cupertino union school district - cusd...
TRANSCRIPT
1
Cupertino Union School District
Measure H Bond Program Update
For
Citizens Bond Oversight Committee
March 8, 2017
WORK IN PROGRESS
Measure H Bond Program Progress Report
Section 1 — Measure H Bond Program Overview Approved Project List ........................................................................................... 1 Whole Program Summary Report ........................................................................ 15 Project Summary Report ...................................................................................... 16 Cash Flow Projections .......................................................................................... 27 Construction Sequence ........................................................................................ 28 Section 2 — Elementary School Projects Blue Hills............................................................................................................... 29 Collins ................................................................................................................... 30 De Vargas ............................................................................................................. 31 Dilworth ............................................................................................................... 32 Eaton .................................................................................................................... 33 Eisenhower .......................................................................................................... 34 Faria ..................................................................................................................... 35 Garden Gate ......................................................................................................... 36 Lincoln .................................................................................................................. 37 McAuliffe .............................................................................................................. 38 Meyerholz ............................................................................................................ 39 Montclaire ............................................................................................................ 40 Muir...................................................................................................................... 41 Murdock-Portal .................................................................................................... 42 Nimitz ................................................................................................................... 43 Regnart ................................................................................................................. 44 Sedgwick .............................................................................................................. 45 Stevens Creek ....................................................................................................... 46 Stocklmeir ............................................................................................................ 47 West Valley .......................................................................................................... 48 Section 3 — Middle School Projects Cupertino ............................................................................................................. 49 Hyde ..................................................................................................................... 55 Kennedy ............................................................................................................... 58 Lawson ................................................................................................................. 61 Miller .................................................................................................................... 64 Section 4 — Districtwide Projects District Administrative Offices ............................................................................. 67 District Corporation Yard ..................................................................................... 68 Security ................................................................................................................ 70 Technology ........................................................................................................... 71 Purchase of Leased Classrooms ........................................................................... 72 Energy Efficiency/Solar Projects .......................................................................... 73 Interim Housing ................................................................................................... 74 Central Kitchen Upgrades .................................................................................... 75 Furniture, Fixtures & Equipment ......................................................................... 76 Playground/Landscaping/Field Upgrades ............................................................ 77 Hazardous Material Removal ............................................................................... 78 Moving & Storage ................................................................................................ 79
MARCH 3, 2017 i MEASURE H BOND PROGRAM PROGRESS REPORT
Elementary SchoolsBlue Hills Elementary School
Site Utilities Replacement01-8215 $66,183Active Install new backflow preventer.
Modernization01-8502 $6,126,000Active Major ADA upgrades to Student (Kindergarten) and Staff Restrooms. Minor upgrade toStudent and Staff Restrooms. Buildings will receive a new fire alarm service, replacement of finishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms. Improve accessibility for drinking fountains, plumbing fixtures and casework in classrooms. Paint exterior building trim. Add kiln room. Expand kitchen. Replace some HVAC units. Add interior walls in main classroom/admin/GLC building.
New Kinder Play Yard01-8508 $585,405Active Install new kinder play yard at Blue Hills Elementary School.
Exterior Painting01-8525 $156,025Complete Paint exterior.
Technology01-8536 $162,736Active District's IT Department site refresh program.
Kindergarten Fencing01-8552 $0Cancelled Add fencing at Kindergarten play area. Project Cancelled
Blue Hills Elementary School Totals: $7,096,349
De Vargas Elementary School
Site Utilities Replacement02-8215 $108,410Active Replacement of sanitary sewer lines. Add additional storm drain to eliminate ponding.
Modernization02-8502 $4,299,379Active Major ADA upgrades to Student (Kindergarten) and Staff Restrooms at Building B. Minorupgrade to Student and Staff Restrooms at buildings A, C and D. Buildings will receive a new fire alarm service, replacement of finishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms. Improve accessibility for plumbing fixtures and casework in classrooms. Replace doors and panic hardware at GLC. Minor HVAC/duct repair. Paint exterior trim, Repair dry rot and replace door and door frames as needed.
Lighting Upgrades02-8521 $56,084Complete Addition of new parking lot light fixtures/poles, repair/servicing of existing pole mountedlight fixtures and the replacement of outdated wall mounted light fixtures with new (energy efficient) light fixtures.
Technology02-8536 $184,602Active District's IT Department site refresh program.
De Vargas Elementary School Totals: $4,648,474
Dilworth Elementary School
Master Project List Report
BudgetCategory/Project
Cupertino Union School District
Status Description
Measure H Bond ProgramBond Project List - December 31, 2016
MARCH 3, 2017 1 MEASURE H BOND PROGRAM PROGRESS REPORT
Elementary Schools
Site Utilities Replacement03-8215 $58,013Active Add additional storm drain to eliminate ponding. Install new backflow preventer.
Modernization03-8502 $4,008,829Active Major ADA upgrades to Student (Kindergarten) Restrooms at Building A. Minor upgradeto Student and Staff Restrooms at Buildings B, C and D. Buildings will receive a new fire alarm service, replacement of finishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms. Improve accessibility for plumbing fixtures and casework in classrooms. Minor HVAC/duct repair. Paint exterior trim and replace door and door frames as needed.
Lighting Upgrades03-8521 $94,206Complete Repair/servicing of existing pole mounted light fixtures and the replacement of outdatedwall mounted light fixtures with new (energy efficient) light fixtures.
Technology03-8536 $170,041Active District's IT Department site refresh program.
Data Infrastructure Upgrade03-8557 $369,448Complete Replace data infrastructure cabling.
Dilworth Elementary School Totals: $4,700,537
Collins Elementary School
Modernization22-8502 $245,025Active ADA Upgrades
Technology22-8536 $196,320Active District's IT Department site refresh program.
Collins Elementary School Totals: $441,345
Eaton Elementary School
Modernization23-8502 $1,205,141Active Buildings will receive a new fire alarm service, exterior trim painting and new roofing.
Technology23-8536 $220,254Active District's IT Department site refresh program.
Eaton Elementary School Totals: $1,425,395
Eisenhower Elementary School
Site Utilities Replacement04-8215 $335,059Active Replace domestic water lines. Install new backflow preventer.
Master Project List Report
BudgetCategory/Project
Cupertino Union School District
Status Description
Measure H Bond ProgramBond Project List - December 31, 2016
MARCH 3, 2017 2 MEASURE H BOND PROGRAM PROGRESS REPORT
Elementary SchoolsModernization04-8502 $3,468,819Active Major ADA upgrades to Student (Kindergarten) and Staff Restrooms at Buildings A and
1. Minor upgrade to Student and Staff Restrooms at Buildings B, 2, 3 and 5. Buildings will receive a new fire alarm service, replacement of finishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms. Improve accessibility for routes of travel, plumbing fixtures and casework in classrooms. Replace doors and panic hardware at GLC. Replace select HVAC units. Paint exterior trim and replace door and door frames as needed.
Technology04-8536 $193,457Active District's IT Department site refresh program.
Eisenhower Elementary School Totals: $3,997,335
Faria Elementary School
Site Utilities Replacement05-8215 $53,504Active Replace (70)LF section of sanitary sewer line. Add additional storm drain to eliminateponding.
Modernization05-8502 $3,950,814Active Major ADA upgrades to Student (Kindergarten) and Staff Restrooms at Building B. Minorupgrade to Student and Staff Restrooms at Buildings A, C and D. Buildings will receive a new fire alarm service, replacement of finishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms. Improve accessibility for plumbing fixtures and casework in classrooms. Replace finishes and HVAC at warming kitchen. Paint exterior trim and replace door and door frames as needed.
Technology05-8536 $220,782Active District's IT Department site refresh program.
Growth Portables05-8550 $238,750Active Purchase and installation of growth portables.
Portable Restroom05-8567 $167,089Active New portable restroom facility to serve expanded campus facilities.
Faria Elementary School Totals: $4,630,939
Garden Gate Elementary School
Site Utilities Replacement06-8215 $323,322Active Replace domestic water lines. Install new backflow preventer
Modernization06-8502 $6,600,000Active Major ADA upgrades to Student Restrooms at Buildings 1 and 3. Minor upgrade toStudent and Staff Restrooms at buildings 1, 2, 3, 5 and MP. Buildings will receive a new fire alarm service, replacement of finishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms. Improve accessibility for plumbing fixtures and casework in classrooms. Replace doors and hardware at the multi-purpose room. Replace finishes at warming kitchen. Paint exterior trim and new roofing.
Master Project List Report
BudgetCategory/Project
Cupertino Union School District
Status Description
Measure H Bond ProgramBond Project List - December 31, 2016
MARCH 3, 2017 3 MEASURE H BOND PROGRAM PROGRESS REPORT
Elementary SchoolsWalkway Resurfacing06-8526 $0Deferred Project consolidated with 06-8502
Technology06-8536 $206,050Active District's IT Department site refresh program.
Data Infrastructure Upgrade06-8557 $512,846Complete Replace data infrastructure cabling.
Garden Gate Elementary School Totals: $7,642,218
John Muir Elementary School
Site Utilities Replacement10-8215 $0Deferred Project consolidated into 10-8502
Modernization10-8502 $4,903,809Active Major ADA upgrades to Student and Staff Restrooms at Buildings A, B, C and D. Minorupgrades to Student and Staff Restrooms at Buildings C, E and F. Earthquake Retrofits for Building A. Buildings will receive a new fire alarm service, replacement of finishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms. Improve accessibility for plumbing fixtures and casework in classrooms. Replace finishes at warming kitchen. Replace door and door frames as needed, paint exterior trim and repair dry rot. Expand administration area.
Kinder Play Yard Improvements10-8508 $135,000Active Kinder play yard improvements at John Muir Elementary School.
Roofing10-8528 $152,059Complete Roof Replacement Classroom Wing 11–18
Technology10-8536 $220,894Active District's IT Department site refresh program.
YCC/CAP Relocation10-8567 $1,040,000Active Relocation of 3 YCC classrooms and 2 CAP facilities from Sedgwick Elementary
John Muir Elementary School Totals: $6,451,762
Lincoln Elementary School
Site Utilities Replacement07-8215 $255,904Active Replace domestic water system.
Master Project List Report
BudgetCategory/Project
Cupertino Union School District
Status Description
Measure H Bond ProgramBond Project List - December 31, 2016
MARCH 3, 2017 4 MEASURE H BOND PROGRAM PROGRESS REPORT
Elementary SchoolsModernization07-8502 $4,575,430Active Major ADA upgrades to Student (Kindergarten) and Staff Restrooms at Building B and K.
Minor upgrade to Student and Staff Restrooms at buildings A, C, D and F. Buildings will receive a new fire alarm service, replacement of finishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms. Improve accessibility for drinking fountains, plumbing fixtures and casework in classrooms. Replace HVAC at portable. Convert old kitchen to science lab. Replace finishes at warming kitchen. New roofing and re-roof at Buildings C and D, Paint exterior trim, repair dry rot and replace door and door frames as needed. New lunch tables. Replace existing sewer piping, add backflow preventer and install booster pump for irrigation system.
Kinder Play Yard Improvements07-8508 $169,583Active Kinder play yard improvements at Lincoln Elementary School.
Lighting Upgrades07-8521 $39,391Complete Replacement of outdated wall mounted light fixtures with new (energy efficient) lightfixtures.
Roofing07-8528 $510,010Complete Roof Replacement, Buildings ‘C’, ‘D,’ and ‘E.’
Technology07-8536 $223,177Active District's IT Department site refresh program.
New Portable Restroom07-8567 $165,000Active New portable restroom facility to serve expanded campus facilities.
Roofing Phase II07-8579 $385,270Active This project is to redo a portion of the scope of work completed during project 07-8528 -Re-Roof Buildings ‘C’, ‘D,’ and ‘E.’
Lincoln Elementary School Totals: $6,323,765
McAuliffe Elementary School
Site Utilities Replacement16-8215 $83,378Active Add additional storm drain to eliminate ponding. Install new backflow preventer.
Modernization16-8502 $5,108,109Active Major ADA upgrades to Student and Staff Restrooms. Minor upgrade to all Student andStaff Restrooms. Buildings will receive a new fire alarm service, replacement of finishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms. Improve accessibility for plumbing fixtures and casework in classrooms. Replace finishes at warming kitchen. New roofing, paint exterior trim.
Lighting Upgrades16-8521 $119,998Complete Addition of new parking lot light fixtures/poles and the replacement of outdated wallmounted light fixtures with new (energy efficient) light fixtures.
Exterior Painting16-8525 $158,576Complete Paint exterior.
Technology16-8536 $176,035Active District's IT Department site refresh program.
Data Infrastructure Upgrade16-8557 $252,818Complete Replace data infrastructure cabling.
