csn1, 14 maggio 2007 calorimetria em a lar di atlas 1 eca barrel ecc
TRANSCRIPT
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 1
Calorimetria EM a LAr di ATLAS
ECA
Barrel ECC
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 2
Detector Status Barrel:
Cold and filled with Lar. In stable conditions since June 06
Endcap A (ECA): Cold and filled with Lar.
In stable conditions since mid March 07
Endcap C (ECC): Cool down started on
March 22 and should be finished by the beginning of June
ECA cool- down
80,00
100,00
120,00
140,00
160,00
180,00
200,00
220,00
240,00
260,00
280,00
300,00
Tem
pera
ture
(K)
Minimum detector temperatureMaximum detector temperature
ECA filling
0
10
20
30
40
50
60
70
cryo
stat
lev
el (
%)
He contact gas, circulation of gaseous N2 in heat exchangers
He contact gas, circulation of liquid N2 in heat exchangers
Purging of He gas, introduction of Ar gas in cold tank
Last part of cool down: Ar contact gas, liquid N2 circulating in heat exchangers
ECC Cool- down Temperature
80.00
100.00
120.00
140.00
160.00
180.00
200.00
220.00
240.00
260.00
280.00
300.00
29/0
3/2
007
05/0
4/2
007
12/0
4/2
007
19/0
4/2
007
26/0
4/2
007
03/0
5/2
007
10/0
5/2
007
Date
Tem
pera
ture
(K)
Minimum detector temperature read on the cryo system
Maximum detector temperature read on the cryo system
Last updated 07-05-2007
Start cool down 22/03/07
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 3
Detector Status Lots of debugging going on on the systems:
Noise studies, electronic calibration, signal reconstruction,…
Cosmic runs with Tile trigger: Barrel: first data taking period in August 06 and
October 06. Now systematically (~every weekend) since March 07
ECA: taking combined data (ECA+Barrel+Tile) since Easter
Cosmic run is being proving a great opportunity to drive developments in DCS, DAQ, Monitoring, Reconstruction, Electronics Calibration, conditions DB,…
Strong Milano involvement on HV activity and especially on DCS software
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 4
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 5
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 6
HV DCS Barrel and Presampler calorimeters HV
DCS are partly integrated into the ATLAS DCS: Full integration expected before M3 week
(June 4-18) Complete barrel integration and then
move to endcap calorimeters: FSM: barrel only so far Condition DB: barrel only so far Configuration DB: to be done Alerts: to be done
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 7
HV status Due to limited availability of HV power supplies only a subset of
the detector can be powered Barrel:
Barrel EM: 1.6 kV on 12/32 modules (cosmic set-up) since begin of March 07
Barrel Presampler: 2000 V on 32/64 modules
Endcap A: EM:
At nominal voltage since end of April Hadronic:
At nominal voltage since beginning of April. Temporarily OFF to debug HV/LV interlock for safety of HEC preamps
Forward:At nominal voltage since beginning of April
Endcap C: EM:
Partial 50 V during cool down
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 8
HV status Two old problems:
1. Failures of Iseg HV modules2. Shorts in some calorimeter sectors
1. Failures of Iseg modules:
Solved. The problem has been identified and Iseg is retrofitting all modules bought by the Collaboration (136/151)
Retrofitting: 75% done (of 114 which need retrofitting). Should be finished by Mid June.
40 “new generation” modules ordered: 15 to complete set-up (end August) + spares (end 2007-beginning 2008).
