Title: Module Name User Manual FI10.06 Customer Project Settlement Controlling Module Controlling – Project Settlement External Project settlement Overview: Business Process Procedure Overview With respect to BSNL, cost within a project is getting captured at network activity level i.e. cost is getting debited in the financial books against a project in controlling document. Each Network activity is attached to higher node of WBS. Customer projects are of the nature which has periodic revenue recognition along with cost. Following steps are followed for these type of projects: Applying overhead cost if applicable Calculation of Result Analysis i.e. Work in Process Settlement once the project is over and is ready for delivery to customer. Input - Required Fields Field Value / Comments WBS Period Output – Results Comments Settlement Document Tips and Tricks Last changed on: Last changed by: Version: 1.0 Page: 11-Jun-10 Ravi Shankar Gupta Release: ECC 6.0 1 of 13

Upload: abdelhamid-harakat

Post on 15-Jul-2016

212 views

Category:

Documents


0 download

DESCRIPTION

Customer Project Settlement 10

TRANSCRIPT

Page 1: Customer Project Settlement 10

Title:Module Name

User Manual FI10.06

Customer Project Settlement Controlling Module

Controlling – Project Settlement

External Project settlement

Overview:

Business Process Procedure OverviewWith respect to BSNL, cost within a project is getting captured at network activity level i.e. cost is getting debited in the financial books against a project in controlling document.

Each Network activity is attached to higher node of WBS. Customer projects are of the nature which has periodic revenue recognition along with cost. Following steps are followed for these type of projects:

Applying overhead cost if applicable Calculation of Result Analysis i.e. Work in Process Settlement once the project is over and is ready for delivery to customer.

Input - Required Fields Field Value / CommentsWBSPeriod

Output – Results CommentsSettlement Document

Tips and Tricks

Last changed on: Last changed by: Version: 1.0 Page:11-Jun-10 Ravi Shankar Gupta Release: ECC 6.0 1 of 10

Page 2: Customer Project Settlement 10

Title:Module Name

User Manual FI10.06

Customer Project Settlement Controlling Module

Procedural Steps

FI10.06.01 Access to apply Overhead of WBS by:

Via Menus Accounting Project System Financials Period – End Closing Single Functions Applied Overhead Individual Processing, Actual

Via Transaction Code CJ44

From the main menu SAP Easy Access screen as shown below

Last changed on: Last changed by: Version: 1.0 Page:11-Jun-10 Ravi Shankar Gupta Release: ECC 6.0 2 of 10

Page 3: Customer Project Settlement 10

Title:Module Name

User Manual FI10.06

Customer Project Settlement Controlling Module

On screen “Actual Overhead Calculation: Project/WBS Element/Network”, enter information in the fields as specified in the table below:

Field Name Description R/O/C User Action and Values CommentsProject/WBS/Network

Enter the Project/WBS or Network R Enter the top node WBS or Project with tick on Hierarchy

With Hierarchy Hierarchy to be included OWith Orders Orders to be included OPeriod Overhead Calculation Period RFiscal Fiscal Year RTest Run For 1st run only ODetails List Detail information O

EXECUTE

Last changed on: Last changed by: Version: 1.0 Page:11-Jun-10 Ravi Shankar Gupta Release: ECC 6.0 3 of 10

Page 4: Customer Project Settlement 10

Title:Module Name

User Manual FI10.06

Customer Project Settlement Controlling Module

Last changed on: Last changed by: Version: 1.0 Page:11-Jun-10 Ravi Shankar Gupta Release: ECC 6.0 4 of 10

Page 5: Customer Project Settlement 10

Title:Module Name

User Manual FI10.06

Customer Project Settlement Controlling Module

Procedural Steps

FI10.06.02 - Access to Calculate Result Analysis of WBS by:

Via Menus Accounting Project System Financials Period – End Closing Single FunctionsResult Analysis ProceedIndividual Processing

Via Transaction Code KKA2

From the main menu SAP Easy Access screen as shown below

On screen “Result Analysis of Project”, enter information in the fields as specified in the table below:

Last changed on: Last changed by: Version: 1.0 Page:11-Jun-10 Ravi Shankar Gupta Release: ECC 6.0 5 of 10

Page 6: Customer Project Settlement 10

Title:Module Name

User Manual FI10.06

Customer Project Settlement Controlling Module

Field Name Description R/O/C User Action and Values CommentsWBS Element Enter the WBS Element R Enter the top node WBS Period RA Calculation Period RFiscal Fiscal Year RRA Version Result Analysis Version R Always enter ‘0’Full Log Full information O

EXECUTE

Last changed on: Last changed by: Version: 1.0 Page:11-Jun-10 Ravi Shankar Gupta Release: ECC 6.0 6 of 10

Page 7: Customer Project Settlement 10

Title:Module Name

User Manual FI10.06

Customer Project Settlement Controlling Module

Last changed on: Last changed by: Version: 1.0 Page:11-Jun-10 Ravi Shankar Gupta Release: ECC 6.0 7 of 10

Page 8: Customer Project Settlement 10

Title:Module Name

User Manual FI10.06

Customer Project Settlement Controlling Module

Procedural Steps

FI10.06.03 - Access to Settlement of WBS by:

Via Menus Accounting Project System Financials Period – End Closing Single FunctionsSettlement Individual Processing

Via Transaction Code CJ88

From the main menu SAP Easy Access screen as shown below

On screen “Actual Settlement: Projects/WBS Element/Network”, enter information in the fields as specified in the table below:

Last changed on: Last changed by: Version: 1.0 Page:11-Jun-10 Ravi Shankar Gupta Release: ECC 6.0 8 of 10

Page 9: Customer Project Settlement 10

Title:Module Name

User Manual FI10.06

Customer Project Settlement Controlling Module

Field Name Description R/O/C User Action and Values CommentsWBS Element WBS Element Code RWith Hierarchy Settlement will consider the

HierarchyO Always tick it

With Orders Settlement will consider the Hierarchy

O Always tick it

Settlement Period Period on which settlement is done RFiscal Year Year of settlement RProcessing Type R Always AutomaticPosting Period Posting period for financial

documentR

Test Run Tick for the first time ODetail List Detail information O Always tick it

Execute

Last changed on: Last changed by: Version: 1.0 Page:11-Jun-10 Ravi Shankar Gupta Release: ECC 6.0 9 of 10

Page 10: Customer Project Settlement 10

Title:Module Name

User Manual FI10.06

Customer Project Settlement Controlling Module

Tips & Tricks

Project gets settled booking the unrealized gain and loss. Document for both COPA settlement and financial transaction gets posted at the time of settlement.

------------------------------------------------------------End of Document----------------------------------------------------------------