    GOVERNMENT OF INDIA

    CENTRAL PUBLIC WORKS DEPARTMENT

    ANALYSIS OF RATES

    FOR DELHI

    (VOL -2)

    2014

    Published Under The Authority of Director General CPWD, Nirman Bhawan, New DelhiPublished Under The Authority of Director General CPWD, Nirman Bhawan, New DelhiPublished Under The Authority of Director General CPWD, Nirman Bhawan, New DelhiPublished Under The Authority of Director General CPWD, Nirman Bhawan, New DelhiPublished Under The Authority of Director General CPWD, Nirman Bhawan, New Delhi

  • 8/9/2019 DAR14-Vol2

    2/710

    © All rights reserved. No part of this publication, either in English or in Hindi, may be reproduced in

    any form or by any means, electronic or mechanical including photocopy, recording or any information

    storage and retrieval system, without permission, in writing, from the Director General, CPWD, New

    Delhi

    This Analysis of Rates 2014 for Delhi is prepared for the use of CPWD. However, this may be usedby other Govt. departments, PSUs, private bodies & individuals also at their own discretion. CPWD

    shall not be responsible for any ambiguity, discrepancy, dispute or financial loss, arising directly or

    indirectly by using or following items of DSR by such Govt./Private bodies or individuals.

    Printed and Marketed by

    M/s Kshitiz EnterprisesD-57 South Extension Part-1

    New Delhi-110049

    Phone : 011-41648857,

    Mobile : 9811032311, 9311332311

    Email : [email protected]

    [email protected]

    Published by

    Director GeneralCentral Public Works Department

    Nirman Bhawan

    New Delhi-110011

    Also available at

    All leading Govt. Book Dealers in India

    Price : Rs. 3000/-

    Per Set of 2 Volumes

    Excluding, Postage, Packing and Delivery Charges etc.

    A GOVERNMENT OF INDIA PUBLICATION

    ii

  • 8/9/2019 DAR14-Vol2

    3/710

    V.K. GUPTADirector General

     dsUæh; yksd fuekZ.k foHkkx  dsUæh; yksd fuekZ.k foHkkx  dsUæh; yksd fuekZ.k foHkkx  dsUæh; yksd fuekZ.k foHkkx  dsUæh; yksd fuekZ.k foHkkx 

     fuekZ .k Hkou] ubZ  fnYyh & 110011

    Central Public Works DepartmentNirman Bhawan, New Delhi-110011

    Tel.:23062556/1317, Fax : 23061884Email: [email protected]

    Hkkjr Hkkjr Hkkjr Hkkjr Hkkjr  ljdkj  ljdkj  ljdkj  ljdkj  ljdkj Government of India

    FOREWORD

    Central Public Works Department Analysis of Rates for Delhi is a very

    comprehensive and useful document forming basis for the rates of various items.

    It is based on scientific assessment of Inputs of materials, labour and machineryin various items of work normally involved in civil construction projects.

    It was first compiled in the year 1950, followed by subsequent publication or

    revision in the years 1955, 1962, 1972, 1977, 1985, 1997, 2007, 2012 & 2013.

    Since publication of Analysis of Rates for Delhi -2013, prices of labour and

    materials have registered substantial increase. Besides the increased cost, there

    has been a spurt of new construction materials and introduction of Green Building

    Concept of construction. This has necessitated revision of existing Analysis of 

    Rates for Delhi 2013 to include the above changes. Accordingly, this Analysis of 

    Rates for Delhi 2014 has been prepared.

    The analysis of existing items has been updated in conformity with updated itemsof works in DSR 2014.

    I wish to place on record the technical input and the effective coordination on the

    part of Shri Diwakar Garg, Special D.G.(HQ), Shri Mukesh Vij, ADG (TD), Shri B.B.

    Dhar, Chief Engineer(CSQ) and the efforts put in by Shri Mathura Prasad, SE TAS

    (CSQ) and his team of officers in TAS unit in finalizing Analysis of Rates for Delhi

    2014 in a record time.

    I am sure that C.P.W.D. Analysis of Rates for Delhi 2014 shall be very useful

    document to various Central Govt. Ministries, Departments & Public Sector

    Undertakings also besides various units of CPWD.

    Place : New Delhi

    Date : July 2014 (V.K. Gupta)

    iii

  • 8/9/2019 DAR14-Vol2

    4/710

    ..

  • 8/9/2019 DAR14-Vol2

    5/710

    PREFACE

    1. C.P.W.D. Analysis of Rates for Delhi 2014 is the revised edition of C.P.W.D. Analysis

    of Rates for Delhi 2013.

     2. Analysis of Rates for Delhi 2014 incorporates most of the analysis of items of Analysis

    of Rates for Delhi 2013 with updated correction slips, including analysis of existingitems and also corresponding new items introduced in DSR 2014.

    3. Analysis of Rates for Delhi, 2014 is published in two volumes i.e. volume I & II asunder:

    Volume Sub-head No. Content/ Sub-headNumber

    One 00 Basic Rates01 Carriage of materials02 Earth Work

    03 Mortars

    04 Concrete Work05 Reinforced Cement Concrete

    06 Brick Work07 Stone Work08 Marble & Granite Work09 Wood and PVC Work

    10 Steel Work11 Flooring12 Roofing

    Two 13 Finishing

    14 Repairs to Buildings

    15 Dismantling and Demolishing16 Road Work17 Sanitary Installations

    18 Water Supply19 Drainage20 Pile work21 Aluminium Work

    22 Water Proofing23 Horticulture and Landscaping24 Rain Water Harvesting & Tube wells

    25 Conservation of Heritage buildings26 Structural Glazing and Composite

    Aluminium Panel

    4. The new items for 100 mm thick M-25, RCC drain covers and M-30 PU mould paverblocks have been introduced in Sub head-16 Road work.

    Analysis of few existing items in sub head -20 (pile Work) have been deleted. Similarly,analyses of many items have been modified to correspond to items of DSR 2014.

    Few new analysis and sub items have been introduced in Analysis of Rates for Delhi

    2014.

    v

  • 8/9/2019 DAR14-Vol2

    6/710

    5. Analysis of Rates for Delhi, 2014 is based on the current market rates of materials atDelhi, collected during the period of March- April 2014. The basic rates of materials,incorporated in the analysis, pertain to materials conforming to BIS Standards/ CPWDSpecifications/Materials of good quality generally available in the market. Labour rates

    are the minimum wages issued by the Government of Delhi w.e.f. 01.04.2014.

    6. The nomenclatures of main items have been printed along with the analysis of firstSub item only to conserve the space and number of pages.

    7. Sundries have been considered as 1.78 times, based on Cost Index of Delhi as on01.04.2014 with a base as per PAR-2007.

    8. A lot of effort has gone into the preparation of this DAR-2014, I convey my deepappreciation and sincere thanks to Shri Mathura Prasad SE(TAS), Sh.P.P. SinghSE(QA), Shri K.R. Meena EE (TAS-I), Sh. A.K. Goel EE(QA-I), Shri Chhabilal SinghAE, Shri S.C. Saxena AE, Shri Ram Janam Chaudhary JE, Shri Vijay Kumar Chief

    Estimator, Shri Bahal Singh Sr. Drafts Man, Shri Vijay Singh Sr.Drafts Man, and otherofficers & staff of TAS unit for sincere efforts made in the preparation of this documentin such a short time. Various field units, who contributed field inputs, also deserveappreciation for their timely help.

    9. Due care has been taken to print the C.P.W.D. Analysis of Rates for Delhi as correctlyas possible. It is, however possible that some errors might have crept in. In case anyerror or omission is noticed, it may be brought to the notice of the SuperintendingEngineer (TAS), CPWD, Room no. 418, A-wing, Nirman Bhawan, New Delhi.

      (Mukesh Vij)  ADG (TD), CPWD,

    Nirman Bhawan, New Delhi.New DelhiJune, 2014

    vi

  • 8/9/2019 DAR14-Vol2

    7/710

    SH. No. NAME OF SUB-HEAD PAGE No.

    13. Finishing 689-740

    14. Repairs to Building 741-796

    15. Dismantling & Demolishing 797-830

    16. Road Work 831-936

    17. Sanitary Installations 937-1008

    18. Water Supply 1009-1202

    19. Drainage 1203-1280

    20. Pile Work 1281-1306

    21. Aluminium Work 1307-1330

    22. Water Proofing 1331-1350

    23. Horticulture & Landscaping 1351-1352

    24. Rain Water Harvesting & Tubewells 1353-1372

    25. Conservation of Heritage Buildings 1373-1380

    26. Structural Glazing and Aluminium Composite Panel 1381-1392

    Note : For Sub Heads 1 to 12 refer to Vol.1

    Vol. 2

    C O N T E N T S

    vii

  • 8/9/2019 DAR14-Vol2

    8/710

    .

  • 8/9/2019 DAR14-Vol2

    9/710

    SUB HEAD : 13.0

    FINISHING

    689

  • 8/9/2019 DAR14-Vol2

    10/710

    690

  • 8/9/2019 DAR14-Vol2

    11/710

    13.1 12 mm cement plaster of mix:

    13.1.1 1:4 (1 cement : 4 fine sand)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm.MATERIAL:Cement mortar 1 : 4 (1 cement: 4 fine sand)

    3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.144 3637.05 523.740155 Mason (average) day 0.670 417.00 279.390115 Coolie day 0.750 329.00 246.750101 Bhisti day 0.920 363.00 333.969999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    TOTAL 1406.29Add Water Charges @ 1% 14.06

    TOTAL 1420.35Add CPOH @ 15% 213.05

    Cost of 10 sqm 1633.40Cost of 1 sqm 163.34

    Say 163.35

    13.1.2 1:6 (1 cement : 6 fine sand)

    Code No Description Unit Quantity Rate  `  Amount ` Details of cost for 10 sqm MATERIAL:Cement mortar 1 : 6 (1 cement: 6 fine sand)

    3.6 Rate as per Item Number 3.6 of SH: Mortars cum 0.144 2805.75 404.03LABOUR:

    0155 Mason (average) day 0.670 417.00 279.390115 Coolie day 0.750 329.00 246.750101 Bhisti day 0.920 363.00 333.969999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    TOTAL 1286.58Add Water Charges @ 1% 12.87

    TOTAL 1299.45Add CPOH @ 15% 194.92

    Cost of 10 sqm 1494.37Cost of 1 sqm 149.44

    Say 149.45

    13.2 15 mm cement plaster on the rough side of single or half brick wall of mix:

    13.2.1 1:4 (1 cement : 4 fine sand)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:Cement mortar 1 : 4 (1 cement: 4 fine sand)

    3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.172 3637.05 625.57LABOUR:

    0155 Mason (average) day 0.800 417.00 333.60

    0115 Coolie day 0.880 329.00 289.520101 Bhisti day 0.990 363.00 359.379999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    TOTAL 1630.51Add Water Charges @ 1% 16.31

    TOTAL 1646.82Add CPOH @ 15% 247.02

    Cost of 10 sqm 1893.84Cost of 1 sqm 189.38

    Say 189.40

    SUB HEAD : 13 - FINISHING  691

  • 8/9/2019 DAR14-Vol2

    12/710

    SUB HEAD : 13 - FINISHING 692

    13.2.2 1:6 (1 cement : 6 fine sand)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:Cement mortar 1 : 6 (1 cement: 6 fine sand)

    3.6 Rate as per Item Number 3.6 of SH: Mortars cum 0.172 2805.75 482.59

    LABOUR:0155 Mason (average) day 0.800 417.00 333.600115 Coolie day 0.880 329.00 289.520101 Bhisti day 0.990 363.00 359.379999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    TOTAL 1487.53Add Water Charges @ 1% 14.88

