current detector configuration june 6, 2000
DESCRIPTION
Current Detector Configuration June 6, 2000. Solenoid, Central Preshower installed in central bore A-layer MDTs installed on inner faces of end irons Central muon system installed, being commissioned South end calorimeter, end irons on sidewalk - PowerPoint PPT PresentationTRANSCRIPT
DoE ReviewJune 6-7, 2000
DD Current Detector Configuration
June 6, 2000
Solenoid, Central Preshower installed in central bore A-layer MDTs installed on inner faces of end irons Central muon system installed, being commissioned South end calorimeter, end irons on sidewalk North and south trusses in Hi Bay, being prepped for
move to sidewalk Central iron, north calorimeter in open positions to allow
access Shield wall up
DoE ReviewJune 6-7, 2000
DD Current Detector Configuration
June 6, 2000
South end calorimeter, end irons on sidewalk A-layer MDTs installed on faces of end irons Commissioning Level 1 trigger, muon system,
online, silicon front-end, solenoid
DoE ReviewJune 6-7, 2000
DD Install Fiber Tracker in Solenoid
June 16-29, 2000
Fiber Tracker being installed in central bore North A-layer pixel sheet mounted on shield wall Commissioning of DAQ, online, central muon
system, etc. continues
DoE ReviewJune 6-7, 2000
DD Move Platform West, Pick Up End Irons
July 11-28, 2000
Fiber Tracker installed, south end calorimeter back in place on platform
Platform moves west to pick up two end irons Detector buttoned up for move Commissioning interrupted until platform
returns east (services disconnected)
DoE ReviewJune 6-7, 2000
DD Move Platform West, Pick Up End Irons
July 11-28, 2000 Platform moves west to pick up two end irons Movable Counting House moves with detector during pick up Assembled north A-layer pixel plane remains on shield wall
DoE ReviewJune 6-7, 2000
DD North & South Trusses Move to Sidewalk
July 31 – August 25, 2000
Platform returns to east position with end irons installed North & south trusses, shielding brought down to sidewalks
from Hi Bay, assembled Detector remains buttoned up until trusses are down Cabling of Fiber Tracker begins after south truss is in place Platform services reconnected, commissioning resumes
DoE ReviewJune 6-7, 2000
DD North & South Trusses Move to Sidewalk
July 31 – August 25, 2000 Platform returns to east position with end irons installed North & south trusses brought down to sidewalks South calorimeter, end iron opens to allow cabling of Fiber Tracker A-layer north pixel sheet mounted on shield wall, awaits installation
DoE ReviewJune 6-7, 2000
DD A- & C-layer Pixels & MDTs Installed
November 10, 2000 A- and C-layer detectors mounted SMT-S installed, hooked up – SMT-N being installed Trusses ready to install in Collision Hall South calorimeter, end irons open to allow access to inter-cryostat region Commissioning of CFT, SMT, Forward and Central Muon, attendant readout
DoE ReviewJune 6-7, 2000
DD Trusses Installed in Collision HallNov 20 – Dec 11, 2000
North & south ends of shield wall removed, blocks stacked in Hi Bay
Loaded trusses rolled into Collision Hall, surveyed Platform remains in Assembly Hall, rolled in after
trusses in place Commissioning of detectors on platform continues
DoE ReviewJune 6-7, 2000
DD Trusses Installed in Collision HallNov 20 – Dec 11, 2000
Mounting of B-layer MDTs on outer faces of end irons near completion
North B-layer pixel plane assembled on shield wall End cryostats/irons open as logistics allow Cosmic ray commissioning & triggering using SMT, CFT, and
muon
DoE ReviewJune 6-7, 2000
DD Detector Rolled in and Hooked Up
February 16, 2001
Platform rolled in to meet trusses Full detector in final closed position: hooked up, ready for beam Shield wall back up Movable Counting House travels with detector, cable bridge down Commissioning with cosmic rays continues until beam is delivered
(March 1, 2001)
DoE ReviewJune 6-7, 2000
DD Access to Detector in Collision Hall
Closed Position - Data-Taking Open Position - Detector Access
Shielding retracted
