dawn hub successfully meeting market growth€¦ · dawn compressor (2017) lobo d compressor (2017)...
TRANSCRIPT
1
Paolo Mastronardi, Manager, Business Development
November 16, 2017
Dawn Hub – Successfully Meeting Market Growth
2
Agenda
• Enbridge/Union Gas Overview
• The Value of Dawn – Defining
Liquidity
Supply & Demand at Dawn
Infrastructure Expansions
Storage Expansion
• Expansions Challenges
• Mitigation
3
Dawn
Enbridge Assets
4
Union Gas
• Major Canadian natural gas storage, transmission and distribution company based in Ontario
• Over 100 years of experience and safe service to customers
• Dawn Storage facility – largest underground storage facility in Canada
• Dawn Hub, the second most traded hub in North America
• Assets of $8.2 billion, ~1.5 million customers, ~2,300 employees
• One of Canada's Top 100 Employers 2011-2017
• An Enbridge company
1.5 Million Retail Customers
1.2Tcf
Pipeline Throughput
65,390 km / 40,630 mi Distribution Pipe
278 Bcf
Storage Capacity
4,850 km / 3,015mi Transmission Pipe
5
LIQUID
HUB
The Value of Dawn – Defining Liquidity
Storage
Gas Supply
Take Away
Buyers & Sellers
Price Discovery
Trading Activity
6
Sourcing Supply at the Dawn Hub
Winter 3.2 Bcf/d Summer 3.0 Bcf/d
Gas Supply
7
Existing Supply
New Supply
DAWN HUB
Sourcing Supply at the Dawn Hub Diversity = Reliability
Abundant and diverse natural gas serving the growing needs of the market
Gas Supply
DAWN
LTFP
NEXUS
ROVER
8
Average Daily Dawn System Demand
Take Away
Winter 4.2 Bcf/d Summer 2.4 Bcf/d
Total Peak Demand – ~ 8.7 Bcf/d
9
Brantford-Kirkwall Pipeline (2015)
Parkway West & Parkway D
Compressors (2015)
Lobo C Compressor (2016)
Hamilton-Milton Pipeline (2016)
Dawn Compressor (2017)
Lobo D Compressor (2017)
Bright C Compressor (2017)
Bluewater
St. Clair
Ojibway
Lobo
Bright
Kirkwall
Parkway
Maple
Dawn
Dawn – Downstream Connectivity Expansion Projects
Take Away
10
2015-2017 Dawn Parkway System Growth 1.2 Bcf ~85% contracted by Ontario/Québec LDCs with a 15 year term
Dawn – Downstream Connectivity Utilities Supporting Expansion
2015-2017 Expansion Capacity
Take Away
11
11 DAWN HUB
New markets and growing Dawn demand
The energy
advantage for
Eastern Canada
and U.S.
Northeast
Downstream Connectivity Growing connectivity to meet market demand
Take Away
12
• 278 Bcf – Total Storage
• 120 Bcf total merchant storage
• 5.5 Bcf Peak Day Deliverability
– 3.1 Bcf/d Union Gas
– 2.4 Bcf/d Enbridge Gas Distribution
• Storage Enhancement Projects:
– 2016/17 - 3.2 Bcf incremental storage space
– 2017/18 - ~0.2 Bcf/d of incremental deliverability
– Post 2019 – incremental space
Dawn Storage Growing to Meet Demand
Storage
13
• External Issues:
– Stakeholder requirements differ at federal, provincial and municipal levels
– Permitting process changes
• Internal Issues:
– Growth outpacing available resources
– Definition of roles and responsibilities
• Union’s multi-million expansion project faced some hurdles
Infrastructure Challenges
14
• Stakeholder outreach plan
• Development of a centralized permitting group
• Escalation process when delays occur
• Development of tools to track status
Infrastructure Challenges - Mitigation
www.uniongas.com