daily program mayl-2012
TRANSCRIPT
-
8/13/2019 Daily Program Mayl-2012
1/6
S.l.
No.Description Work Program of May 7,2012 Achievement of May 6,2012 Remarks
1 Yard Drainage2 Lean Concrete
3 Sub-station Building Bricks work & Plastering Bricks work & Plastering in progress.
Thai glass work of window.
4 RTG Track
5 Service Area Rebar binding & Shuttering Rebar binding & Shuttering in progress
6 Cable Trench work Wall casting of Electric Pit & Reffer DB.
1 Yard Drainage Pipe laying & CC casting Pipe laying & CC casting in progress
2 Manhole & Gully hole3 Cable Trench work
1 Surcharge Surcharge material removing Surcharge material removing in progress.
2 Yard Drainage Earth excavation Earth excavation in progress.
1 Surcharge Settlement Record Settlement Record in progress.
1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.
1 Surcharge Settlement Record Settlement Record in progress.
1 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.
1 Surface drain work
2 Cable Line Installation Termination of laid cable Termination suspended due to objection of Navy
3 Main gate
1 Column Work Shutter removing
1 Bracing Pre-cast bracing casting (10 Nos) Rebar binding & Shuttering executed.
1 Interlocking Block Compressive strength test / ILB Compressive strength test / ILB
1 Sheet Pile
ILB Production. ILB Production (10,520 Nos)
Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Project Manager
NCT Back-up/PBL
Segment-3
Segment-4
Navy Area
Boundary Wall
Open Deep Drain
Laboratory / Field Test
Bank Protection work
Interlocking Block Production (ILB)
Segment-4A
Segment-1
Segment-2
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of May 7,2012
Segment-1A
Segment-2A
-
8/13/2019 Daily Program Mayl-2012
2/6
S.l.
No.Description Work Program of May 8,2012 Achievement of May 7,2012 Remarks
1 Yard Drainage
2 Lean Concrete
3 Sub-station Building Bricks work & Plastering Bricks work & Plastering in progress.
Thai glass work of window. Thai glass work of window in progress.
4 RTG Track Lean mix concrete. Lean mix concrete in progress.
5 Service Area Rebar binding & Shuttering Rebar binding & Shuttering in progress
6 Cable Trench work Top slab casting Rebar binding & Shuttering executed.
1 Yard Drainage Pipe laying & CC casting Pipe laying & CC casting in progress
2 Manhole & Gully hole3 Cable Trench work
1 Surcharge Surcharge material removing Surcharge material removing in progress.
2 Yard Drainage Earth excavation Earth excavation in progress.
1 Surcharge Settlement Record Settlement Record in progress.
1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.
1 Surcharge Settlement Record Settlement Record in progress.
1 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.
1 Surface drain work
2 Cable Line Installation Cable laying Cable laying in progress.
3 Main gate
1 Bracing Pre-cast bracing casting (10 Nos) Rebar binding & Shuttering executed.
1 Interlocking Block Compressive strength test / ILB Compressive strength test / ILB
1 Sheet Pile
ILB Production.
Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Segment-4A
Segment-1
Segment-2
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of May 8,2012
Segment-1A
Segment-2A
Project Manager
NCT Back-up/PBL
Segment-3
Segment-4
Navy Area
Open Deep Drain
Laboratory / Field Test
Bank Protection work
Interlocking Block Production (ILB)
-
8/13/2019 Daily Program Mayl-2012
3/6
S.l.
No.Description Work Program of May 9,2012 Achievement of May 8,2012 Remarks
1 Yard Drainage
2 Lean Concrete
3 Sub-station Building Bricks work & Plastering Bricks work & Plastering in progress.
Thai glass work of window. Thai glass work of window in progress.
4 RTG Track Lean mix concrete (18 Mpa) Lean mix concrete in progress.
5 Service Area Rebar binding & Shuttering Rebar binding & Shuttering in progress
6 Cable Trench work Wall casting Rebar binding & Shuttering executed.
1 Yard Drainage Pipe laying & CC casting Pipe laying & CC casting in progress
2 Manhole & Gully hole3 Cable Trench work
1 Surcharge Surcharge material removing Surcharge material removing in progress.
2 Yard Drainage Earth excavation Earth excavation in progress.
1 Surcharge Settlement Record Settlement Record in progress.
1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.
2 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.
1 Surcharge Settlement Record Settlement Record in progress.
1 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.
1 Surface drain work
2 Cable Line Installation Cable laying Cable laying in progress.
3 Main gate
1 Bracing
1 Interlocking Block Compressive strength test / ILB Compressive strength test / ILB
1 Boundary Wall Dismantling work Dismantling work in progress.
2 Existing Road Road cutting & Removal
ILB Production
Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Project Manager
NCT Back-up/PBL
Segment-3
Segment-4
Navy Area
Open Deep Drain
Laboratory / Field Test
Dismantling Work
Interlocking Block Production (ILB)
Segment-4A
Segment-1
Segment-2
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of May 9,2012
Segment-1A
Segment-2A
-
8/13/2019 Daily Program Mayl-2012
4/6
S.l.
