crossrail brief to incose · crossrail brief to incose chris sexton technical director ... • each...
TRANSCRIPT
What is Crossrail?• Largest civil engineering project in Europe• Biggest addition to London and South East transport
network for 50 years • High-frequency, convenient and accessible rail service
linking Maidenhead and Heathrow to the City, Docklands, Kent and Essex
Crossrail Services• Crossrail will operate 24 trains per hour through the
central tunnel in the peak• Each train will be 200m in length and will be capable
of carrying up to 1,500 seated and standing passengers
Business caseBusiness case
10% extra capacity
1.5 million people within 45mins of central London
GDP benefit - £42bn
14,000 Jobs
Business OutcomesBusiness Outcomes
World Class• Passenger experience• Railway Operations• Industry Legacy
2 MajorStructures
27 Stations(10 Major)
Track 66km 61 PlatformExtensions
360 SignallingUnits
2 ReplacementInterlockings
CrossrailCrossrailSurface WorksSurface Works
Electrification146km
112 CabCCTV Platforms
Key Challenges• Safety, value, cost and time• Being a good neighbour• Systems Integration• The right trains• The right architecture/art• 2018 World Class
Client / project wide rules and/or initiatives, best or most efficiently
done once
PC with another scheme
Golden Rules, Occupational Health standards,Site Safety newspaper, technical training and standards
D&A policy, Method Statement standards, RIVO/info sharing etc
PC with Zero Harm.
ZeroHarm
PC With IIFContractors’ basic H&S / site management and
control, assured on evidence/observation
Contractors’ own H&S programmes, behavioural, near‐miss reporting, Safety Stand‐downs etc
CRL’s client responsibilities under CDM, HSAWA etc
CRL’s vision ‐ home safe every day,new standards for Health and Safety performance (both leading and
lagging indicators)
Legal and clientresponsibilities
TargetZero
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
May 2009 Construction started
2013 - 2018Systems Integration &
Commissioning
2012 - 2018Tunnelling and StationsLaunch first TBM March 2012
2017 - 2018Trial-RunningPhased Opening
Key PhasesKey Phases
Crossrail ‐ Physical % Complete
0.00
20.00
40.00
60.00
80.00
100.00
120.00
2Q081Q
093Q
091Q
103Q
101Q
113Q
111Q
123Q
121Q
133Q
131Q
143Q
141Q
153Q
151Q
163Q
161Q
173Q
171Q
183Q
181Q
193Q
19
% Com
plete
Design
Procurement
Construction
Testing & Comm.
Retail Park
Canary Wharf Station
Retail ground level
Retail promenade level
Retail
Retail
Station Ticket hall level
Station Platform level
Tunnelling• All contracts awarded
Royal Oak portal completed and handed over
• Conducted Factory Acceptance Test of first TBM
• Shaft construction underway at LimmoPeninsula, Stepney Green, Liverpool Street and Whitechapel
• Segment manufacturing facility commissioned
• Portal construction underway at Pudding Mill Lane and Plumstead
• First TBM launches March 2012 from Royal Oak Portal
StationsStations• Main works contracts awarded for
Paddington, Farringdon and Whitechapel
• Paddington integrated project scheduled relocating taxis in February 2012
• Diaphragm wall advance works underway at all stations
• Compensation grout shafts underway• Spray Concrete Lined access shafts
underway at Liverpool Street and Whitechapel
• Woolwich Station: Successful completed utilities diversion and surface ( ~3m) strip.
