csxt emergency response for may 2010 flood …...to flood waters west embankment and roadbed damaged...
TRANSCRIPT
![Page 1: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/1.jpg)
CSXT Emergency Response for May 2010 Flood Repairs11th Annual Geohazards ForumChattanooga, Tennessee
Christopher Ramsey, PEAMEC
![Page 2: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/2.jpg)
2
Project Overview
Record rainfalls affecting greater Nashville. Some areas recorded greater than 19 inches of rain over May 1 & 2, 2010 Tailwaters of the Cumberland River flood due to
the unprecedented precipitation event CSX Transportation lines in the Kingston
Springs area west of Nashville along the Harpeth River, and beyond, are damaged and in need of repair CSXT selects a team of engineers and
contractors, which included AMEC, to inspect, permit, re-design & repair over 200 miles of track which extended from Nashville to Memphis
![Page 3: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/3.jpg)
3
Project Overview, cont’d
Over 37,000 feet of railroad track required repair of some kind Several culverts were washed out which then had to be restored,
cleaned or upgraded Two bridges, which supported track over the Harpeth River were
damaged. Both bridges were 3 span structures. One was completely washed out,
including loss of 2 center piers.The other had one span washed away. Bridges affectedwere located at mileposts (MP) 17.4 & 23.5
![Page 4: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/4.jpg)
4
Project Overview, cont’d
The project team collaborated to determine the best solution that would restore rail traffic in a rapid and safe manner The team sought out available equipment and materials prior to
commencing design Items such as available pre-fabricated steel spans, drilled shaft steel
casing and appropriate foundation equipment were evaluated for suitability
![Page 5: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/5.jpg)
5
Milepost 17.4 assesment
MP17.4 constructed in 1878 and rebuilt in 1930, 2 piers and 2 abutments consisting of stone masonry bearing on bedrock All three spans washed down stream, both piers were forced over due
to flood waters West embankment and roadbed damaged
![Page 6: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/6.jpg)
6
Milepost 17.4 assessment, cont’d
![Page 7: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/7.jpg)
7
Milepost 17.4 assessment, cont’d
![Page 8: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/8.jpg)
8
Milepost 17.4 assessment, cont’d
![Page 9: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/9.jpg)
9
Milepost 17.4 assessment, cont’d
![Page 10: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/10.jpg)
10
Milepost 23.5 assessment
MP 23.5 is a three span bridge totaling approximately 296 feet, with eastern most span washed out Both approach embankments damaged with severe roadbed damage
mainly to the east Constructed in 1922, consisting of stone masonry piers and
abutments bearing on bedrock
![Page 11: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/11.jpg)
11
Milepost 23.5 assessment, cont’d
![Page 12: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/12.jpg)
12
Milepost 23.5 assessment, cont’d
![Page 13: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/13.jpg)
13
Milepost 23.5 assessment, cont’d
![Page 14: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/14.jpg)
14
Milepost 23.5 assessment, cont’d
![Page 15: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/15.jpg)
15
Site Investigation
Preliminary plan is to install two new piers at MP17.4 and one new pier at MP23.5 Drill one boring, including rock core, at each bridge site Boring at MP17.4 site drilled just downstream at approximately center
of total span. Boring at MP23.5 site drilled on location of proposed replacement pier
![Page 16: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/16.jpg)
16
The Repair Plan, MP17.4
Utilize steel spans available for immediate delivery and tailor design based on that availability Permanently cased, rock bearing, steel reinforced drilled shafts for
new pier supports Drilled shafts also sized based on availability of material, specifically
casing sizes
![Page 17: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/17.jpg)
17
The Repair Plan, MP17.4 (as conceived)
Single element was used to extend from base of pier cap into bedrock Single piece of steel casing placed into drilled
rock socket Reinforcing steel cage placed and the element
was concreted Annulus between casing and bedrock socket
was grouted
![Page 18: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/18.jpg)
18
The Repair Plan, MP17.4 (as constructed)
Single element was used to extend from base of pier cap into bedrock Temporary casing, left in place, used through shot rock fill bench to
bedrock Single piece of steel casing
placed into drilled rock socketand welded to temporarycasing Annulus between casing and
bedrock socket was grouted Reinforcing steel cage placed
and the element was concreted
![Page 19: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/19.jpg)
19
Milepost 17.4 Repair
![Page 20: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/20.jpg)
20
Milepost 17.4 Repair
![Page 21: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/21.jpg)
21
Milepost 17.4 Repair, cont’d
![Page 22: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/22.jpg)
22
Milepost 17.4 Repair cont’d
![Page 23: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/23.jpg)
23
Milepost 17.4 Repair cont’d
![Page 24: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/24.jpg)
24
The Repair Plan, MP23.5
Same approach taken, to utilize steel spans available for immediate delivery and tailor design based on that availability Span too large for any available material, so an intermediate pier was
installed Permanently cased, rock bearing, steel reinforced drilled shafts for new
pier support Relatively lighter load, so drilled shaft casing sizes were readily
available
![Page 25: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/25.jpg)
25
Milepost 23.5 Repair
![Page 26: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/26.jpg)
26
Milepost 23.5 Repair cont’d
![Page 27: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/27.jpg)
27
Project Summary
Rail traffic was restored in just 21 calendar days after initial inspection AMEC coordinated with concerned agencies such as USACE, TDEC
and US Coast Guard to discuss environmental permitting requirements HDR, Inc. performed superstructure design while AMEC design the
foundations AMEC aided design and inspection of localized slope and culvert
failures along the Bruceton and Henderson Subdivisions The project team worked together to provide a comprehensive solution
after a crippling catastrophe
![Page 28: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/28.jpg)
28
Project Summary, cont’d
ACEC of Tennessee Engineering Excellence Grand Award winner, Special Project Category Quotes from Award Judges: “The complexities of a disaster, coupled with pressure from the client for
a high quality and rapid repair, requires a level of rigor that surpasses the “normal” engineering project. In this case, superb orchestration of construction, design and permitting, which were all running parallel paths, resulted in the 21 day return to service of the CSX mainline rail.” “Special consideration for disaster response, engineering design
decisions, mobilization & construction/repair all contributed to make this project unique and worthy of the Engineering Excellence Award.”
![Page 29: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/29.jpg)
29
Bridge 17.4, Finished
![Page 30: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/30.jpg)
30
Bridge 17.4, Finished
![Page 31: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/31.jpg)
31
Bridge 23.5, Finished
![Page 32: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/32.jpg)
32
Bridge 23.5, Finished
![Page 33: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/33.jpg)
33
Bridge 23.5, Finished
![Page 34: CSXT Emergency Response for May 2010 Flood …...to flood waters West embankment and roadbed damaged 6 Milepost 17.4 assessment, cont’d 7 Milepost 17.4 assessment, cont’d 8 Milepost](https://reader033.vdocument.in/reader033/viewer/2022060512/5f2ae442f74c6462bb071d94/html5/thumbnails/34.jpg)
34
Questions?