Cyberinfrastructure Release 2
Production Readiness Review
12 December 2013
Agenda
Time Topic Presenter
1000/1300 Introduction: Entry and Exit Criteria
Kathy Carr
1015/1315 Overview of Project State Mike Kelly
1030/1330 R2 Demonstration Tim Ampe / Luke Campbell
1130/1430 R2 Engineering Status - Test and Integration
Tim Ampe
1200/1500 R2 Verification Kathy Carr
1230/1530 R2 Deployment Rod Cressey
1245/1545 Wrap-up / Q&A Kathy Carr
Entry Criteria
The entry criteria for PRR are completion of the review
artifacts listed in Table 5 of Section 4.2. of the CI System
Life Cycle Plan:
Artifact Set Content
Management System Life Cycle PlanLCO, LCA & IOC Report and ResponseITV Strategy Integration and Verification Plan (baselined)
Requirements None
Design None
Implementation Source code repositoryTest Reports (baselined)Integration and Verification Procedures (baselined)Integration Report (baselined)Verification Report (baselined)Beta Testing Report (baselined)Defect List
Deployment Integrated and Verified Release (baselined)Deployment Plan (baselined)
Success Criteria / Exit Criteria(from SEMP and CI System Life Cycle Plan)
•Have all of the blocker and major defects been
corrected?
• Is the integrated and verified release mature and
stable enough for deployment into a production
environment?
• Is the integrated and verified release ready for
PMO acceptance?
• Is there appropriate final documentation to inform
and train the user and operations communities?
• Is the release ready to transition to operation?
R2 Timeline
•LCO: Aug 30 – Sep 1, 2011
•LCA: March 20-21, 2012
• IOC: Nov 16, 2012
•Beta Testing: December 2012 – January 2013
•Pathfinder Testing: Feb 1, 2013 – March 28, 2013
•MIRR: Sept 18, 2013
•Load Tests: Oct 24, 2013; Dec 11, 2013
•PRR: Dec 12, 2013
R2 Assumptions for Production/Operations
• R2 will only be used by Marine IOs and will not be exposed to external
users.
• The San Diego facility will host OOINet R2 after PRR during initial
operations.
• OOINet will be in state such that, upon passing the PRR, the Marine
Operators can begin using it for their operational tasks the next day for
the deployed Endurance platforms. The initial tasks of the Marine
Operators may be to transition “planned” assets into a “deployed” state
and to edit the information about those assets. Thus OOINet must
support those tasks.
• No non-operational information will be included in production baseline
version of OOINet. For example, the CI Bench Test Facility will not be
listed.
• No data or metadata entered in the system will be lost during software
upgrades during production.
PRR Documents• CI Release 2 System Integration Test Procedures -2160-
00100
• CI Release 2 System Integration Test Report - 2160-00101
• CI Release 2 Verification Procedures - 2160-00103
• CI Release 2 Verification Report - 2160-00104 (Confluence)
• CI Release 2 Beta Test Plan - 2160-00105
• CI Release 2 Beta Test Report - 2160-00106
• CI Release 2 Test Report - 2160-00102
• CI Deployment Plan - 2160-00200
Additional Release 2 documents
•R2 LCO Report
•R2 LCA Report
•R2 IOC Report
•R2 Pathfinder Effort Summary (2013-04-04)
•R2 Load Test Report (1152-02191; 2013-11-13)
•Online Help Documentation
Load Tests
October 24, 2013 December 11, 2013
# participants 31 26
Length of test 3 hours 3 hours
Test Procedure Version 0-05 Version 2-01
Functionality Coverage 100% of test steps (95% of functionality)
100% of test steps (95% of functionality)
# Blockers 2 0
# Majors 28 TBD
# Minors 61 TBD
Next Steps• If R2 passes PRR:
– R2 will move to the Production environment
– MIOs may start using it to manage deployed marine
platforms
– PMO will begin validation testing. (R2 won’t actually be in
“Operations” until PMO validation testing is complete.)
• If panel determines that R2 is not ready to transition to
operations:
– R2 will remain in the Transition phase until whatever
Actions we determine are completed.