cscp project management procedures

21
CSCP Project Management Procedures PRINCE2 Methods

Upload: kaleb-mulat

Post on 15-Apr-2017

111 views

Category:

Documents


8 download

TRANSCRIPT

Page 1: CSCP Project Management Procedures

CSCP Project Management Procedures PRINCE2 Methods

Page 2: CSCP Project Management Procedures

Why Do You need P. management tool?

• Non uniformity • Late project completion • Misuse Budget • Poor quality of products • No lesson has been taken • Uncontrolled risk • Uncontrolled scope • Poor planning

Page 3: CSCP Project Management Procedures

What Is PRINCE2? PR-project IN C- controlled E- environment Project parameters Time, cost, quality, scope, benefit, risk

Page 4: CSCP Project Management Procedures

Elements of PRINCE2Principle

s

Themes

Process

Tailoring

Page 5: CSCP Project Management Procedures

The Seven Principles of PRINCE2

Continued Business

justification

Defined Roles &

Responsibilities

Learn from experience

Mange By stage

Manage By Exception

Focus on products

Tallor to suit the project

Page 6: CSCP Project Management Procedures

The Seven themes of PRINCE2

Business case

Organization

Quality

PlansRisks

Change

Progress

Page 7: CSCP Project Management Procedures

The Seven Process of PRINCE2

Starting up a project

Directing a project

Initiating a project

Controlling a stage

Managing project

delivery

Managing a stage

boundary

Closing a project

Page 8: CSCP Project Management Procedures

ScopeThis document will be applicable to all type projects carried out by WWDSE.

Page 9: CSCP Project Management Procedures

Project Organization Corporate

DCEO for Engineering Works CEO DCEO for Supporting Works

Project Board Executive:

Planning Senior User:

HR and Finance processes Senior Supplier:

Construction Supervision Core Process

Design Core Process (optional)

Project Assurance: Sub Processes

Project Coordinators Editorial Quality

Controller

Project Manager: Resident Engineer

Project Support: IT Accountant Secretary Drivers

Team 01Manger Team 02 Manger Team 03 Manger

Page 10: CSCP Project Management Procedures

Roles and Responsibilities Project Board• The Project Board is accountable to corporate or programme

management for the success of the project, and has the authority to direct the project within the remit set by corporate or programme management as documented in the project mandate.

• The Project Board is also responsible for the communications between the project management team and stakeholders external to that team (e.g. corporate and programme management).

• Project Board members may delegate some Project Assurance tasks to separate individuals.

• The Project Board may also delegate decisions regarding changes to a Change Authority.

Page 11: CSCP Project Management Procedures

Roles and Responsibilities

Project Assurance:• Project Assurance covers the primary

stakeholder interests (business, user and supplier).

• Project Assurance has to be independent of the Project Manager; therefore the Project Board cannot delegate any of its assurance activities to the Project Manager.

Page 12: CSCP Project Management Procedures

Roles and Responsibilities

Project AssuranceOverall Responsibility:• The quality methods are being correctly followed • Quality control follow-up actions are dealt with

correctly • An acceptable solution is being developed • The scope of the project is not changing

unnoticed • Internal and external communications are working • Applicable standards are being used • The needs of specialist interests (for example, security)

are being observed.

Page 13: CSCP Project Management Procedures

Roles and Responsibilities

Project Manager:• The Project Manager has the authority to run the

project on a day-to-day basis on behalf of the Project Board within the constraints laid down by them.

• The Project Manager's prime responsibility is to ensure that the project produces the required products within the specified tolerances of time, cost, quality, scope, risk and benefits.

• The Project Manager is also responsible for the project producing a result capable of achieving the benefits defined in the Business Case.

Page 14: CSCP Project Management Procedures

Roles and Responsibilities

Team Manager(s):• The Team Manager's prime responsibility

is to ensure production of those products defined by the Project Manager to an appropriate quality, in a set timescale and at a cost acceptable to the Project Board.

• The Team Manager role reports to, and takes direction from, the Project Manager.

Page 15: CSCP Project Management Procedures

Procedures Pre Project

Prepared By

Product Process Approved

Contract Management

Project Mandate

Corporate

Starting Up Project

Project Manager

Stage Plan

Project Board

Project Manger

Project Brief

Project Board

Page 16: CSCP Project Management Procedures

Procedures Initiation Stage

Prepared By Product Process ApprovedInitiating a

projectProject Manger PID Project

Board Project Manger Benefit

Review Plan

Project Board

Managing stage

BoundaryStage Plan Project

Board

Page 17: CSCP Project Management Procedures

Procedures Subsequent Stages

Prepared By

Product Process Approved

P. Manger End stage assessment

Project Board

Directing a project

Team Leader

WP P. Manager

Controlling Stage

Team Leader

CP Report P. Manager

Team Leader

WP Comple P. Manger

Page 18: CSCP Project Management Procedures

Subsequent Stages

Prepared By Product Process ApprovedProduct Delivery

PM Highlight report Project Board Controlling Stage

Page 19: CSCP Project Management Procedures

Procedures Final Stages

Prepared By Product Process ApprovedTeam Leader WP P. Manager

Controlling Stage

Team Leader CP Report P. ManagerTeam Leader WP Comple P. Manger

Product Delivery

PM Highlight report

Project Board

Controlling Stage

PM End Project Report

Corporate

Closing A project

Page 20: CSCP Project Management Procedures

Records CEOs, EOs, SPMs, should ensure the records are maintained, included; •Project Mandate;•Authorise Project •Project File •Project Brief;•Plan •Authorise initiation •Project Initiation Document (PID);•Organization•Business Case •Product Description •Project Quality Plan•Product Status Checklist •Benefit Review Plan •Work Package•Lesson Log

Page 21: CSCP Project Management Procedures

•Stage Log•Issue Register •Risk Register•Project/Stage Log/Diary •Project Stage Log•Issue Report•Lessons Report •Quality Review Error List•Quality Review Follow-up Action List•Quality Review Invitation•Quality Review Sign-off•Check Point Report •Risk Management Strategy •Highlight Report•Project Highlight Report•Programme Highlight Report •Exception Report •End Stage Report •Authorise Exception Plan •Authorise Continuation •End project report•Plan Text