    TOTAL 1502.41Add CPOH @ 15% 225.36

    Cost of 10 sqm 1727.77Cost of 1 sqm 172.78

    Say 172.80

    13.3 20 mm cement plaster of mix:

    13.3.1 1:4 (1 cement : 4 fine sand)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:Cement mortar 1 : 4 (1 cement: 4 fine sand)

    3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.224 3637.05 814.70LABOUR:

    0155 Mason (average) day 0.940 417.00 391.980115 Coolie day 1.020 329.00 335.580101 Bhisti day 1.100 363.00 399.309999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    TOTAL 1964.01Add Water Charges @ 1% 19.64

    TOTAL 1983.65

    Add CPOH @ 15% 297.55Cost of 10 sqm 2281.20

    Cost of 1 sqm 228.12Say 228.10

    13.3.2 1:6 (1 cement : 6 fine sand)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:Cement mortar 1 : 6 (1 cement: 6 fine sand)

    3.6 Rate as per Item Number 3.6 of SH: Mortars cum 0.224 2805.75 628.49LABOUR:

    0155 Mason (average) day 0.940 417.00 391.98

    0115 Coolie day 1.020 329.00 335.580101 Bhisti day 1.100 363.00 399.309999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    TOTAL 1777.80Add Water Charges @ 1% 17.78

    TOTAL 1795.58Add CPOH @ 15% 269.34

    Cost of 10 sqm 2064.92Cost of 1 sqm 206.49

    Say 206.50

  • 8/9/2019 DAR14-Vol2

    13/710

    SUB HEAD : 13 - FINISHING  693

    13.4 12 mm cement plaster of mix:

    13.4.1 1:4 (1 cement : 4 coarse sand)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:Cement mortar 1:4 (1 cement : 4 coarse sand)

    3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.144 4172.05 600.78LABOUR:

    0155 Mason (average) day 0.670 417.00 279.390115 Coolie day 0.750 329.00 246.750101 Bhisti day 0.920 363.00 333.969999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    TOTAL 1483.33Add Water Charges @ 1% 14.83

    TOTAL 1498.16Add CPOH @ 15% 224.72

    Cost of 10 sqm 1722.88Cost of 1 sqm 172.29

    Say 172.30

    13.4.2 1:6 (1 cement : 6 coarse sand)

    Code No Description Unit Quantity Rate  `  Amount ` 

    MATERIAL:Cement mortar 1:6 (1 cement : 6 coarse sand)

    3.11 Rate as per Item Number 3.11 of SH: Mortars cum 0.144 3340.75 481.07LABOUR:

    0155 Mason (average) day 0.670 417.00 279.390115 Coolie day 0.750 329.00 246.750101 Bhisti day 0.920 363.00 333.969999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    TOTAL 1363.62Add Water Charges @ 1% 13.64

    TOTAL 1377.26Add CPOH @ 15% 206.59

    Cost of 10 sqm 1583.85Cost of 1 sqm 158.39

    Say 158.40

    13.5 15 mm cement plaster on rough side of single or half brick wall of mix:

    13.5.1 1:4 (1 cement : 4 coarse sand)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:Cement mortar 1:4 (1 cement : 4 coarse sand)

    3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.172 4172.05 717.59LABOUR:

    0155 Mason (average) day 0.800 417.00 333.60

    0115 Coolie day 0.880 329.00 289.520101 Bhisti day 0.990 363.00 359.379999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    TOTAL 1722.53Add Water Charges @ 1% 17.23

    TOTAL 1739.76Add CPOH @ 15% 260.96

    Cost of 10 sqm 2000.72Cost of 1 sqm 200.07

    Say 200.05

  • 8/9/2019 DAR14-Vol2

    14/710

    SUB HEAD : 13 - FINISHING 694

    13.5.2 1:6 (1 cement : 6 coarse sand)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:Cement mortar 1:6 (1 cement : 6 coarse sand)

    3.11 Rate as per Item Number 3.11 of SH: Mortars cum 0.172 3340.75 574.61

    LABOUR:0155 Mason (average) day 0.800 417.00 333.600115 Coolie day 0.880 329.00 289.520101 Bhisti day 0.990 363.00 359.379999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    TOTAL 1579.55Add Water Charges @ 1% 15.80

    TOTAL 1595.35Add CPOH @ 15% 239.30

    Cost of 10 sqm 1834.65Cost of 1 sqm 183.47

    Say 183.45

    13.6 20 mm cement plaster of mix:

    13.6.1 1:4 (1 cement : 4 coarse sand)Code No Description Unit Quantity Rate  `  Amount ` 

    MATERIAL:Cement mortar 1:4 (1 cement : 4 coarse sand)

    3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.224 4172.05 934.54LABOUR:

    0155 Mason (average) day 0.940 417.00 391.980115 Coolie day 1.020 329.00 335.580101 Bhisti day 1.100 363.00 399.309999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    TOTAL 2083.85Add Water Charges @ 1% 20.84

    TOTAL 2104.69

    Add CPOH @ 15% 315.70Cost of 10 sqm 2420.39

    Cost of 1 sqm 242.04Say 242.05

    13.6.2 1:6 (1 cement : 6 coarse sand)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:Cement mortar 1:6 (1 cement : 6 coarse sand)

    3.11 Rate as per Item Number 3.11 of SH: Mortars cum 0.224 3340.75 748.33LABOUR:

    0155 Mason (average) day 0.940 417.00 391.980115 Coolie day 1.020 329.00 335.580101 Bhisti day 1.100 363.00 399.309999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    TOTAL 1897.64Add Water Charges @ 1% 18.98

    TOTAL 1916.62Add CPOH @ 15% 287.49

    Cost of 10 sqm 2204.11Cost of 1 sqm 220.41

    Say 220.40

  • 8/9/2019 DAR14-Vol2

    15/710

    SUB HEAD : 13 - FINISHING  695

    13.7 12 mm cement plaster finished with a floating coat of neat cement of mix:

    13.7.1 1:3 (1 cement : 3 fine sand)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    Cement mortar 1:3 (1 cement : 3 fine sand)

    3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.144 4468.35 643.44LABOUR:

    0155 Mason (average) day 0.670 417.00 279.39

    0115 Coolie day 0.750 329.00 246.75

    0101 Bhisti day 0.920 363.00 333.969999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    0367 Portland Cement tonne 0.020 6300.00 126.002209 Carriage of cement tonne 0.020 94.65 1.89

    0155 Mason (average) day 0.270 417.00 112.59

    0115 Coolie day 0.270 329.00 88.839999 Scaffolding and sundries. L.S. 8.060 1.78 14.35

    TOTAL 1869.65

    Add Water Charges @ 1% 18.70TOTAL 1888.35

    Add CPOH @ 15% 283.25Cost of 10 sqm 2171.60

    Cost of 1 sqm 217.16

    Say 217.15

    13.7.2 1:4 (1 cement : 4 fine sand)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:

    Cement mortar 1 : 4 (1 cement: 4 fine sand)3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.144 3637.05 523.74

    LABOUR:

    0155 Mason (average) day 0.670 417.00 279.39

    0115 Coolie day 0.750 329.00 246.750101 Bhisti day 0.920 363.00 333.969999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    0367 Portland Cement tonne 0.020 6300.00 126.00

    2209 Carriage of cement tonne 0.020 94.65 1.890155 Mason (average) day 0.270 417.00 112.59

    0115 Coolie day 0.270 329.00 88.839999 Scaffolding and sundries. L.S. 8.060 1.78 14.35

    TOTAL 1749.95

    Add Water Charges @ 1% 17.50

    TOTAL 1767.45Add CPOH @ 15% 265.12

    Cost of 10 sqm 2032.57Cost of 1 sqm 203.26

    Say 203.25

    13.8 15 mm cement plaster on rough side of single or halfbrick wall finished with a floating coat of neat

    cement of mix :

    13.8.1 1:3 (1 cement : 3 fine sand)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    Cement mortar 1:3 (1 cement : 3 fine sand)

  • 8/9/2019 DAR14-Vol2

    16/710

    SUB HEAD : 13 - FINISHING 696

    Code No Description Unit Quantity Rate  `  Amount ` 

    3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.172 4468.35 768.56LABOUR:

    0155 Mason (average) day 0.800 417.00 333.60

    0115 Coolie day 0.880 329.00 289.520101 Bhisti day 0.990 363.00 359.37

    9999 Scaffolding and sundries. L.S. 12.610 1.78 22.450367 Portland Cement tonne 0.020 6300.00 126.00

    2209 Carriage of cement tonne 0.020 94.65 1.890155 Mason (average) day 0.270 417.00 112.59

    0115 Coolie day 0.270 329.00 88.83

    9999 Scaffolding and sundries. L.S. 8.060 1.78 14.35

    TOTAL 2117.16Add Water Charges @ 1% 21.17

    TOTAL 2138.33

    Add CPOH @ 15% 320.75Cost of 10 sqm 2459.08

    Cost of 1 sqm 245.91Say 245.90

    13.8.2 1:4 (1 cement : 4 fine sand)Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:Cement mortar 1 : 4 (1 cement: 4 fine sand)

    3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.172 3637.05 625.57

    LABOUR:0155 Mason (average) day 0.800 417.00 333.60

    0115 Coolie day 0.880 329.00 289.520101 Bhisti day 0.990 363.00 359.37

    9999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    0367 Portland Cement tonne 0.020 6300.00 126.002209 Carriage of cement tonne 0.020 94.65 1.89

    0155 Mason (average) day 0.270 417.00 112.590115 Coolie day 0.270 329.00 88.83

    9999 Scaffolding and sundries. L.S. 8.060 1.78 14.35

    TOTAL 1974.17

    Add Water Charges @ 1% 19.74TOTAL 1993.91

    Add CPOH @ 15% 299.09Cost of 10 sqm 2293.00

    Cost of 1 sqm 229.30

    Say 229.30

    13.9 cement plaster 1:3 (1 cement : 3 coarse sand) finished with a floating coat of neat cement.

    13.9.1 12 mm cement plaster

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    Cement mortar 1:3 (1 cement : 3 coarse sand)3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.144 5003.35 720.48

    LABOUR:0155 Mason (average) day 0.670 417.00 279.39

    0115 Coolie day 0.750 329.00 246.750101 Bhisti day 0.920 363.00 333.96

    9999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

  • 8/9/2019 DAR14-Vol2

    17/710

    SUB HEAD : 13 - FINISHING  697

    Code No Description Unit Quantity Rate  `  Amount ` 

    0367 Portland Cement tonne 0.020 6300.00 126.00

    2209 Carriage of cement tonne 0.020 94.65 1.89

    0155 Mason (average) day 0.270 417.00 112.59

    0115 Coolie day 0.270 329.00 88.83

    9999 Scaffolding and sundries. L.S. 8.060 1.78 14.35

    TOTAL 1946.69

    Add Water Charges @ 1% 19.47

    TOTAL 1966.16

    Add CPOH @ 15% 294.92

    Cost of 10 sqm 2261.08

    Cost of 1 sqm 226.11

    Say 226.10

    13.9.2 20 mm cement plaster

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    Cement mortar 1:3 (1 cement : 3 coarse sand)3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.224 5003.35 1120.75

    LABOUR:

    0155 Mason (average) day 0.940 417.00 391.98

    0115 Coolie day 1.020 329.00 335.58

    0101 Bhisti day 1.100 363.00 399.30

    9999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    0367 Portland Cement tonne 0.020 6300.00 126.00

    2209 Carriage of cement tonne 0.020 94.65 1.89

    0155 Mason (average) day 0.270 417.00 112.59

    0115 Coolie day 0.270 329.00 88.83

    9999 Scaffolding and sundries. L.S. 8.060 1.78 14.35

    TOTAL 2613.72

    Add Water Charges @ 1% 26.14TOTAL 2639.86

    Add CPOH @ 15% 395.98

    Cost of 10 sqm 3035.84

    Cost of 1 sqm 303.58

    Say 303.60

    13.10 15 mm cement plaster 1:3 (1 cement : 3 coarse sand) finished with a floating coat of neat cement on the

    rough side of single or half brick wall.