Master Project List Report
BudgetCategory/Project
Cupertino Union School District
Status Description
Measure H Bond ProgramBond Project List - December 31, 2016
MARCH 3, 2017 5 MEASURE H BOND PROGRAM PROGRESS REPORT
Elementary Schools
McAuliffe Elementary School Totals: $5,898,914
Meyerholz Elementary School
Site Utilities Replacement08-8215 $0Deferred
Modernization08-8502 $6,402,959Active Modernization of Buildings C, D and E. Minor upgrade to Student and Staff Restrooms atbuildings A, B and E. Major ADA upgrades to Student (Kindergarten) and Staff Restrooms at Building B, C and D. Earthquake retrofit for Buildings B, C and D. Modernization of Buildings C, D and E. Buildings will receive a new fire alarm service, replacement of finishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms. Improve accessibility for plumbing fixtures and casework in classrooms. Replace some HVAC units. New roofing, paint exterior trim. Expansion of office space.
Lighting Upgrades08-8521 $65,875Complete Addition of new parking lot light fixtures/poles.
Technology08-8536 $198,792Active District's IT Department site refresh program.
Growth Portables08-8550 $275,000Active Purchase and installation of growth portables.
Data Infrastructure Upgrade08-8557 $252,814Complete Replace data infrastructure cabling.
Interim Housing08-8567 $194,352Active Temporary classroom space to house students displaced due to Meyerholz ElementarySchool - Interim Housing (08-8502)
Meyerholz Elementary School Totals: $7,389,792
Montclaire Elementary School
Modernization09-8502 $5,091,876Active Major ADA upgrades to Student and Staff Restrooms C and D. Minor upgrade to Studentand Staff Restrooms at Buildings A, C and C. Buildings will receive a new fire alarm service, replacement of finishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms. Improve accessibility for drinking fountains, plumbing fixtures and casework in classrooms. Paint exterior trim.
Drainage Upgrade and Track Refurbishment09-8512 $98,969Active Due to existing conditions, the track needs to be repaired for PE classes.
Technology09-8536 $174,139Active District's IT Department site refresh program.
SDC Relocation09-8567 $226,031Active Relocate CAP classes out of general classroom wing.
Master Project List Report
BudgetCategory/Project
Cupertino Union School District
Status Description
Measure H Bond ProgramBond Project List - December 31, 2016
MARCH 3, 2017 6 MEASURE H BOND PROGRAM PROGRESS REPORT
Elementary Schools
Montclaire Elementary School Totals: $5,591,015
Murdock Portal Elementary School
Modernization21-8502 $607,405Active Paint exterior building trim and minor site utilities.
Domestic Water Replacement21-8527 $254,019Complete The main water supply has deteriorated to the point of catastrophic failure. This existingmain black iron pipe needs to be fully removed and replaced.
Technology21-8536 $178,078Active District's IT Department site refresh program.
Murdock Portal Elementary School Totals: $1,039,502
Nimitz Elementary School
Site Utilities Replacement12-8215 $0Deferred Project consolidated with 12-8502
Modernization12-8502 $5,465,100Active Minor upgrade to all Student and Staff Restrooms. Buildings will receive a new fire alarmservice, replacement of finishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms. Improve accessibility for plumbing fixtures and casework in classrooms. Replace finishes at warming kitchen. Paint exterior building trim and new roof. Replace select HVAC units.
Technology12-8536 $273,242Active District's IT Department site refresh program.
Nimitz Elementary School Totals: $5,738,342
Regnart Elementary School
Site Utilities Replacement17-8215 $59,163Active Add additional storm drain to eliminate ponding.
Modernization17-8502 $5,131,663Active Major ADA upgrades to Student (Kindergarten) and Staff Restrooms at Building B. Minorupgrade to Student and Staff Restrooms at buildings A, C and D. Replace covered walkway. Buildings will receive a new fire alarm service, replacement of finishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms. Improve accessibility for plumbing fixtures and casework in classrooms. Replace doors and hardware at multi-purpose room. Paint exterior building trim and new roofing. Replace select HVAC units.
Kinder Play Yard Improvements17-8508 $20,000Active Kinder play yard improvements at Regnart Elementary School.
Master Project List Report
BudgetCategory/Project
Cupertino Union School District
Status Description
Measure H Bond ProgramBond Project List - December 31, 2016
MARCH 3, 2017 7 MEASURE H BOND PROGRAM PROGRESS REPORT
Elementary SchoolsLighting Upgrades17-8521 $53,819Complete Addition of new parking lot light fixtures/poles, repair/servicing of existing pole mounted
light fixtures and the replacement of outdated wall mounted light fixtures with new (energy efficient) light fixtures.
Technology17-8536 $195,094Active District's IT Department site refresh program.
Data Infrastructure Upgrade17-8557 $344,498Complete Replace data infrastructure cabling.
Regnart Elementary School Totals: $5,804,238
Sedgwick Elementary School
Modernization14-8502 $5,569,640Active Minor upgrades to Student and Staff Restrooms. Buildings will receive a new fire alarmservice, replacement of finishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms. Improve accessibility for plumbing fixtures and casework in classrooms. Replace doors and hardware at multi-purpose room. Paint exterior of Building B and new roofing.
Technology14-8536 $233,626Active District's IT Department site refresh program.
Sedgwick Elementary School Totals: $5,803,266
Stevens Creek Elementary School
Site Utilities Replacement18-8215 $109,753Active Replacement of sanitary sewer lines. Add additional storm drain to eliminate ponding.
Modernization18-8502 $8,585,649Active Major ADA upgrades to Student (Kindergarten) and Staff Restrooms at Building A, B, Dand E. Minor upgrade to Student and Staff Restrooms at buildings A, B and C. Modernization at Building D and E. Buildings will receive a new fire alarm service, replacement of finishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms. Improve accessibility for plumbing fixtures and casework in classrooms. Replace entry doors and hardware at Building A. Replace finishes at warming kitchen. Paint exterior of building and new roofing. New dumpster enclosure. Replace selected HVAC units in Building A
Technology18-8536 $178,299Active District's IT Department site refresh program.
Data Infrastructure Upgrade18-8557 $318,150Complete Replace data infrastructure cabling.
Replacement of Aged Portables18-8567 $575,000Active Replace three relocatable classroom buildings
Stevens Creek Elementary School Totals: $9,766,851
Master Project List Report
BudgetCategory/Project
Cupertino Union School District
Status Description
Measure H Bond ProgramBond Project List - December 31, 2016
MARCH 3, 2017 8 MEASURE H BOND PROGRAM PROGRESS REPORT
Elementary SchoolsStocklmeir Elementary School
Site Utilities Replacement19-8215 $30,075Active Install new backflow preventer.
Modernization19-8502 $5,289,235Active Minor upgrades to Student and Staff Restrooms at buildings 1, 2, 4, 5 and 6. Earthquakeretrofits for Pod C. Buildings will receive a new fire alarm service, replacement of finishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms. Improve accessibility for plumbing fixtures and casework in classrooms. Replace finishes at warming kitchen. Paint exterior of trim.
Technology19-8536 $288,900Active District's IT Department site refresh program.
Modernization - Phase I19-8567 $2,100,000Active Consolidation of the two Campus Administrative Offices into one temporary facility morecentralyl located on the campus, relocation of the Campus Library into a temporary facility, expand kinder play yard and lunch area, expand upper play yard and apparatus
Stocklmeir Elementary School Totals: $7,708,210
West Valley Elementary School
Modernization20-8502 $7,287,066Active Major ADA upgrades to Student (Kindergarten) and Staff Restrooms at Buildings A, B , Cand K. Minor upgrade to Student and Staff Restrooms at buildings A and D. Replace covered walkway. Earthquake retrofit for Buildings B and C. Buildings will receive a new fire alarm service, replacement of finishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms. Improve accessibility for plumbing fixtures and casework in classrooms. New special Ed classrooms. Replace finishes at warming kitchen. Replace windows in B and C (excluding Admin area). New roofing and paint exterior trim.
Technology20-8536 $152,868Active District's IT Department site refresh program.
Replace Portable Classroom20-8550 $726,387Active Replace portable classrooms 23-27.
Interim Housing20-8567 $1,029,255Active Temporary classroom space for Fall 2014 & Spring 2015 to house students displaceddue to West Valley Elementary School - Modernization (20-8502)
West Valley Elementary Totals: $9,195,576
Elementary Schools Totals: $111,293,825
Middle SchoolsCupertino Middle School
Master Project List Report
BudgetCategory/Project
Cupertino Union School District
Status Description
Measure H Bond ProgramBond Project List - December 31, 2016
MARCH 3, 2017 9 MEASURE H BOND PROGRAM PROGRESS REPORT
Middle SchoolsSite Infrastructure25-8215 $1,853,215Active The demolition of the one story locker room buildings (Building 400) and the installation
of electrical (conduit only), domestic water, storm drain and sewer line infrastructure for the new Multi-Purpose Building and Two-Story Classroom Building.
New Classroom Building25-8501 $6,576,364Active The project includes the construction of a new two story classroom building that will addneeded science (10) and general education classrooms (10), and replace outdated portables.
Mod. of Bldg. 100, 200, 300 and Classroom1 and 2
25-8502 $5,222,407Active The modernization of Building 100, the Administration will be remodeled to allow foradditional support staff, Building 200 will be reconfigured to allow expanded library areas, Building 300 will be remodeled for the expanding performing arts program and to improve the student “point of service” for food service and a portion of Building 500 (classroom 1 and 2) will be reconfigured to provide a new staff work room, teacher lounge and restrooms. Reroofing of buildings 100, 200 and 300.
Multi-Purpose Building25-8505 $11,346,270Active The construction of Multi-Purpose Building and playground area, which will provideadditional space for the physical education program and the performing arts programs.
Modernization of 500, 600, 700 , 800 and900
25-8506 $6,265,283Active Buildings will receive upgrades to restrooms, fire alarm service, and replacement offinishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms and exterior painting of the building trim.
Quad and PE Improvements25-8512 $2,877,477Active Create a quadrangle area for student breaks and physical education improvements.
Technology25-8536 $371,387Active District's IT Department site refresh program.
Site Work for Modular Installation25-8550 $175,000Active Construction and site work necessary to install 24 x 40 modular classroom building:including electrical, telephone, network, intercom and fire alarm.
Interim Housing25-8567 $1,211,658Active The project is the installation of 7 new portables (6 classrooms and 1 restroom) andrelocation of 3 existing classroom portables.
Cupertino Middle School Totals: $35,899,060
Hyde Middle School
Campus Modernization26-8502 $6,208,285Active Buildings will receive upgrades to restrooms, a new fire alarm service, replacement offinishes (flooring, paint, tackable walls, and selected ceiling), refurbishing of casework, window treatments at classrooms, replacement of the clay tile roof and exterior painting of the building trim.
The site will also receive replacement of concrete walks at the Quad, upgrade to the storm drain and domestic water system, additional exterior lighting and an enlarged bike cage area.
Roofing Replacement26-8528 $450,000Active Reroofing of Multipurpose (Building 400) and Gym (Building 500).
Technology26-8536 $271,896Active District's IT Department site refresh program.
Master Project List Report
BudgetCategory/Project
Cupertino Union School District
Status Description
Measure H Bond ProgramBond Project List - December 31, 2016
MARCH 3, 2017 10 MEASURE H BOND PROGRAM PROGRESS REPORT
Middle SchoolsInterim Housing26-8550 $469,768Active Temporary classroom space to house students displaced due to Hyde Middle School -
Campus Modernization (26-8502)Replacement of Leased Portables26-8567 $265,000Active Replacement of 3 portables and addition of 2 new portables.
Hyde Middle School Totals: $7,664,948
Kennedy Middle School
Campus Modernization27-8502 $7,182,052Active Buildings will receive upgrades to restrooms, a new fire alarm service, replacement offinishes (flooring, paint, tackable walls and selected ceilings) refurbishing of casework, window treatments at classrooms and exterior painting of the building trim. Temporary classroom space to house students displaced due to modernization.The site will also receive upgrades to the sewer system, additional exterior lighting, repair of ramps to portables and an enlarged bike cage area.
Technology27-8536 $303,774Active District's IT Department site refresh program.
Interim Housing27-8550 $0Consolidated Temporary classroom space to house students displaced due to Kennedy Middle School- Campus Modernization (27-8502).
Replacement of Aged Portables27-8567 $365,000Active Replacement of portable classrooms A, B and C.
Kennedy Middle School Totals: $7,850,826
Lawson Middle School
Soil Remediation24-8213 $160,607Complete The off haul and disposal of Class 1 material to an authorized landfill from around the oldDistrict Office site.
Site Infrastructure24-8215 $558,844Active The installation of electrical (conduit only), domestic water, storm drain and sewer lineinfrastructure for the new Music Building and Two-Story Classroom Building.
New Classroom Building24-8501 $10,125,809Active The project includes the construction of a new two story classroom building that will addneeded science (10) and general education classrooms (10), and replace outdated portables.
Modernization of Classrooms 3, 25 and 2624-8502 $944,840Active The existing spaces will be modernized to provide additional space for the physicaleducation program and the performing arts program and the modernization of existing staff area.
New Music Building24-8505 $2,389,845Active The construction of Music Building, which will provide additional space for the performingarts programs.
Campus Modernization24-8506 $1,631,562Active Roofing repair and exterior painting of building trim.
Track & Field24-8512 $3,685,544Active Construct a new track and field and expand playground area.
