cryogenic update before fermilab meeting (and after the helium tank review) coordination meeting 6...

15
Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1 1

Upload: fay-dalton

Post on 05-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1

1

Cryogenic updatebefore Fermilab meeting

(and after the helium tank review)

Coordination meeting 6th May 2015

K. Brodzinski

HiLumi-LHC-CC-Cryo-PPT-18_v1

Page 2: Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1

K. Brodzinski - CC coordination 2015.05.062

Contents

• Main refrigerator – update after cost and schedule review

• Heat load evolution and limitations

• Helium tank review and remarks

• Flow diagrams and interfaces for SM18 and SPS

• Work progress and conclusions

Page 3: Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1

K. Brodzinski - CC coordination 2015.05.063

Infrastructure – SPS simplified layout

After cost and schedule review, taking into account present possibilities of helium liquefaction for SPS test, it was preliminarily approved to orient the solution of cold box selection to a new refrigerator. The refrigerator will be configured as mobile plug and play mobile cold box with capacity of ~800 – 1000 W @4.5 K i.e. ~10 g/s of liquefaction rate.

Page 4: Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1

K. Brodzinski - CC coordination 2015.05.064

Heat load summary tableThe summarized heat load overview concerns the evolution of heat inleak analysis into the Crab Cavity SPS test module over design period between 2012 and 2015.

Additional information:- Column B – calculation done for BA4 with ~10m long transfer line- Column C – represents required liquefaction at 2 K to cover heat load from column A- Column D – represents required liquefaction at 4.5 K to cover heat load from columns B- Column E – represents converted from 2 K to 4.5 K required liquefaction to cover heat load from column A- Column F – represents total required liquefaction rate at 4.5 K, sum of values from columns D and E- Column G – represents total required liquefaction rate from column F multiplied with factor 1.5

A B C D E F GYear CC load at 2 K cryo infra load at 4.5 K req. lique at 2 K req. lique at 4.5 K req. lique at 4.5 K req.tot.lique @4.5 K req.tot.lique. at 4.5 K

2011.5 W W g/s g/s (only 4.5 K load) g/s (only 2 K load) g/s g/s (*1.5)2012 11.6 2.8 0.50 0.15 0.56 0.71 1.062013 13.4 7.4 0.58 0.39 0.65 1.04 1.56

2013.9 25 8 1.08 0.43 1.21 1.63 2.452014 32 8 1.39 0.43 1.54 1.97 2.952015 32 8 1.39 0.43 1.54 1.97 2.95

Page 5: Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1

K. Brodzinski - CC coordination 2015.05.065

Heat load evolution curve

The summarized heat load overview concerns the evolution of the analysis of the heat inleak into the Crab Cavity SPS test module over design period between 2012 and 2015.

Page 6: Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1

K. Brodzinski - CC coordination 2015.05.066

Required liquefaction rate and cold boxes capacity

The new proposed mobile cold box is not included in the above curve. It will have liquefaction capacity of about 8-10 g/s and will allow for using of full capacity of 2 K pumping units (~3.5 g/s @30 mbar) as well as to cover requirements for 80 K screen cooling with helium gas.

Page 7: Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1

K. Brodzinski - CC coordination 2015.05.067

2 K helium pumps

2 stage pumping group

2 batteries of He gas bottles

<200 bar

2 stage pumping group (Leybold: RUVAG WS2001 and SV630)

PT01: pressure transmitter, Rosemount, 0… 2000 mbara TT01: Pt100FT: flow transmitter, Brooks, 0… 1.5 g/sPT02: pressure transmitter, GE, 0… 100 mbara

Recuperation line towards liquifier

PSV01

PI02

PI01

PI03

HV01

HV04

FT

PT01

TT01

PT02

HV02

HV03

The check shows that assuming inlet pressure of 20 mbar two pumping units are capable to pump ~2.3 g/s of helium, what gives ~3.5 g/s at 30 mbar (2 K saturation)

Capacity >2.9 g/s -> OK for CC SPS testKEK 2014

Page 8: Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1

K. Brodzinski - CC coordination 2015.05.068

Helium tank reviewGeneral remark: very interesting, with nice progress of work

Specific remarks:

• Superfluid helium layer above the cavity should be maximized between the cavity

and the tank wall,

• Magnetic shield should be with min. distance from cavity wall of 5 mm,

• Cool down line to be connected in the middle of enlarged bypass between the

helium tanks,

• Helium head above the cavity is to be reviewed and redesigned – requirements

from Fermilab 2012 meeting are not respected because of integration geometrical

problems.