Prototypes being delivered: to be tested at CERN, Dresden and Milano before starting production
Retrofitted modules are continuously ON since beginning March (April) for Barrel (ECA) cosmic runs with good performance
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 9
HV status2. Shorts in the calorimeter:
Since the first cold tests in B180, some HV sectors have been found in short
Two approaches to cure the shorts (Barrel EM, Barrel PS, EM Endcap):
“short burning”: send a fast large spike in the faulty HV line to burn the resistive impurity causing the short cut
“hospitalization” (if the above fails): since the “short” has usually a resistance in the ~1 Mregion (few hundreds k in worst cases), the affected channel can be put on special high current modules where they can operated drawing currents (up to 3 mA) at reduced voltage (if needed)
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 10
Shorts in calorimeter Barrel Presampler:
All channel OK at nominal voltage after “burning” procedure Barrel EM:
Burning tried beginning of July: unsuccessfull 23/896 lines on high current modules 12/23 lines operated drawing current at nominal or reduced voltage
since beginning of March (cosmic set-up) Affected sectors can be operated successfully, currents are pretty
stable Endcap EM A:
27 lines in shorts during first ramp up after cool down Short burning: 16/27 lines cured Remaining 11 lines will be put on high current modules (modules
ordered) All the other lines OK at nominal voltages
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 11
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 12
LV Power Supplies 58 (Barrel+Endcaps) DC-DC
converters located on the cryostats: 280 V DC input, 4.5 kW per box,
rad tol Several problems found during
production: Weak design and construction,
thermal problems, deterioration of components
Only 12 PS available for cosmic run so far
After a deep re-evaluation of the design the Collaboration decided to retrofit all 68 units: Each unit has 27 module: 20
components/module to be replaced
Job assigned to ALGEN Design Services Inc
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 13
LV PS After an initial delay,
retrofitting is now well on going and retrofitted modules are getting at CERN: 23 done, 16 already at
CERN (2 on Barrel replacing old ones, 7 on ECA)
OK so far: 2 PS ON for about 2 weeks
Retrofitting will be completed by late July
However it is only a temporary solution (2 yrs): Because of time and
component availability not all desidered changed could be integrated
Two new companies identified to start a new design/prototyping phases: Wiener Algen+AEI
Decision for production will be taken after the prototype phase
Line of Balance - Production
37
1115
18
23
0
10
20
30
40
50
60
70
80
3/30 4/6 4/13 4/20 4/27 5/4 5/11 5/18 5/25 6/1 6/8 6/15 6/22 6/29 7/6 7/13 7/20 7/27 8/3
Baseline Production Critical Production Actual Production Equivalent of Side-A completion Equivalent of Detector completion
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 14
SW activities Calibration activities:
Calibration of photons and electrons “Calibration hits” methods, will be available in release
13 Work on going to demonstrate if it can also be used in
Etmiss calibration Etmiss calibration:
Overall performance (CSC note: D. Cavalli co-conv):
Hadronic calibration workshop held in Milano 26-27 april 07
Physics analyses: H->analysis (CSC note: L. Carminati co-convener) A/H-> (CSC note: S. Resconi co-convener)
Additional Slides
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 16
Richieste Finanziarie Missioni Italiane ed Estere: Integrazione MI, ME
Marcello Mazzanti e’ in pensione dal settembre 2006,
era stato cancellato, dal 1 ° gennaio 07 e’ associato senior.
- successivamente integrazione missioni estere sulla base delle
necessita’ ( per 2007: proposti 132 keur, finanziati 92.5 )
Capitolo Consumo - Sblocco s j 40 Keur (M&O 56 Kfr CH + cong.) 2007
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 17
M&O ATLAS LAr 2007
Piano di spesa (K CHF) :
2006 2007 2008 2009 2010
750 1170 1285 1285 1285
Nel 2007 per LAr non ci sono piu’ C&I e CC.
L’incremento nel 2007 rispetto al 2006, risente del rimborso di 350 KCHF per “spares “ (elettronica di FE), gia’ da tempo programmato.
La prima valutazione dei costi M&O per il 2007 ( maggio 06) e’ stata ridotta del ~ 14 %, per tener conto della nuova schedula di LHC.
le cifre relative agli anni 2008 2010 sono oggi superate !!
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 18
2007 M&O Sharing
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 19
CORE %
M&O SparesFE
Totale(KCHF)
INFN(Milano)
4.8 39.4 16.8 56
La riga che riguarda l’INFN (Milano) e’:
Calorimetria EM a LAr di ATLAS
Meccanica 5 Acquisti/Lavoraz. meccanic. , saldature…..
