csse 372 software project management: introduction to ... · q6 . earned value management terms !...

22
CSSE 372 Software Project Management: Introduction to Earned Value Analysis (EVA) Shawn Bohner Office: Moench Room F212 Phone: (812) 877-8685 Email: [email protected] Q1

Upload: others

Post on 16-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

CSSE 372 Software Project Management:

Introduction to Earned Value Analysis (EVA)

Shawn Bohner Office: Moench Room F212 Phone: (812) 877-8685 Email: [email protected]

Q1

Page 2: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

Planned or unplanned?

Page 3: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

Learning Outcomes: Plan (verb)

Create a plan for an intermediate size software project and manage to the plan. Maintain a software project schedule. n  Controlling Software Projects

to the Plan n  Introduce Value and

describe how it can be measured

n  Examine Earned Value Analysis Concepts

Page 4: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

What is the “value” of a software product to an individual customer? An information system to a firm?

n  Think for 14.5 seconds… n  Turn to a neighbor and

discuss it for a minute

Page 5: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

How do you answer the question: “What have we done so far?”

n  What are the Estimates vs. Actuals? % of Budget spent… % of Work completed… % of Time Elapsed…

n  Planned progress can be: ¨ Subjective, inaccurate, and incomplete ¨ Prone to false conclusions

n  Actual progress, on the other hand is… often like plans

Q2

Page 6: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

Earned Value Earned value compares the planned amount of work with what has actually been completed, to determine if cost, schedule, and work accomplished are progressing as planned n  Work is “Earned” or

“credited” as it is completed

Q3

Page 7: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

Why Earned Value? n  Provides “Early Warning”

call for corrective actions

n  Quantifies many of the diverse activities in the development process

n  Organizes for pachyderm management :-) ¨ Large seemingly impossible

projects

Q4

Page 8: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

Earned Value Starts with Good WBS n  One WBS per Program/Project

¨ Deliverable-oriented ¨ Work not in the WBS is out-of-scope

n  Full (and accurate) definition is key ¨ Defined deliverable(s) ¨ Timeframe for delivery

n  Total cost (direct and indirect) to deliver product

In other words, you need a good plan before earned value is of any value!

Q5

Page 9: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

Work Packages n  Lowest level WBS elements

n  Have three measurable components

1.  Scope of work to be accomplished 2.  Total (direct and indirect) cost 3.  Timeframe for completion

n  Size Work Package so that it can be handed

off to a task manager/engineer ¨ Too large: multiple people responsible for work ¨ Too small: program manager winds up micro-

managing everything

Page 10: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

Enough With the WBS Stuff Already !

Let’s talk about Earned Value…

Page 11: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

Earned Value Management (EVM)

n  Popular project performance measurement technique that integrates scope, time, and cost data

n  With a baseline (plan + approved changes), you can determine how well the project is meeting its goals ¨ Actual project information periodically collected to

determine Earned Value

Q6

Page 12: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

Earned Value Management Terms n  Planned value (PV) is the portion of the approved

cost estimate planned to be spent on an activity during a given period ¨  Also called the budgeted cost of work scheduled (BCWS)

n  Actual cost (AC) is the total costs (direct and

indirect) incurred in completing work on an activity during a given period ¨  Also called actual cost of work performed (ACWP)

n  Earned value (EV) is an estimate of the value of the

work actually completed ¨  Also called the budgeted cost of work performed (BCWP), ¨  EV based on original planned project costs and the rate at

which the team is completing work on the project to date Q7

Page 13: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

Time

Progress

1/3 Time - 1/4 Progress

Earned Value – The Standard S-Curve

2/3 Time - 3/4 Progress

Page 14: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

No ramp up - no learning time

Time

Progress

Earned Value – The Aggressive Curve

Page 15: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

About 30% of the work done

70% to 80% of the time gone by

Time

Progress

Earned Value – The Curve to Avoid

Page 16: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

Early years of Computer Addition…

Then laptops, smart phones, iPads…

Page 17: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

Earned Value – Basic Performance Metrics

Cost Performance Index A measure of how close the project is to spending on the work performed to what was planned to have been spent.

Schedule Performance Index A measure of how close the project is to performing work as it was actually scheduled.

INDEX VALUES < 1: over budget or behind schedule > 1: under budget or ahead of schedule

Q8

Cost Variance Difference between projected cost and actual cost.

Schedule Variance Difference between projected schedule and actual schedule.

CV = EV–AC SV = EV–PV

CPI = EV/AC SPI = EV/PV

Page 18: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

How to Measure Earned Value

Page 19: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

Earned Value – PV, EV and AC Curves

Page 20: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

Let’s talk Final Project: Software Project Management Plan n  See Assignment n  Template with Rubric n  Extensive Example n  Work with team effectively – Team Changes...

n  Due: 11:55pm, Friday, November 2nd, 2012. ¨ No late days – will be reviewed by another team

for last homework!

Page 21: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

Tomorrow we will bend the mind a bit more with Earned Value…

Page 22: CSSE 372 Software Project Management: Introduction to ... · Q6 . Earned Value Management Terms ! Planned value (PV) is the portion of the approved cost estimate planned to be spent

Homework and Reading Reminders n  Complete Homework 5 – Software Schedule

¨ Due by 11:55pm, Tuesday, October 9th, 2012

n  Final Project – Software Project Management Plan (SPMP) ¨ Completed by team… ¨ Due by 11:55pm, Friday, November 2nd, 2012. ¨ No late days – will be reviewed by another team

for last homework!