• Probably additional helium tank of ~8 L will be necessary to be integrated

between the cavities – tbd. see next slides. The goal is to design the He head

in the way to allow linear lowering of the level over the head height

(necessary for reliable regulation reasons).

Page 9: Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1

K. Brodzinski - CC coordination 2015.05.069

Helium volumeEstimation of needed helium volume in the cryostat – for one cavity.

9

Volume A – layer of L mm of helium,Volume B – additional helium volumeVolume C – additional head of helium for transients(for C=7dm3 -> ~30 min for head evaporation, loading at 20 W)

Assumptions:• Cavity in shape of a cylinder (D=175 mm, Lcav=700 mm)• Helium layer of L mm of thickness analyzed (see data below)• Head of additional Lc=50 mm layer of He taken above the cavity (see figure below)

Volume A

Volume B

Volume C

L A B Lc C total He volumemm dm3 dm3 mm dm3 dm310 4.66 2.94 50 7.02 14.6220 10.02 3.68 50 7.96 21.6630 16.12 4.51 50 8.93 29.5640 22.99 5.45 50 9.95 38.3950 30.66 6.5 50 11 48.16

Operation with one buffer tank of 8 m3 is limited …

“The CC x 2 cryostat should not be bigger than 40 dm3 (if reasonably possible)”

L

LcLcav

D

L

Fermilab 2012

Page 10: Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1

K. Brodzinski - CC coordination 2015.05.0610

GHe return collectorRecommendations coming from LHC cryogenics operation.

10

~ 30

mm

~100

mm

LHC RF GHe return line (too low for reliable level regulation)

GHe return collector should be placed on side as presented in above sketch, with reasonable distance above LHe level (~ 100 mm) for reliable level regulation (avoiding LHe presence in return line). The supply tapping is recommended to be placed in gas volume “far” from outlet pumping ports for efficient separation during the filling.

Volume of ~10 – 15 liters is to be respected (without collector)

Fermilab 2012

Page 11: Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1

112015-05-06 - R.Leuxe - CERN

1. Main Views of DQW & RFD Designs

DQW RFD

Page 12: Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1

K. Brodzinski - CC coordination 2015.05.0612

Helium head – optionsLevel decrease profile - sketch

Level decrease profile - sketch

Page 13: Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1

K. Brodzinski - CC coordination 2015.05.0613

SPS PFD for crabs4.5 K cold box

> 15

0 L

dew

ar

Valve box CC module

Heater for returning gas

Helium storage

To recovery system

VLP 2 K, 30 mbar

Supply 2 K, 30 mbar

C-D supply 4.5 K, 1.3 mbar

4.5

K tr

ansf

er li

ne

Return 80 K, 4 bar

flex

flex

flex

flex Supply screen 50 K, 4 bar

50/8

0 K

tran

sfer

line

Compressor and pressure management panel

Shuffling module

TT PT LT

TT

EH

TT

TT

EH

TT

PT

LT

1.3 bar

Page 14: Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1

K. Brodzinski - CC coordination 2015.05.0614

SM18 interface for crabs

> 15

0 L

dew

ar

Valve box CC module

VLP 2 K, 30 mbar

Supply 2 K, 30 mbar

C-D supply 4.5 K, 1.3 mbar

Liqu

id s

uppl

y 4.

5 K,

1.3

5 ba

r

Return 80 K, 1.1 bar

flex

flex

flex Supply screen 5 K, 1.2 bar

Scre

en s

uppl

y 5

K, 1

.2 b

ar

TT PT LT

EH

TT

EH

TT

PT

LT

Vapo

r ret

urn

4.5

K, 1

.1 b

ar

1.35 bar

Scre

en re

turn

80

K, 1

.1 b

ar

VLP

3 K,

30

mba

r

flex

Double channel coaxial bayonet

Internally sealed flange, externally sealed mobile sleeve

Internally welded, externally sealed mobile sleeve

Page 15: Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1

K. Brodzinski - CC coordination 2015.05.0615

Work progress and conclusions• Work is progressing well, specification for cold part of the infrastructure advanced

in ~50 %, order to be done in Autumn 2015, produced by end of 2016 for SM18 test on the beginning of 2017,

• New cold box to be ordered in Autumn 2015 to be delivered at CERN by mid 2017,

• Regular progress meeting between CRG and MME necessary from mid May 2015 (every week or 2 weeks),

• Close collaboration between CRG and MME concerning the CC cryomodule in place and to be continued,

• Definition of location for SPS test strongly needed!