Criteria to track nZEB
renovations in the Netherlands ERIC 2013 - Energy efficient Restoration International Conference, Groningen, 19 September 2013
Erwin Mlecnik, Ad Straub, TU Delft (OTB)
Bogdan Atanasiu, Sara Kunkel, Ilektra Koulumpi, Buildings Performance Institute Europe (BPIE)
• Introduction - IEE Cohereno: Goal
• Research methodology
• Definitions for nZEB renovations - International developments
- Dutch developments
• The Dutch nZEB radar
• Conclusion
2 Criteria to track nZEB renovations in the Netherlands
• Goal of the Intelligent Energy Europe project COHERENO:
- Reinforce collaboration between suppliers
- for developing an integrated offer
- for “nearly zero-energy“ renovations
- of owner-occupied single-family homes
• Coordinator - Delft University of Technology (NL)
• Partners - Passiefhuis-Platform (PHP), BE;
- Flemish Institute for Technological research (VITO), BE;
- Austrian Society for Environment and Technology (OGUT), AT;
- Segel Consulting Company, NO;
- Germen Energy Agency (DENA), DE;
- Building Performance Institute Europe (BPIE), BE;
- Flemish Contractor Federation (VCB), BE;
- SINTEF Building and Infrastructure, NO.
• Timing - April 2013 – March 2016
3 Criteria to track nZEB renovations in the Netherlands
4 Criteria to track nZEB renovations in the Netherlands
Existing nZEB renovations
Actor listing/ quality
assurance
Structures for supply chain collaboration
Business collaboration
events
Facilitation of new business
models
• Research methodology - Desk research/ literature study on evolution of nZEB
- Presentation for National Advisory Board
- Draft definition development
- Review by selected experts/ policy developers and partners
• National advisory board (NL) - Contractors: BAM Woningbouw, HEMUBO, NDA, OnderhoudNL, Uneto-VNI, VDM (Prestatiehuis),
Weijman Vastgoedonderhoud, E.nu
- Advice and information: SBR, BNA, Vastgoedbelang, VvEs met Energie, VACpunt Wonen, (ICDUBO), (EvEPA)
- Financing and policy: Meer met Minder, Platform31, SVN Stimuleringsfonds Volkshuisvesting, (Rabobank)
• Consulted experts (NL) - Meer met Minder
- Platform31
- SBR
- ICDUBO
- Henk Wegkamp, Carl-Peter Goossen
5 Criteria to track nZEB renovations in the Netherlands
• Definitions of nZEB renovations
- International developments
- Dutch developments
6 Criteria to track nZEB renovations in the Netherlands
Grant Agreement No: IEE/12/704/SI2.645922
COHERENO
Collaboration for housing nearly zero-energy renovation
Criteria to track nZEB housing
renovation
D2.1
6.09.2013
Lead partner: BPIE
Start date of project: 1 April 2013
Duration: 36 Month
Target group: Partners and Public
Classification: PU (Public)
File name : D2.1_BPIE_WP2.1_12/09/2013_(3.4)
Project website: http://www.cohereno.eu/
• Concerted Action supporting EPBD (Erhorn & Erhorn-Kluttig, 2011). - Identifies 23 different terms in use to describe energy-efficient buildings
across Europe (according to EPBD, 2010)
- Notes that Passive House voluntary standard is probably the best-defined and -accepted in various countries and regions
• nZEB Principles for nearly Zero-Energy Buildings (BPIE,2011) - proposed further thresholds for primary delivered energy, renewable energy
share and CO2 emissions
• REHVA Task Force on nZEB (REHVA, 2011) - Defines nZEB through the net zero energy building, which is a building
using 0 kWh/(m²a) primary energy under national cost-optimal conditions
• IEA Task 40 Annex 52 (http://task40.iea-shc.org/) - Introduces a better understanding of Net Zero Energy Buildings (source
book, verification tool and data sets)
7 Criteria to track nZEB renovations in the Netherlands
A variety of nZEB terms is already being used
• Energy Efficiency Directive (EED, 2012) - Article 4 requires member states to establish a long-term strategy
for the renovation of the building stock.
