  • 8/13/2019 Daily Program Mayl-2012

    1/6

    S.l.

    No.Description Work Program of May 7,2012 Achievement of May 6,2012 Remarks

    1 Yard Drainage2 Lean Concrete

    3 Sub-station Building Bricks work & Plastering Bricks work & Plastering in progress.

    Thai glass work of window.

    4 RTG Track

    5 Service Area Rebar binding & Shuttering Rebar binding & Shuttering in progress

    6 Cable Trench work Wall casting of Electric Pit & Reffer DB.

    1 Yard Drainage Pipe laying & CC casting Pipe laying & CC casting in progress

    2 Manhole & Gully hole3 Cable Trench work

    1 Surcharge Surcharge material removing Surcharge material removing in progress.

    2 Yard Drainage Earth excavation Earth excavation in progress.

    1 Surcharge Settlement Record Settlement Record in progress.

    1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.

    1 Surcharge Settlement Record Settlement Record in progress.

    1 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.

    1 Surface drain work

    2 Cable Line Installation Termination of laid cable Termination suspended due to objection of Navy

    3 Main gate

    1 Column Work Shutter removing

    1 Bracing Pre-cast bracing casting (10 Nos) Rebar binding & Shuttering executed.

    1 Interlocking Block Compressive strength test / ILB Compressive strength test / ILB

    1 Sheet Pile

    ILB Production. ILB Production (10,520 Nos)

    Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Project Manager

    NCT Back-up/PBL

    Segment-3

    Segment-4

    Navy Area

    Boundary Wall

    Open Deep Drain

    Laboratory / Field Test

    Bank Protection work

    Interlocking Block Production (ILB)

    Segment-4A

    Segment-1

    Segment-2

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of May 7,2012

    Segment-1A

    Segment-2A

  • 8/13/2019 Daily Program Mayl-2012

    2/6

    S.l.

    No.Description Work Program of May 8,2012 Achievement of May 7,2012 Remarks

    1 Yard Drainage

    2 Lean Concrete

    3 Sub-station Building Bricks work & Plastering Bricks work & Plastering in progress.

    Thai glass work of window. Thai glass work of window in progress.

    4 RTG Track Lean mix concrete. Lean mix concrete in progress.

    5 Service Area Rebar binding & Shuttering Rebar binding & Shuttering in progress

    6 Cable Trench work Top slab casting Rebar binding & Shuttering executed.

    1 Yard Drainage Pipe laying & CC casting Pipe laying & CC casting in progress

    2 Manhole & Gully hole3 Cable Trench work

    1 Surcharge Surcharge material removing Surcharge material removing in progress.

    2 Yard Drainage Earth excavation Earth excavation in progress.

    1 Surcharge Settlement Record Settlement Record in progress.

    1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.

    1 Surcharge Settlement Record Settlement Record in progress.

    1 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.

    1 Surface drain work

    2 Cable Line Installation Cable laying Cable laying in progress.

    3 Main gate

    1 Bracing Pre-cast bracing casting (10 Nos) Rebar binding & Shuttering executed.

    1 Interlocking Block Compressive strength test / ILB Compressive strength test / ILB

    1 Sheet Pile

    ILB Production.

    Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Segment-4A

    Segment-1

    Segment-2

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of May 8,2012

    Segment-1A

    Segment-2A

    Project Manager

    NCT Back-up/PBL

    Segment-3

    Segment-4

    Navy Area

    Open Deep Drain

    Laboratory / Field Test

    Bank Protection work

    Interlocking Block Production (ILB)

  • 8/13/2019 Daily Program Mayl-2012

    3/6

    S.l.

    No.Description Work Program of May 9,2012 Achievement of May 8,2012 Remarks

    1 Yard Drainage

    2 Lean Concrete

    3 Sub-station Building Bricks work & Plastering Bricks work & Plastering in progress.

    Thai glass work of window. Thai glass work of window in progress.

    4 RTG Track Lean mix concrete (18 Mpa) Lean mix concrete in progress.

    5 Service Area Rebar binding & Shuttering Rebar binding & Shuttering in progress

    6 Cable Trench work Wall casting Rebar binding & Shuttering executed.

    1 Yard Drainage Pipe laying & CC casting Pipe laying & CC casting in progress

    2 Manhole & Gully hole3 Cable Trench work

    1 Surcharge Surcharge material removing Surcharge material removing in progress.

    2 Yard Drainage Earth excavation Earth excavation in progress.

    1 Surcharge Settlement Record Settlement Record in progress.

    1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.

    2 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.

    1 Surcharge Settlement Record Settlement Record in progress.

    1 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.

    1 Surface drain work

    2 Cable Line Installation Cable laying Cable laying in progress.

    3 Main gate

    1 Bracing

    1 Interlocking Block Compressive strength test / ILB Compressive strength test / ILB

    1 Boundary Wall Dismantling work Dismantling work in progress.

    2 Existing Road Road cutting & Removal

    ILB Production

    Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Project Manager

    NCT Back-up/PBL

    Segment-3

    Segment-4

    Navy Area

    Open Deep Drain

    Laboratory / Field Test

    Dismantling Work

    Interlocking Block Production (ILB)

    Segment-4A

    Segment-1

    Segment-2

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of May 9,2012

    Segment-1A

    Segment-2A

  • 8/13/2019 Daily Program Mayl-2012

    4/6

    S.l.