Master Project List Report
BudgetCategory/Project
Cupertino Union School District
Status Description
Measure H Bond ProgramBond Project List - December 31, 2016
MARCH 3, 2017 11 MEASURE H BOND PROGRAM PROGRESS REPORT
Middle SchoolsTechnology24-8536 $375,580Active District's IT Department site refresh program.
District Office Demolition24-8551 $994,109Active Demolition of two (2) one story office buildings, one (1) storage buildings and one (1)hazardous material collection station. Site prep for four (4) modular buildings, site grading, hydro-seeding, asphalt paving, fencing, electrical, domestic water, and, sewer line infrastructure and new hazardous material collection station.
Interim Housing24-8567 $993,313Active The project is the installation of 4 new portable classrooms and relocation of 5 existingclassroom portables and modifications to the existing track and field.
Lawson Middle School Totals: $21,860,054
Miller Middle School
Campus Modernization28-8502 $6,427,766Active Buildings will receive upgrades to restrooms, a new fire alarm service, replacement offinishes (flooring, paint, tackable walls and selected ceiling) refurbishing of casework, window treatments at classrooms and exterior painting of the building trim.
The site will also receive additional exterior lighting, ball wall and additional lunch tablesSite Work for Modular Installation28-8505 $175,000Active Construction and site work necessary to install 24 x 40 modular classroom building:
including electrical, telephone, network, intercom and fire alarm.Roofing Repairs28-8528 $500,000Active Campus-wide roofing repairs at Miller Middle School.
Technology28-8536 $265,398Active District's IT Department site refresh program.
Interim Housing28-8550 $500,343Active Temporary classroom space to house students displaced due to Miller Middle School -Campus Modernization (28-8502).
Replacement of Leased Portables28-8567 $180,000Active Replacement of 3 portables
Miller Middle School Totals: $8,048,506
Middle Schools Totals: $81,323,394
DistrictwideDistrictwide - General
Property Acquisition/Improvement14-8501 $3,630,440Active Acquisition of property and improvement
Central Kitchen - Lease Option15-8511 $0Active Lease space within District attendance boundaries, for the District's Central Kitchen(currently at Stocklmeir).
District Corporation Yard31-8501 $1,194,326Active Construct new pre-fabricated metal building to replace disrupted storage and shops.
Master Project List Report
BudgetCategory/Project
Cupertino Union School District
Status Description
Measure H Bond ProgramBond Project List - December 31, 2016
MARCH 3, 2017 12 MEASURE H BOND PROGRAM PROGRESS REPORT
DistrictwideDistrict Office - Lease Option32-8537 $3,433,872Active Lease commercial office space within District attendance boundaries, determine space
program and construct new office space for all District administrative functions. Move District administrative staff into new facilities.
Energy Efficiency / Solar Projects66-8201 $2,210,000Active Implement long term savings through more effective energy consumption
Hazardous Material Removal66-8213 $1,000,021Active As part of the budget, funds have been set aside to abatement of asbestos, lead paintand other materials as needed.
Playgrounds / Landscaping / Fields66-8508 $1,750,000Active As part of the budget, a fund have been set aside for the refurbishment of blacktop andparking lots, playground/fall surface replacement and fields those most in need of work.
Furniture, Fixtures & Equipment66-8534 $1,000,000Active Classroom furniture for new facilities.
District Wide Security66-8540 $35,293Active New project for computer charging cart security.
Interim Housing66-8550 $0Active As part of the budget, funds have been set aside to accommodate temporary housing ofeducational programs displaced while facilities are under construction or renovation.
DSA Legacy Project Closeout66-8562 $160,000Active DSA closeout activities related to legacy projects.
Moving and Storage66-8565 $1,600,000Active As part of the budget, funds have been set aside to move and storage classroomfurniture/ equipment while facilities are under construction or renovation.
Purchase of District-Leased PortableClassrooms
66-8567 $41,871Active As part of the program, the District will purchase some modular which are deemed to beneeded long term.
Expense Pass-Through Account66-XXXX $0Pending
Districtwide - General Totals $16,055,823
Program Costs
Bond Program Admin Expenses66-8502 $2,550,000Active As part of the budget, funds have been set aside for District employee expenses relatedto the direct management of Measure H.
Bond Program Planning66-8541 $1,300,000Active As part of the budget, funds have been set aside for district wide planning efforts,studies, reports and other planning costs.
Bond Program Miscellaneous Expenses66-8561 $1,550,000Active As part of the budget, funds have been set aside for Bond Costs, Legal Fees, District-wide consultants and other miscellaneous costs.
Program Costs Totals: $5,400,000
Technology
Master Project List Report
BudgetCategory/Project
Cupertino Union School District
Status Description
Measure H Bond ProgramBond Project List - December 31, 2016
MARCH 3, 2017 13 MEASURE H BOND PROGRAM PROGRESS REPORT
DistrictwideTechnology63-8536 $3,943,612Active Replace computers, peripheral devices and user software platforms which don't meet
District standards. Replace aging voice-over-IP phone system. Upgrade campus local area networks to increase speed and capacity. Provide wireless access points in each classroom, ancillary space and large assembly area to support wireless access to digital information. Create a new network portal to support multi-device usage by students and staff.
Technology - Data Infrastructure66-8536 $475,602Active Replace data infrastructure cabling.
Technology Totals: $4,419,214
Contingency
Growth Contingency52-8513 $588,570Active For new facilities required from additional enrollment.
Program Contingency66-8513 $1,989,713Active Contingency funds to use throughout Measure H.
$2,578,283Contingency Totals:
Districtwide Totals: $28,453,320
Grand Total: $221,070,540
Master Project List Report
BudgetCategory/Project
Cupertino Union School District
Status Description
Measure H Bond ProgramBond Project List - December 31, 2016
MARCH 3, 2017 14 MEASURE H BOND PROGRAMPROGRESS REPORT
A&E, Oversight, DSA & Other $32,226,855 $17,666,030$49,892,885
Construction & Contingency $105,560,683 $54,586,804$160,147,487
District Facilities Leases $1,427,571 $1,894,014$3,321,586
Furniture & Equipment $7,555,100 $153,482$7,708,581
Totals: $221,070,540 $146,770,210 $74,300,330
Total Budget Total Expenses
Budget vs Expenses
Available Funds Total Expenses
Available Funds vs Expenses
Whole Program Summary Report
Funding Sources (Budget)
Cupertino Union School District
Measure H Bond ProgramReporting Period: Inception through 12/31/2016
Bond Authorization
Bond Interest EarnedUnallocated Bond Interest Earned
Total Bond:
Cost Status
Budget Group Total Budget
Actual Expenses To Date
Remaining BalanceBond
$220,000,000$1,070,540
$163,576
$221,234,115
99.44 %
0.07 %
0.48 %
100.00 %
Bond Authorization: Measure HBond Interest Earned: Measure H Interest Earnings Allocated to ProjectsUnallocated Interest Earned: Interest Earnings not yet allocated to specific projectsExpenses in the "Actual Expenses to Date" column include paid and accrued expenses through the reporting period end date.Available Funds: Series A Bond Sale of $50M + Series B Bond Sale of $99.995M + Series C Bond Sale of $55M + Bond Interest EarnedRounding variances in dollar amounts may occurActual Expenses To Date includes Cost of Issuance
This report reflects funding sources, actual expenses to date and accruals posted for fiscal year end close.
MARCH 3, 2017 15 MEASURE H BOND PROGRAMPROGRESS REPORT
Elementary SchoolsBlue Hills Elementary School
Site Utilities Replacement 01-8215 $66,183 $66,183 $0Active 6/12/2017 11/30/2017 100 %0 %$66,183
Modernization 01-8502 $6,126,000 $556,388 $5,569,612Active 6/1/2018 12/31/2018 9 %0 %$6,126,000
New Kinder Play Yard 01-8508 $585,405 $452,452 $132,953Active N/A N/A 77 %N/A$585,405
Exterior Painting 01-8525 $156,025 $156,025 $0Complete 6/21/2013 8/9/2013 100 %100 %$156,025
Technology 01-8536 $162,736 $162,736 $0Active N/A N/A 100 %N/A$162,736
Blue Hills Elementary School Totals: $7,096,349 $1,393,783 $5,702,566 $7,096,349
De Vargas Elementary School
Site Utilities Replacement 02-8215 $108,410 $108,410 $0Active 6/3/2013 8/8/2013 100 %100 %$108,410
Modernization 02-8502 $4,299,379 $755,841 $3,543,538Active 4/10/2017 9/14/2017 18 %0 %$4,695,879
Lighting Upgrades 02-8521 $56,084 $56,084 $0Complete 6/17/2013 8/8/2013 100 %100 %$56,084
Technology 02-8536 $184,602 $184,602 $0Active N/A N/A 100 %N/A$184,602
De Vargas Elementary School Totals: $4,648,474 $1,104,936 $3,543,538 $5,044,974
Dilworth Elementary School
Site Utilities Replacement 03-8215 $58,013 $58,013 $0Active 6/3/2013 8/8/2013 100 %100 %$58,013
Modernization 03-8502 $4,008,829 $625,663 $3,383,165Active 2/16/2017 8/16/2017 16 %0 %$4,530,456
Lighting Upgrades 03-8521 $94,206 $94,206 $0Complete 6/17/2013 8/8/2013 100 %100 %$94,206
Technology 03-8536 $170,041 $170,041 $0Active N/A N/A 100 %N/A$170,041
Data Infrastructure Upgrade 03-8557 $369,448 $369,448 $0Complete 6/3/2013 8/8/2013 100 %100 %$369,448
Project Summary Report
BondBudgetCategory/Project
Cupertino Union School DistrictMeasure H Bond ProgramReporting Period: Inception through 12/31/16
Project Number
Bond Exp.To Date
BudgetRemainingStatus Start
DateEnd Date
% Complete Construction
% Complete Financial
BLRChange
Estimate at Completion
MARCH 3, 2017 16 MEASURE H BOND PROGRAM PROGRESS REPORT
Elementary Schools
Dilworth Elementary School Totals: $4,700,537 $1,317,371 $3,383,165 $5,222,164
Collins Elementary School
Modernization 22-8502 $245,025 $2,107 $242,918Active 6/7/2018 10/10/2018 1 %0 %$245,025
Technology 22-8536 $196,320 $196,320 $0Active N/A N/A 100 %N/A$196,320
Collins Elementary School Totals: $441,345 $198,427 $242,918 $441,345
Eaton Elementary School
Modernization 23-8502 $1,205,141 $69,446 $1,135,695Active 6/11/2019 8/12/2019 6 %0 %$1,205,141
Technology 23-8536 $220,254 $220,254 $0Active N/A N/A 100 %N/A$220,500
Eaton Elementary School Totals: $1,425,395 $289,701 $1,135,695 $1,425,641
Eisenhower Elementary School
Site Utilities Replacement 04-8215 $335,059 $335,059 $0Active 6/3/2013 8/8/2013 100 %100 %$335,059
Modernization 04-8502 $3,468,819 $30,021 $3,438,798Active 4/3/2018 2/28/2019 1 %0 %$3,468,819
Technology 04-8536 $193,457 $193,457 $0Active N/A N/A 100 %N/A$193,457
Eisenhower Elementary School Totals: $3,997,335 $558,536 $3,438,798 $3,997,335
Faria Elementary School
Site Utilities Replacement 05-8215 $53,504 $53,504 $0Active 6/3/2013 8/8/2013 100 %100 %$53,504
Modernization 05-8502 $3,950,814 $106,224 $3,844,590Active 4/3/2018 2/28/2019 3 %0 %$3,950,814
Technology 05-8536 $220,782 $220,782 $0Active N/A N/A 100 %N/A$220,782
