Cryo Capture Cavity II Progress Mike McGee April 6, 2005

Upload: sani

Post on 06-Jan-2016

32 views

Category:

Documents


0 download

DESCRIPTION

Cryo Capture Cavity II Progress. Mike McGee April 6, 2005. DESY will Provide. 1.3 GHz cavity. Helium vessel. Magnet shielding (short). 2 VAT valves. Input coupler assembly. Status at Fermilab. Finalizing US AND DS warm-to-cold transition and VAT valve to cavity spool design. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Cryo Capture Cavity II Progress

Cryo Capture Cavity II Progress

Mike McGee April 6, 2005

Page 2: Cryo Capture Cavity II Progress

DESY will Provide

•Input coupler assembly

•2 VAT valves

•Magnet shielding (short)

•Helium vessel

•1.3 GHz cavity

Page 3: Cryo Capture Cavity II Progress

Status at Fermilab

•Designing VAT valve supports, shipping/installation fixture (to be made of 316 L)

•316 LN material and tube ready to order

•316 L bellows specified and ordered (to arrive 4/24)

•Finalizing US AND DS warm-to-cold transition and VAT valve to cavity spool design

Page 4: Cryo Capture Cavity II Progress

US warm-to-cold transition

Page 5: Cryo Capture Cavity II Progress

DS warm-to-cold transition

Page 6: Cryo Capture Cavity II Progress

Fermilab will Provide•To be send to DESY

•Cleaned US and DS warm-to-cold transitions (w/isolation flanges on ends and slight positive Ar pressure)

•Drawing and procedure for assembly with fixture to be shipped

•Shipping/installation fixture

•Cleaned VAT valve supports

•Cleaned helium vessel support clamps

•Cleaned spool between cavity and VAT valve (also capped on ends)

Page 7: Cryo Capture Cavity II Progress

Fermilab will Provide•Currently at Fermilab

•Vacuum vessel and instrumentation•80 K shielding•5 K manifold•Tuner •2 Spare VAT valves

Page 8: Cryo Capture Cavity II Progress

Process•Send to DESY (May 2005)

•Cleaned US and DS warm-to-cold transitions and spool

•Under argon positive pressure

valvew/filter

blankflange

Page 9: Cryo Capture Cavity II Progress

Process cont…

•2 helium vessel support clamps

Page 10: Cryo Capture Cavity II Progress

Process cont…•VAT valve supports

Page 11: Cryo Capture Cavity II Progress

Process cont…•Shipping/installation fixture with temporary supports for bellows with crate

Page 12: Cryo Capture Cavity II Progress

Process cont…•Work at DESY (May-June 2005)

•Warm-to-cold transition•Magnet shielding

•VAT valves with supports

•Cavity and helium vessel•Assemble

•Clean US and DS warm-to-cold transitions

•Spool between VAT valve and cavity

Page 13: Cryo Capture Cavity II Progress

Process cont…•Send to Fermilab (July 2005)

•Assembled cavity with VAT valves, shielding, spool and transitions

Page 14: Cryo Capture Cavity II Progress

Process cont…•Work at Fermilab (July-August 2005)

•Modify helium return

•Install cavity assembly into vacuum vessel

•Pressure test helium vessel

•Make up cryogenic connections

•Test fit feedcan and leak check circuits

Page 15: Cryo Capture Cavity II Progress

Process cont…•Install cavity assembly into vacuum vessel

Page 16: Cryo Capture Cavity II Progress

Layout

Page 17: Cryo Capture Cavity II Progress

Layout

Page 18: Cryo Capture Cavity II Progress

Process cont…

•Make up cryogenic connections

•Test fit feedcan and leak check circuits

•Commission Cryo Capture Cavity II

Page 19: Cryo Capture Cavity II Progress

Questions and RequestsNeed DESY cleaning procedure

Need to confirm critical measurements

Page 20: Cryo Capture Cavity II Progress

ScheduleMicrosoft Excel

Worksheet