No.Description Work Program of May 10,2012 Achievement of May 9,2012 Remarks
1 Yard Drainage
2 Lean Concrete(Yard)
3 Sub-station Building Bricks work & Plastering Bricks work & Plastering in progress.
Thai glass work of window. Thai glass work of window in progress.
4 RTG Track Lean mix concrete (18 Mpa) Lean mix concrete in progress.
5 Service Area Concrete Pouring (02 Nos block) Rebar binding & Shuttering executed.
6 Cable Trench work Wall casting Rebar binding & Shuttering executed.
7 RMG Track Concrete Pouring (02 Nos span)
1 Yard Drainage Pipe laying & CC casting Pipe laying & CC casting in progress
2 Manhole & Gully hole Wall casting of 01 Nos Gully hole.3 Cable Trench work
1 Surcharge Surcharge material removing Surcharge material removing in progress.
2 Yard Drainage Earth excavation Earth excavation in progress.
1 Surcharge Settlement Record Settlement Record in progress.
1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.
2 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.
1 Surcharge Settlement Record Settlement Record in progress.
1 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.
1 Surface drain work
2 Cable Line Installation Cable laying Cable laying in progress.
3 Main gate
1 Bracing
1 Interlocking Block Compressive strength test / ILB Compressive strength test / ILB
1 Boundary Wall Dismantling work Dismantling work in progress.
2 Existing Road Road cutting & Removal Road cutting & Removal in progress.
ILB Production
Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Segment-4A
Segment-1
Segment-2
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of May 10,2012
Segment-1A
Segment-2A
Project Manager
NCT Back-up/PBL
Segment-3
Segment-4
Navy Area
Open Deep Drain
Laboratory / Field Test
Dismantling Work
Interlocking Block Production (ILB)
-
8/13/2019 Daily Program Mayl-2012
5/6
S.l.
No.Description Work Program of May 11,2012 Achievement of May 10,2012 Remarks
1 Yard Drainage
2 Lean Concrete(Yard)
3 Sub-station Building Bricks work & Plastering Bricks work & Plastering in progress.
4 RTG Track Lean mix concrete executed.
5 Service Area Rebar binding & Shuttering work.
6 Cable Trench work Rebar binding & Shuttering work. Wall casting executed
7 RMG Track Concrete Pouring (02 Nos span) Rebar binding & Shuttering executed.
1 Yard Drainage Pipe laying & CC casting Pipe laying & CC casting in progress
2 Manhole & Gully hole Wall casting of 01 No Gully hole.
3 Cable Trench work
1 Surcharge Surcharge material removing Surcharge material removing in progress.
2 Yard Drainage Earth excavation Earth excavation in progress.
1 Surcharge Settlement Record Settlement Record in progress.
1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.
2 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.
1 Surcharge Settlement Record Settlement Record in progress.
1 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.
1 Surface drain work
2 Cable Line Installation Shutdown of laid cable. Cable laying executed.
3 Main gate
1 Bracing
1 Interlocking Block Compressive strength test / ILB Compressive strength test / ILB
1 Boundary Wall Dismantling work Dismantling work in progress.
2 Existing Road Road cutting & Removal Road cutting & Removal in progress.
1 ILB Production ILB Production in progress (11200 Nos)
Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Project Manager
NCT Back-up/PBL
Segment-3
Segment-4
Navy Area
Open Deep Drain
Laboratory / Field Test
Dismantling Work
Interlocking Block Production (ILB)
Segment-4A
Segment-1
Segment-2
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of May 11,2012
Segment-1A
Segment-2A
-
8/13/2019 Daily Program Mayl-2012
6/6
S.l.
No.Description Work Program of May 19,2012 Achievement of May 18,2012 Remarks
1 Sub-base work Sub-base work of Yard Sub-base work of Yard in progress.
2 Lean Concrete(Yard)
3 Sub-station Building Bricks work & Plastering Bricks work & Plastering in progress.
4 RTG Track Shuttering of RTG pavement Rebar binding executed.
5 Service Area
6 Cable Trench work Rebar binding & Shuttering of Reffer (Base)
7 RMG Track
1 Yard Drainage Pipe laying & CC casting Pipe laying & CC casting in progress
2 Manhole & Gully hole
3 Cable Trench work
1 Yard Drainage RCC pipe laying. RCC pipe laying in progress.
1 Surcharge Settlement Record Settlement Record in progress.
1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.
2 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.
1 Surcharge Settlement Record Settlement Record in progress.
1 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.
1 Surface drain work
2 Cable Line Installation
3 Navy Boundary wall Navy boundary wall dismantling.
1 Bracing
1 Interlocking Block Compressive strength test / ILB Compressive strength test / ILB
1 Boundary Wall
2 Existing Road Road cutting & Removal Road cutting & Removal in progress.
1 ILB Production ILB Production in progress (10460 Nos)
Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Segment-4A
Segment-1
Segment-2
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of May 19,2012
Segment-1A
Segment-2A
Project Manager
NCT Back-up/PBL
Segment-3
Segment-4
Navy Area
Open Deep Drain
Laboratory / Field Test
Dismantling Work
Interlocking Block Production (ILB)