• Canary Wharf station well advanced
High Level Programme2017 20182013 2014 2015 20162011 2012 2019
Central Section Works
Central Section Construction
Track/Systems Installation
Aug 2018
ProcurementRolling Stock & Depot
Design & Manufacture Trains
Central Section T & C
Old Oak Common
1st Train @ OOC
Surface Works
Western Inner
South East
North East
Western Outer
Stage 1 – NE Leg Substitution
Stage 2 – H/L Paddington to Heathrow
Stage 3 – L/L Paddington to Abbey Wood
Stage 4 – L/L Paddington to Abbey Wood & Shenfield
Stage 5 – Full Service Opening
May 2017
May 2018
Dec 2018
Dynamic Testing/Trial Running
Trial Ops
20122012• This year is an even more important year• Critical year for Systems procurement• First TBM launch at Royal Oak Portal – Drive X –
March 2012 • Wallasea Island operational – July 2012• All station contracts awarded – August 2012• Start tunnelling Y-Drive from Limmo – October 2012• Both TBMs on X-Drive meet at Bond Street –
December 2012
West
West
West tunnels - TBM launch at ROPWest Tunnels - commence production of segment rings PIP - complete steel erection; start installation of lift, escalator, and canopy glass to bring the Taxi facilityinto usePAD - commence D-Walling for the main stationTCR - complete piling and D-Walling for the main station and start of excavation
Summary of key activities next six monthsSummary of key activities next six months
Summary of key activities next six monthsSummary of key activities next six monthsCentral
Central
Award C502 contract for Liverpool Street main station worksAward C340 and C360 for Victoria Dock Portal and Eleanor Street/Mile End shaftsCommence diaphragm wall works at Whitechapel and Liverpool StreetCommence compensation grouting TAMs at WhitechapelFactory acceptance testing for first C305 TBM
Summary of key activities next six monthsSummary of key activities next six monthsEast C310 Thames tunnel and
Woolwich: Commence diaphragm wall works for Plumstead portal and Woolwich box.C310 Thames tunnel: Commence
mobilisation to North Woolwich, including completion of utility diversion work by contract C233.C315 Connaught tunnel: Issue IFC drawings and specs, and commence piling work on surface section.Custom House station: Issue
tender documentation.
Systems Integration Defined• Definition for Crossrail:
“Systems Integration ensures the rail systems, rolling stock and infrastructure, combined with operations and maintenance inputs, delivers a resilient operational railway meeting Sponsors’Requirements”
29
CRL is ‘System Integrator’• Requirements & Configuration
– Engineering Change Control and Requirements Management– Standards & Concessions
• Systems Delivery– Project Management and Interface Engineering– Review & Acceptance of Contractor Designs
• Systems Engineering & Integration– System Architect, RAMS, Modelling, Ops Concepts etc.
• Engineering Safety Management– Management of Notified Body, System Safety Plans etc.
• CRL / NR / LU / RfL Interfaces– Joint Working Groups, Traffic Management, Operating Rules
• Testing & Commissioning– Testing, Commissioning and Handover
30
• 'The collapses could have been prevented but a cultural mindset focused attention on the apparent economies and the need for production rather than the particular risks, ' it says.
• 'Warnings of the approaching collapse were present from an early stage in construction but these were not recognised.‘
• Errors were made, it says, 'leading to poor design and planning, a lack of quality during construction, a lack of engineering control and most importantly a lack of safety management.'
• Investigators found the incident exhibited 'all the hallmarks of an organisational accident‘.
Client Client -- Technical AuthorityTechnical Authority
Heathrow Express Tunnel Collapse Heathrow Express Tunnel Collapse
Systems Design and Assurance• Systems developed to ‘Reference Design’ stage by CRL. • Reference Design includes performance output based Technical &
Interface Specifications in Works Information (except Floating Track Slab based on Engineers Design)
• Systems Contractors will perform Detailed Design and Build (D&B)• CRL responsibilities include:
– Reviewing and accepting designs from D&B Contractors– Managing development of integrated railway system designs (30%, 60%,
90% design review and acceptance gates)– Co-ordinating work of Systems, Rolling Stock and Civil Contractors – and
securing development of end-to-end railway against controlled baselines– Securing acceptance of the designs from the IM’s as well as testing,
commissioning and handover of completed railway– Providing necessary assurance evidence to IM’s under ROGS Regulations– Appointing and managing a Notified Body (NoBo) as part of legal commitment
under the Interoperability Regulations33
Systems Integration Authority (SIA)• Technical Authority for “end-to-end route” Integration• Represented by competent technical heads from CRL,
NR, LU and RfL• Ensures System Integrity • Owns configuration of the whole railway• Ensures coherence between the design, operations,
maintenance and safety• Reviews integration issues and change proposals• Communicates Integration status• Provides single-point co-ordination and support
34