Impianti Gas 1 Affitto bombole e racks
Sist. Criogenici 30 Manten. sist. Crio., gas x tests, slow control
Sist. Cooling 30 Coolling PS, FE crates, mantenim., upgrades
Elettronica 160 Strumentaz per laboratori, affitto pool, RO, manuten., upgrades
Contr. DCS,DSS 30 Componenti per ELMBs, sensori, sniffers
PS(LV,HV) 200 Manutenzione, upgrades
Magazzino 50 Componenti meccanici, elettrici, etc…
Gestione Aree 30 Trasporti,logistica, pulizia aree sperim.
Comunicazioni 4 Telefoni portatili, videoconferenze
Manpower 280 Personale tecnico,ingegn. esterno/gruppi
Elettronica FE 350 Spares, rimborso
Totale 1170 kCHF
M&O Voci di Spesa 2007
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 21
Ricercatori : D. Banfi (Dottorando, 100%) L. Carminati (Ass. Uni., 100%) D. Cavalli (Dir. Ric., 100%) G. Costa (Dir. Ric., 100%) M. Fanti (Ric. Uni., 100%) L. Mandelli (PO, 100%) L. Perini (PO, 100%) S. Resconi (art. 23, 0 %) F. Tartarelli ( Ric., 100%)
Tecnologi: M. Citterio ( Tec., 50.%)
Totale: 8 Ricercatori, 2 Tecnologi→ ( 8.5 FTE )
Tecnici: B.Monticelli (100%), F.Alberti (50
%)- Servizio Elettronica ( 8mu)
Coordinatrice WG Jet, t e PTmiss Perf.
Responsabile ATLAS Italia
LAr Electronic Coordinator
Responsabile locale
Composizione del Gruppo
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 22
Richieste Finanziarie 2007 Missioni interne 1. K€ x8.5 +3 resp. naz. 11.5 K€
Missioni Estere Meetings etc. 8.5 x 1.5= 12.8 mux 4.4 K€ 56.1 Integraz. Responsabilita’ 3 x 4.4 K€ 13.2 Commissioning HV 2p x 12w → 6X4.4 K€ 26.4 ____Totale mesi uomo :21.8 mu Totale 95.7 K€
Missioni Est. per gestione app.+ shifts LAr /ATLAS - 07) (*) assumendo 1.5 FTE/y (18 mesi uomo) 79.2 K€ Consumi
Metabolismo (1.5 K€x8.5) 12.8 K€ M+O (2007) 56 KFrCH 37.3 K€
Programma R&D SLHC ( SiGe) (se approvato) 30. K€
(*) E’ solo una valutazione preliminare !! Totale 266.5 K€ ( criterio di “sharing” non ancora definito in ATLAS ).
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 23
Richieste Finanziarie 2007 Missioni interne 1. K€ x8.5 +3 resp. naz. 11.5 K€
Missioni Estere Meetings etc. 8.5 x 1.5= 12.8 mux 4.4 K€ 56.1 Integraz. Responsabilita’ 3 x 4.4 K€ 13.2 Commissioning HV 2p x 12w → 6X4.4 K€ 26.4 ____Totale mesi uomo :21.8 mu Totale 95.7 K€
Missioni Est. per gestione app.+ shifts LAr /ATLAS - 07) (*) assumendo 1.5 FTE/y (18 mesi uomo) 79.2 K€ Consumi
Metabolismo (1.5 K€x8.5) 12.8 K€ M+O (2007) 56 KFrCH 37.3 K€
Programma R&D SLHC ( SiGe) (se approvato) 30. K€
(*) E’ solo una valutazione preliminare !! Totale 266.5 K€ ( criterio di “sharing” non ancora definito in ATLAS ).