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    Cement mortar 1:3 (1 cement : 3 coarse sand)

    3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.172 5003.35 860.58LABOUR:

    0155 Mason (average) day 0.800 417.00 333.60

    0115 Coolie day 0.880 329.00 289.52

    0101 Bhisti day 0.990 363.00 359.37

    9999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    0367 Portland Cement tonne 0.020 6300.00 126.00

    2209 Carriage of cement tonne 0.020 94.65 1.89

    0155 Mason (average) day 0.270 417.00 112.59

    0115 Coolie day 0.270 329.00 88.83

  • 8/9/2019 DAR14-Vol2

    18/710

    SUB HEAD : 13 - FINISHING 698

    Code No Description Unit Quantity Rate  `  Amount ` 

    9999 Scaffolding and sundries. L.S. 8.060 1.78 14.35

    TOTAL 2209.18Add Water Charges @ 1% 22.09

    TOTAL 2231.27

    Add CPOH @ 15% 334.69

    Cost of 10 sqm 2565.96Cost of 1 sqm 256.60

    Say 256.60

    13.11 18 mm cement plaster in two coats under layer 12 mm thick cement plaster 1:5 (1 cement : 5 coarse

    sand) finished with a top layer 6mm thick cement plaster 1:6 (1 cement : 6 fine sand).

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:Under layer Cement mortar 1:5 (1 cement : 5 coarse

    sand)3.10 Rate as per Item Number 3.10 of SH: Mortars cum 0.144 3724.40 536.31

    Top layer Cement mortar 1:6 (1 cement : 6 fine sand)

    3.6 Rate as per Item Number 3.6 of SH: Mortars cum 0.072 2805.75 202.01LABOUR:

    0155 Mason (average) day 1.210 417.00 504.570115 Coolie day 1.290 329.00 424.41

    0101 Bhisti day 1.050 363.00 381.159999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    TOTAL 2070.90Add Water Charges @ 1% 20.71

    TOTAL 2091.61Add CPOH @ 15% 313.74

    Cost of 10 sqm 2405.35Cost of 1 sqm 240.54

    Say 240.55

    13.12 18 mm cement plaster in two coats under layer 12 mm thick cement plaster 1:5 (1 cement : 5 coarsesand) and a top layer 6 mm thick cement plaster 1:3 (1 cement : 3 coarse sand) finished rough withsponge.

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:Under layer Cement mortar 1:5 (1 cement :

    5 coarse sand)

    3.10 Rate as per Item Number 3.10 of SH: Mortars cum 0.144 3724.40 536.31Top layer Cement mortar 1:3 (1 cement : 3 coarse sand)

    3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.072 5003.35 360.24LABOUR:

    0155 Mason (average) day 1.210 417.00 504.57

    0115 Coolie day 1.290 329.00 424.410101 Bhisti day 1.050 363.00 381.15

    9999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    TOTAL 2229.13Add Water Charges @ 1% 22.29

    TOTAL 2251.42

    Add CPOH @ 15% 337.71Cost of 10 sqm 2589.13

    Cost of 1 sqm 258.91Say 258.90

  • 8/9/2019 DAR14-Vol2

    19/710

    SUB HEAD : 13 - FINISHING  699

    13.13 12 mm cement plaster 1:2 (1 cement : 2 stone dust)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:

    Cement mortar 1:2 (1 cement : 2 stone dust)3.12 Rate as per Item Number 3.12 of SH: Mortars cum 0.144 5838.65 840.77

    LABOUR:0155 Mason (average) day 0.670 417.00 279.390115 Coolie day 0.750 329.00 246.75

    0101 Bhisti day 0.920 363.00 333.969999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    TOTAL 1723.32

    Add Water Charges @ 1% 17.23

    TOTAL 1740.55Add CPOH @ 15% 261.08

    Cost of 10 sqm 2001.63Cost of 1 sqm 200.16

    Say 200.15

    13.14 15 mm cement plaster 1:2 (1 cement : 2 stone dust) on the rough side of single or half brick wall.

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:Cement mortar 1:2 (1 cement : 2 stone dust)

    3.12 Rate as per Item Number 3.12 of SH: Mortars cum 0.172 5838.65 1004.25LABOUR:

    0155 Mason (average) day 0.800 417.00 333.600115 Coolie day 0.880 329.00 289.52

    0101 Bhisti day 0.990 363.00 359.37

    9999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    TOTAL 2009.19Add Water Charges @ 1% 20.09

    TOTAL 2029.28

    Add CPOH @ 15% 304.39Cost of 10 sqm 2333.67

    Cost of 1 sqm 233.37Say 233.35

    13.15 20 mm cement plaster 1:2 (1 cement : 2 stone dust)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:Cement mortar 1:2 (1 cement : 2 stone dust)

    3.12 Rate as per Item Number 3.12 of SH: Mortars cum 0.224 5838.65 1307.86

    LABOUR:0155 Mason (average) day 0.940 417.00 391.98

    0115 Coolie day 1.020 329.00 335.580101 Bhisti day 1.100 363.00 399.30

    9999 Scaffolding and sundries. L.S. 12.610 1.78 22.45

    TOTAL 2457.17

    Add Water Charges @ 1% 24.57TOTAL 2481.74

    Add CPOH @ 15% 372.26Cost of 10 sqm 2854.00

    Cost of 1 sqm 285.40

    Say 285.40

  • 8/9/2019 DAR14-Vol2

    20/710

    SUB HEAD : 13 - FINISHING 700

    13.16 6 mm cement plaster of mix:

    13.16.1 1:3 (1 cement : 3 fine sand)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    Cement mortar 1:3 (1 cement : 3 fine sand)

    3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.072 4468.35 321.72LABOUR:

    0155 Mason (average) day 0.510 417.00 212.67

    0115 Coolie day 0.750 329.00 246.75

    0101 Bhisti day 0.920 363.00 333.96

    9999 Extra for removing burrs, cleaning with wire brushes,

    pock making with pointed tool etc. L.S. 13.390 1.78 23.83

    9999 Scaffolding and sundries. L.S. 11.700 1.78 20.83

    TOTAL 1159.76

    Add Water Charges @ 1% 11.60

    TOTAL 1171.36

    Add CPOH @ 15% 175.70

    Cost of 10 sqm 1347.06

    Cost of 1 sqm 134.71Say 134.70

    13.17 6 mm cement plaster 1:3 (1 cement : 3 fine sand) finished with a floating coat of neat cement and thick

    coat of Lime wash on top of walls when dry for bearing of R.C.C. slabs and beams.

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    Cement mortar 1:3 (1 cement : 3 fine sand)

    3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.072 4468.35 321.72

    LABOUR:

    0155 Mason (average) day 0.510 417.00 212.67

    0115 Coolie day 0.750 329.00 246.75

    0101 Bhisti day 0.920 363.00 333.969999 Extra for removing burrs, cleaning with wire brushes,

    pock making with pointed tool etc.

    complete L.S. 13.390 1.78 23.83

    9999 Scaffolding and sundries. L.S. 11.700 1.78 20.83

    0367 Portland Cement tonne 0.020 6300.00 126.00

    2209 Carriage of cement tonne 0.020 94.65 1.89

    0155 Mason (average) day 0.270 417.00 112.59

    0115 Coolie day 0.270 329.00 88.83

    9999 Scaffolding and sundries. L.S. 8.060 1.78 14.35

    0776 Satna lime quintal 0.010 500.00 5.00

    9999 Indigo gum etc. L.S. 2.080 1.78 3.70

    9999 Sundries, ladder etc. L.S. 0.520 1.78 0.93

    0141 White Washer day 0.070 363.00 25.41

    0115 Coolie day 0.070 329.00 23.039999 Sundries L.S. 2.730 1.78 4.86

    TOTAL 1566.35

    Add Water Charges @ 1% 15.66

    TOTAL 1582.01

    Add CPOH @ 15% 237.30

    Cost of 10 sqm 1819.31

    Cost of 1 sqm 181.93

    Say 181.95

  • 8/9/2019 DAR14-Vol2

    21/710

    SUB HEAD : 13 - FINISHING  701

    13.18 Neat cement punning

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm LABOUR:

    0367 Portland Cement tonne 0.022 6300.00 138.602209 Carriage of cement tonne 0.022 94.65 2.08

    0155 Mason (average) day 0.270 417.00 112.590115 Coolie day 0.270 329.00 88.839999 Scaffolding and sundries. L.S. 8.060 1.78 14.35

    TOTAL 356.45

    Add Water Charges @ 1% 3.56TOTAL 360.01

    Add CPOH @ 15% 54.00

    Cost of 10 sqm 414.01Cost of 1 sqm 41.40

    Say 41.40

    13.19 Rough cast plaster upto 10 m height above ground level with a mixture of sand and gravel or crushedstone from 6 mm to 10 mm nominal size, dashed over and including the fresh plaster in two layers, under

    layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand) and top layer 10 mm cement plaster 1:3 (1

    cement : 3 fine sand) mixed with 10% finely grounded hydrated lime by volume of cement.13.19.1 Ordinary cement finish using ordinary cement

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    Under layer 12 mm thick cement plaster with cementmortar 1:4 (1 cement : 4 coarse sand)

    3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.144 4172.05 600.780155 Mason (average) day 0.670 417.00 279.39

    0115 Coolie day 0.750 329.00 246.750101 Bhisti day 0.920 363.00 333.96

    9999 Scaffolding and sundries. L.S. 9.880 1.78 17.59

    Top layer 10 mm thick cement plaster with cement

    mortar 1:3 (1 cement : 3 fine sand)3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.120 4468.35 536.200155 Mason (average) day 0.610 417.00 254.37

    0114 Beldar day 0.690 329.00 227.01

    0101 Bhisti day 0.850 363.00 308.559999 Scaffolding and sundries. L.S. 9.880 1.78 17.59

    1179 Crushed stone 2.36 mm to 12.5 mm size cum 0.100 1100.00 110.000101 Bhisti day 0.010 363.00 3.63

    0777 Dry hydrated lime (factory made) quintal 0.090 230.00 20.70

    9999 Carriage of lime L.S. 3.640 1.78 6.480155 Mason (average) day 0.500 417.00 208.50

    0114 Beldar day 0.500 329.00 164.500101 Bhisti day 0.100 363.00 36.30

    9999 Scaffolding and sundries. L.S. 9.880 1.78 17.59

    0123 Mason (brick layer) 1 st class day 0.250 435.00 108.750114 Beldar day 0.250 329.00 82.25

    TOTAL 3580.89

    Add Water Charges @ 1% 35.81TOTAL 3616.70

    Add CPOH @ 15% 542.50

    Cost of 10 sqm 4159.20Cost of 1 sqm 415.92

    Say 415.90

  • 8/9/2019 DAR14-Vol2

    22/710

    SUB HEAD : 13 - FINISHING 702

    13.20 Pebble dash plaster upto 10 m height above ground level with a mixture of washed pebble or crushedstone 6 mm to 12.5 mm nominal size, dashed over and including fresh plaster in two layers under layer12 mm cement plaster 1:4 (1 cement : 4 coarse sand) and top layer 10 mm cement plaster with cementmortar 1:3 (1 cement : 3 fine sand) mixed with 10% finely grounded hydrated lime by volume of cement.

