current detector configuration june 6, 2000

25
DoE Review June 6-7, 2000 D D Current Detector Configuration June 6, 2000 Solenoid, Central Preshower installed in central bore A-layer MDTs installed on inner faces of end irons Central muon system installed, being commissioned South end calorimeter, end irons on sidewalk North and south trusses in Hi Bay, being prepped for move to sidewalk Central iron, north calorimeter in open positions to allow access Shield wall up

Upload: damien

Post on 16-Jan-2016

20 views

Category:

Documents


0 download

DESCRIPTION

Current Detector Configuration June 6, 2000. Solenoid, Central Preshower installed in central bore A-layer MDTs installed on inner faces of end irons Central muon system installed, being commissioned South end calorimeter, end irons on sidewalk - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD Current Detector Configuration

June 6, 2000

Solenoid, Central Preshower installed in central bore A-layer MDTs installed on inner faces of end irons Central muon system installed, being commissioned South end calorimeter, end irons on sidewalk North and south trusses in Hi Bay, being prepped for

move to sidewalk Central iron, north calorimeter in open positions to allow

access Shield wall up

Page 2: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD Current Detector Configuration

June 6, 2000

South end calorimeter, end irons on sidewalk A-layer MDTs installed on faces of end irons Commissioning Level 1 trigger, muon system,

online, silicon front-end, solenoid

Page 3: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD Install Fiber Tracker in Solenoid

June 16-29, 2000

Fiber Tracker being installed in central bore North A-layer pixel sheet mounted on shield wall Commissioning of DAQ, online, central muon

system, etc. continues

Page 4: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD Move Platform West, Pick Up End Irons

July 11-28, 2000

Fiber Tracker installed, south end calorimeter back in place on platform

Platform moves west to pick up two end irons Detector buttoned up for move Commissioning interrupted until platform

returns east (services disconnected)

Page 5: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD Move Platform West, Pick Up End Irons

July 11-28, 2000 Platform moves west to pick up two end irons Movable Counting House moves with detector during pick up Assembled north A-layer pixel plane remains on shield wall

Page 6: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD North & South Trusses Move to Sidewalk

July 31 – August 25, 2000

Platform returns to east position with end irons installed North & south trusses, shielding brought down to sidewalks

from Hi Bay, assembled Detector remains buttoned up until trusses are down Cabling of Fiber Tracker begins after south truss is in place Platform services reconnected, commissioning resumes

Page 7: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD North & South Trusses Move to Sidewalk

July 31 – August 25, 2000 Platform returns to east position with end irons installed North & south trusses brought down to sidewalks South calorimeter, end iron opens to allow cabling of Fiber Tracker A-layer north pixel sheet mounted on shield wall, awaits installation

Page 8: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD A- & C-layer Pixels & MDTs Installed

November 10, 2000 A- and C-layer detectors mounted SMT-S installed, hooked up – SMT-N being installed Trusses ready to install in Collision Hall South calorimeter, end irons open to allow access to inter-cryostat region Commissioning of CFT, SMT, Forward and Central Muon, attendant readout

Page 9: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD Trusses Installed in Collision HallNov 20 – Dec 11, 2000

North & south ends of shield wall removed, blocks stacked in Hi Bay

Loaded trusses rolled into Collision Hall, surveyed Platform remains in Assembly Hall, rolled in after

trusses in place Commissioning of detectors on platform continues

Page 10: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD Trusses Installed in Collision HallNov 20 – Dec 11, 2000

Mounting of B-layer MDTs on outer faces of end irons near completion

North B-layer pixel plane assembled on shield wall End cryostats/irons open as logistics allow Cosmic ray commissioning & triggering using SMT, CFT, and

muon

Page 11: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD Detector Rolled in and Hooked Up

February 16, 2001

Platform rolled in to meet trusses Full detector in final closed position: hooked up, ready for beam Shield wall back up Movable Counting House travels with detector, cable bridge down Commissioning with cosmic rays continues until beam is delivered

(March 1, 2001)

Page 12: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD Access to Detector in Collision Hall