Growth Portables 05-8550 $238,750 $236,930 $1,820Active 6/26/2014 8/17/2014 99 %100 %$238,750
Project Summary Report
BondBudgetCategory/Project
Cupertino Union School DistrictMeasure H Bond ProgramReporting Period: Inception through 12/31/16
Project Number
Bond Exp.To Date
BudgetRemainingStatus Start
DateEnd Date
% Complete Construction
% Complete Financial
BLRChange
Estimate at Completion
MARCH 3, 2017 17 MEASURE H BOND PROGRAM PROGRESS REPORT
Elementary SchoolsPortable Restroom 05-8567 $167,089 $164,171 $2,918Active 6/5/2015 8/7/2015 98 %100 %$167,089
Faria Elementary School Totals: $4,630,939 $781,610 $3,849,329 $4,630,939
Garden Gate Elementary School
Site Utilities Replacement 06-8215 $323,322 $323,322 $0Active 6/3/2013 12/31/2014 100 %100 %$323,322
Modernization 06-8502 $6,600,000 $6,241,611 $358,389Active 6/8/2015 12/31/2015 95 %100 %$6,644,904
Technology 06-8536 $206,050 $206,050 $0Active N/A N/A 100 %N/A$206,050
Data Infrastructure Upgrade 06-8557 $512,846 $512,846 $0Complete 6/3/2013 11/22/2013 100 %100 %$512,846
Garden Gate Elementary School Totals: $7,642,218 $7,283,829 $358,389 $7,687,121
John Muir Elementary School
Modernization 10-8502 $4,903,809 $4,516,604 $387,205Active 6/15/2015 6/24/2016 92 %100 %$4,903,809
Kinder Play Yard Improvements 10-8508 $135,000 $109,527 $25,473Active 7/1/2015 7/31/2015 81 %100 %$135,000
Roofing 10-8528 $152,059 $152,059 $0Complete 6/28/2012 7/27/2012 100 %100 %$152,059
Technology 10-8536 $220,894 $220,894 $0Active N/A N/A 100 %N/A$220,894
YCC/CAP Relocation 10-8567 $1,040,000 $1,029,622 $10,378Active 6/23/2014 8/8/2014 99 %100 %$1,040,000
John Muir Elementary School Totals: $6,451,762 $6,028,705 $423,057 $6,451,762
Lincoln Elementary School
Site Utilities Replacement 07-8215 $255,904 $255,904 $0Active 6/13/2014 8/17/2014 100 %100 %$255,904
Modernization 07-8502 $4,575,430 $28,915 $4,546,516Active 4/1/2019 11/30/2019 1 %0 %$4,575,430
Kinder Play Yard Improvements 07-8508 $169,583 $164,183 $5,400Active 7/1/2015 7/31/2015 97 %100 %$169,583
Project Summary Report
BondBudgetCategory/Project
Cupertino Union School DistrictMeasure H Bond ProgramReporting Period: Inception through 12/31/16
Project Number
Bond Exp.To Date
BudgetRemainingStatus Start
DateEnd Date
% Complete Construction
% Complete Financial
BLRChange
Estimate at Completion
MARCH 3, 2017 18 MEASURE H BOND PROGRAM PROGRESS REPORT
Elementary SchoolsLighting Upgrades 07-8521 $39,391 $39,391 $0Complete 6/17/2013 8/8/2013 100 %100 %$39,391
Roofing 07-8528 $510,010 $510,010 $0Complete 1/10/2013 2/11/2013 100 %100 %$510,010
Technology 07-8536 $223,177 $223,177 $0Active N/A N/A 100 %N/A$223,177
New Portable Restroom 07-8567 $165,000 $3,000 $162,000Active 1/1/2019 12/31/2019 2 %0 %$165,000
Roofing Phase II 07-8579 $385,270 $385,270 $0Active 7/15/2014 8/15/2014 100 %100 %$385,270
Lincoln Elementary School Totals: $6,323,765 $1,609,849 $4,713,916 $6,323,765
McAuliffe Elementary School
Site Utilities Replacement 16-8215 $83,378 $83,378 $0Active 6/3/2013 8/8/2013 100 %100 %$83,378
Modernization 16-8502 $5,108,109 $4,762,652 $345,457Active 6/15/2015 6/30/2016 93 %100 %$5,108,109
Lighting Upgrades 16-8521 $119,998 $119,998 $0Complete 6/17/2013 8/8/2013 100 %100 %$119,998
Exterior Painting 16-8525 $158,576 $158,576 $0Complete 6/21/2013 8/8/2013 100 %100 %$158,576
Technology 16-8536 $176,035 $176,035 $0Active N/A N/A 100 %N/A$176,035
Data Infrastructure Upgrade 16-8557 $252,818 $252,818 $0Complete 6/3/2013 8/8/2013 100 %100 %$252,818
McAuliffe Elementary School Totals: $5,898,914 $5,553,456 $345,457 $5,898,914
Meyerholz Elementary School
Modernization 08-8502 $6,402,959 $6,362,134 $40,825Active 8/5/2014 2/23/2015 99 %100 %$6,402,959
Lighting Upgrades 08-8521 $65,875 $65,875 $0Complete 6/17/2013 8/8/2013 100 %100 %$65,875
Technology 08-8536 $198,792 $198,792 $0Active N/A N/A 100 %N/A$198,792
Growth Portables 08-8550 $275,000 $256,952 $18,048Active 6/26/2014 8/17/2014 93 %100 %$275,000
Data Infrastructure Upgrade 08-8557 $252,814 $252,814 $0Complete 6/3/2013 8/8/2013 100 %100 %$252,814
Project Summary Report
BondBudgetCategory/Project
Cupertino Union School DistrictMeasure H Bond ProgramReporting Period: Inception through 12/31/16
Project Number
Bond Exp.To Date
BudgetRemainingStatus Start
DateEnd Date
% Complete Construction
% Complete Financial
BLRChange
Estimate at Completion
MARCH 3, 2017 19 MEASURE H BOND PROGRAM PROGRESS REPORT
Elementary SchoolsInterim Housing 08-8567 $194,352 $194,352 $0Active 11/13/2014 12/31/2014 100 %100 %$194,352
Meyerholz Elementary School Totals: $7,389,792 $7,330,919 $58,873 $7,389,792
Montclaire Elementary School
Modernization 09-8502 $5,091,876 $815,765 $4,276,111Active 6/12/2017 2/28/2018 16 %0 %$5,091,876
Drainage Upgrade and TrackRefurbishment
09-8512 $98,969 $98,969 $0Active 5/19/2014 6/18/2014 100 %100 %$98,969
Technology 09-8536 $174,139 $174,139 $0Active N/A N/A 100 %N/A$174,139
SDC Relocation 09-8567 $226,031 $99,209 $126,821Active 3/16/2016 4/26/2016 44 %100 %$226,031
Montclaire Elementary School Totals: $5,591,015 $1,188,082 $4,402,933 $5,591,015
Murdock Portal Elementary School
Modernization 21-8502 $607,405 $19,109 $588,296Active 6/12/2017 8/1/2017 3 %0 %$607,405
Domestic Water Replacement 21-8527 $254,019 $254,019 $0Complete 6/27/2013 8/8/2013 100 %100 %$254,019
Technology 21-8536 $178,078 $178,078 $0Active N/A N/A 100 %N/A$178,078
Murdock Portal Elementary School Totals: $1,039,502 $451,206 $588,296 $1,039,502
Nimitz Elementary School
Modernization 12-8502 $5,465,100 $178,656 $5,286,444Active 6/1/2018 12/31/2018 3 %0 %$5,465,100
Technology 12-8536 $273,242 $273,242 $0Active N/A N/A 100 %N/A$273,242
Nimitz Elementary School Totals: $5,738,342 $451,898 $5,286,444 $5,738,342
Regnart Elementary School
Site Utilities Replacement 17-8215 $59,163 $59,163 $0Active 6/3/2013 8/8/2013 100 %100 %$59,163
Project Summary Report
BondBudgetCategory/Project
Cupertino Union School DistrictMeasure H Bond ProgramReporting Period: Inception through 12/31/16
Project Number
Bond Exp.To Date
BudgetRemainingStatus Start
DateEnd Date
% Complete Construction
% Complete Financial
BLRChange
Estimate at Completion
MARCH 3, 2017 20 MEASURE H BOND PROGRAM PROGRESS REPORT
Elementary SchoolsModernization 17-8502 $5,131,663 $5,049,506 $82,157Active 5/5/2014 8/20/2014 98 %100 %$5,131,663
Kinder Play Yard Improvements 17-8508 $20,000 $0 $20,000Active 7/1/2015 7/31/2015 0 %100 %$20,000
Lighting Upgrades 17-8521 $53,819 $53,819 $0Complete 6/17/2013 8/8/2013 100 %100 %$53,819
Technology 17-8536 $195,094 $195,094 $0Active N/A N/A 100 %N/A$195,094
Data Infrastructure Upgrade 17-8557 $344,498 $344,498 $0Complete 6/3/2013 8/8/2013 100 %100 %$344,498
Regnart Elementary School Totals: $5,804,238 $5,702,080 $102,157 $5,804,238
Sedgwick Elementary School
Modernization 14-8502 $5,569,640 $5,459,544 $110,096Active 6/12/2014 8/15/2014 98 %100 %$5,569,640
Technology 14-8536 $233,626 $233,626 $0Active N/A N/A 100 %N/A$233,626
Sedgwick Elementary School Totals: $5,803,266 $5,693,170 $110,096 $5,803,266
Stevens Creek Elementary School
Site Utilities Replacement 18-8215 $109,753 $109,753 $0Active 6/3/2013 8/8/2013 100 %100 %$109,753
Modernization 18-8502 $8,585,649 $6,338,602 $2,247,047Active 4/11/2016 2/28/2017 74 %82 %$8,585,649
Technology 18-8536 $178,299 $178,299 $0Active N/A N/A 100 %N/A$178,299
Data Infrastructure Upgrade 18-8557 $318,150 $318,150 $0Complete 6/3/2013 11/22/2013 100 %100 %$318,150
Replacement of Aged Portables 18-8567 $575,000 $525,259 $49,741Active N/A N/A 91 %N/A$575,000
Stevens Creek Elementary School Totals: $9,766,851 $7,470,063 $2,296,788 $9,766,851
Stocklmeir Elementary School
Site Utilities Replacement 19-8215 $30,075 $30,075 $0Active 6/3/2013 8/8/2013 100 %100 %$30,075
Project Summary Report
BondBudgetCategory/Project
Cupertino Union School DistrictMeasure H Bond ProgramReporting Period: Inception through 12/31/16
Project Number
Bond Exp.To Date
BudgetRemainingStatus Start
DateEnd Date
% Complete Construction
% Complete Financial
BLRChange
Estimate at Completion
MARCH 3, 2017 21 MEASURE H BOND PROGRAM PROGRESS REPORT
Elementary SchoolsModernization 19-8502 $5,289,235 $243,404 $5,045,831Active 6/1/2018 2/28/2019 5 %0 %$5,289,235
Technology 19-8536 $288,900 $288,900 $0Active N/A N/A 100 %N/A$288,900
Modernization - Phase I 19-8567 $2,100,000 $776,685 $1,323,315Active 6/1/2016 12/31/2016 37 %100 %$2,100,000
Stocklmeir Elementary School Totals: $7,708,210 $1,339,065 $6,369,146 $7,708,210
West Valley Elementary School
Modernization 20-8502 $7,287,066 $7,278,610 $8,456Active 5/16/2014 8/14/2015 100 %100 %$7,287,066
Technology 20-8536 $152,868 $152,868 $0Active N/A N/A 100 %N/A$152,868
Replace Portable Classroom 20-8550 $726,387 $726,387 $0Active 6/5/2015 8/7/2015 100 %100 %$726,387
Interim Housing 20-8567 $1,029,255 $986,881 $42,374Active 5/6/2014 9/1/2014 96 %100 %$1,029,255
West Valley Elementary Totals: $9,195,576 $9,144,746 $50,830 $9,195,576
Elementary Schools Totals: $111,293,825 $64,891,434 $46,402,391 $112,257,101
Middle SchoolsCupertino Middle School
Site Infrastructure 25-8215 $1,853,215 $1,853,215 $0Active 6/18/2013 8/14/2013 100 %100 %$1,853,215
New Classroom Building 25-8501 $6,576,364 $6,576,364 $0Active 11/11/2013 8/13/2014 100 %100 %$6,576,364
Mod. of Bldg. 100, 200, 300 andClassroom 1 and 2
25-8502 $5,222,407 $5,222,407 $0Active 4/14/2014 8/12/2015 100 %100 %$5,222,407
Multi-Purpose Building 25-8505 $11,346,270 $11,337,640 $8,630Active N/A N/A 100 %N/A$11,346,270
Modernization of 500, 600, 700 ,800 and 900
25-8506 $6,265,283 $247,018 $6,018,265Active 6/14/2017 2/6/2018 4 %0 %$6,265,283
Quad and PE Improvements 25-8512 $2,877,477 $2,733,889 $143,588Active 6/12/2014 8/6/2014 95 %100 %$2,877,477
Technology 25-8536 $371,387 $371,387 $0Active N/A N/A 100 %N/A$371,387
Project Summary Report
BondBudgetCategory/Project
Cupertino Union School DistrictMeasure H Bond ProgramReporting Period: Inception through 12/31/16
Project Number
Bond Exp.To Date
BudgetRemainingStatus Start
DateEnd Date
% Complete Construction
% Complete Financial
BLRChange
Estimate at Completion
MARCH 3, 2017 22 MEASURE H BOND PROGRAM PROGRESS REPORT
Middle SchoolsSite Work for Modular Installation 25-8550 $175,000 $82,827 $92,173Active 6/12/2017 4/1/2018 47 %0 %$175,000
Interim Housing 25-8567 $1,211,658 $1,211,658 $0Active 5/20/2013 8/13/2013 100 %100 %$1,211,658
Cupertino Middle School Totals: $35,899,060 $29,636,404 $6,262,656 $35,899,060
Hyde Middle School
Campus Modernization 26-8502 $6,208,285 $5,991,859 $216,426Active 1/12/2015 7/24/2015 97 %100 %$6,208,285
Roofing Replacement 26-8528 $450,000 $435,076 $14,924Active 1/1/2015 12/31/2015 97 %100 %$450,000
Technology 26-8536 $271,896 $271,896 $0Active N/A N/A 100 %N/A$272,633
Interim Housing 26-8550 $469,768 $469,768 $0Active 11/17/2014 1/1/2015 100 %100 %$469,768
Replacement of Leased Portables 26-8567 $265,000 $245,381 $19,619Active 6/18/2015 9/30/2016 93 %100 %$265,000
Hyde Middle School Totals: $7,664,948 $7,413,980 $250,968 $7,665,686
Kennedy Middle School