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:Under layer 12mm thick cement plasterUnder layer 12 mm thick cement plasterwith cement mortar 1:4 (1 cement : 4 coarse sand)

    3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.144 4172.05 600.78LABOUR:

    0155 Mason (average) day 0.670 417.00 279.390114 Beldar day 0.750 329.00 246.750101 Bhisti day 0.920 363.00 333.969999 Scaffolding and sundries. L.S. 9.880 1.78 17.59

    Top layer 10mm thick cement plasterTop layer 10 mm thick cement plaster with cementmortar 1:3 (1 cement : 3 fine sand)

    3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.120 4468.35 536.200155 Mason (average) day 0.610 417.00 254.37

    0114 Beldar day 0.690 329.00 227.010101 Bhisti day 0.850 363.00 308.559999 Scaffolding and sundries. L.S. 9.880 1.78 17.591179 Crushed stone 2.36 mm to 12.5 mm size cum 0.100 1100.00 110.000101 Bhisti day 0.010 363.00 3.630777 Dry hydrated lime (factory made) quintal 0.090 230.00 20.709999 Carriage of lime L.S. 3.640 1.78 6.480155 Mason (average) day 0.500 417.00 208.500114 Beldar day 0.500 329.00 164.500101 Bhisti day 0.100 363.00 36.309999 Scaffolding and sundries. L.S. 9.880 1.78 17.599999 Scaffolding and sundries. L.S. 4.420 1.78 7.87

    TOTAL 3397.76Add Water Charges @ 1% 33.98

    TOTAL 3431.74Add CPOH @ 15% 514.76Cost of 10 sqm 3946.50

    Cost of 1 sqm 394.65Say 394.65

    13.21 Extra for providing and mixing water proofing material in cement plaster work in proportion recommendedby the manufacturers.

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 12 mm cement plaster 1:3 (1 cement:3 sand) = 10 sqm or 1.48 bags of cement used in the mix Cement required for 10 sqm = 73.89 kgWater proofing material required @ 1 kg per

    50 kg of cement = 1.48 kg1213 Water proofing materials kilogram 1.480 35.00 51.809999 Sundries L.S. 7.150 1.78 12.73

    TOTAL 64.53Add Water Charges @ 1% 0.65

    TOTAL 65.18Add CPOH @ 15% 9.78

    Cost of 1.48 per bag of 50kg 74.96per bag of 50 kg cement used in the mix. 50.65

    Say 50.65

  • 8/9/2019 DAR14-Vol2

    23/710

    SUB HEAD : 13 - FINISHING  703

    13.22 Extra for plastering exterior walls of height more than 10 m from ground level for every additional height

    of 3 m or part thereof.

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    9999 Scaffolding and sundries. L.S. 53.820 1.78 95.80

    LABOUR:0155 Mason (average) day 0.200 417.00 83.40

    0115 Coolie day 0.300 329.00 98.70

    0101 Bhisti day 0.100 363.00 36.30

    9999 Sundries L.S. 7.150 1.78 12.73

    TOTAL 326.93

    Add Water Charges @ 1% 3.27

    TOTAL 330.20

    Add CPOH @ 15% 49.53

    Cost of 10 sqm 379.73

    Cost of 1 sqm 37.97

    Say 37.95

    13.23 Extra for plastering on circular work not exceeding 6 m in radius.

    13.23.1 In one coat

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    LABOUR:

    0155 Mason (average) day 0.200 417.00 83.40

    0114 Beldar day 0.200 329.00 65.80

    9999 Sundries L.S. 7.150 1.78 12.73

    TOTAL 161.93

    Add Water Charges @ 1% 1.62

    TOTAL 163.55Add CPOH @ 15% 24.53

    Cost of 10 sqm 188.08

    Cost of 1 sqm 18.81

    Say 18.80

    13.23.2 In two coats

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    LABOUR:

    0155 Mason (average) day 0.300 417.00 125.10

    0114 Beldar day 0.300 329.00 98.709999 Sundries L.S. 13.390 1.78 23.83

    TOTAL 247.63

    Add Water Charges @ 1% 2.48

    TOTAL 250.11

    Add CPOH @ 15% 37.52

    Cost of 10 sqm 287.63

    Cost of 1 sqm 28.76

    Say 28.75

  • 8/9/2019 DAR14-Vol2

    24/710

    SUB HEAD : 13 - FINISHING 704

    13.24 Extra for plastering done on moulding cornices or architraves including neat finish to line and level:

    13.24.1 In one coat

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    LABOUR:

    0155 Mason (average) day 3.000 417.00 1251.000114 Beldar day 2.000 329.00 658.00

    0115 Coolie day 1.000 329.00 329.00

    0101 Bhisti day 0.250 363.00 90.75

    9999 Sundries L.S. 13.390 1.78 23.83

    TOTAL 2352.58

    Add Water Charges @ 1% 23.53

    TOTAL 2376.11

    Add CPOH @ 15% 356.42

    Cost of 10 sqm 2732.53

    Cost of 1 sqm 273.25

    Say 273.25

    13.24.2 In two coats

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    LABOUR:

    0155 Mason (average) day 5.000 417.00 2085.00

    0114 Beldar day 3.000 329.00 987.00

    0115 Coolie day 2.000 329.00 658.00

    0101 Bhisti day 0.330 363.00 119.79

    9999 Sundries L.S. 13.390 1.78 23.83

    TOTAL 3873.62

    Add Water Charges @ 1% 38.74

    TOTAL 3912.36

    Add CPOH @ 15% 586.85

    Cost of 10 sqm 4499.21

    Cost of 1 sqm 449.92

    Say 449.90

    13.25 Extra for plastering :

    13.25.1 Spherical ceiling

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    LABOUR:

    0155 Mason (average) day 0.750 417.00 312.75

    0114 Beldar day 0.740 329.00 243.46

    9999 Sundries L.S. 26.910 1.78 47.90

    TOTAL 604.11

    Add Water Charges @ 1% 6.04

    TOTAL 610.15

    Add CPOH @ 15% 91.52

    Cost of 10 sqm 701.67

    Cost of 1 sqm 70.17

    Say 70.15

  • 8/9/2019 DAR14-Vol2

    25/710

    SUB HEAD : 13 - FINISHING  705

    13.25.2 Groined ceiling

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    LABOUR:

    0155 Mason (average) day 0.800 417.00 333.60

    0114 Beldar day 0.800 329.00 263.20

    9999 Sundries L.S. 34.060 1.78 60.63

    TOTAL 657.43

    Add Water Charges @ 1% 6.57

    TOTAL 664.00

    Add CPOH @ 15% 99.60

    Cost of 10 sqm 763.60

    Cost of 1 sqm 76.36

    Say 76.35

    13.25 Extra for plastering :

    13.25.3 Flewing soffits

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm LABOUR:

    0155 Mason (average) day 0.500 417.00 208.50

    0114 Beldar day 0.500 329.00 164.50

    9999 Sundries L.S. 13.390 1.78 23.83

    TOTAL 396.83

    Add Water Charges @ 1% 3.97

    TOTAL 400.80

    Add CPOH @ 15% 60.12

    Cost of 10 sqm 460.92

    Cost of 1 sqm 46.09

    Say 46.10

    13.26 Providing and applying plaster of paris putty of 2 mm thickness over plastered surface to prepare the

    surface even and smooth complete.

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10sqm 

    MATERIAL:

    Plaster of paris

    10x0.002 x 1121 = 22.42kg

    Add 2% wastage= 0.45kg

    Total = 22.87kg

    Say 23 kg

    0869 Plaster of Paris kilogram 23.000 4.50 103.50

    9999 Carriage of plaster of paris L.S. 3.900 1.78 6.94

    LABOUR:

    0122 Mason (for plaster of paris work) 1 st class day 0.910 435.00 395.85

    0114 Beldar day 0.910 329.00 299.39

    9999 Scaffolding and sundries. L.S. 83.980 1.78 149.48

    TOTAL 955.16

    Add Water Charges @ 1% 9.55

    TOTAL 964.71

    Add CPOH @ 15% 144.71

    Cost of 10 sqm 1109.42

    Cost of 1 sqm 110.94

    Say 110.95

  • 8/9/2019 DAR14-Vol2

    26/710

    SUB HEAD : 13 - FINISHING 706

    13.27 Extra for lining out plaster to imitate stone or concrete blocks walling.

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    LABOUR:

    0155 Mason (average) day 0.500 417.00 208.50

    0114 Beldar day 0.500 329.00 164.50

    9999 Solution of lime putty L.S. 1.820 1.78 3.24

    TOTAL 376.24

    Add Water Charges @ 1% 3.76

    TOTAL 380.00

    Add CPOH @ 15% 57.00

    Cost of 10 sqm 437.00

    Cost of 1 sqm 43.70

    Say 43.70

    13.28 12 mm thick plain cement mortar bands in cement mortar 1:4 (1 cement : 4 fine sand) :

    13.28.1 Flush Band

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 metre long and 10cm wide band MATERIAL:

    Cement mortar 1:4 (1 cement : 4 fine sand)

    3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.014 3637.05 50.92

    LABOUR:

    0155 Mason (average) day 0.270 417.00 112.59

    0115 Coolie day 0.270 329.00 88.83

    0101 Bhisti day 0.050 363.00 18.15

    9999 Sundries L.S. 1.430 1.78 2.55

    TOTAL 273.04

    Add Water Charges @ 1% 2.73

    TOTAL 275.77

    Add CPOH @ 15% 41.37

    Cost of 10 metre long and 10cm wide band 317.14

    Cost of 1 cm per metre 3.17

    Say 3.15

    13.28.2 Sunk Band

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 metre long and 10cm wide band 

    MATERIAL:

    Cement mortar 1:4 (1 cement : 4 fine sand)

    3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.014 3637.05 50.92

    LABOUR:

    0155 Mason (average) day 0.300 417.00 125.10

    0115 Coolie day 0.300 329.00 98.70

    0101 Bhisti day 0.050 363.00 18.15

    9999 Sundries L.S. 2.080 1.78 3.70

    TOTAL 296.57

    Add Water Charges @ 1% 2.97

    TOTAL 299.54

    Add CPOH @ 15% 44.93

    Cost of 10 metre long and 10cm wide band 344.47

    Cost of 1 cm per metre 3.44

    Say 3.45

  • 8/9/2019 DAR14-Vol2

    27/710

    SUB HEAD : 13 - FINISHING  707

    13.28.3 Raised Band

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 metre long and 10cm wide band MATERIAL:Cement mortar 1:4 (1 cement : 4 fine sand)

    3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.014 3637.05 50.92LABOUR:0155 Mason (average) day 0.350 417.00 145.950115 Coolie day 0.350 329.00 115.150101 Bhisti day 0.050 363.00 18.159999 Sundries L.S. 2.730 1.78 4.86

    TOTAL 335.03Add Water Charges @ 1% 3.35

    TOTAL 338.38Add CPOH @ 15% 50.76

    Cost of 10 metre long and 10cm wide band 389.14Cost of 1 cm per metre 3.89

    Say 3.90

    13.28.4 Moulded Band

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 metre long and 10cm wide band MATERIAL:Cement mortar 1:4 (1 cement : 4 fine sand)

    3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.014 3637.05 50.92LABOUR:

    0155 Mason (average) day 0.650 417.00 271.050115 Coolie day 0.650 329.00 213.850101 Bhisti day 0.050 363.00 18.159999 Sundries L.S. 1.560 1.78 2.78

    TOTAL 556.75Add Water Charges @ 1% 5.57

    TOTAL 562.32

    Add CPOH @ 15% 84.35Cost of 10 metre long and 10cm wide band 646.67

    Cost of 1 cm per metre 6.47Say 6.45

    13.29 18 mm thick plain cement mortar band in cement mortar 1:4 (1 cement : 4 fine sand):

    13.29.1 Flush Band

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 metre long and 10cm wide band MATERIAL:Cement mortar 1:4 (1 cement : 4 fine sand)

    3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.020 3637.05 72.74LABOUR:

    0155 Mason (average) day 0.320 417.00 133.44

    0115 Coolie day 0.320 329.00 105.280101 Bhisti day 0.060 363.00 21.789999 Sundries L.S. 2.080 1.78 3.70

    TOTAL 336.94Add Water Charges @ 1% 3.37

    TOTAL 340.31Add CPOH @ 15% 51.05

    Cost of 10 metre long and 10cm wide band 391.36Cost of 1 cm per metre 3.91

    Say 3.90

  • 8/9/2019 DAR14-Vol2

    28/710

    SUB HEAD : 13 - FINISHING 708

    13.29.2 Sunk Band

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 metre long and 10cm wide band MATERIAL:

    Cement mortar 1:4 (1 cement : 4 fine sand)3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.020 3637.05 72.74

    LABOUR:0155 Mason (average) day 0.360 417.00 150.120115 Coolie day 0.360 329.00 118.44

    0101 Bhisti day 0.060 363.00 21.789999 Sundries L.S. 2.730 1.78 4.86

    TOTAL 367.94

    Add Water Charges @ 1% 3.68

    TOTAL 371.62Add CPOH @ 15% 55.74

    Cost of 10 metre long and 10cm wide band 427.36Cost of 1 cm per metre 4.27

    Say 4.25

    13.29.3 Raised Band

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 metre long and 10cm wide band 

    MATERIAL:Cement mortar 1:4 (1 cement : 4 fine sand)

    3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.020 3637.05 72.74LABOUR:

    0155 Mason (average) day 0.420 417.00 175.140115 Coolie day 0.420 329.00 138.18

    0101 Bhisti day 0.060 363.00 21.78

    9999 Sundries L.S. 4.420 1.78 7.87

    TOTAL 415.71Add Water Charges @ 1% 4.16

    TOTAL 419.87

    Add CPOH @ 15% 62.98Cost of 10 metre long and 10cm wide band 482.85

    Cost of 1 cm per metre 4.83Say 4.85

    13.29.4 Moulded Band

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 metre long and 10cm wide band 

    MATERIAL:Cement mortar 1:4 (1 cement : 4 fine sand)

    3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.024 3637.05 87.29

    LABOUR:0155 Mason (average) day 0.860 417.00 358.62

    0115 Coolie day 0.860 329.00 282.940101 Bhisti day 0.050 363.00 18.15

    9999 Sundries L.S. 2.730 1.78 4.86

    TOTAL 751.86

    Add Water Charges @ 1% 7.52TOTAL 759.38

    Add CPOH @ 15% 113.91Cost of 10 metre long and 10cm wide band 873.29

    Cost of 1 cm per metre 8.73

    Say 8.75

  • 8/9/2019 DAR14-Vol2

    29/710

    SUB HEAD : 13 - FINISHING  709

    13.30 18 mm thick moulded cement mortar band in two coats under layer 12 mm thick with cement mortar 1:5

    (1 cement : 5 coarse sand) top layer 6mm thick with cement mortar 1:4 (1 cement : 4 fine sand).

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 metre long and 10cm wide band 

    MATERIAL:

    Cement mortar 1:5 (1 cement : 5 coarse sand)

    3.10 Rate as per Item Number 3.10 of SH: Mortars cum 0.014 3724.40 52.14Cement mortar 1:4 (1 cement : 4 fine sand)

    3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.010 3637.05 36.37

    LABOUR:

    0155 Mason (average) day 0.860 417.00 358.62

    0115 Coolie day 0.860 329.00 282.94

    0101 Bhisti day 0.050 363.00 18.15

    9999 Sundries L.S. 2.730 1.78 4.86

    TOTAL 753.08

    Add Water Charges @ 1% 7.53

    TOTAL 760.61

    Add CPOH @ 15% 114.09

    Cost of 10 metre long and 10cm wide band 874.70

    Cost of 1 cm per metre 8.75Say 8.75

    13.31 Pointing on brick work or brick flooring with cement mortar 1:3 (1 cement : 3 fine sand) :

    13.31.1 Flush / Ruled / Struck or weathered pointing

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    Cement mortar 1:3 (1 cement : 3 fine sand)

    3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.030 4468.35 134.05

    LABOUR:

    0155 Mason (average) day 0.500 417.00 208.50

    0115 Coolie day 0.600 329.00 197.40

    0101 Bhisti day 0.930 363.00 337.599999 Sundries L.S. 7.150 1.78 12.73

    9999 Scaffolding and racking out joints including sundries L.S. 14.300 1.78 25.45

    TOTAL 915.72

    Add Water Charges @ 1% 9.16

    TOTAL 924.88

    Add CPOH @ 15% 138.73

    Cost of 10 sqm 1063.61

    Cost of 1 sqm 106.36

    Say 106.35

    13.31.2 Raised and cut pointing

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    Cement mortar 1:3 (1 cement : 3 fine sand)

    3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.046 4468.35 205.54

    LABOUR:

    0155 Mason (average) day 1.070 417.00 446.19

    0115 Coolie day 1.310 329.00 430.99

    0101 Bhisti day 1.000 363.00 363.00

    9999 Sundries L.S. 7.150 1.78 12.73

  • 8/9/2019 DAR14-Vol2

    30/710

    SUB HEAD : 13 - FINISHING 710

    Code No Description Unit Quantity Rate  `  Amount ` 

    9999 Scaffolding and racking out joints including sundries L.S. 16.120 1.78 28.69

    TOTAL 1487.14

    Add Water Charges @ 1% 14.87

    TOTAL 1502.01

    Add CPOH @ 15% 225.30Cost of 10 sqm 1727.31

    Cost of 1 sqm 172.73

    Say 172.75

    13.32 Pointing on tile brick work with cement mortar 1:3 (1 cement :3 fine sand):

    13.32.1 Flush / Ruled / Struck or weathered pointing

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    Cement mortar 1:3 (1 cement : 3 fine sand)

    3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.046 4468.35 205.54

    9999 Sundries L.S. 7.150 1.78 12.73

    LABOUR:

    0155 Mason (average) day 0.670 417.00 279.39

    0115 Coolie day 0.800 329.00 263.20

    0101 Bhisti day 1.280 363.00 464.64

    9999 Scaffolding and racking out joints including sundries L.S. 16.120 1.78 28.69

    TOTAL 1254.19

    Add Water Charges @ 1% 12.54

    TOTAL 1266.73

    Add CPOH @ 15% 190.01

    Cost of 10 sqm 1456.74

    Cost of 1 sqm 145.67

    Say 145.65

    13.33 Pointing on stone work with cement mortar 1:3 (1 cement : 3 fine sand) :

    13.33.1 Flush / Ruled pointing

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    Cement mortar 1:3 (1 cement : 3 fine sand)

    3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.023 4468.35 102.77

    9999 Sundries L.S. 7.150 1.78 12.73

    LABOUR:

    0155 Mason (average) day 0.920 417.00 383.64

    0115 Coolie day 1.370 329.00 450.73

    0101 Bhisti day 0.930 363.00 337.599999 Scaffolding and racking out joints including sundries L.S. 16.120 1.78 28.69

    TOTAL 1316.15

    Add Water Charges @ 1% 13.16

    TOTAL 1329.31

    Add CPOH @ 15% 199.40

    Cost of 10 sqm 1528.71

    Cost of 1 sqm 152.87

    Say 152.85

  • 8/9/2019 DAR14-Vol2

    31/710

    SUB HEAD : 13 - FINISHING  711

    13.33.2 Raised and cut pointing

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    Cement mortar 1:3 (1 cement : 3 fine sand)

    3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.038 4468.35 169.80

    9999 Sundries L.S. 7.150 1.78 12.73LABOUR:

    0155 Mason (average) day 2.000 417.00 834.00

    0115 Coolie day 2.960 329.00 973.84

    0101 Bhisti day 1.000 363.00 363.00

    9999 Scaffolding and racking out joints including sundries L.S. 16.120 1.78 28.69

    TOTAL 2382.06

    Add Water Charges @ 1% 23.82

    TOTAL 2405.88

    Add CPOH @ 15% 360.88

    Cost of 10 sqm 2766.76

    Cost of 1 sqm 276.68

    Say 276.70

    13.34 Raised and cut pointing on stone work in white cement mortar 1:3 (1 white cement : 3 marble dust)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    White cement mortar 1:3 (1 white cement :

    3 marble dust)

    3.16 Rate as per Item Number 3.16 of SH: Mortars cum 0.038 8716.35 331.22

    9999 Sundries L.S. 7.150 1.78 12.73

    LABOUR:

    0155 Mason (average) day 2.000 417.00 834.00

    0115 Coolie day 2.960 329.00 973.84

    0101 Bhisti day 1.000 363.00 363.00

    9999 Scaffolding and racking out joints including

    sundries L.S. 16.120 1.78 28.69

    TOTAL 2543.48

    Add Water Charges @ 1% 25.43

    TOTAL 2568.91

    Add CPOH @ 15% 385.34

    Cost of 10 sqm 2954.25

    Cost of 1 sqm 295.43

    Say 295.40

    13.35 Pointing on stone slab ceiling with cement mortar 1:2 (1 cement : 2 fine sand):

    13.35.1 Flush / Ruled pointing

    Code No Description Unit Quantity Rate ` 

    Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    Cement mortar 1:2 (1 cement : 2 fine sand)

    3.2 Rate as per Item Number 3.2 of SH: Mortars cum 0.015 5458.65 81.88

    LABOUR:

    0155 Mason (average) day 0.470 417.00 195.99

    0115 Coolie day 0.690 329.00 227.01

    0101 Bhisti day 0.590 363.00 214.17

  • 8/9/2019 DAR14-Vol2

    32/710

    SUB HEAD : 13 - FINISHING 712

    Code No Description Unit Quantity Rate  `  Amount ` 

    9999 Scaffolding and racking out joints including L.S. 16.120 1.78 28.69

    TOTAL 747.74Add Water Charges @ 1% 7.48

    TOTAL 755.22

    Add CPOH @ 15% 113.28

    Cost of 10 sqm 868.50Cost of 1 sqm 86.85

    Say 86.85

    13.36 Extra for pointing on walls on the outside at height more than 10 m from ground level for every additional

    height of 3 m or part there of.