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 24
Barrel• Pressure variations in expansion vessel: ± 4 mbar;
• Temperature variations (in time) in liquid argon (as measured by DCS): < 20 mK; (Tmin 88.2 K, Tmax 88.6 K)
• Running on “lost” nitrogen (losses too small to run with refrigerator)
• Impurity level measured with four purity cells: (0.20 +- 0.05) ppm O2 Stable in time !
expansion vessel pressure
1,2
1,22
1,24
1,26
1,28
1,3
8.6.06 0:00 10.6.060:00
12.6.060:00
14.6.060:00
16.6.060:00
18.6.060:00
20.6.060:00
22.6.060:00
date
arg
on
pre
ssu
re (
bar
a)
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 25
‘OR’ of top modules
EBC LBC
EBC LBC
LBA
LBA
EBA
EBA
5 6 7 8 ‘OR’ of bottom modules
4 new boards from LAr
1 2 3 4
‘AND’ top - bottom
4 boards from Tile
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 26
March 2007 HV = 1.6 kV
August 2006 (13k evts) 2. 0 kV
October 2006 (78k evts) 1.6 kV
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 27
Some starting studies:
Uniformity of response by P.S. Mangeard (old runs)
η
No
rma
lize
d
Mu
on
Re
spo
nse
S2 cell depthdata
normalized to 1
Muon energy deposited in LAr by M.CookeOptimizing clustering algorithm
• follows expectations
Error bar per point is ~2 % in average (1% around =0.4 and 3% at borders)
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 28
subdetector allr=retrofitted
o=old hc=high current
EMB+SP
EMB-PS
HEC+ Pur
EMEC EMEC-PS+ Pur-N
FCAL Hospital barrel
Hospitalend-caps
NeededTotal 151 + 6hc 32+3 16 32+1 48 4+1 14 2 4
CERN orderSUNNY orderTotal order
1363
139
sacrificed(cleaning/epoxy)
- 5
new piggy + 2
totalproduced
136 + 2hc 72 44 6 14 2 ordered
in operationUSA15 racks just arrived at
CERNto be repaired
77r + 2o +15 + 2hc
39r +2o 38r 3 12 2
7r+1 6r 1r 1
1r 1r
to be retrofittedas of today done
still to be retrofitted
11486r28
7046r24
4440r
4
at CERNat ISEG
at TU-Dresdenat PROTVINO
SUM=
103 + 2hc30
12
136 + 2hc
4824
72
394
1r
44
41
16
121
114
2hc
2hc
ordered
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 29
HV sectors The calorimeter has a large HV granularity and the impact of
HV failures is limited In the Barrel EM there are 448 HV sectors; each HV sector is
x=0.2x0.2 (2‰) and biased by 2 lines, each one providing HV to a set of 32 semigaps of LAr
If one line fails a reduced signal is seen that can be corrected offline
No dead zones (holes)
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 30
LAr Cosmic Run: 600 V region Most of the “short” > 1 M
< 1 mA at 1000 V -> <1 W dissipation. reduced acceptance loss to x = 0.075x0.025 (or 0.05) wrt x =
0.2x0.2 the effect should be quite similar to a dead
middle cell ... but lower signal-to-noise ratio due to 20%
reduction of signal Detection of in the region with lower rate but no dead region
Signal is observed with ~30 % longer drift time
Signal in 1600 V region Signal in 600 V region
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 31
Linee di lavoro:
• Validazione software, formati e tools di analisi. • Messa a punto di un framework comune di lavoro in previsione dei primi dati
• Studio e ottimizzazione della risoluzione del picco di massa dell’Higgs:• calibrazione dei fotoni, ricostruzione del vertice primario, conversioni…)
• Fondo riducibile: studio e ottimizzazione dei “fake jets” in collaborazione con e/gamma performance groups
• Fondo irriducibile: studio di tool statistici per ottimizzare l’estrazione del
segnale sul fondo irriducibile.