- Defines the need for cost-effective deep renovation.
- Introduces ‘deep renovations’ as ‘refurbishments that reduce both the delivered and the final energy consumption of a building by a significant percentage compared with the pre-renovation levels leading to a very high energy performance’
• Global Buildings Performance Network (GBPN, 2013) - Noted worldwide various existing terms regarding deep renovation,
such as Deep (Energy) Renovation, Deep (Energy) Retrofit, Deep (Energy) Reduction, Zero Carbon/Energy Renovation, Factor 2,4,6,10 Renovation..
- Concluded that a ‘window of possibility’ exists for defining a ‘deep renovation’.
- Proposed a common definition for deep renovation:
8 Criteria to track nZEB renovations in the Netherlands
Only few references aim to define nZEB for renovation
• The energy performance after renovation fulfils the nZEB requirements for new buildings as they are defined at level of the EU MS and regions or/and
• The primary energy consumption after renovation is reduced by 75% as comparing to the pre-renovation status or/and
• Potentially additional: – Limit primary energy consumption for heating/cooling, domestic hot
water, ventilation energy consumption of auxiliary building’s systems (e.g. ≤ 50-60kWh/m2/yr (GBPN, 2013))
– Define renewable energy share (e.g. at least 50% of the remaining energy demand)
– Define minimum CO2 requirement (e.g. ≤ 3kg CO2/m2/yr suggested in (BPIE, 2011) based on the needs to meet the sectoral long-term decarbonisation goals)
9 Criteria to track nZEB renovations in the Netherlands
Potential definition of deep renovation of a house (GBPN, 2013)
E.g. Netherlands: “Nationaal Plan Bijna Energieneutrale Gebouwen (BENG)” (October 2012)
• ‘Energy neutral’ buildings are defined as: EPC=0 according to NEN 7120 - Calculates net energy use on a yearly basis applying standard
useage and climat
- Energy use inside the building, energy production inside or outside the building
- 2015: EPC from 0,6 to 0,4; obligation from the end of 2020
• For deep renovations that follow the Dutch Building Decree ‘Nearly energy neutral' means ‘in the neighborhood of EPC = 0’
10 Criteria to track nZEB renovations in the Netherlands
Legal nZEB definitions have mainly been developed for newly-built constructions
E.g. Brussels Capital Region: the Energy Performance of Buildings Ordinance (MB, 2011) requires
from January 2015 onwards for residential buildings:
- a primary energy consumption for heating, domestic hot water and auxiliary energy below or
equal to 45 kWh per m² per year;
- a net space heating need below or equal to 15 kWh per m² per year;
- ..
• Major renovations: the renovation activities cover at least 75% of the heat loss surface area and
the HVAC system.
- all limits for requirements are multiplied with a factor 1.2 (except for indoor temperature overrun)
• Small renovations:
- requirements on thermal insulation (U-values and risk assessment of thermal bridges) and ventilation.
• Allternative solutions possible taking account of specific urban characteristics such as a poor
compactness and/or less solar gains, requiring thermal insulation (U-) values of the building skin:
- average U-value 0.85 W/m²K for transparent parts;
- average U-value 0.12 W/m²K for non-transparent parts
11 Criteria to track nZEB renovations in the Netherlands
Only a few countries already have a legal framework for nZEB renovation
• Energy labels/ energy performance certificates (NL) – usually only for homes that are being sold or rented (including
relatively new homes)
- not clear if and how a house was renovated
- not clear which range can be defined as nZEB
12 Criteria to track nZEB renovations in the Netherlands
Energy label systems exist but nZEB renovations can not easily be detected
• nZEB renovations already exist with voluntary ‘quality assurance’ - Passive house certified projects
- Awards (e.g. Nationale Renovatieprijs/ Klus je Rijk/..)