    No.Description Work Program of May 10,2012 Achievement of May 9,2012 Remarks

    1 Yard Drainage

    2 Lean Concrete(Yard)

    3 Sub-station Building Bricks work & Plastering Bricks work & Plastering in progress.

    Thai glass work of window. Thai glass work of window in progress.

    4 RTG Track Lean mix concrete (18 Mpa) Lean mix concrete in progress.

    5 Service Area Concrete Pouring (02 Nos block) Rebar binding & Shuttering executed.

    6 Cable Trench work Wall casting Rebar binding & Shuttering executed.

    7 RMG Track Concrete Pouring (02 Nos span)

    1 Yard Drainage Pipe laying & CC casting Pipe laying & CC casting in progress

    2 Manhole & Gully hole Wall casting of 01 Nos Gully hole.3 Cable Trench work

    1 Surcharge Surcharge material removing Surcharge material removing in progress.

    2 Yard Drainage Earth excavation Earth excavation in progress.

    1 Surcharge Settlement Record Settlement Record in progress.

    1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.

    2 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.

    1 Surcharge Settlement Record Settlement Record in progress.

    1 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.

    1 Surface drain work

    2 Cable Line Installation Cable laying Cable laying in progress.

    3 Main gate

    1 Bracing

    1 Interlocking Block Compressive strength test / ILB Compressive strength test / ILB

    1 Boundary Wall Dismantling work Dismantling work in progress.

    2 Existing Road Road cutting & Removal Road cutting & Removal in progress.

    ILB Production

    Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Segment-4A

    Segment-1

    Segment-2

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of May 10,2012

    Segment-1A

    Segment-2A

    Project Manager

    NCT Back-up/PBL

    Segment-3

    Segment-4

    Navy Area

    Open Deep Drain

    Laboratory / Field Test

    Dismantling Work

    Interlocking Block Production (ILB)

  • 8/13/2019 Daily Program Mayl-2012

    5/6

    S.l.

    No.Description Work Program of May 11,2012 Achievement of May 10,2012 Remarks

    1 Yard Drainage

    2 Lean Concrete(Yard)

    3 Sub-station Building Bricks work & Plastering Bricks work & Plastering in progress.

    4 RTG Track Lean mix concrete executed.

    5 Service Area Rebar binding & Shuttering work.

    6 Cable Trench work Rebar binding & Shuttering work. Wall casting executed

    7 RMG Track Concrete Pouring (02 Nos span) Rebar binding & Shuttering executed.

    1 Yard Drainage Pipe laying & CC casting Pipe laying & CC casting in progress

    2 Manhole & Gully hole Wall casting of 01 No Gully hole.

    3 Cable Trench work

    1 Surcharge Surcharge material removing Surcharge material removing in progress.

    2 Yard Drainage Earth excavation Earth excavation in progress.

    1 Surcharge Settlement Record Settlement Record in progress.

    1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.

    2 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.

    1 Surcharge Settlement Record Settlement Record in progress.

    1 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.

    1 Surface drain work

    2 Cable Line Installation Shutdown of laid cable. Cable laying executed.

    3 Main gate

    1 Bracing

    1 Interlocking Block Compressive strength test / ILB Compressive strength test / ILB

    1 Boundary Wall Dismantling work Dismantling work in progress.

    2 Existing Road Road cutting & Removal Road cutting & Removal in progress.

    1 ILB Production ILB Production in progress (11200 Nos)

    Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Project Manager

    NCT Back-up/PBL

    Segment-3

    Segment-4

    Navy Area

    Open Deep Drain

    Laboratory / Field Test

    Dismantling Work

    Interlocking Block Production (ILB)

    Segment-4A

    Segment-1

    Segment-2

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of May 11,2012

    Segment-1A

    Segment-2A

  • 8/13/2019 Daily Program Mayl-2012

    6/6

    S.l.

    No.Description Work Program of May 19,2012 Achievement of May 18,2012 Remarks

    1 Sub-base work Sub-base work of Yard Sub-base work of Yard in progress.

    2 Lean Concrete(Yard)

    3 Sub-station Building Bricks work & Plastering Bricks work & Plastering in progress.

    4 RTG Track Shuttering of RTG pavement Rebar binding executed.

    5 Service Area

    6 Cable Trench work Rebar binding & Shuttering of Reffer (Base)

    7 RMG Track

    1 Yard Drainage Pipe laying & CC casting Pipe laying & CC casting in progress

    2 Manhole & Gully hole

    3 Cable Trench work

    1 Yard Drainage RCC pipe laying. RCC pipe laying in progress.

    1 Surcharge Settlement Record Settlement Record in progress.

    1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.

    2 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.

    1 Surcharge Settlement Record Settlement Record in progress.

    1 Ground Improvement Sub-grade Preparation Sub-grade Preparation in progress.

    1 Surface drain work

    2 Cable Line Installation

    3 Navy Boundary wall Navy boundary wall dismantling.

    1 Bracing

    1 Interlocking Block Compressive strength test / ILB Compressive strength test / ILB

    1 Boundary Wall

    2 Existing Road Road cutting & Removal Road cutting & Removal in progress.

    1 ILB Production ILB Production in progress (10460 Nos)

    Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Segment-4A

    Segment-1

    Segment-2

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of May 19,2012

    Segment-1A

    Segment-2A

    Project Manager

    NCT Back-up/PBL

    Segment-3

    Segment-4

    Navy Area

    Open Deep Drain

    Laboratory / Field Test

    Dismantling Work

    Interlocking Block Production (ILB)