• EDITORS: L. Carminati (Milano), B. Mellado (Wisconsin)
• GRUPPI COINVOLTI: Annecy(France), CERN, Milano(Italy), Montreal (Canada), Orsay, Paris (France), SMU(US), Wisconsin (US)
• ORGANIZZAZIONE: lavoro incominciato nell’autunno 2006,
Nota CSC H
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 32
CSC EtMiss Overall Performance Note
• Editors: D. Cavalli, A. Gupta, Italian contributors: C. Pizio, S. Resconi
1) Introduction
2) The Cell-based method
* Etmiss reconstruction (Noise suppression )
* Etmiss calibration (H1-calibration, LocalHadronCalibration, Refined calibration a la TDR)
* Evaluation of Performance: resolution, linearity, tails
* measurement of Etmiss direction
3) Object-based method
4) Fake Etmiss dedicated studies * Fake Etmiss sources ( jets pointing to cracks,
losses in dead materials,...) * Beam-halo, beam-gas, cavern background
effects * Instrumental effects (noisy/hot/dead cells
(regions) in calorimeters * Etmiss significance5) Etmiss in Atlfast6) Etmiss in early data * resolution in minimum bias events * Etmiss scale from Z to tau-tau event * W-->l-nu events * W+jets events7) Summary and conclusions
CSC (Computer System Challenge) Simulazione MC – detector as built-as
installed-with misallignements Produzione di 20Mevts in corso Testare la catena completa del
computing Produzione, distribuzione, analisi dati Produrre CSC note che
documentano la Performance del rivelatore
Potenzialita’ nello studio dei canali di fisica
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 33
• Introduction:
• Importance of the channel (experimentally and theoretically)
• Previous studies (TDR and after)
• MSSM H/A Production and Cross-sections
• Montecarlo (PHYTIA + SHERPA)
• Experimental setup
• Detector requirements:
• Tau reco and id:
• Electron reconstruction
• Muon reconstruction
• EtMiss reco and calib:
• jet rec, calib and b-tagging
CSC Note HG7 : H°/A°
• For each one of the 3 final decay modes
(lep-had, had-had, lep-lep):
• Event selection
• data carachteristics
• Analysis
• Results
• Systematic uncertainties
• Trigger
• Combine the results from
the 3 decay-modes :
• Discovery curve in the (mA, tanbeta) plane
• Summary and conclusions
• Acknowledgments, References, Appendices: Technical Aspects
• Editors: M. Heldmann, S. Resconi, Italian contributors: D. Cavalli
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 34
Calibrazione elettromagnetica : ‘first principles based calibration’
• La calibrazione elettromagnetica attuale e’ basata su coefficienti estratti con una procedura di minimizzazione. • CONS: Non e’ possibile fattorizzare le correzioni e I pesi longitudinali non correggono esattamente per l’effetto
• PRO: Performance accettabili e metodo semplice
• E’ stato sviluppato un metodo di calibrazione alternativo alla minimizzazione e basato su speciali simulazioni con accesso alle energie depositate anche nei materiali inattivi/passivi del rivelatore
• PRO: Disaccoppiare e capire le correzioni (materiale in fronte, leakage longitudinale…), correggere ogni singolo effetto con una correzione opportuna.• CONS: il metodo e’ piu’ complesso e sono richiesti piu’ parametri.
• Lo studio del metodo e’ terminato ed e’ stato implementato dentro il software ufficiale di ricostruzione di ATLAS:
• Studi e confronti dettagliati verranno effettuati tra i metodi anche nell’ambito del CDC
Banfi,Carminati,Mandelli
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 35
Photons Resolution (/E), All E
Cra
ck B
arr
el-
Endca
p
PS NO PS• 25 GeV• 50 GeV• 75 GeV• 100 GeV• 200 GeV• 500 GeV
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 36
Photons Linearity, All Energies
Cra
ck B
arr
el-
Endca
p
PS NO PS• 25 GeV• 50 GeV• 75 GeV• 100 GeV• 200 GeV• 500 GeV
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 37
Electron Energy Resolution (/E), All Energies
Cra
ck B
arr
el-
Endca
p
PS No PS
Cra
ck B
arr
el-
EndC
ap
• 25 GeV• 50 GeV• 75 GeV• 100 GeV• 200 GeV• 500 GeV
CSN1, 14 maggio 2007 Calorimetria EM a LAr di ATLAS 38
Electrons Linearity, All Energies
Cra
ck B
arr
el-
Endca
p
PS NO PS• 25 GeV• 50 GeV• 75 GeV• 100 GeV• 200 GeV• 500 GeV