Campus Modernization 27-8502 $7,182,052 $1,245,467 $5,936,585Active 1/23/2017 11/23/2017 17 %0 %$7,182,052
Technology 27-8536 $303,774 $303,774 $0Active N/A N/A 100 %N/A$303,774
Replacement of Aged Portables 27-8567 $365,000 $349,985 $15,015Active 6/18/2015 8/14/2015 96 %100 %$365,000
Kennedy Middle School Totals: $7,850,826 $1,899,225 $5,951,600 $7,850,826
Lawson Middle School
Soil Remediation 24-8213 $160,607 $160,607 $0Complete 11/1/2013 11/30/2013 100 %100 %$160,607
Site Infrastructure 24-8215 $558,844 $558,844 $0Active 7/8/2013 8/16/2013 100 %100 %$558,844
New Classroom Building 24-8501 $10,125,809 $10,125,809 $0Active 1/3/2014 9/29/2014 100 %100 %$10,125,809
Project Summary Report
BondBudgetCategory/Project
Cupertino Union School DistrictMeasure H Bond ProgramReporting Period: Inception through 12/31/16
Project Number
Bond Exp.To Date
BudgetRemainingStatus Start
DateEnd Date
% Complete Construction
% Complete Financial
BLRChange
Estimate at Completion
MARCH 3, 2017 23 MEASURE H BOND PROGRAM PROGRESS REPORT
Middle SchoolsModernization of Classrooms 3, 25and 26
24-8502 $944,840 $936,638 $8,202Active 6/12/2014 8/8/2014 99 %100 %$944,840
New Music Building 24-8505 $2,389,845 $2,389,845 $0Active 2/11/2014 9/24/2014 100 %100 %$2,389,845
Campus Modernization 24-8506 $1,631,562 $45,190 $1,586,372Active 6/1/2018 8/30/2018 3 %0 %$1,631,562
Track & Field 24-8512 $3,685,544 $3,596,088 $89,457Active 6/12/2014 1/5/2015 98 %100 %$3,685,544
Technology 24-8536 $375,580 $375,580 $0Active N/A N/A 100 %N/A$376,072
District Office Demolition 24-8551 $994,109 $993,905 $204Active 8/22/2013 12/17/2013 100 %100 %$994,109
Interim Housing 24-8567 $993,313 $993,313 $0Active 4/11/2013 8/19/2013 100 %100 %$993,313
Lawson Middle School Totals: $21,860,054 $20,175,820 $1,684,235 $21,860,546
Miller Middle School
Campus Modernization 28-8502 $6,427,766 $6,429,669 ($1,903)Active 1/12/2015 7/24/2015 100 %100 %$6,427,766
Site Work for Modular Installation 28-8505 $175,000 $80,181 $94,819Active N/A N/A 46 %N/A$175,000
Roofing Repairs 28-8528 $500,000 $134,049 $365,951Active 6/15/2016 8/1/2017 27 %48 %$500,000
Technology 28-8536 $265,398 $265,398 $0Active N/A N/A 100 %N/A$265,398
Interim Housing 28-8550 $500,343 $499,279 $1,063Active 6/1/2015 7/28/2015 100 %100 %$500,343
Replacement of Leased Portables 28-8567 $180,000 $177,823 $2,177Active N/A N/A 99 %N/A$180,000
Miller Middle School Totals: $8,048,506 $7,586,399 $462,107 $8,048,506
Middle Schools Totals: $81,323,394 $66,711,828 $14,611,567 $81,324,624
DistrictwideDistrictwide - General
Property Acquisition/Improvement 14-8501 $3,630,440 $3,664,895 ($34,455)Active N/A N/A 101 %N/A$3,630,440
Project Summary Report
BondBudgetCategory/Project
Cupertino Union School DistrictMeasure H Bond ProgramReporting Period: Inception through 12/31/16
Project Number
Bond Exp.To Date
BudgetRemainingStatus Start
DateEnd Date
% Complete Construction
% Complete Financial
BLRChange
Estimate at Completion
MARCH 3, 2017 24 MEASURE H BOND PROGRAM PROGRESS REPORT
DistrictwideCentral Kitchen - Lease Option 15-8511 $0 $0 $0Active N/A N/A 0 %N/A$0
District Corporation Yard 31-8501 $1,194,326 $1,176,286 $18,040Active N/A N/A 98 %N/A$1,194,326
District Office - Lease Option 32-8537 $3,433,872 $1,539,858 $1,894,014Active N/A N/A 45 %N/A$3,433,872
Energy Efficiency / Solar Projects 66-8201 $2,210,000 $0 $2,210,000Active N/A N/A 0 %N/A$2,210,000
Hazardous Material Removal 66-8213 $1,000,021 $452 $999,569Active N/A N/A 0 %N/A$794,644
Playgrounds / Landscaping / Fields 66-8508 $1,750,000 $260,528 $1,489,472Active N/A N/A 15 %N/A$1,508,397
Furniture, Fixtures & Equipment 66-8534 $1,000,000 $994,873 $5,127Active N/A N/A 99 %N/A$1,000,000
District Wide Security 66-8540 $35,293 $35,293 $0Active N/A N/A 100 %N/A$35,293
Interim Housing 66-8550 $0 $0 $0Active N/A N/A 0 %N/A$0
DSA Legacy Project Closeout 66-8562 $160,000 $34,018 $125,982Active N/A N/A 21 %N/A$160,000
Moving and Storage 66-8565 $1,600,000 $39,450 $1,560,550Active N/A N/A 2 %N/A$1,303,296
Purchase of District-LeasedPortable Classrooms
66-8567 $41,871 $41,871 $0Active N/A N/A 100 %N/A$41,871
Districtwide - General Totals $16,055,823 $7,787,523 $8,268,300 $15,312,138
Program Costs
Bond Program Admin Expenses 66-8502 $2,550,000 $1,463,822 $1,086,178Active N/A N/A 57 %N/A$2,550,000
Bond Program Planning 66-8541 $1,300,000 $1,164,286 $135,714Active N/A N/A 90 %N/A$1,300,000
Bond Program MiscellaneousExpenses
66-8561 $1,550,000 $1,277,614 $272,386Active N/A N/A 82 %N/A$1,550,000
Program Costs Totals: $5,400,000 $3,905,722 $1,494,278 $5,400,000
Technology
Technology 63-8536 $3,943,612 $3,472,261 $471,351Active N/A N/A 88 %N/A$3,942,137
Project Summary Report
BondBudgetCategory/Project
Cupertino Union School DistrictMeasure H Bond ProgramReporting Period: Inception through 12/31/16
Project Number
Bond Exp.To Date
BudgetRemainingStatus Start
DateEnd Date
% Complete Construction
% Complete Financial
BLRChange
Estimate at Completion
MARCH 3, 2017 25 MEASURE H BOND PROGRAM PROGRESS REPORT
DistrictwideTechnology - Data Infrastructure 66-8536 $475,602 $1,442 $474,160Active N/A N/A 0 %N/A$475,602
Technology Totals: $4,419,214 $3,473,703 $945,511 $4,417,739
Contingency
Growth Contingency 52-8513 $588,570 $0 $588,570Active N/A N/A 0 %N/A$588,570
Program Contingency 66-8513 $1,989,713 $0 $1,989,713Active N/A N/A 0 %N/A$1,933,943
Contingency Totals: $2,578,283 $0 $2,578,283 $2,522,513
$28,453,320 $15,166,948 $13,286,373 $27,652,390
Grand Total: $221,234,115 $146,770,210 $74,463,906
Districtwide Totals:
Unallocated Interest Earned: $163,576
$221,234,115
: Notes new changes to budget/scope
: Notes prior budget/scope changes
This report reflects funding sources, actual expenses to date and accruals posted for fiscal year end close.
"Start Date" : Notice to proceed on construction activities."End Date" : When project is available for intended use"% Complete Construction" : Report date vs. construction duration of project."% Complete Financial" : Bond Expenses to Date divided by Bond Budget.Cancelled, Consolidated and Pending projects have been removed from this report for ease of review.Start/End Dates and Estimate at Completion reflect latest project updates and may include data more current than the financial reporting period.Rounding variances in dollar amounts may occur.
Project Summary Report
BondBudgetCategory/Project
Cupertino Union School DistrictMeasure H Bond ProgramReporting Period: Inception through 12/31/16
Project Number
Bond Exp.To Date
BudgetRemainingStatus Start
DateEnd Date
% Complete Construction
% Complete Financial
BLRChange
Estimate at Completion
MARCH 3, 2017 26 MEASURE H BOND PROGRAM PROGRESS REPORT
Measure H Bond Program Cupertino Union School District
Spend Data thru December 31, 2016Fiscal Year 2016-2017 Q2 Cash Flow
MARCH 3, 2017 27 MEASURE H BOND PROGRAMPROGRESS REPORT
Cupertino Union School District - Measure H Bond Program Project Sequence
Site/ProjectConstruction
StartPhase
Districtwide Technology Refresh (All campuses & DO) 2013 CompleteDistrict Administrative Office Relocation 2013 CompleteDistrict Corporation Yard Storage Building 2013 CompleteSummer 2013 Fast-Track Projects 2013 CompleteCupertino Middle School - New Buildings 2013 CompleteLawson Middle School - New Buildings 2013 CompleteCupertino Middle School - 100, 200, 300, CR's 1 & 5 2014 CompleteMeyerholz Elementary School 2014 CompleteRegnart Elementary School 2014 CompleteSedgwick Elementary School 2014 CompleteWest Valley Elementary School 2014 CompleteMontclaire ES (SDC relo, GLC, ext paint, track) 2014 CompleteMuir ES Relocation of 5 YCC/CAP CR's from Sedgwick 2014 CompleteMeyerholz ES Installation of 2 portable classrooms 2014 CompleteFaria ES Installation of 2 portable classrooms 2014 CompleteHyde Middle School 2015 CompleteMiller Middle School 2015 CompleteMcAuliffe Elementary School 2015 CloseoutMuir Elementary School 2015 CloseoutGarden Gate Elementary School 2015 CloseoutKennedy Middle School 2016 DesignDe Vargas Elementary School 2016 Bidding March 2017Dilworth Elementary School 2016 Construction
Stevens Creek Elementary School 2016 Complete
Stocklmeir ES Short-Term Facility Needs 2016 ConstructionBlue Hills Elementary School 2017 DesignMontclaire Elementary School 2017 Bidding April 2017
Cupertino Middle School - Modernization 2017 Bidding March 2017
Lawson Middle School - Modernization 2017 PlanningStocklmeir Elementary School 2017 PlanningEisenhower Elementary School 2018 PendingNimitz Elementary School 2018 PendingCollins Elementary School 2018 PendingEaton Elementary School 2019 PendingFaria Elementary School 2019 PendingLincoln Elementary School 2019 PendingMurdock-Portal Elementary School 2019 Pending
MARCH 3, 2017 28 MEASURE H BOND PROGRAMPROGRESS REPORT
Quick-Start Projects
Architect / Engineer:
Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2013
MODERNIZATION PROJECTDESIGN SCHEDULE: January 2015 - May 2015DOCUMENT PREPARATION SCHEDULE: June 2015 - January 2016. BID & CONTRACT AWARD SCHEDULE: To be determined. The project timeline is currently under review.CONSTRUCTION SCHEDULE: To be determined. The project timeline is currently under review.
Current Project Budget: $
Percent Complete: 23%
Project Cost at Completion: $
Funding Source:
1) Postconstruction certification process associated with the kitchen is complete. District will remove existing kitchen.2) Develop a new project timeline that allows for a realignment effort of project scope to budget.
COMMENTS, ISSUES OR CONCERNS
Measure H Fund 24
7,096,349
7,096,349
NEXT 60 DAYS
Quick-start projects complete.Modernization scheduled for 2018.
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Blue Hills Elementary School
Campuswide Modernization
Exterior painting
PROJECT SUMMARY
Computer replacements, network, and wireless access upgrades
Site utility repairs
SIM Architects
To be determined.
envelope repairs, installation of full height walls for acoustic
improvements, interior finishes, new fire alarm system
Restroom and classroom accessibility upgrades, building
MARCH 3, 2017 29 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Minor accessibility upgrades and exterior painting (trim only)
Architect / Engineer:
Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2013
MODERNIZATION PROJECTDESIGN SCHEDULE: January 2017 - May 2017. The project time line is currently under review.DOCUMENT PREPARATION SCHEDULE: June 2017 - January 2018. The project timeline is currently under review.BID & CONTRACT AWARD SCHEDULE: February 2018 - April 2018. The project timeline is currently under review.CONSTRUCTION SCHEDULE: May 2018 - August 2018. The project timeline is currently under review .
Current Project Budget: $
Percent Complete: 38%
Project Cost at Completion: $
Funding Source:
To be determined.
To be determined.
Campus wide Modernization
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Collins Elementary School
Computer replacements, network, and wireless access upgrades
PROJECT SUMMARY
Quick-start project complete.Modernization scheduled for 2018.
