data center measurement
DESCRIPTION
Data Center Measurement - Building An ROI Baseline Establishing a baseline measurement of your data center is an important first step in developing a meaningful ROI for any data center project. The cost of energy has recently exceeded the cost of IT equipment; understanding your energy footprint in terms of power consumption and cooling demand has become an important management tool. to view the recorded webinar presentation, please visit http://www.42u.com/measurement-techniques-webinar.htmTRANSCRIPT
![Page 1: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/1.jpg)
42U Confidential ©2008 42U All rights reserved Slide 1
Data Center Measurement – Building An ROI Baseline
August 22, 2008
________________________________
![Page 2: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/2.jpg)
Overview
• Big Picture– Why Measure– What to Measure– How To Measure
• Visualization Primer• Case Study• Summary• Q&A
42U Confidential ©2008 42U All rights reserved Slide 2
![Page 3: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/3.jpg)
Why Measure
• Service Level Agreement (SLA)• Information Technology
Infrastructure Library (ITIL)• Total Cost of Ownership (TCO)• Actual Versus Designed• Stranded Capacity• “Can’t Manage What You Can’t
Measure”
42U Confidential ©2008 42U All rights reserved Slide 3
![Page 4: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/4.jpg)
Energy Cost Projection
42U Confidential ©2008 42U All rights reserved Slide 4
Source: Aperture, Greener Pastures for Your Data Center
![Page 5: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/5.jpg)
Energy Benchmark
• Established Benchmark
• Enables Comparison
42U Confidential ©2008 42U All rights reserved Slide 5
Source: The Green Grid
![Page 6: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/6.jpg)
Energy Consumers
• 70% of Power Consumption Goes to the Infrastructure
• Over Twice that of the IT Equipment
42U Confidential ©2008 42U All rights reserved Slide 6
Source: The Green Grid, Guidelines for Energy-Efficient Datacenters
![Page 7: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/7.jpg)
What To Measure
• Power
• Temperature
• Air Pressure
• Humidity
• Water Flow & Temperature
42U Confidential ©2008 42U All rights reserved Slide 7
![Page 8: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/8.jpg)
Best Practice Opportunities
• Chilled Water
• Fans
42U Confidential ©2008 42U All rights reserved Slide 8
Source: Accenture Data Center Energy Forecast Report, July11, 2008
![Page 9: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/9.jpg)
How To Measure
• Level of Precision
• Alternatives– Point In Time– Ongoing– Real-Time
• Modeling Tool Requirements
42U Confidential ©2008 42U All rights reserved Slide 9
![Page 10: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/10.jpg)
Visualization Tools
• System Admins
• Network Admins
• Data Center Managers
42U Confidential ©2008 42U All rights reserved Slide 10
![Page 11: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/11.jpg)
Real-Time Imaging
42U Confidential ©2008 42U All rights reserved Slide 11
![Page 12: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/12.jpg)
Real-Time Imaging
42U Confidential ©2008 42U All rights reserved Slide 12
![Page 13: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/13.jpg)
CFD Visualization
Computational Fluid Dynamics (CFD)
42U Confidential ©2008 42U All rights reserved Slide 13
![Page 14: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/14.jpg)
Case Study
• Lawrence Berkeley National Lab– Continued Increase in Demand– Data Center Capacity ~2011– Strategic Imperative on Efficiency
• Study Results– Improve Airflow– Virtualization– Water Cooling
42U Confidential ©2008 42U All rights reserved Slide 14
![Page 15: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/15.jpg)
Efficiency MeasurementLife-CycleTM
42U Confidential ©2008 42U All rights reserved Slide 15
Reconfiguration
• Measurement Points• Measurement Object Database• Security
• Hardware Configuration & Testing• Network Configuration & Testing• Sensor Installation• Software Installation• Network Verification
• Data Collection• Analysis• System Management
• Facilities Data• IT Infrastructure Data• IT Equipment Data• Integration Requirements
Survey
Planning
Installation
Measurement
![Page 16: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/16.jpg)
Wireless Sensor Network
42U Confidential ©2008 42U All rights reserved Slide 16
![Page 17: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/17.jpg)
Confirmation of Fundamentals
• Impact of a Single Blanking Panel
• Consistent Results For– Floor Leaks– Tile
Arrangement
Top of rack
Middle of rack
42U Confidential ©2008 42U All rights reserved Slide 17
![Page 18: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/18.jpg)
Floor Tile Tuning
• One Day Time Investment– 24 Converted
from Perforated to Solid
– 6 Converted from High- to Low- Flow
– 4 Converted from Low- to High- Flow
Before
After
42U Confidential ©2008 42U All rights reserved Slide 18
![Page 19: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/19.jpg)
Results of Tuning
• Real-Time Verification
• Eliminates Guesswork
Under-Floor Pressure
Rack-Top Temperatures
42U Confidential ©2008 42U All rights reserved Slide 19
![Page 20: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/20.jpg)
Air Flow Tuning
42U Confidential ©2008 42U All rights reserved Slide 20
![Page 21: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/21.jpg)
Measureable Correlations
• Real-Time Feedback
• Enhanced Knowledge of Data Center Redundancy Characteristics
Under-Floor Pressure
Rack-Top Temperatures
42U Confidential ©2008 42U All rights reserved Slide 21
![Page 22: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/22.jpg)
Summary
• Planning– What To Measure– How To Measure
• Interpreting Results
• Efficiency Improvement Plan– Rank By ROI
42U Confidential ©2008 42U All rights reserved Slide 22
![Page 23: Data Center Measurement](https://reader035.vdocument.in/reader035/viewer/2022062615/5482631db07959650c8b474b/html5/thumbnails/23.jpg)
Q&A
42U Confidential ©2008 42U All rights reserved Slide 23
For More InformationContact Your 42U
Data Center Efficiency Consultant:
1-800-638-2638 or www.42U.com
For a Copyof
Today’s Presentation Email:
Thank You