• Large-scale nZEB experiments are ongoing in various countries - Lokaal Alle Lichten op Groen
- Blok voor Blok
• nZEB homeowner web communities exist - www.nzebopendoorsdays.eu
- www.huisvolenergie.nl
• Integrated nZEB renovation concepts are promoted - www.one-stop-shop.org
- www.ikhebeenidee.nu
13 Criteria to track nZEB renovations in the Netherlands
The nZEB renovation market runs ahead of policy development
14 Criteria to track nZEB renovations in the Netherlands
Actor listing/ quality
assurance
Structures for supply chain collaboration
Business collaboration
events
Facilitation of new business
models
Existing nZEB renovations
nZEB working definition needed leading to a sufficient but limited number of actors
• Include a broad range (applicable for all countries): - Adopted future requirements for new or existing buildings
- Passive House
- Energy Performance Certificates
- Governmental support schemes (e.g. Energiesprong)
- Combination of measures from a predefined list
- Existing projects or lists where relevant market actors can be identified
- Other existing databases with exemplary renovation
• Define four nZEB levels in each country - Depending on the number of projects in each country
- Depending on the legal and market situation in each country
- General rule: the closer to zero energy, the better
15 Criteria to track nZEB renovations in the Netherlands
The nZEB radar A tool for tracking nZEB home renovations
16 Criteria to track nZEB renovations in the Netherlands
1. Highest performance level, e.g. Energy
class A++ on EPC, NZEB, countries nZEB 2020 definitions including significant renewable energy generation onsite or nearby
Countries’ nZEB 2015 definitions
4. walls, floors and roofs renovated at very high U-values + correct ventilation
3. National Databases: energy class A or B renovations and ≤ 90-100 kWh/m2/yr
2. Buildings with additional quality assurance test included, e.g. passive house
Discussion nZEB radar A framework for tracking nZEB home renovations
17 Criteria to track nZEB renovations in the Netherlands
The Dutch nZEB radar A tool for tracking nZEB home renovations in the Netherlands
1. EPC 0; alternatively energy bill 0 (frontrunner renovations included in “Lokaal Alle Lichten Op Groen”)
Renovation to EPC ≤0,4 (new buildings requirement in 2015) or label A+
4. Min. label A; alternatively max. space heating; alternatively at least 3 thermal insulation measures + controlled ventilation
3. Frontrunner renovations included in “Huis Vol Energie” or ”Blok voor Blok”
2. Min. label A++, alternatively: Passive House certificate
• Conclusion - Most national action plans in the framework of the EPBD
development did not sufficiently address the definition of an
nZEB renovation
- A national legal definition for nZEB renovation is currently
missing
- The market runs ahead with various initiatives
- The proposed Dutch nZEB radar will be used for tracking
renovations and listing actors in a public list
18 Criteria to track nZEB renovations in the Netherlands
Actors: apply now to become ‚listed‘!
Criteria to track nZEB renovations in the Netherlands 19
Sleephellingstraat Rotterdam
Level 2 (Quality assurance number 09.WR.0001)
Contractors: BAM Woningbouw Volker Bouwmaatschappij Rotterdam
Co-makers: Ferroli, Niveau Kozijnen, Rockwool Benelux, Sto Isoned
Architect: Villanova Architecten Rotterdam
Consultant: Trecodome Roosendaal
Lombardstraat Middelburg
Level 2 (Quality assurance number 10.WR.0001)
Contractor: Bouwgroep Peters Middelburg
Architect: RDH Architecten en Stedenbouwkundigen Middelburg
Consultant: DHV Amersfoort
Thank you
www.cohereno.eu
www.otb.tudelft.nl
www.bpie.eu
Contact: Ad Straub, TU Delft
phone: +31 (0)15 27 82769
Criteria to track nZEB renovations in the Netherlands 20
The sole responsibility for the content of this presentation lies with the authors. It does not necessarily reflect the opinion of the European Union. Neither the EACI nor the European Commission are responsible for any use that may be made of the information contained therein.