South calorimeter
open
North B-layer pixels open
South end iron
open
North end iron closed
DoE ReviewJune 6-7, 2000
DD Forward Muon B-Layer Installation
May, 2000
End irons moved toward center of Assembly Pit to allow access for B-layer installation/surveying
Commissioning continues
DoE ReviewJune 6-7, 2000
DD D0 Commissioning Timeline Commissioning/Integration
Goals 2000 2001 J F M A M J J A S O N D J F M
D
Run II begins:
Mar 1, 2001
Roll in
No LHe
LAr
Beam-ready
#1
#3
#2
DAQ/online system running in user
mode
Integration Goal #1:
dual muon crates, initial muon
triggering/filtering, ship data to farm, run reconstruction, online
event display
Begin full central muon system, integrate Level 2 muon trigger at DAB test
stand
Silicon front-end installed/commissio
ned
Forward muon C-layer MDTs/pixels
installed/commissioned
#6
#5
Forward muon A&B layer MDTs/pixels
installed/commissioned
Integration Goal #2:
Initial triggering on L1 CFT/CPS, begin linking
tracks in CFT/CPS/CMuon, begin Level 2 trigger
integration
Half of CFT, CPS hooked up, checked
out
#4
#9
#10
#11 Integration Goal #4:
Full detector in steady-state Cosmic Ray Commissioning
SMT, CAL fully added to commissioning
chain, exercise full triggering with all
major systems
Integration Goal #3:
Add Central Calorimeter to commissioning
stream, most major systems being commissioned
#8
#7
DoE ReviewJune 6-7, 2000
DDTrusses Assembled on North & South
Sidewalks July 21 – August 25, 2000
Detector returns to east position with end irons installed Trusses brought down from Hi Bay to sidewalks Central irons, calorimeters remain closed for movement of trusses Hookup of Fiber Tracker begins after south truss is in position Commissioning resumes, begin integration of CFT
DoE ReviewJune 6-7, 2000
DD Current Detector ConfigurationPhase I
A-layer MDTs, Pixels being mounted, surveyed onto faces of end irons C-layer truss and shielding has arrived in Hi-Bay, being dressed Remainder of detector remains open for access
DoE ReviewJune 6-7, 2000
DD Current Detector Configuration
Commissioning continues, using Central Muon as prototype system: Multi-crate readout of full central muon system Event monitoring, crate control, steady DAQ running, filtering Exercise reconstruction, online event display (on cosmic ray muons)
DoE ReviewJune 6-7, 2000
DD Forward Muon B-Layer InstallationMay-June, 2000
A-layer planes installed B-layer MDTs, Pixels being mounted, surveyed onto faces of end
irons C-layer trusses and shielding continue to be dressed in Hi-Bay
DoE ReviewJune 6-7, 2000
DD Install Fiber Tracker in Solenoid
May, 2000 Fiber Tracker + Cart/I-Beam system lowered into gap
between South End Calorimeter and Central Calorimeter Rolled into solenoid bore along I-Beam
Fiber TrackerCart System
DoE ReviewJune 6-7, 2000
DD EMCs Installed in Collision Hall December 11, 2000 - January 11, 2001
Shield wall is broken down, moved to now free space in Hi-Bay North and South C-layer trusses/shields, having been assembled on
sidewalk, rolled into Collision Hall - surveyed into place Detector will be rolled into place to meet trusses
DoE ReviewJune 6-7, 2000
DD EMCs Installed in Collision Hall
Full Cosmic Ray Commissioning of all systems continues during most of this period
End irons, calorimeters can be opened for access
DoE ReviewJune 6-7, 2000
DD Detector Rolled In, Hooked UpPhase III
Detector installed in compact space Access to internal tracking detectors, end muon
detector planes must be carefully coordinated
DoE ReviewJune 6-7, 2000
DD South EMC Truss Moves to South Sidewalk
November 29- December 5, 1999
South C-layer truss moves to south sidewalk EMCs, shielding re-assembled on sidewalk to
prepare for rolling in
DoE ReviewJune 6-7, 2000
DD South EMC Truss Moves to South Sidewalk
November 29- December 5, 1999
South C-layer truss moves to south sidewalk in two pieces, reassembled
Preparing to take down shield wall for roll in
DoE ReviewJune 6-7, 2000
DD The DØ Upgrade Tracking System
Charged Particle Momentum ResolutionpT/pT ~ 5% @ pT = 10 GeV/c