Closed Position - Data-Taking Open Position - Detector Access

Shielding retracted

South calorimeter

open

North B-layer pixels open

South end iron

open

North end iron closed

Page 13: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD Forward Muon B-Layer Installation

May, 2000

End irons moved toward center of Assembly Pit to allow access for B-layer installation/surveying

Commissioning continues

Page 14: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD D0 Commissioning Timeline Commissioning/Integration

Goals 2000 2001 J F M A M J J A S O N D J F M

D

Run II begins:

Mar 1, 2001

Roll in

No LHe

LAr

Beam-ready

#1

#3

#2

DAQ/online system running in user

mode

Integration Goal #1:

dual muon crates, initial muon

triggering/filtering, ship data to farm, run reconstruction, online

event display

Begin full central muon system, integrate Level 2 muon trigger at DAB test

stand

Silicon front-end installed/commissio

ned

Forward muon C-layer MDTs/pixels

installed/commissioned

#6

#5

Forward muon A&B layer MDTs/pixels

installed/commissioned

Integration Goal #2:

Initial triggering on L1 CFT/CPS, begin linking

tracks in CFT/CPS/CMuon, begin Level 2 trigger

integration

Half of CFT, CPS hooked up, checked

out

#4

#9

#10

#11 Integration Goal #4:

Full detector in steady-state Cosmic Ray Commissioning

SMT, CAL fully added to commissioning

chain, exercise full triggering with all

major systems

Integration Goal #3:

Add Central Calorimeter to commissioning

stream, most major systems being commissioned

#8

#7

Page 15: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DDTrusses Assembled on North & South

Sidewalks July 21 – August 25, 2000

Detector returns to east position with end irons installed Trusses brought down from Hi Bay to sidewalks Central irons, calorimeters remain closed for movement of trusses Hookup of Fiber Tracker begins after south truss is in position Commissioning resumes, begin integration of CFT

Page 16: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD Current Detector ConfigurationPhase I

A-layer MDTs, Pixels being mounted, surveyed onto faces of end irons C-layer truss and shielding has arrived in Hi-Bay, being dressed Remainder of detector remains open for access

Page 17: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD Current Detector Configuration

Commissioning continues, using Central Muon as prototype system: Multi-crate readout of full central muon system Event monitoring, crate control, steady DAQ running, filtering Exercise reconstruction, online event display (on cosmic ray muons)

Page 18: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD Forward Muon B-Layer InstallationMay-June, 2000

A-layer planes installed B-layer MDTs, Pixels being mounted, surveyed onto faces of end

irons C-layer trusses and shielding continue to be dressed in Hi-Bay

Page 19: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD Install Fiber Tracker in Solenoid

May, 2000 Fiber Tracker + Cart/I-Beam system lowered into gap

between South End Calorimeter and Central Calorimeter Rolled into solenoid bore along I-Beam

Fiber TrackerCart System

Page 20: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD EMCs Installed in Collision Hall December 11, 2000 - January 11, 2001

Shield wall is broken down, moved to now free space in Hi-Bay North and South C-layer trusses/shields, having been assembled on

sidewalk, rolled into Collision Hall - surveyed into place Detector will be rolled into place to meet trusses

Page 21: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD EMCs Installed in Collision Hall

Full Cosmic Ray Commissioning of all systems continues during most of this period

End irons, calorimeters can be opened for access

Page 22: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD Detector Rolled In, Hooked UpPhase III

Detector installed in compact space Access to internal tracking detectors, end muon

detector planes must be carefully coordinated

Page 23: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD South EMC Truss Moves to South Sidewalk

November 29- December 5, 1999

South C-layer truss moves to south sidewalk EMCs, shielding re-assembled on sidewalk to

prepare for rolling in

Page 24: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD South EMC Truss Moves to South Sidewalk

November 29- December 5, 1999

South C-layer truss moves to south sidewalk in two pieces, reassembled

Preparing to take down shield wall for roll in

Page 25: Current Detector Configuration June 6, 2000

DoE ReviewJune 6-7, 2000

DD The DØ Upgrade Tracking System

Charged Particle Momentum ResolutionpT/pT ~ 5% @ pT = 10 GeV/c