csp empowering saudi arabia with solar...
TRANSCRIPT
CSP – Empowering Saudi
Arabia with Solar Energy
Third Saudi Solar Energy Forum
Holger Fuchs,
Senior Executive Manager |
Project Development
Riyadh | April 3, 2011
Page 2Solar Millennium Group – We are developing the future
Solar Millennium’s business and partner model
•Providing technology
•Engineering, procurement of
components and construction
(EPC) of solar-thermal power
plants
•R&D solar/new technologies
•Financial product sales (in-
house, via sales partners)
•Development of innovative
financial products for
institutional and private
investors
•Location search and
qualification
•Approval process
•Securing land / grid access
•Financing of power plant
projects
•Sale of power plant stakes /
minority interests
Project Development &
Financing
Financial Product
Development &
Sales
Technology &
Power Plant
Construction
Generation of local content through involvement of regional partners along the
value chain
Page 3Solar Millennium Group – We are developing the future
Worldwide activities of Solar Millennium
Solar Millennium
sites
Possible future
markets
USA
MENA
Asia
Blythe
(4x250 MWe)
DNI ~
2,600 kWh/a
Andasol 1-3
(3x50 MWe)
Ibersol
(1x50 MWe)
DNI ~ 2,150 kWh/a
Kuraymat
(1x61 MWth)
DNI ~ 2,400 kWh/a
Page 4Solar Millennium Group – We are developing the future
Kuraymat (Egypt), 150 Megawatt (MWe) ISCC**
plant including 61 MWth
Operation of the solar field began at the end of 2010
Total investment: € 250 million, approx. 30% for the
130,000 m² solar field
Engineering, supervision and supply of key
components for the solar field
After start of operations, Flagsol and Orascom will
operate the solar part of the power plant for two
years before ultimately handing it over to the owner
NREA
MENA: Kuraymat, first CSP* plant in Egypt
* CSP = Concentrating solar power, solar-thermal power plants
** ISCC = Integrated Solar Combined Cycle Power Plant
Page 5Solar Millennium Group – We are developing the future
Kuraymat: Construction phase
Page 6Solar Millennium Group – We are developing the future
Kuraymat: Location
Lat.: 29° 16’ North
Long.: 31° 15’ East
Page 7Solar Millennium Group – We are developing the future
Kuraymat: Satellite view of site
Page 8Solar Millennium Group – We are developing the future
3 Bid Packages
EPC for Solar Island and O+M Contract (2 years)
61 MWth (40 Loops)
EPC Combined Cycle power plant
1 gas turbine 80 MW and 1 steam turbine 70 MW
Combined Cycle O+M Contract (5 years)
Timeline
1999: Feasibility Study
2005: Pre-Qualification
2007: decision – Flagsol/Orascom for solar, Iberdrola for
Combined Cycle
January 2008: Effective Date
27 months after Effective Date: Completion of Facilities
30 months after Effective Date: Operational Acceptance
Kuraymat: Procedure
Page 9Solar Millennium Group – We are developing the future
Kuraymat: Scope of work (local content ≤ 60%)
Solutions needed for challenging environment:
Special vehicles for cleaning the mirrors, ensure to
collect the most possible amount of solar radiation
Project Management
Engineering SOF + HTF
Construction &
Commissioning Supervision
O+M Supervision
Mirrors
HCE
Swivel Joints
Control System
Valves
HTF Fluid
Main / Aux. Pumps
HTF Heater
Instrumentation
Photogrammetrie
Commissioning Equipment
Services Components
Page 10Solar Millennium Group – We are developing the future
Kuraymat: Interface
Interface between Contract 1) and 2) is the inlet and outlet flange of the
heat exchanger
600°C
Gas turbine(s)
Steam
Turbine
Condenser
Steam
540°C, 100bar
Stack Exhaust
100°C
393°C
Electricity
to the grid
Parabolic
Trough Field
293°C
Air and
vapour
Air Air
G
~
HRSG
Cooling
Tower
G
~
Solar HX
Page 11Solar Millennium Group – We are developing the future
Kuraymat: Organisation
NREA
(New and RenewableEnergy Authority)
Flagsol
NSF
National Steel Fabrication
OCI
ORASCOM Construction
industries
Overview Organisation of El Kuraymat Project – Solar Island
Owner
EPC-
Contractor
Sub Contractor
Page 12Solar Millennium Group – We are developing the future
Best Practice: Europe’s first parabolic trough power plants, full CSP
Video
Page 13Solar Millennium Group – We are developing the future
3x50 MW = 150 MW
Total financing volume approx. EUR 1bn
Solar power for more than half a million people
Andasol 3: start of operation expect. in summer 2011;
Co-investors: Stadtwerke München (Munich City
Utilities), RWE Innogy, Rhein Energie, Ferrostaal
the first parabolic trough power plant in Europe and
until now the only one in the world working with
thermal storage (allows a stable electricity supply
24 h / 7 d)
Regulation
Feed-in compensation for CSP definitively guaranteed
by Spanish RD #661 (May 2007)
Best Practice: Andasol 1-3 (stand alone CSP Plant incl. TES*)
* TES – Thermal Energy Storage
Page 14Solar Millennium Group – We are developing the future
Blythe, California: 1 Gigawatt (1GW)
The world’s largest solar power plant
solar power for more than 300,000 US households
Construction on Blythe 1 - 2 (2x250 MW) started
Blythe 1 - 4: 1,120 loops* 179,200 absorber pipes
2.15 million mirrors 192,000 tons of steel
2,240 hectares of land
more than 1,000 jobs
more than 1 million tons of CO2 emissions saved p.a.
Solar Millennium US projects (2 GW in California and
Nevada) will feature dry cooling technology that uses
90% less water than water-cooled design
Best Practice: Blythe, pot. model for Saudi Arabia with dry cooling concept
* HelioTrough technology
Page 15Solar Millennium Group – We are developing the future
Thank you for your attention!