COMMENTS, ISSUES OR CONCERNS
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
Measure H Fund 24
441,345
441,345
NEXT 60 DAYS
MARCH 3, 2017 30 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Architect / Engineer:
KCEM Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2013
MODERNIZATION PROJECTDESIGN SCHEDULE: January 2015 - May 2015DOCUMENT PREPARATION SCHEDULE: June 2015 - January 2016REBID & CONTRACT AWARD SCHEDULE: January 2017 - March 2017CONSTRUCTION SCHEDULE: April 2017 - September 2017
Current Project Budget: $
Percent Complete: 39%
Project Cost at Completion: $
Funding Source:
Site utility repairs
HMC Architects
Mark Casini, Project Manager,
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
De Vargas Elementary School
Campus wide Modernization
Site lighting upgrades
envelope repairs, interior and exterior finish enhancements
(walls, floors & casework), new fire alarm system
PROJECT SUMMARY
Computer replacements, network, and wireless access upgrades
Restroom and classroom accessibility upgrades, building
Quick-start projects complete.Modernization scheduled for 2017.
COMMENTS, ISSUES OR CONCERNS
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
Measure H Fund 24
2) The project has been issued to bid with pricing due on March 2, 2017.
3) Construction is scheduled to start early April and be completed by September 2017.
4,648,474
4,648,474
NEXT 60 DAYS
1) The revised documents have been approved by DSA.
MARCH 3, 2017 31 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Architect / Engineer:
KCEM Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2013
MODERNIZATION PROJECTDESIGN SCHEDULE: January 2015 - May 2015DOCUMENT PREPARATION SCHEDULE: June 2015 - January 2016REBID & CONTRACT AWARD SCHEDULE: December 2016 - January 2017CONSTRUCTION SCHEDULE: February 2017 - August 2017
Current Project Budget:
Percent Complete: 32%
Project Cost at Completion: $
Funding Source:
1) The revised documents have been approved by DSA.
2) The project has been issued to bid with pricing recived on January 20, 2017.
3) The project bids were approximately $375K beyond the projected budget.
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Dilworth Elementary School
Campus wide Modernization
Site lighting upgrades, site utility repairs
Data infrastructure upgrades
envelope repairs, interior and exterior finish enhancements
(walls, floors & casework), new fire alarm system
PROJECT SUMMARY
Computer replacements, network, and wireless access upgrades
Restroom and classroom accessibility upgrades, building
Quick-start projects complete.Modernization work scheduled for 2017.
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
IBI Group
Thomas Barton, Project Manager
4) Construction started early February and will be completed by August 2017.
COMMENTS, ISSUES OR CONCERNS
4,700,537$
4,700,537
NEXT 60 DAYS
Measure H Fund 24
MARCH 3, 2017 32 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Campuswide ModernizationRestroom and classroom accessibility upgrades, building
envelope repairs, interior and exterior finish enhancements
Architect / Engineer:
Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2013
MODERNIZATION PROJECTDESIGN SCHEDULE: January 2017 - May 2017. The project time line is currently under review.DOCUMENT PREPARATION SCHEDULE: June 2017 - January 2018. The project timeline is currently under review.BID & CONTRACT AWARD SCHEDULE: February 2018 - April 2018. The project timeline is currently under review.CONSTRUCTION SCHEDULE: May 2018 - August 2018. The project time line is currently under review.
Current Project Budget: $
Percent Complete: 20%
Project Cost at Completion: $
Funding Source:
To be determined.
To be determined.
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Eaton Elementary School
Computer replacements, network, and wireless access upgrades
(walls, floors & casework), new fire alarm system
PROJECT SUMMARY
Quick-start projects complete.Modernization scheduled for 2019.
COMMENTS, ISSUES OR CONCERNS
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
Measure H Fund 24
1,425,395
1,425,395
NEXT 60 DAYS
MARCH 3, 2017 33 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Architect / Engineer:
Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2013
MODERNIZATION PROJECTDESIGN SCHEDULE: January 2016 - May 2016. The project time line is currently under review.DOCUMENT PREPARATION SCHEDULE: June 2016 - January 2017. The project timeline is currently under review.BID & CONTRACT AWARD SCHEDULE: February 2017 - April 2017. The project timeline is currently under review.CONSTRUCTION SCHEDULE: May 2017 - August 2017. The project time line is currently under review.
Current Project Budget: $
Percent Complete: 14%
Project Cost at Completion: $
Funding Source:
Campuswide ModernizationRestroom and classroom accessibility upgrades, building
Site utility repairs
Computer replacements, network, and wireless access upgrades
To be determined.
To be determined.
Quick-start projects complete.Modernization scheduled for 2018.
PROJECT SUMMARY
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Eisenhower Elementary School
envelope repairs, interior and exterior finish enhancements
(walls, floors & casework), new fire alarm system
COMMENTS, ISSUES OR CONCERNS
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
Measure H Fund 24
3,997,335
3,997,335
NEXT 60 DAYS
MARCH 3, 2017 34 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Architect / Engineer:
Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: Phase 1 - Jan. 2013 - Aug. 2013; Phase 2 - Feb. 2014 - Aug. 2014
MODERNIZATION PROJECTDESIGN SCHEDULE: January 2016 - May 2016. The project time line is currently under review.DOCUMENT PREPARATION SCHEDULE: June 2016 - January 2017. The project timeline is currently under review.BID & CONTRACT AWARD SCHEDULE: February 2017 - April 2017. The project timeline is currently under review.CONSTRUCTION SCHEDULE: May 2017 - August 2017. The project timeline is currently under review.
Current Project Budget: $
Percent Complete: 17%
Project Cost at Completion: $
Funding Source:
4,630,939
4,630,939
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
Measure H Fund 24
envelope repairs, interior and exterior finish enhancements
(walls, floors & casework), new fire alarm system
PROJECT SUMMARY
Install two new portable classrooms to accommodate growth
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Faria Elementary School
Campuswide ModernizationRestroom and classroom accessibility upgrades, building
Site utility repairs
Computer replacements, network, and wireless access upgrades
To be determined.
To be determined.
Quick-start projects complete.Modernization scheduled for 2019.
MARCH 3, 2017 35 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Architect / Engineer:
KCEM Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2013
MODERNIZATION PROJECTDESIGN SCHEDULE: January 2014 - June 2014DOCUMENT PREPARATION SCHEDULE: June 2014 - February 2015BID & CONTRACT AWARD SCHEDULE: March 2015 - April 2015CONSTRUCTION SCHEDULE: May 2015 - July 2017
Current Project Budget: $
Percent Complete: 97%
Project Cost at Completion: $
Funding Source:
7,642,218
7,642,218
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
1) Kiln room relocation project is complete.
2) The team is progressing on the Health Department concerns associated with finalizing the kitchen modernization. Installation of an exhaust hood will commence in June and be completed by the end of July 2017.
1) The claim filed by the contractor associated with electrical scope of work has been rejected by the Owner.
3) Closeout of the modernization contract scope is now complete.
Measure H Fund 24
Quick-start projects complete.Modernization work complete.
WLC Architects
Duke Sonderegger, Project Engineer
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
interior/exterior finish enhancements (walls, floors & casework)
new fire alarm system, voluntary structural upgrades,
PROJECT SUMMARY
Computer replacements, network, and wireless access upgrades
Restroom/classroom ADA upgrades, bldg. envelope repairs,
domestic water piping replacement
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Garden Gate Elementary School
Campus wide Modernization
Site utility repairs
Data infrastructure upgrades
MARCH 3, 2017 36 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Architect / Engineer:
Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2013
MODERNIZATION PROJECTDESIGN SCHEDULE: January 2017 - May 2017. The project timeline is currently under review.DOCUMENT PREPARATION SCHEDULE: June 2017 - January 2018. The project timeline is currently under review.BID & CONTRACT AWARD SCHEDULE: February 2018 - April 2018. The project timeline is currently under review.CONSTRUCTION SCHEDULE: May 2018 - August 2018. The project timeline is currently under review.
Current Project Budget: $
Percent Complete: 27%
Project Cost at Completion: $
Funding Source:
Lighting upgrades
To be determined.
To be determined.
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Lincoln Elementary School
Campuswide Modernization
Roofing replacement
envelope repairs, interior and exterior finish enhancements
(walls, floors & casework), new fire alarm system
PROJECT SUMMARY
Computer replacements, network, and wireless access upgrades
Restroom and classroom accessibility upgrades, building
Quick-start projects complete.Modernization scheduled for 2019.
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
6,323,765
6,323,765
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
Measure H Fund 24
MARCH 3, 2017 37 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Architect / Engineer:
KCEM Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2013
MODERNIZATION PROJECTDESIGN SCHEDULE: January 2014 - May 2014DOCUMENT PREPARATION SCHEDULE: June 2014 - January 2015BID & CONTRACT AWARD SCHEDULE: February 2015 - April 2015CONSTRUCTION SCHEDULE: May 2015 - December 2016
Current Project Budget: $
Percent Complete: 100%
Project Cost at Completion: $
Funding Source:
Campus wide ModernizationRestroom and classroom accessibility upgrades, building
Exterior painting, lighting upgrades, site utility repairs
Data infrastructure upgrades
HMC Architects
Kent Brown, Program Manager
Quick-start projects complete.Modernization work complete.
PROJECT SUMMARY
Computer replacements, network, and wireless access upgrades
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
McAuliffe Elementary School
envelope repairs, interior and exterior finish enhancements
(walls, floors & casework), new fire alarm system
COMMENTS, ISSUES OR CONCERNS
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
Measure H Fund 24
1) Corrective modernization work is complete.2) Contractual closeouts associated with original modernization team are now complete.
5,898,914
5,898,914
NEXT 60 DAYS
MARCH 3, 2017 38 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Architect / Engineer:
Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2013
MODERNIZATION PROJECTDESIGN SCHEDULE: May 2013 - February 2014BID & CONTRACT AWARD SCHEDULE: February 2014 - March 2014CONSTRUCTION SCHEDULE: May 2014 - August 2014OFFICE EXPANSION SCHEDULE: June 2014 - July 2015
Current Project Budget: $
Percent Complete: 100%
Project Cost at Completion: $
Funding Source:
7,389,792
7,389,792
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
Measure H Fund 24
Quick-start projects complete.Modernization work is complete.
repairs, interior and exterior finish enhancements (wall, floors &
casework), new fire alarm system, office expansion
PROJECT SUMMARY
Computer replacements, network, and wireless access upgrades
Accessibility upgrades, seismic upgrades, building envelope
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Meyerholz Elementary School
Campuswide Modernization
Site utility repairs, lighting upgrades
Data infrastructure upgrades
WLC ArchitectsTo be determined.
MARCH 3, 2017 39 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Architect / Engineer:
Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2014
MODERNIZATION PROJECTDESIGN SCHEDULE: January 2015 - May 2015DOCUMENT PREPARATION SCHEDULE: June 2015 - January 2016BID & CONTRACT AWARD SCHEDULE: February 2017 - April 2017CONSTRUCTION SCHEDULE: May 2017 - August 2018
Current Project Budget: $
Percent Complete: 17%
Project Cost at Completion: $
Funding Source:
Campuswide Modernization
SIM Architects
CUSD
Quick-start projects complete.SDC, painting & track upgrades complete.Modernization work scheduled for 2017.
Track replacement
Restroom and classroom accessibility upgrades, building
PROJECT SUMMARY
SDC classroom remodel, exterior painting
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Montclaire Elementary School
Computer replacements, network, and wireless access upgrades
envelope repairs, interior and exterior finish enhancements
(walls, floors & casework), new fire alarm system
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
5,591,015
5,591,015
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
Measure H Fund 24
1) Postconstruction certification of the two existing shade structures is an ongoing effort.
2) Prebid walk was conducted on February 28, 2017. Bid opening is April 4, 2017.
MARCH 3, 2017 40 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Campus wide ModernizationRestroom and classroom accessibility upgrades, building
envelope repairs, interior and exterior finish enhancements
Architect / Engineer:
KCEM Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: Phase 1: Jan. 2013 - Aug. 2013; Phase 2: Feb. 2014 - Aug. 2014
MODERNIZATION PROJECTDESIGN SCHEDULE: January 2014 - May 2014DOCUMENT PREPARATION SCHEDULE: June 2014 - January 2015BID & CONTRACT AWARD SCHEDULE: February 2015 - April 2015CONSTRUCTION SCHEDULE: Phase I and II: May 2015 - September 2015. Phase III: June 2016 to December 2016
Current Project Budget: $
Percent Complete: 99%
Project Cost at Completion: $
Funding Source:
1) Corrective modernization work is complete.
6,451,762
6,451,762
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
2) Contractual closeouts associated with original modernization team are now complete.
Measure H Fund 24
(walls, floors & casework), new fire alarm system,
add five portable classrooms for YCC/CAP programs
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
PROJECT SUMMARY
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Muir Elementary School
Roofing
Computer replacements, network, & wireless access upgrades
IBI Architects
Kent Brown, Program ManagerQuick-start projects complete.
Installation of YCC/CAP rooms complete.Modernization work complete.