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    LABOUR:9999 Scaffolding L.S. 13.390 1.78 23.83

    9999 Sundries L.S. 13.390 1.78 23.83

    TOTAL 47.66Add Water Charges @ 1% 0.48

    TOTAL 48.14Add CPOH @ 15% 7.22

    Cost of 10 sqm 55.36

    Cost of 1 sqm 5.54Say 5.55

    13.37 White washing with lime to give an even shade:

    13.37.1 New work (three or more coats)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:0775 Dehradun white lime quintal 0.030 650.00 19.50

    9999 Carriage of lime L.S. 0.910 1.78 1.62

    LABOUR:0141 White Washer day 0.200 363.00 72.60

    0115 Coolie day 0.100 329.00 32.909999 Indigo gum etc. L.S. 4.420 1.78 7.87

    9999 Sundries ladders etc. L.S. 2.730 1.78 4.86

    TOTAL 139.35

    Add Water Charges @ 1% 1.39TOTAL 140.74

    Add CPOH @ 15% 21.11Cost of 10 sqm 161.85

    Cost of 1 sqm 16.19

    Say 16.20

    13.38 Satna lime wash on walls with one coat

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    0776 Satna lime quintal 0.010 500.00 5.009999 Carriage of lime L.S. 2.080 1.78 3.70

    9999 Indigo gum etc. L.S. 0.520 1.78 0.93LABOUR:

    0141 White Washer day 0.080 363.00 29.04

  • 8/9/2019 DAR14-Vol2

    33/710

    SUB HEAD : 13 - FINISHING  713

    Code No Description Unit Quantity Rate  `  Amount ` 

    0115 Coolie day 0.040 329.00 13.16

    9999 Sundries ladders etc. L.S. 2.730 1.78 4.86

    TOTAL 56.69

    Add Water Charges @ 1% 0.57

    TOTAL 57.26Add CPOH @ 15% 8.59

    Cost of 10 sqm 65.85

    Cost of 1 sqm 6.59

    Say 6.60

    13.39 Colour washing such as green, blue or buff to give an even shade:

    13.39.1 New work (two or more coats) with a base coat of white washing with lime

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    0775 Dehradun white lime quintal 0.030 650.00 19.50

    9999 Carriage of lime L.S. 8.060 1.78 14.35

    9999 Add for colouring stuff L.S. 0.910 1.78 1.62

    LABOUR:

    0141 White Washer day 0.300 363.00 108.90

    0115 Coolie day 0.100 329.00 32.90

    9999 Indigo gum etc. L.S. 4.420 1.78 7.87

    9999 Sundries ladders etc. L.S. 2.730 1.78 4.86

    TOTAL 190.00

    Add Water Charges @ 1% 1.90

    TOTAL 191.90

    Add CPOH @ 15% 28.78

    Cost of 10 sqm 220.68

    Cost of 1 sqm 22.07

    Say 22.05

    13.39.2 New work (two or more coats) with a base coat of whiting

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    0775 Dehradun white lime quintal 0.030 650.00 19.50

    9999 Carriage of lime L.S. 8.060 1.78 14.35

    9999 Add for colouring stuff L.S. 0.910 1.78 1.62

    LABOUR:

    0141 White Washer day 0.300 363.00 108.90

    0115 Coolie day 0.100 329.00 32.90

    9999 Indigo gum etc. L.S. 2.730 1.78 4.86

    9999 Sundries ladders etc. L.S. 2.730 1.78 4.86

    TOTAL 186.99

    Add Water Charges @ 1% 1.87

    TOTAL 188.86

    Add CPOH @ 15% 28.33

    Cost of 10 sqm 217.19

    Cost of 1 sqm 21.72

    Say 21.70

  • 8/9/2019 DAR14-Vol2

    34/710

    SUB HEAD : 13 - FINISHING 714

    13.40 Distempering with dry distemper of approved brand and manufacture (two or more coats) of requiredshade on new work, over and including water thinnable priming coat to give an even shade :

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:0808 Water thinnable cement primer for interior wall surface,

    having VOC content less than 50 grams/ litre litre 0.700 80.00 56.009999 Putty, glue etc. L.S. 2.730 1.78 4.860815 Dry distemper kilogram 1.500 36.00 54.00

    9999 Carriage of material L.S. 1.560 1.78 2.789999 Brushes, sand paper etc. L.S. 7.150 1.78 12.73

    LABOUR:

    0131 Painter day 0.800 399.00 319.200115 Coolie day 0.400 329.00 131.60

    9999 Sundries L.S. 5.330 1.78 9.49

    TOTAL 590.66Add Water Charges @ 1% 5.91

    TOTAL 596.57

    Add CPOH @ 15% 89.49Cost of 10 sqm 686.06

    Cost of 1 sqm 68.61Say 68.60

    13.41 Distempering with oil bound washable distemper of approved brand and manufacture to give an even

    shade :

    13.41.1 New work (two or more coats) over and including priming coat with water thinnable cement primer

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:

    0808 Water thinnable cement primer for interior wall surface,having VOC content less than 50 grams/ litre litre 0.700 80.00 56.00

    9999 Brushes, putty etc. L.S. 7.150 1.78 12.73

    9999 Sundries including carriage L.S. 8.060 1.78 14.35

    0816 Oil bound washable distemper/ Acrylic distemper kilogram 1.500 55.00 82.509999 Carriage of material L.S. 4.420 1.78 7.879999 Brushes, sand paper and putty for filling holes L.S. 11.700 1.78 20.83

    LABOUR:

    0131 Painter day 1.000 399.00 399.000115 Coolie day 0.500 329.00 164.50

    9999 Sundries L.S. 8.060 1.78 14.35

    TOTAL 772.13Add Water Charges @ 1% 7.72

    TOTAL 779.85

    Add CPOH @ 15% 116.98Cost of 10 sqm 896.83

    Cost of 1 sqm 89.68Say 89.70

    13.42 Distempering with 1st quality acrylic washable distemper (ready mixed) of approved manufacturer, of

    required shade and colour complete as per manufacturer’s specification.

    13.42.1 Two or more coats on new work

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:

    0816 Oil bound washable distemper/ Acrylic distemper kilogram 1.500 55.00 82.50

  • 8/9/2019 DAR14-Vol2

    35/710

    SUB HEAD : 13 - FINISHING  715

    Code No Description Unit Quantity Rate  `  Amount ` 

    9999 Carriage of material L.S. 4.420 1.78 7.879999 Brushes, sand paper and putty for filling holes L.S. 11.570 1.78 20.59

    LABOUR:

    0131 Painter day 0.400 399.00 159.600114 Beldar day 0.460 329.00 151.34

    9999 Sundries L.S. 8.060 1.78 14.35TOTAL 436.25

    Add Water Charges @ 1% 4.36

    TOTAL 440.61

    Add CPOH @ 15% 66.09Cost of 10 sqm 506.70

    Cost of 1 sqm 50.67Say 50.65

    13.43 Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface:

    13.43.1 Water thinnable cement primer

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10sqm 

    MATERIAL:0808 Water thinnable cement primer for interior wall surface,

    having VOC content less than 50 grams/ litre litre 0.700 80.00 56.00

    9999 Brushes, putty etc. L.S. 7.150 1.78 12.73LABOUR:

    0131 Painter day 0.400 399.00 159.600115 Coolie day 0.200 329.00 65.80

    9999 Sundries includingcarriage L.S. 8.060 1.78 14.35

    TOTAL 308.48

    Add Water Charges @ 1% 3.08TOTAL 311.56

    Add CPOH @ 15% 46.73Cost of 10 sqm 358.29

    Cost of 1 sqm 35.83

    Say 35.85

    13.44 Finishing walls with water proofing cement paint of required shade:

    13.44.1 New work (Two or more coats applied @ 3.84 kg/ 10 sqm)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:0851 Water proofing cement paint kilogram 3.840 45.00 172.80

    9999 Carriage of material L.S. 1.560 1.78 2.78

    LABOUR:0131 Painter day 0.460 399.00 183.54

    0115 Coolie day 0.230 329.00 75.670101 Bhisti day 0.100 363.00 36.30

    9999 Brushes, sand paper etc. L.S. 7.150 1.78 12.739999 Sundries L.S. 8.060 1.78 14.35

    TOTAL 498.17Add Water Charges @ 1% 4.98

    TOTAL 503.15Add CPOH @ 15% 75.47

    Cost of 10 sqm 578.62

    Cost of 1 sqm 57.86Say 57.85

  • 8/9/2019 DAR14-Vol2

    36/710

    SUB HEAD : 13 - FINISHING 716

    13.45 Finishing walls with textured exterior paint of required shade :

    13.45.1 New work (Two or more coats applied @ 3.28 ltr/ 10 sqm) over and including priming coat of exteriorprimer applied @ 2.20 kg/ 10 sqm

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    8507 Textured exterior paint litre 3.280 240.00 787.200809 Exterior primer kilogram 2.200 40.00 88.009999 Carriage of material L.S. 1.560 1.78 2.78

    LABOUR:

    0131 Painter day 0.600 399.00 239.400115 Coolie day 0.300 329.00 98.70

    0101 Bhisti day 0.050 363.00 18.159999 Brushes, sand paper etc. L.S. 7.020 1.78 12.50

    9999 Sundries L.S. 8.060 1.78 14.35

    TOTAL 1261.08

    Add Water Charges @ 1% 12.61TOTAL 1273.69

    Add CPOH @ 15% 191.05Cost of 10 sqm 1464.74

    Cost of 1 sqm 146.47Say 146.45

    13.46 Finishing walls with Acrylic Smooth exterior paint of required shade :

    13.46.1 New work (Two or more coat applied @ 1.67 ltr/ 10 sqm over and including priming coat of exterior primerapplied @ 2.20 kg/ 10 sqm)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:8505 Acrylic exterior paint litre 1.670 180.00 300.60

    0809 Exterior primer kilogram 2.200 40.00 88.009999 Carriage of material L.S. 1.560 1.78 2.78

    LABOUR:

    0131 Painter day 0.600 399.00 239.400115 Coolie day 0.300 329.00 98.70

    0101 Bhisti day 0.050 363.00 18.159999 Brushes, sand paper etc. L.S. 7.150 1.78 12.73

    9999 Sundries L.S. 8.060 1.78 14.35

    TOTAL 774.71

    Add Water Charges @ 1% 7.75TOTAL 782.46

    Add CPOH @ 15% 117.37Cost of 10 sqm 899.83

    Cost of 1 sqm 89.98

    Say 90.00

    13.47 Finishing walls with Premium Acrylic Smooth exterior paint with Silicone additives of required shade:

    13.47.1 New work (Two or more coats applied @ 1.43 ltr/ 10 sqm over and including priming coat of exterior

    primer applied @ 2.20 kg/ 10 sqm)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:

    8506 Premium Acrylic exterior paint litre 1.430 240.00 343.20

    0809 Exterior primer kilogram 2.200 40.00 88.009999 Carriage of material L.S. 1.560 1.78 2.78

  • 8/9/2019 DAR14-Vol2

    37/710

    SUB HEAD : 13 - FINISHING  717

    Code No Description Unit Quantity Rate  `  Amount ` 

    LABOUR:

    0131 Painter day 0.600 399.00 239.40

    0115 Coolie day 0.300 329.00 98.70

    0101 Bhisti day 0.050 363.00 18.15

    9999 Brushes, sand paper etc. L.S. 7.150 1.78 12.73

    9999 Sundries L.S. 8.060 1.78 14.35

    TOTAL 817.31

    Add Water Charges @ 1% 8.17

    TOTAL 825.48

    Add CPOH @ 15% 123.82

    Cost of 10 sqm 949.30

    Cost of 1 sqm 94.93

    Say 94.95

    13.48 Finishing with Deluxe Multi surface paint system for interiors and exteriors using Primer as per

    manufacturers specifications :

    13.48.1 Two or more coats applied on walls @ 1.25 ltr/10 sqm over and including one coat of special primer

    applied @ 0.75 ltr /10 sqmCode No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    8504 Multi surface paint litre 1.250 290.00 362.50

    8509 Special Primer (C.W.) litre 0.750 150.00 112.50

    9999 Carriage of material L.S. 1.560 1.78 2.78

    LABOUR:

    0131 Painter day 0.600 399.00 239.40

    0115 Coolie day 0.300 329.00 98.70

    0101 Bhisti day 0.050 363.00 18.15

    9999 Brushes, sand paper etc. L.S. 7.020 1.78 12.50

    9999 Sundries L.S. 8.060 1.78 14.35

    TOTAL 860.88

    Add Water Charges @ 1% 8.61

    TOTAL 869.49

    Add CPOH @ 15% 130.42

    Cost of 10 sqm 999.91

    Cost of 1 sqm 99.99

    Say 100.00

    13.48.2 Painting wood work with Deluxe Multi Surface Paint of required shade. Two or more coat applied @ 0.90

    ltr/ 10 sqm over an under coat of primer applied @ 0.75 ltr/ 10 sqm of approved brand and manufacture

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    8504 Multi surface paint litre 0.900 290.00 261.00

    8509 Special Primer (C.W.) litre 0.750 150.00 112.50

    9999 Carriage of material L.S. 1.560 1.78 2.78

    LABOUR:

    0131 Painter day 0.600 399.00 239.40

    0115 Coolie day 0.300 329.00 98.70

    0101 Bhisti day 0.050 363.00 18.15

    9999 Brushes, sand paper etc. L.S. 7.020 1.78 12.50

  • 8/9/2019 DAR14-Vol2

    38/710

    SUB HEAD : 13 - FINISHING 718

    Code No Description Unit Quantity Rate  `  Amount ` 

    9999 Sundries L.S. 8.060 1.78 14.35

    TOTAL 759.38

    Add Water Charges @ 1% 7.59

    TOTAL 766.97

    Add CPOH @ 15% 115.05

    Cost of 10 sqm 882.02

    Cost of 1 sqm 88.20

    Say 88.20

    13.48.3 Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two or more coat applied @

    0.90 ltr/ 10 sqm over an under coat of primer applied @ 0.80 ltr/ 10 sqm of approved brand and manufacture

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    8504 Multi surface paint litre 0.900 290.00 261.00

    8510 Metal Primer (U.G.) litre 0.800 160.00 128.00

    9999 Carriage of material L.S. 1.560 1.78 2.78

    LABOUR:0131 Painter day 0.600 399.00 239.40

    0115 Coolie day 0.300 329.00 98.70

    0101 Bhisti day 0.050 363.00 18.15

    9999 Brushes, sand paper etc. L.S. 7.020 1.78 12.50

    9999 Sundries L.S. 8.060 1.78 14.35

    TOTAL 774.88

    Add Water Charges @ 1% 7.75

    TOTAL 782.63

    Add CPOH @ 15% 117.39

    Cost of 10 sqm 900.02

    Cost of 1 sqm 90.00

    Say 90.00

    13.50 Applying priming coat:

    13.50.1 With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft

    wood)

    Details of cost for 10 sqm 

    Code No Description Unit Quantity Rate  `  Amount ` 

    MATERIAL:

    0823 Pink primer (for wood) litre 0.750 90.00 67.50

    9999 Putty L.S. 2.730 1.78 4.86

    9999 Carriage L.S. 0.390 1.78 0.69

    LABOUR:

    0131 Painter day 0.250 399.00 99.75

    0115 Coolie day 0.250 329.00 82.25

    9999 Brushes, sand paper etc. L.S. 5.330 1.78 9.499999 Sundries L.S. 10.790 1.78 19.21

    TOTAL 283.75

    Add Water Charges @ 1% 2.84

    TOTAL 286.59

    Add CPOH @ 15% 42.99

    Cost of 10 sqm 329.58

    Cost of 1 sqm 32.96

    Say 32.95

  • 8/9/2019 DAR14-Vol2

    39/710

    SUB HEAD : 13 - FINISHING  719

    13.50.2 With ready mixed aluminium primer of approved brand and manufacture on resinous wood and plywood

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:

    4201 Aluminium primer litre 0.750 130.00 97.509999 Putty L.S. 2.730 1.78 4.86

    9999 Carriage L.S. 0.390 1.78 0.69LABOUR:0131 Painter day 0.250 399.00 99.750115 Coolie day 0.250 329.00 82.259999 Brushes, sand paper etc. L.S. 5.330 1.78 9.499999 Sundries L.S. 10.790 1.78 19.21

    TOTAL 313.75Add Water Charges @ 1% 3.14

    TOTAL 316.89Add CPOH @ 15% 47.53

    Cost of 10 sqm 364.42Cost of 1 sqm 36.44

    Say 36.45

    13.50.3 With ready mixed red oxide zinc chromate primer of approved brand and manufacture on steel galvanisediron/steel works

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:

    4202 Red oxide Zinc chromate primer litre 0.540 70.00 37.809999 Carriage L.S. 0.520 1.78 0.93

    LABOUR:0131 Painter day 0.240 399.00 95.760115 Coolie day 0.240 329.00 78.969999 Brushes, sand paper including sundries L.S. 10.790 1.78 19.21

    TOTAL 232.66Add Water Charges @ 1% 2.33

    TOTAL 234.99Add CPOH @ 15% 35.25

    Cost of 10 sqm 270.24Cost of 1 sqm 27.02

    Say 27.00

    13.50.4 With ready mixed red oxide zinc chromate primer of approved brand and manufacture on steel work(second coat)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:

    4202 Red oxide Zinc chromate primer litre 0.360 70.00 25.209999 Carriage L.S. 0.390 1.78 0.69

    LABOUR:

    0131 Painter day 0.120 399.00 47.880115 Coolie day 0.120 329.00 39.489999 Brushes, sand paper including sundries L.S. 7.150 1.78 12.73

    TOTAL 125.98Add Water Charges @ 1% 1.26

    TOTAL 127.24Add CPOH @ 15% 19.09

    Cost of 10 sqm 146.33Cost of 1 sqm 14.63

    Say 14.65

  • 8/9/2019 DAR14-Vol2

    40/710

    SUB HEAD : 13 - FINISHING 720

    13.51 Painting with silicon & acrylic emulsion based water thinnable sealer of approved brand and manufactureon wet or patchy portion of plastered surfaces:

    13.51.1 One coat

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    0801 Silicon and acrylic emulsion litre 1.800 200.00 360.009999 Carriage of material L.S. 0.520 1.78 0.939999 Putty etc. L.S. 2.730 1.78 4.86

    LABOUR:

    0131 Painter day 0.270 399.00 107.730115 Coolie day 0.270 329.00 88.83

    9999 Brushes, sand paper etc. L.S. 5.330 1.78 9.499999 Sundries L.S. 10.790 1.78 19.21

    TOTAL 591.05

    Add Water Charges @ 1% 5.91

    TOTAL 596.96Add CPOH @ 15% 89.54

    Cost of 10 sqm 686.50Cost of 1 sqm 68.65

    Say 68.65

    13.51.2 Two coats

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:0801 Silicon and acrylic emulsion litre 2.880 200.00 576.00

    9999 Carriage of material L.S. 0.520 1.78 0.939999 Putty etc. L.S. 2.730 1.78 4.86

    LABOUR:0131 Painter day 0.430 399.00 171.57

    0115 Coolie day 0.430 329.00 141.47

    9999 Brushes, sand paper etc. L.S. 8.530 1.78 15.18

    9999 Sundries L.S. 17.260 1.78 30.72

    TOTAL 940.73

    Add Water Charges @ 1% 9.41

    TOTAL 950.14Add CPOH @ 15% 142.52

    Cost of 10 sqm 1092.66Cost of 1 sqm 109.27

    Say 109.25

    13.52 Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer’s

    specifications including appropriate priming coat, preparation of surface, etc. complete.

    13.52.1 On steel work

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:4202 Red oxide Zinc chromate primer litre 0.750 70.00 52.50

    9999 Putty L.S. 2.730 1.78 4.86

    9999 Carriage L.S. 0.390 1.78 0.69LABOUR:

    0131 Painter day 0.250 399.00 99.750115 Coolie day 0.250 329.00 82.25

    9999 Brushes, sand paper etc. L.S. 5.460 1.78 9.72

  • 8/9/2019 DAR14-Vol2

    41/710

    SUB HEAD : 13 - FINISHING  721

    Code No Description Unit Quantity Rate  `  Amount ` 

    9999 Sundries L.S. 10.660 1.78 18.97

    EPOXY PAINTING

    MATERIAL:

    7239 Epoxy paint litre 1.250 250.00 312.50

    9999 Carriage of material L.S. 1.430 1.78 2.55LABOUR:

    0131 Painter day 0.540 399.00 215.46

    0115 Coolie day 0.540 329.00 177.66

    9999 Putty, brushes, sand paper etc. L.S. 6.760 1.78 12.03

    9999 Sundries L.S. 8.060 1.78 14.35

    TOTAL 1003.29

    Add Water Charges @ 1% 10.03

    TOTAL 1013.32

    Add CPOH @ 15% 152.00

    Cost of 10 sqm 1165.32

    Cost of 1 sqm 116.53

    Say 116.55

    13.52.2 On concrete work

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    PRIMING COAT

    MATERIAL:

    0821 Distemper primer litre 0.840 90.00 75.60

    9999 Putty L.S. 13.520 1.78 24.07

    9999 Carriage L.S. 0.520 1.78 0.93

    LABOUR:

    0131 Painter day 0.250 399.00 99.75

    0115 Coolie day 0.250 329.00 82.25

    9999 Brushes, sand paper etc. L.S. 2.730 1.78 4.86

    9999 Sundries L.S. 8.060 1.78 14.35

    EPOXY PAINTING

    MATERIAL:

    7239 Epoxy paint litre 1.210 250.00 302.50

    9999 Materials for filling in holes and cracks L.S. 6.760 1.78 12.03

    9999 Carriage of material L.S. 1.430 1.78 2.55

    LABOUR:

    0131 Painter day 0.540 399.00 215.46

    0115 Coolie day 0.540 329.00 177.66

    9999 Putty, brushes, sand paper etc. L.S. 10.790 1.78 19.21

    9999 Sundries L.S. 6.760 1.78 12.03

    TOTAL 1043.25

    Add Water Charges @ 1% 10.43

    TOTAL 1053.68

    Add CPOH @ 15% 158.05

    Cost of 10 sqm 1211.73

    Cost of 1 sqm 121.17

    Say 121.15

  • 8/9/2019 DAR14-Vol2

    42/710

    SUB HEAD : 13 - FINISHING 722

    13.53 Painting on G.S. sheet with synthetic enamel paint of approved brand and manufacture of required colour

    to give an even shade:

    13.53.1 New work (two or more coats) including a coat of approved steel primer but excluding a coat of mordant

    solution.

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm PRIMING COAT

    MATERIAL:

    4202 Red oxide Zinc chromate primer litre 0.360 70.00 25.20

    9999 Carriage L.S. 0.390 1.78 0.69

    LABOUR:

    0131 Painter day 0.120 399.00 47.88

    0114 Beldar day 0.120 329.00 39.48

    9999 Brushes, sand paper etc. L.S. 7.150 1.78 12.73

    EPOXY PAINTING

    MATERIAL:

    0834 Synthetic enamel paint in all shades except black or

    chocolate shade litre 0.800 160.00 128.00

    9999 Carriage L.S. 1.430 1.78 2.55

    LABOUR:

    0131 Painter day 0.540 399.00 215.46

    0115 Coolie day 0.540 329.00 177.66

    9999 Putty, brushes, sand paper etc. L.S. 6.760 1.78 12.03

    9999 Sundries L.S. 8.060 1.78 14.35

    TOTAL 676.03

    Add Water Charges @ 1% 6.76

    TOTAL 682.79

    Add CPOH @ 15% 102.42

    Cost of 10 sqm 785.21

    Cost of 1 sqm 78.52

    Say 78.50

    13.54 Applying a coat of mordant solution on G.S. sheet:

    13.54.1 With a solution of 38 gms of copper acetate in a litre of soft water

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 25 sqm 

    MATERIAL:

    4203 Copper acetate kilogram 0.038 300.00 11.40

    9999 Soft water L.S. 1.820 1.78 3.24

    9999 Carriage L.S. 0.910 1.78 1.62

    LABOUR:

    0131 Painter day 0.600 399.00 239.40

    0115 Coolie day 0.600 329.00 197.40

    9999 Brushes, sand paper etc. L.S. 35.880 1.78 63.879999 Sundries L.S. 35.880 1.78 63.87

    TOTAL 580.80

    Add Water Charges @ 1% 5.81

    TOTAL 586.61

    Add CPOH @ 15% 87.99

    Cost of 25 sqm 674.60

    Cost of 1 sqm 26.98

    Say 27.00

  • 8/9/2019 DAR14-Vol2

    43/710

    SUB HEAD : 13 - FINISHING  723

    13.54.2 With a solution made of 13 gms of hydrochloric acid in a solution of 13 gms each of copper chloride,

    copper nitrate and ammonium chloride dissolved in a litre of soft water

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 25 sqm 

    MATERIAL:

    4204 Hydrochloric acid kilogram 0.013 35.00 0.45

    4205 Copper chloride kilogram 0.013 300.00 3.904206 Copper nitrate kilogram 0.013 220.00 2.86

    4207 Ammonium chloride kilogram 0.013 20.00 0.26

    9999 Soft water L.S. 1.820 1.78 3.24

    9999 Carriage L.S. 0.910 1.78 1.62

    LABOUR:

    0131 Painter day 0.600 399.00 239.40

    0115 Coolie day 0.600 329.00 197.40

    9999 Brushes, sand paper etc. L.S. 35.880 1.78 63.87

    9999 Sundries L.S. 35.880 1.78 63.87

    TOTAL 576.87

    Add Water Charges @ 1% 5.77

    TOTAL 582.64

    Add CPOH @ 15% 87.40Cost of 25 sqm 670.04

    Cost of 1 sqm 26.80

    Say 26.80

    13.55 Painting (two or more coats) on rain water, soil, waste and vent pipes and fittings with black anticorrosive

    bitumastic paint of approved brand and manufacture, over and including a priming of ready mixed zinc

    chromate yellow primer on new work:

    13.55.1 100 mm diameter pipes

    Code No Description Unit Quantity Rate  `  Amount ` 

    Area=22/7x106.4mm x30m=10.032sqm

    MATERIAL:

    4202 Red oxide Zinc chromate primer litre 0.540 70.00 37.809999 Carriage L.S. 0.520 1.78 0.93

    LABOUR:

    0131 Painter day 0.240 399.00 95.76

    0115 Coolie day 0.240 329.00 78.96

    9999 Brushes, sand paper etc. L.S. 10.790 1.78 19.21

    MATERIAL:

    0828 Anticorrosive bituminous paint (black) litre 0.950 115.00 109.25

    9999 Carriage L.S. 1.430 1.78 2.55

    LABOUR:

    0131 Painter day 0.540 399.00 215.46

    0115 Coolie day 0.540 329.00 177.66

    9999 Putty , sand paper etc. L.S. 5.330 1.78 9.49

    9999 Sundries L.S. 8.060 1.78 14.35

    9999 Wire brushes for cleaning L.S. 5.330 1.78 9.499999 Extra for delays L.S. 61.100 1.78 108.76

    TOTAL 879.67

    Add Water Charges @ 1% 8.80

    TOTAL 888.47

    Add CPOH @ 15% 133.27

    Cost of 30 metre 1021.74

    Cost of 1 metre 34.06

    Say 34.05

  • 8/9/2019 DAR14-Vol2

    44/710

    SUB HEAD : 13 - FINISHING 724

    13.55.2 150 mm diameter pipes

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 30 mtrs 

    Area =22/7 x 0.15720 x 30 m = 14.82

    MATERIAL:

    4202 Red oxide Zinc chromate primer litre 0.800 70.00 56.00

    LABOUR:

    0131 Painter day 0.360 399.00 143.64

    0115 Coolie day 0.360 329.00 118.44

    9999 Brushes, sand paper etc. L.S. 15.990 1.78 28.46

    9999 Carriage L.S. 0.910 1.78 1.62

    MATERIAL:

    0828 Anticorrosive bituminous paint (black) litre 1.410 115.00 162.15

    9999 Carriage L.S. 2.080 1.78 3.70

    LABOUR:

    0131 Painter day 0.800 399.00 319.20

    0115 Coolie day 0.800 329.00 263.20

    9999 Putty , sand paper etc. L.S. 8.600 1.78 15.31

    9999 Sundries L.S. 11.960 1.78 21.299999 Wire brushes for cleaning L.S. 7.150 1.78 12.73

    9999 extra for delays L.S. 94.120 1.78 167.53

    TOTAL 1313.27

    Add Water Charges @ 1% 13.13

    TOTAL 1326.40

    Add CPOH @ 15% 198.96

    Cost of 30 metre 1525.36

    Cost of 1 metre 50.85

    Say 50.85

    13.56 Painting (two or more coats) on rain water, soil, waste and vent pipes and fittings with synthetic enamel

    paint of approved brand and manufacture and required colour over a priming coat of approved steel

    primer on new work.13.56.1 100 mm diameter pipes

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 30 mtrs 

    Area=22/7 x 106.40/1000 x 30 m = 10.032

    MATERIAL:

    4202 Red oxide Zinc chromate primer litre 0.540 70.00 37.80

    9999 Carriage L.S. 0.520 1.78 0.93

    LABOUR:

    0131 Painter day 0.240 399.00 95.76

    0115 Coolie day 0.240 329.00 78.96

    9999 Sundries L.S. 10.790 1.78 19.21

    MATERIAL:

    0833 Synthetic enamel paint in black or chocolate shade litre 1.160 180.00 208.80

    9999 Carriage L.S. 1.430 1.78 2.55

    9999 Putty , sand paper etc. L.S. 5.330 1.78 9.49

    LABOUR:

    0131 Painter day 0.540 399.00 215.46

    0115 Coolie day 0.540 329.00 177.66

    9999 Sundries L.S. 6.760 1.78 12.03

    9999 Wire brushes for cleaning L.S. 11.960 1.78 21.29

  • 8/9/2019 DAR14-Vol2

    45/710

    SUB HEAD : 13 - FINISHING  725

    Code No Description Unit Quantity Rate  `  Amount ` 

    9999 extra for delays L.S. 66.430 1.78 118.25

    TOTAL 998.19Add Water Charges @ 1% 9.98

    TOTAL 1008.17Add CPOH @ 15% 151.23

    Cost of 30 metre 1159.40Cost of 1 metre 38.65

    Say 38.65

    13.56.2 150 mm diameter pipes

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 30 mtrs Area = 22/7 x157.2mm x30m =14.82sqmMATERIAL:

    4202 Red oxide Zinc chromate primer litre 0.800 70.00 56.009999 Carriage L.S. 0.650 1.78 1.16

    LABOUR:0131 Painter day 0.360 399.00 143.640115 Coolie day 0.360 329.00 118.44

    9999 Sundries L.S. 15.990 1.78 28.46MATERIAL:

    0833 Synthetic enamel paint in black or chocolate shade litre 1.720 180.00 309.609999 Carriage L.S. 2.080 1.78 3.709999 Putty , sand paper etc. L.S. 7.930 1.78 14.12

    LABOUR:0131 Painter day 0.800 399.00 319.200115 Coolie day 0.800 329.00 263.209999 Sundries L.S. 10.010 1.78 17.829999 Wire brushes for cleaning L.S. 17.810 1.78 31.709999 extra for delays L.S. 101.400 1.78 180.49

    TOTAL 1487.53Add Water Charges @ 1% 14.88

    TOTAL 1502.41

    Add CPOH @ 15% 225.36Cost of 30 metre 1727.77

    Cost of 1 metre 57.59Say 57.60

    13.57 Painting with oil type wood preservative of approved brand and manufacture:

    13.57.1 New work (two or more coats)

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:

    0859 Oil type wood preservative litre 1.000 150.00 150.009999 Carriage of material L.S. 0.520 1.78 0.93

    LABOUR:0131 Painter day 0.150 399.00 59.850115 Coolie day 0.150 329.00 49.359999 Brushes etc. L.S. 4.160 1.78 7.409999 Sundries L.S. 3.900 1.78 6.94

    TOTAL 274.47Add Water Charges @ 1% 2.74

    TOTAL 277.21Add CPOH @ 15% 41.58

    Cost of 10 sqm 318.79Cost of 1 sqm 31.88

    Say 31.90

  • 8/9/2019 DAR14-Vol2

    46/710

    SUB HEAD : 13 - FINISHING 726

    13.58 Providing and applying two coats of fire retardant paint on cleaned wood/ply surface @ 3.5 sqm per litre

    per coat including preparation of base surface as per recommendations of manufacturer to make the

    surface fire retardant.

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    7240 Fire retardant paint litre 5.700 300.00 1710.009999 Carriage of material L.S. 1.430 1.78 2.55

    LABOUR:

    0131 Painter day 0.540 399.00 215.46

    0114 Beldar day 0.540 329.00 177.66

    9999 Putty , brushes sand paper etc. L.S. 6.760 1.78 12.03

    9999 Sundries L.S. 8.060 1.78 14.35

    TOTAL 2132.05

    Add Water Charges @ 1% 21.32

    TOTAL 2153.37

    Add CPOH @ 15% 323.01

    Cost of 10 sqm 2476.38

    Cost of 1 sqm 247.64

    Say 247.65

    13.59 Coal tarring two coats on new work using 0.16 litre and 0.12 litre coal tar per sqm in the first coat and

    second coat respectively.

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    9999 Lime L.S. 1.430 1.78 2.55

    0324 Coal Tar litre 2.800 30.00 84.00

    9999 Carriage of material L.S. 1.430 1.78 2.55

    0771 Kerosene oil litre 0.500 48.00 24.00

    LABOUR:

    0114 Beldar day 0.430 329.00 141.47

    9999 Brushes etc. L.S. 5.330 1.78 9.49

    9999 Sundries L.S. 5.330 1.78 9.49

    TOTAL 273.55

    Add Water Charges @ 1% 2.74

    TOTAL 276.29

    Add CPOH @ 15% 41.44

    Cost of 10 sqm 317.73

    Cost of 1 sqm 31.77

    Say 31.75

    13.60 Wall painting with acrylic emulsion paint of approved brand and manufacture to give an even shade:

    13.60.1 Two or more coats on new work

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm MATERIAL:

    0835 Plastic emulsion paint litre 1.210 210.00 254.10

    9999 Materials for filling in holes and cracks

    (putty etc.) L.S. 6.760 1.78 12.03

    9999 Carriage of material L.S. 1.430 1.78 2.55

    LABOUR:

    0131 Painter day 0.540 399.00 215.46

    0115 Coolie day 0.540 329.00 177.66

    9999 Brushes, sand paper etc. L.S. 10.790 1.78 19.21

  • 8/9/2019 DAR14-Vol2

    47/710

    SUB HEAD : 13 - FINISHING  727

    Code No Description Unit Quantity Rate  `  Amount ` 

    9999 Sundries L.S. 6.760 1.78 12.03

    TOTAL 693.04

    Add Water Charges @ 1% 6.93

    TOTAL 699.97

    Add CPOH @ 15% 105.00

    Cost of 10 sqm 804.97

    Cost of 1 sqm 80.50

    Say 80.50

    13.61 Painting with synthetic enamel paint of approved brand and manufacture to give an even shade:

    13.61.1 Two or more coats on new work

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    0833 Synthetic enamel paint in black or chocolate shade litre 1.160 180.00 208.80

    9999 Materials for filling in holes and cracks (putty etc.) L.S. 5.330 1.78 9.49

    9999 Carriage L.S. 1.430 1.78 2.55

    LABOUR:0131 Painter day 0.540 399.00 215.46

    0115 Coolie day 0.540 329.00 177.66

    9999 Brushes, sand paper etc. L.S. 6.760 1.78 12.03

    9999 Sundries L.S. 8.060 1.78 14.35

    TOTAL 640.34

    Add Water Charges @ 1% 6.40

    TOTAL 646.74

    Add CPOH @ 15% 97.01

    Cost of 10 sqm 743.75

    Cost of 1 sqm 74.38

    Say 74.40

    13.62 Painting with synthetic enamel paint of approved brand and manufacture of required colour to give aneven shade:

    13.62.1 Two or more coats on new work over an under coat of suitable shade with ordinary paint of approved

    brand and manufacture.

    Code No Description Unit Quantity Rate  `  Amount ` 

    Details of cost for 10 sqm 

    MATERIAL:

    0823 Pink primer (for wood) litre 0.750 90.00 67.50

    9999 Putty