers employed in the performance of any contract for public work subject to the Pennsylvania Prevailing Wage Act approved August 15, 1961 (Act No. 442), as amended August 9, 1963 (Act No. 342), and the regulations issued pursuant thereto, and all supplements and amendments thereto, shall be made a part of this contract as fully as if attached hereto, and that s/he will comply in all respects with the provisions thereof, insofar as the same affects this contract.

60. ANTI-SWEATSHOP PROVISIONS - Contractor will be required to submit an executed statement of compliance with Pittsburgh Code § 161.02(b)(4), which certifies that nothing has come to its attention that would lead it to believe that any of the goods/products provided herein were made under sweatshop conditions. Goods/products are NOT made under sweatshop conditions if all of the conditions listed in section 161.02(e) of the Pittsburgh Code apply in the manufacturing facility in which the goods/products are made.

If the City is presented with information that would lead the City to reasonably believe that the Contractor or its suppliers may be obtaining goods or products for sale, re-sale, lease or rental to the City that where made under sweatshop condition, upon request of the City, Contractor shall disclose information, data and materials reflecting Contractor’s practices as they pertain to the procurement and manufacturing of goods/products in compliance with the Anti-sweatshop provisions of Pittsburgh Code Section 160.02.

61. WORKERS COMPENSATION - Contractor hereby agrees to perform the work described in this contract in accordance with the Articles of Agreement, and further certifies that it has accepted the provisions of the Worker's Compensation and Occupational Disease Acts, as amended and supplemented, insofar as the work covered by this contract is concerned, and that it has insured its liability thereunder in accordance with the terms of the said Acts, as evidenced by the certificate of insurance it has caused to be attached hereto, or will file with the DIRECTOR OF THE DEPARTMENT OF FINANCE, before the execution of this contract, a certificate of exemption form for insurance from the Bureau of Workmen’s Compensation of the Department of Labor and Industry.

62. COMPLIANCE WITH LAWS - Contractor shall fully obey and comply with all laws, ordinances, resolutions, and administrative regulations, which are or should be applicable to any work performed under this contract.

63. GOVERNING LAW - The contract that is formed subject to these articles of Agreement will be construed and interpreted in accordance with the laws of the Commonwealth of Pennsylvania.

64. DEBARMENT - Contractor warrants that it is not prohibited from entering into this Contract with the City by reason of disqualification under subsection (b) of Section 161.22 of the Pittsburgh Code. An affidavit certifying compliance with this Section is attached hereto as an Exhibit and incorporated into and made a part of this contract.

65. STATEMENT OF AFFILIATIONS - Contractor hereby files a Statement of Affiliations with the City, attached hereto as an Exhibit, in compliance with Section 197.08(c) of the Pittsburgh Code.

66. TERMINATION – The County and City may terminate this contract at any time, without cause or liability, by giving Contractor thirty (30) days advance written notice of its intention to terminate.

67. .OPTION TO EXTEND - the City of Pittsburgh, Department of Finance, in cooperation with the successful contractor(s) in regard to this contract, reserves the right to extend this contract for up to 90 days after the indicated expiration date as described in this contract. This mechanism would be utilized in the event that a lapse in the current contract occurs before a new contract can be established for the goods or services indicated on the contract. When applicable, an extension notice will be issued defining the exact extension of the contract; all other terms and conditions of the extended contract will remain in full force and effect.

Page 32: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

31

68. EXAMINATION OF FINANCIAL RECORDS - Bidder/Contractor shall maintain books, program and financial records, documents and other evidence pertaining to costs and expenses related to this Bid/Agreement in such detail as will properly reflect all costs of labor, materials, equipment, supplies, services and other costs and expenses of whatever nature for which County funding has been provided under the provisions of this Bid/Agreement. The Bidder/Contractor shall maintain such books, records, documents and other materials in accordance with Generally Accepted Accounting Principles, where applicable. The Bidder/Contractor shall provide access, during normal business hours, to such books, program and financial records, documents and other evidence upon request of the County Manager, the County Controller or their designees upon receipt of reasonable advance notice, either oral or written. Bidder’s/Contractor’s books, records, program and financial records, documents and other evidence pertaining to services provided under this Bid/Agreement shall be preserved and made available for a period of three (3) years following the termination of this Bid/Agreement. The County Manager, the County Controller or their designees may audit, examine, review, photocopy, and/or make excerpts or transcripts of any of Bidder’s/Contractor’s books, records, program and financial records, documents and other evidence. Any deficiencies noted in any audit reports or otherwise must be fully resolved by the Bidder/Contractor, to the County’s sole satisfaction, within thirty (30) days after the Bidder’s/Contractor’s receipt of written notice of such deficiencies. Failure of the Bidder/Contractor to comply with the provisions set forth in this paragraph may constitute a violation of this Bid/Agreement and, at the County’s sole discretion, may result in the County withholding future payments.