MARCH 3, 2017 41 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Architect / Engineer:
Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2013
MODERNIZATION PROJECTDESIGN SCHEDULE: January 2017 - May 2017. The project timeline is currently under review.DOCUMENT PREPARATION SCHEDULE: June 2017 - January 2018. The project timeline is currently under review.BID & CONTRACT AWARD SCHEDULE: February 2018 - April 2018. The project timeline is currently under review.CONSTRUCTION SCHEDULE: May 2018 - August 2018. The project timeline is currently under review.
Current Project Budget: $
Percent Complete: 43%
Project Cost at Completion: $
Funding Source:
Computer replacements, network, and wireless access upgrades
To be determined.
To be determined.
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Murdock-Portal Elementary School
Campuswide Modernization
Domestic water piping replacement
PROJECT SUMMARY
Exterior painting
Quick-start projects complete.Modernization scheduled for 2019.
COMMENTS, ISSUES OR CONCERNS
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
Measure H Fund 24
1,039,502
1,039,502
NEXT 60 DAYS
MARCH 3, 2017 42 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Campuswide ModernizationRestroom and classroom accessibility upgrades, building
envelope repairs, interior and exterior finish enhancements
Architect / Engineer:
Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2013
MODERNIZATION PROJECTDESIGN SCHEDULE: January 2016 - May 2016. The project timeline is currently under review.DOCUMENT PREPARATION SCHEDULE: June 2016 - January 2017. The project timeline is currently under review.BID & CONTRACT AWARD SCHEDULE: February 2017 - April 2017. The project timeline is currently under review.CONSTRUCTION SCHEDULE: May 2017 - August 2017. The project timeline is currently under review.
Current Project Budget: $
Percent Complete: 8%
Project Cost at Completion: $
Funding Source:
5,738,342
5,738,342
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
Measure H Fund 24
Quick-start projects complete.Modernization work scheduled for 2018.
(walls, floors & casework), new fire alarm system
PROJECT SUMMARY
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Nimitz Elementary School
Computer replacements, network, and wireless access upgrades
To be determined.
To be determined.
MARCH 3, 2017 43 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Architect / Engineer:
Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2013
MODERNIZATION PROJECTDESIGN SCHEDULE: May 2013 - September 2013DOCUMENT PREPARATION SCHEDULE: October 2013 - February 2014BID & CONTRACT AWARD SCHEDULE: February 2014 - March 2014CONSTRUCTION SCHEDULE: May 2014 - August 2014
Current Project Budget: $
Percent Complete: 100%
Project Cost at Completion: $
Funding Source:
DSA certification and closeout letter received.
5,804,238
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
Measure H Fund 24
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
envelope repairs, interior and exterior finish enhancements
(walls, floors & casework), new fire alarm system, new roofs
McKim Design Group
To be determined
Quick-start projects complete.Modernization work complete.
PROJECT SUMMARY
Computer replacements, network, and wireless access upgrades
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Regnart Elementary School
Site lighting upgrades, site utility repairs
Data infrastructure upgrades
5,804,238
Campus wide ModernizationRestroom and classroom accessibility upgrades, building
MARCH 3, 2017 44 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Campus wide ModernizationRestroom and classroom accessibility upgrades, building
envelope repairs, interior and exterior finish enhancements
Architect / Engineer:
Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2013
MODERNIZATION PROJECTDESIGN SCHEDULE: May 2013 - October 2013DOCUMENT PREPARATION SCHEDULE: November 2013 - February 2014BID & CONTRACT AWARD SCHEDULE: February 2014 - April 2014CONSTRUCTION SCHEDULE: June 2014 - August 2014CONSTRUCTION SCHEDULE Phase II: Fall 2016 - Winter 2017
Current Project Budget: $
Percent Complete: 95%
Project Cost at Completion: $
Funding Source:
5,803,266
5,803,266
NEXT 60 DAYS
1) Casework replacement project scheduled for fall/winter 2016-2017.
COMMENTS, ISSUES OR CONCERNS
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
Measure H Fund 24
(walls, floors & casework), new fire alarm system
PROJECT SUMMARY
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Sedgwick Elementary School
Computer replacements, network, and wireless access upgrades
McKim Design Group
Travis Kirk, Facility Modernization Director
Quick-start projects complete.Modernization work complete.
MARCH 3, 2017 45 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Architect / Engineer:
Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2013
MODERNIZATION PROJECTDESIGN SCHEDULE: February 2015 - January 2016BID & CONTRACT AWARD SCHEDULE: February 2016 - April 2016CONSTRUCTION SCHEDULE: April 2016 - spring 2017
Current Project Budget: $
Percent Complete: 94%
Project Cost at Completion: $
Funding Source:
Restroom and classroom accessibility upgrades, building
envelope repairs, interior and exterior finish enhancements
Site utility repairs & data infrastructure upgrades
Computer replacements, network, and wireless access upgrades
McKim Design Group
Mark Casini, Program ManagerQuick-start projects complete.
Modernization work substantially complete. Punch list items remain.
PROJECT SUMMARY
Campus wide Modernization
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Stevens Creek Elementary School
(walls, floors & casework), new fire alarm system, and
complete modernization of buildings D & E
COMMENTS, ISSUES OR CONCERNS
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
Measure H Fund 24
1) Major construction is complete.2) The team is addressing the final agency closeout and approval as well as the final contractual project closeout.
9,766,851
9,766,851
NEXT 60 DAYS
MARCH 3, 2017 46 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start ProjectsSite utility repairs
Architect / Engineer:
KCEM Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2013
MODERNIZATION PROJECT SHORT-TERM FACILITY NEEDS PROJECTDESIGN SCHEDULE: January 2016 - May 2016 DESIGN SCHEDULE: January 2016 - May 2016DOCUMENT PREPARATION SCHEDULE: June 2016 - April 2017 DOCUMENT PREPARATION SCHEDULE: March 2016 - June 2016BID & CONTRACT AWARD SCHEDULE: February 2017 - April 2017 BID & CONTRACT AWARD SCHEDULE: April 2016 - July 2016CONSTRUCTION SCHEDULE: May 2017 - August 2017 CONSTRUCTION SCHEDULE: May 2016 - March 2017
Current Project Budget: $
Percent Complete: 38%
Project Cost at Completion: $
Funding Source:
3) The upper grade level play structure project is complete.4) The campus library relocation project is complete.
7,708,210
7,708,210
NEXT 60 DAYS
1) The final project scope associated with the short-term facility needs effort has bid. The consolidation of the campus administration building is under construction. 2) The kinder play yard expansion project is complete.
COMMENTS, ISSUES OR CONCERNS
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
Measure H Fund 24
envelope repairs, interior and exterior finish enhancements
(walls, floors & casework), new fire alarm system
PROJECT SUMMARY
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Stocklmeir Elementary School
Campus wide ModernizationRestroom and classroom accessibility upgrades, building
Computer replacements, network, and wireless access upgrades
HMC Architects
Amy Gosal, Program Manager
Quick-start projects complete.Modernization work scheduled for 2017.
MARCH 3, 2017 47 MEASURE H BOND PROGRAM PROGRESS REPORT
Quick-Start Projects
Campuswide ModernizationAccessibility upgrades, seismic upgrades, building envelope
repairs, interior and exterior finish enhancements (wall, floors &
casework), new fire alarm system, interim housing
Architect / Engineer:
Project Manager:
Project Status:
QUICK-START PROJECTSDESIGN & IMPLEMENTATION: January 2013 - August 2013
MODERNIZATION PROJECTDESIGN SCHEDULE: May 2013 - October 2013DOCUMENT PREPARATION SCHEDULE: November 2013 - February 2014BID & CONTRACT AWARD SCHEDULE: February 2014 - March 2014CONSTRUCTION SCHEDULE: May 2014 - August 2015
Current Project Budget: $
Percent Complete: 100%
Project Cost at Completion: $
Funding Source:
PROJECT SUMMARY
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
West Valley Elementary School
Computer replacements, network, and wireless access upgrades
COMMENTS, ISSUES OR CONCERNS
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
Measure H Fund 24
SIM Architects
Quick-start projects complete.Interim housing complete.
Modernization work complete.
9,195,576
9,195,576
NEXT 60 DAYS
MARCH 3, 2017 48 MEASURE H BOND PROGRAM PROGRESS REPORT
CUPERTINO MIDDLE SCHOOL
Site Project Overview The project includes construction of a new multiuse gymnasium and performing arts building that will include locker rooms; fitness and weights rooms; teachers’ offices and support spaces; a new two-story 20-classroom building that will enclose a new quadrangle for student activities, lunch, and gathering; renovations to wings 100, 200, 300 and 500; and modernization of the rest of the campus. This program will allow for the removal of many of the existing classroom portables and an expansion of the outdoor physical education and play areas. Additionally, this project will include the construction of a new parking lot located on Bernardo Avenue. The project also includes modifications to the teaching environment to allow for transition to the Common Core curriculum standards, including allowing for rigorous wireless access points at each classroom and for modernized projection of teaching materials.
MARCH 3, 2017 49 MEASURE H BOND PROGRAM PROGRESS REPORT
Project Schedule PHASE CONSTRUCTION PERIOD Technology Upgrades Ongoing Infrastructure and Interim Housing Project is now complete.
New Multiuse Building Project is now complete. New Classroom Building Project is now complete. Building 100, 200, 300 & 500 Renovations Project is now complete.
Building 100, 200, 300 Roofing Project is now complete. Corner Parking Lot Project is now complete. Bernardo Ave. Parking Lot Project is now complete.
Site Work Improvements Project is now complete. Modernization of Buildings 600, 700, 800 & 900 June 2017 – August 2018 Site Work for Modular Installation Project is now complete.
Project Budgets
Site Infrastructure $ 1,853,215 New Classroom Building $ 6,576,364 Modern. of Buildings 100, 200, 300, Classrooms 1 & 2 $ 5,222,407 New Multipurpose Building $ 11,346,270 Modernization of Buildings 500, 600, 700, 800 & 900 $ 6,265,283 Quad $ 2,877,477 Technology Upgrades $ 371,387 Site Work for Modular Installation $ 175,000 Interim Housing U$ 1,211,658 Totals $35,899,060
MARCH 3, 2017 50 MEASURE H BOND PROGRAM PROGRESS REPORT
New Multipurpose Building
Project Overview
Project Description: The project includes construction of a new gymnasium combined with a new performance space, with bleachers, new boys’ and girls’ locker room areas, instructional spaces, staff preparations areas, and two fitness rooms.
MARCH 3, 2017 51 MEASURE H BOND PROGRAM PROGRESS REPORT
Completed Project Photos
New Multipurpose Building – North Exterior
New Multipurpose Gym
MARCH 3, 2017 52 MEASURE H BOND PROGRAM PROGRESS REPORT
New Classroom Building Project Overview
Project Description: The project includes the construction of a new two-story classroom building, which will house new general education classrooms and new science classrooms.
MARCH 3, 2017 53 MEASURE H BOND PROGRAM PROGRESS REPORT
Completed Project Photos
New Classroom Building – Interior
New Classroom Building & Quad – Exterior
MARCH 3, 2017 54 MEASURE H BOND PROGRAM PROGRESS REPORT
Site Project Overview Hyde is a wonderful place where students of diverse backgrounds grow educationally, socially, and have a meaningful middle school experience. Students will be challenged and supported in their core academics as well as have opportunities to explore a rich elective program. At Hyde we are committed to the continual development of our students’ learning and social needs. A strong partnership with our parent community is paramount in supporting our students. The work at Hyde Middle School is focused on the modernization of teaching and support services spaces to support 21st-century learning. The first phase of work, completed in 2013, included replacement of aging computer hardware as well as network and wireless access upgrades. The next phase covers the installation of temporary portable classrooms to house students while the permanent facilities are undergoing modernization. The modernization phase includes all permanent classrooms, offices, and support spaces.
Project Schedule PHASE CONSTRUCTION PERIOD Technology Upgrades Ongoing Interim Housing Project is now complete. Modernization The main project is now complete. Additional scope (cabinetry) June 2016-September 2017 Roofing Replacement Project is now complete. Replacement of Leased Portables Project is now complete.
Project Budgets
Campus Modernization $ 6,208,285 Roofing Replacement $ 450,000 Technology $ 271,896 Interim Housing $ 469,768 Replacement of Leased Portables $ 265,000 Total $ 7,664,948
MARCH 3, 2017 56 MEASURE H BOND PROGRAM PROGRESS REPORT
Campus Modernization
Completed Project Photos
Renovated Classroom
Renovated Science Classroom
MARCH 3, 2017 57 MEASURE H BOND PROGRAM PROGRESS REPORT
KENNEDY MIDDLE SCHOOL
Street View
Aerial View
MARCH 3, 2017 58 MEASURE H BOND PROGRAM PROGRESS REPORT
Site Project Overview Kennedy Middle School is a warm, supportive learning environment. Our staff is committed to meeting the needs of early adolescent children as well as teaching them to be responsible for their learning. We provide a rigorous academic program in a supportive, compassionate environment. Student independence and lifelong learning is encouraged through a committed and evolving partnership between students, parents, school, and community. Kennedy Middle School provides a safe, caring, and inclusive environment. Academic achievement is balanced with respect for self and others, self-discipline, and individual responsibility. The work at Kennedy is focused on modernizing each classroom and support space to allow for the latest in 21st-century learning environments. The first phase of work, completed in 2013, included replacement of aging computer hardware as well as network and wireless access upgrades. The next phase covers the installation of temporary portable classrooms to house students while the permanent facilities are undergoing modernization. The modernization phase includes all permanent classrooms, offices, and support spaces.
