cve 4070 construction engineering project organization test #1 review prof. ralph v. locurcio, pe

23
CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Upload: kelley-peters

Post on 18-Jan-2018

242 views

Category:

Documents


1 download

DESCRIPTION

Constructon Organizations…

TRANSCRIPT

Page 1: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

CVE 4070Construction Engineering

Project OrganizationTest #1 review

Prof. Ralph V. Locurcio, PE

Page 2: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Design Process

Construction Process

Project Delivery Process…Need for a project

Is recognizedOwner appointsProject Manager

Project Manager develops project

program: scope & cost parameters

Project is entered into an annual

capital program

Designer prepares concept design & preliminary cost

estimate

Designer completes plans &

specifications

Owner orders bid documents

Project Manager advertises for

construction bids

Contractors assemble team,

prepare & submit bid

Bids reviewed by owner

(with designer)

Builder’s credentials &

bonding approved

Owner approves program

Project Manager advertises for

designer

Owner hires designer

Owner authorizes final

design

Owner selectsbuilder

Notice to Proceed

Constructionbegins

Resident Engineeroversees

construction

Project phase(s)completed

All work completed final inspection

made

ProgresspaymentFinal paymentOwner accepts

facility

Page 3: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Constructon Organizations…Owner

Quality Control

Superintendent Project Engineer

Project Engineer

Project Manager

Subcontractor

Subcontractor

Subcontractor

Subcontractor

Subcontractor

Design Manager

ProjectArchitect

StructuralEngineer

CivilEngineer

MechEngineer

ElectricalEngineer

A

B

C

Quality Assure

OfficeEngineer

TechnicalInspectors

A/E Const Staff

Resident Engineer

UsingAgency

Contractor or

Construction Manager

Page 4: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Project Organization-designOwner

ProjectArchitect

StructuralEngineer

CivilEngineer

MechanicalEngineer

Design Manager

Corporate Management

Project Manager

ConstructionContract

UsingAgency

ElectricalEngineer

Design Staff Design Staff Design Staff Design Staff Design Staff

Consultant A Consultant B Consultant C

Page 5: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Project Organization-const mgt…Owner

Quality Assurance

OfficeEngineer

TechnicalInspectors

A/E Const Staff

ResidentEngineer

Corporate Management

Corporate staff

Field site

FoundationElectrical

Mechanical

Shop DrawingsRFI controlMaterialsSamples

SchedulesPayments

RFI responsesClarification of drawings

Monitor compliance

Monitor QC processPrepare QA reports

Monitor corrective actionsDocument QA/QC

Project Manager

ConstructionContract

Responsibility

Page 6: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Project Organization-const opnsOwner

Quality Control

Superintendent Project Engineer

Project Engineer

Corporate Management

Corporate staff

Field site

Interpret Drawings & SpecsShop Drawings

RFI controlMaterialsSamples

Construction operationsCoordination of trades

SchedulesPayments

Safety-OSHAChanges

RFI responsesClarification of drawings

Monitor compliance

Monitor QC processPrepare QC reportsMake inspections

Take corrective actionDocument QC checks

Project Manager

ConstructionContract

Subcontractor A Subcontractor B Subcontractor C Subcontractor D Subcontractor E

Sub-contracts

Contractor orConstruction

Manager

Page 7: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Project Organization…Owner

Quality Control

Superintendent Project Engineer

Project Engineer

Project Manager

Subcontractor

Subcontractor

Subcontractor

Subcontractor

Subcontractor

Design Manager

ProjectArchitect

StructuralEngineer

CivilEngineer

MechEngineer

ElectricalEngineer

A

B

C

Quality Assure

OfficeEngineer

TechnicalInspectors

A/E Const Staff

Resident Engineer

UsingAgency

Contractor or

Construction Manager

Page 8: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Concepts to Remember… Government vs. private contracting

Different selection process Documentation is key

All contracts differ; read your contract Design-build is faster but more difficult & risky Only Resident Engineer issues directives Only Project Manager can make changes Professional CM firm must be independent One-to-One concept; single point of contact

Page 9: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Preconstruction Activities… The 5-Step Process revisited…

Owner selects builder

PM advertises for builder

Bids opened, reviewed

(w/designer)

Builder’s credentials

checked

Awardmade

Notice To

ProceedConstruction

Begins

Const contract signed

Builders assemble

teams & prep bids

4

1 2

3

5

Page 10: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

WBS & Flow Chart Three parts to this assignment

1. Arrange all tasks in order2. Prepare flow chart with all tasks3. Prepare WBS with all tasks & durations

Page 11: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Part 2 – Flow Chart

5% 15% 50% 95%

Page 12: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Part 2 – Flow Chart

5% 15% 50% 95%

Page 13: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Part 1 – Order Task List

Page 14: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Part 1 – Order Task List

Page 15: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Part 1 – Order Task List

Page 16: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Part 3 – WBS

Page 17: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Part 3 – WBS

Page 18: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Submittal Review Process…Inspecton

Work & Materials

Visual Or

Lab Test

Lab TestVisual Test

Compare w Plans & Specifications

Samples to lab

Lab Results

Conform? Test OK?Yes

No

Issue Non-Comp

Defective Mat Report

No Payment till corrected

Follow-upRecord in log

Reinspect When Corrected

No

Issue Non-Comp

Defective Mat Report

No Payment till corrected

Follow-upRecord in log

Resample When Corrected

Make FinalInspection

Work AcceptedPayment Authorized

Shop Drawing?

AE Review

Page 19: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

One-to-One authority…

Organization Organization Organization Organization Organization Organization

One to One

PM CM

Page 20: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

One-to-One authority…

Org

an

izatio

nO

rga

niza

tion

Org

an

izatio

n Org

aniz

atio

nO

rga

niz

atio

nO

rga

niz

atio

n

One to One

Page 21: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Don’t forget… Sept 22… Test #1 – The Basics CON 2001 – OLIN Engr – Rm 118 - 1100-1215 CVE 4070 – OLIN Life Sci – Rm 130 – 500-615 Study guide

Habitat info coming… Sept 26 best date Also Wed & Fri

Grading resumes now

Page 22: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Now it’s over

Page 23: CVE 4070 Construction Engineering Project Organization Test #1 review Prof. Ralph V. Locurcio, PE

Grading Assignment #1