Page 33: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

32

Print Name of Business *** FOR PAYMENT PURPOSES ***

Business Address Remit to Address

City State Zip Code City State Zip Code

Contact Person Telephone Contact Person Telephone (Print Name) Number (Print Name) Number

800 number if one is applicable Email

FAX number if one is applicable

Email

IN THE PRESENCE OF - INDIVIDUAL

Witness (Individual Principal) PARTNERSHIP

Witness (Partner)

Witness (Partner)

Witness (Partner) CORPORATION

attest Secretary President

(State where Incorporated)

Please check the appropriated box: Corporation Partnership Sole Proprietor Unincorporated

Include either Social Security or Federal Tax Identification Number:

THIS PAGE MUST BE SIGNED IN BLUE INK

Page 34: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

Attachment A STATEMENT OF AFFILIATIONS

Exhibit "1"

1.

Name of Contractor

Office Address and Phone Number

2. List your qualifications and experience for performance of the contract

3. Please give a brief description of any contractual or business relationships you have had with the City within the past three years. Please include the dollar value of the contract or business relationship.

4. Please identify the contractor's principals, including the names and addresses of all owners or partners or shareholders and

officers, or, if the contractor is a public corporation, the officers, the members of the board of directors, and shareholders holding-more than three (3) percent of the corporate stock

Additional pages may be attached to complete the information herein requested.

COMMONWEALTH OR STATE OF

COUNTY OF

) ) SS: )

Page 35: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

2

Attachment B

AFFIDAVIT OF CONTRACTOR UNDER PITTSBURGH CODE §161.22 (f)

BEFORE ME, the undersigned authority, personally appeared

who, being duly sworn according to law,

and under penalty of perjury, deposes and says that neither (s)he nor,

to the best of his/her actual, knowledge, information or belief, the

company, corporation, partnership ("Contractor"), or any affiliated

individual is prohibited from entering a bid or participating in a CITY

of Pittsburgh contract by reason of disqualification as set forth at

Pittsburgh Code §161.22 (b).

Name: Title:

SWORN TO and subscribed

before me this day

of , 20 .

Notary Public (SEAL)

Page 36: County of Allegheny City of Pittsburgh · Pittsburgh, PA 15219. Include one (1) original and one (1) identical photocopy of agreement. Both documents must ... surfaces within the

3

Attachment C

ALLEGHENY COUNTY DEPARTMENT OF ADMINISTRATIVE SERVICES

DIVISION OF PURCHASING AND SUPPLIES

ANTI-SWEATSHOP PROVISIONS

In response to Allegheny County Invitation For Bid or Request For Quotation # ,

certifies that nothing has come to my / our attention that would lead I / us to believe that

any of the goods or products proposed in our Bid or Quotation were made under sweatshop conditions, as defined by Part

9, § 5-903.02 as amended, of Article 903 of the County’s Administrative Code (Ordinance Number 08-07-OR). I /we

certify that I / we have read and understand the above mentioned Administrative Code provisions.

If the County/City is presented with information that would lead the County/City to reasonably believe that the Supplier or its suppliers may be obtaining goods or products for sale, re-sale, lease or rental to the County/City that where made under sweatshop condition, upon request of the County/City, the Supplier shall disclose information, data and materials reflecting Supplier’s practices as they pertain to the procurement and manufacturing of goods/products in compliance with the Anti-Sweatshop provisions of the County’s Administrative Code.

COMPANY NAME:

ADDRESS:

PHONE NO: FAX NO:

CONTACT PERSON: E-MAIL:

AUTHORIZED SIGNATURE

TITLE OF AUTHORIZED SIGNER

Jd/ anti sweatshop supdoc