Project Schedule PHASE CONSTRUCTION PERIOD Technology Upgrades Ongoing
Modernization June 2016 – December 2017 Replacement of Aged Portables Project is now complete.
Project Budgets
Campus Modernization $ 7,182,052 Technology $ 303,774 Replacement of Aged Portables $ 365,000 Total $ 7,850,826
MARCH 3, 2017 59 MEASURE H BOND PROGRAM PROGRESS REPORT
Campus Modernization Preliminary Planning Concepts
MARCH 3, 2017 60 MEASURE H BOND PROGRAM PROGRESS REPORT
LAWSON MIDDLE SCHOOL
Street View
Site Project Overview Lawson Middle School celebrates the whole child by providing opportunities for academic, social, and emotional success. Academically, students are recognized for their work. Their projects and work are displayed in the classroom and around the campus. They have a variety of opportunities to demonstrate their unique talents. We strive to understand the motivations, aspirations, and learning styles of each student. Each student is encouraged to achieve a personal best and receives recognition for it. Students leave Lawson with a portfolio showing their growth as scholars and people. Socially, students are involved in a variety of extracurricular activities and feel welcome to participate. Lawson Middle School was constructed originally in 1947 as an elementary school, which was previously known as Collins. In 2005, the District had a need for an additional middle school so Collins was significantly modernized, renamed, and a new administration, gym/guided learning center, and science classroom wings were added to the campus. The campus currently houses approximately 1,100 students, but the current plan adds two new instructional buildings and the remodel of several existing buildings to support growth up to 1,500 students. The scope of work includes the construction of a new two-story classroom building to house general education and science classrooms. Additionally, the work includes the construction of a new music classroom building to allow for the expansion of the music program. The work includes the renovation of three rooms to support the growth on campus. Lastly, with the demolition of the existing District Office building complete, a new track and field facility was built to allow for additional outdoor physical education.
MARCH 3, 2017 61 MEASURE H BOND PROGRAM PROGRESS REPORT
Project Schedule PHASE CONSTRUCTION PERIOD Technology Upgrades Ongoing Infrastructure and Interim Housing Project is now complete. District Office Demolition Project is now complete. Music Building Project is now complete. Classroom Building Project is now complete. Track and Field Project is now complete. Modernization of Library and Rooms 3, 35 & 26 Project is now complete. Campus Modernization Project schedule is pending. Project Budgets
Soil Remediation $ 160,607 Site Infrastructure $ 558,844 New Classroom Building $10,125,809 Modernization of Library & Rooms 3, 25 & 26 $ 944,840 New Music Building $ 2,389,845 Campus Modernization $ 1,631,562 Track & Field $ 3,685,544 Technology $ 375,580 District Office Demolition $ 994,109 Interim Housing $ 993,313 Total $21,860,054
MARCH 3, 2017 62 MEASURE H BOND PROGRAM PROGRESS REPORT
Music Building
Completed Project Photo
New Music Building Exterior
New Classroom Building
Completed Project Photo
New Classroom Building Exterior
MARCH 3, 2017 63 MEASURE H BOND PROGRAM PROGRESS REPORT
MILLER MIDDLE SCHOOL
Street View
Aerial View
MARCH 3, 2017 64 MEASURE H BOND PROGRAM PROGRESS REPORT
Site Project Overview ___________________________ Our mission is to educate the whole child. We believe that all children can excel at academics, and that activities and citizenship are just as important. Our students know that we have high expectations for them, and they strive to meet them. We welcome involvement from parents and the community. The work at Miller is focused on modernizing each classroom and support space to allow for the latest in 21st-century learning environments. The first phase of work, completed in 2013, included replacement of aging computer hardware as well as network and wireless access upgrades. The next phase covers the installation of temporary portable classrooms to house students while the permanent facilities are undergoing modernization. The modernization phase includes all permanent classrooms, offices, and support spaces. This project phase is now complete while there is limited roofing repair scope to be completed during the summer of 2017. Project Schedule ___________________________ PHASE CONSTRUCTION PERIOD
Modernization Project is now complete.
Site Work for Modular Installation Project is now complete. Roofing Repairs February 2017 – August 2017 Technology Upgrades Ongoing
Interim Housing Project is now complete.
Replacement of Leased Portables Project is now complete. Project Budget ___________________________ Campus Modernization $6,427,766
Site Work for Modular Installation $ 175,000 Roofing Repairs $ 500,000 Technology $ 265,398 Interim Housing $ 500,343 Replacement of Leased Portables $ 180,000 Total $8,048,506
MARCH 3, 2017 65 MEASURE H BOND PROGRAM PROGRESS REPORT
Campus Modernization
Completed Project Photos
Renovated Classroom
Library Renovation
MARCH 3, 2017 66 MEASURE H BOND PROGRAM PROGRESS REPORT
Relocate District administrative functions to leased facility
so Lawson Middle School can be expanded to accommodate
Architect / Engineer:
Project Manager:
Project Status:
DESIGN: October 2012 - January 2013CONSTRUCTION: January 2013 - April 2013MOVE: April 2013
Current Project Budget: $
Percent Complete:
Proj. Cost at Completion $
Funding Source:
3,433,872
3,433,872
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
Measure H Fund 24
Move - 100%, Lease - 43%
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
District Office Relocation
PROJECT SUMMARY
enrollment growth
Not applicable.
Not applicable.
Completed.
Not StartedIn ProgressCompleted
Legend
MARCH 3, 2017 67 MEASURE H BOND PROGRAM PROGRESS REPORT
DISTRICT OFFICE/CORPORATION YARD
Site Project Overview The project includes the demolition of the existing District Office to make room for additional educational outdoor classroom space for Lawson Middle School. As part of this project, a new storage building was constructed to consolidate storage and to house all necessary materials for the District corporation yard support.
Project Schedule PHASE CONSTRUCTION PERIOD District Office Demolition July 2013 - November 2013 Storage Building July 2013 - October 2013 BCR & Staff Room Replacement June 2015 - August 2015
Project Budget Total Project Budget: $1,194,326 Estimated Cost at Completion: $1,194,326
Progress Photos
Demolition of Old District Offices
MARCH 3, 2017 68 MEASURE H BOND PROGRAM PROGRESS REPORT
New Corporation Yard Storage Building
Steel Framing for New Corporation Yard Storage Building
MARCH 3, 2017 69 MEASURE H BOND PROGRAM PROGRESS REPORT
Monitor status of high-value electronic devices.
Architect / Engineer:
Project Manager:
Project Status:
AS NEEDED
Current Project Budget: $
Percent Complete: 100%
Proj. Cost at Completion $
Funding Source:
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Districtwide Security
PROJECT SUMMARY
Measure H Fund 24
Monies are transferred to individual projects as needed.
Not applicable.
Not applicable.
Completed.
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
35,293
35,293
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
Not StartedIn ProgressCompleted
Legend
MARCH 3, 2017 70 MEASURE H BOND PROGRAM PROGRESS REPORT
Districtwide technology upgrades:
Network
Architect / Engineer:
Project Manager:
Project Status:
AS NEEDED
Current Project Budget: $
Percent Complete: 83%
Proj. Cost at Completion $
Funding Source:
4,419,214
4,419,214
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
Monies are transferred to individual projects as needed.
Expenditures to date are $3,669,740.Remaining funds are $749,474.
Measure H Fund 24
Not applicable.
Not applicable.
Ongoing.
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Technology
Computers
PROJECT SUMMARY
Phones
Wireless access points
Data infrastructure upgrades
Not StartedIn ProgressCompleted
Legend
MARCH 3, 2017 71 MEASURE H BOND PROGRAM PROGRESS REPORT
Buy out leases for existing classrooms.
Architect / Engineer:
Project Manager:
Project Status:
AS NEEDED
Replacement of leased classrooms at Hyde and Miller Middle Schools: June-August 2015
Current Project Budget: $
Percent Complete: 100%
Proj. Cost at Completion $
Funding Source:
41,871
41,871
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
Measure H Fund 24
Not applicable.
Not applicable.
Completed.
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
$675,000 transferred to Hyde and Miller Middle Schools' budgets on 5/20/15 for replacement of leased portables at those sites.
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Purchase of Leased Classrooms
PROJECT SUMMARY
Not StartedIn ProgressCompleted
Legend
MARCH 3, 2017 72 MEASURE H BOND PROGRAM PROGRESS REPORT
Replace aging HVAC, lighting and control system with high-
efficiency equipment. Install photovoltaic systems.
Architect / Engineer:
Project Manager:
Project Status:
TO BE DETERMINED
Current Project Budget: $
Percent Complete: 0%
Proj. Cost at Completion $
Funding Source:
To be determined.
To be determined.
Pending.
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Energy Efficiency/Solar Projects
PROJECT SUMMARY
COMMENTS, ISSUES OR CONCERNS
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
Measure H Fund 24
2,210,000
2,210,000
NEXT 60 DAYS1) Coordinate Measure H program with Prop 39 Clean Energy Act program.
Not StartedIn ProgressCompleted
Legend
MARCH 3, 2017 73 MEASURE H BOND PROGRAM PROGRESS REPORT
Provide temporary classroom facilities for students and staff
displaced by construction activities.
Architect / Engineer:
Project Manager:
Project Status:
AS NEEDED
Current Project Budget: $
Percent Complete: n/a
Proj. Cost at Completion $
Funding Source:
-
-
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
Measure H Fund 24
All funds have been transferred to individual projects.
Not applicable.
Not applicable.
Completed.
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Interim Housing
PROJECT SUMMARY
Not StartedIn ProgressCompleted
Legend
MARCH 3, 2017 74 MEASURE H BOND PROGRAM PROGRESS REPORT
Upgrade existing central kitchen at Stocklmeir Elementary
School.
Architect / Engineer:
Project Manager:
Project Status:
TO BE DETERMINED
Current Project Budget: $
Percent Complete: 0%
Proj. Cost at Completion $
Funding Source:
-
-
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
Measure H Fund 24
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Central Kitchen Upgrades
PROJECT SUMMARY
To be determined.
To be determined.
Canceled.
Not StartedIn ProgressCompleted
Legend
MARCH 3, 2017 75 MEASURE H BOND PROGRAM PROGRESS REPORT
Purchase new furniture, fixtures and equipment for new
classrooms, labs and offices.
Architect / Engineer:
Project Manager:
Project Status:
AS NEEDED
Current Project Budget: $
Percent Complete: 100%
Proj. Cost at Completion $
Funding Source:
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Furniture, Fixtures & Equipment
PROJECT SUMMARY
Measure H Fund 24
Not applicable.
Not applicable.
Completed.
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
1,000,000
1,000,000
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
Not StartedIn ProgressCompleted
Legend
MARCH 3, 2017 76 MEASURE H BOND PROGRAM PROGRESS REPORT
Upgrade and repair outdoor elements.
Architect / Engineer:
Project Manager:
Project Status:
AS NEEDED
Current Project Budget: $
Percent Complete: 15%
Proj. Cost at Completion $
Funding Source:
Money will be transferred to sites that have had playgrounds installed
1,750,000
1,750,000
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
with the modernization money.
Measure H Fund 24
Monies are transferred to individual projects as needed.
Not applicable.
Not applicable.
Ongoing.
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Playgrounds/Landscaping/Fields
PROJECT SUMMARY
Not StartedIn ProgressCompleted
Legend
MARCH 3, 2017 77 MEASURE H BOND PROGRAM PROGRESS REPORT
Remove hazardous materials such as lead paint and asbestos
as required to complete construction work.
Architect / Engineer:
Project Manager:
Project Status:
AS NEEDED
Current Project Budget: $
Percent Complete: n/a
Proj. Cost at Completion $
Funding Source:
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Hazardous Material Removal
PROJECT SUMMARY
Measure H Fund 24
Monies are transferred to individual projects as needed.
Not applicable.
Not applicable.
Ongoing.
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
1,000,021
1,000,021
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
Not StartedIn ProgressCompleted
Legend
MARCH 3, 2017 78 MEASURE H BOND PROGRAM PROGRESS REPORT
Covers moving and storage costs associated with construction.
Architect / Engineer:
Project Manager:
Project Status:
AS NEEDED
Current Project Budget: $
Percent Complete: n/a
Proj. Cost at Completion $
Funding Source:
CUPERTINO UNION SCHOOL DISTRICTMeasure H Bond Program
Moving & Storage
PROJECT SUMMARY
Measure H Fund 24
Monies are transferred to individual projects as needed.
Not applicable.
Not applicable.
Ongoing.
OVERALL PROJECT SCHEDULE
PROJECT BUDGET
1,600,000
1,600,000
NEXT 60 DAYSCOMMENTS, ISSUES OR CONCERNS
Not StartedIn ProgressCompleted
Legend
MARCH 3, 2017 79 MEASURE H BOND PROGRAM PROGRESS REPORT