day in the life of an ercot operator / shift engineer during the january 6, 2014 eea event jimmy...

37
Day in the life of an ERCOT Operator / Shift Engineer during the January 6, 2014 EEA Event Jimmy Hartmann Manager, System Operations ERCOT Seminar 2015

Upload: nigel-chase

Post on 19-Dec-2015

215 views

Category:

Documents


1 download

TRANSCRIPT

Day in the life of an ERCOT Operator / Shift Engineer during the January 6, 2014 EEA Event

Jimmy HartmannManager, System Operations ERCOT Seminar 2015

2

• Shift Engineer

• Shift Supervisor

• Transmission and Security

• Real-Time

• DC-Tie

• Resource

• RUC

Introductions

3

ERCOT Control Room

4

At the completion of this presentation you will:

• Describe actions taken by ERCOT operators in response to a capacity shortage

• Explain the current process for TCEQ enforcement discretion during an EEA

• Describe ERCOT operator desk specific tasks associated with responding to an extreme cold weather event

• Define the possible Market Notifications issued by ERCOT during an extreme cold weather event

• Identify where Market Participants can locate the ERCOT operator desk procedures

• Explain Operator Authority

Objectives

5

Events of the January 6th, 2014EEA

6

January 5, 2014, a cold weather front swept across the ERCOT region, bringing with it freezing conditions across much of the interconnection the evening of the 5th and into the 6th.

An Advisory for extreme cold weather was issued at 10:00 on January 5th.

Extreme cold weather notifications are called when the daily temperatures are forecasted to remain 32°F or below in the following weather zones:• North Central (NORTH_C)• South Central (SOUTH_C)• Coast (COAST)

Pre-Event Conditions

7

The morning of January 6, 2014, ERCOT entered into emergency operations. The unavailability of generation resources due to outages, derates, and failures to start in conjunction with freezing conditions contributed to the event.

As the load increased due to the morning ramp and generation resource unavailability continued to increase, reserves declined. At 06:52 ERCOT entered level 1 of its Energy Emergency Alert (EEA) plan. EEA level 2 was declared at 07:01

Event Summary

8

At the completion of this presentation you will:

• Describe actions taken by ERCOT operators in response to a capacity shortage

• Explain the current process for TCEQ enforcement discretion during an EEA

• Describe ERCOT operator desk specific tasks associated with responding to an extreme cold weather event

• Define the possible Market Notifications issued by ERCOT during an extreme cold weather event

• Identify where Market Participants can locate the ERCOT operator desk procedures

• Explain Operator Authority

Time-Line of Events

9

Physical Responsive Capability VS. Frequency

10

• Describe actions taken by ERCOT operators in response to a capacity shortage

• Explain the current process for TCEQ enforcement discretion during an EEA

• Describe ERCOT operator desk specific tasks associated with responding to an extreme cold weather event

• Define the possible Market Notifications issued by ERCOT during an extreme cold weather event

• Identify where Market Participants can locate the ERCOT operator desk procedures

• Explain Operator Authority

Load Forecast

11

RUC Operator – Running HRUC

Enough generation to cover load forecast and solve transmission congestion.

Commit any generation with a unit status of OFF or EMR that can be On-line within the timeframe of the emergency.

RUC Operator – Response to a Capacity Shortage

12

Monitors PRC and makes the Hotline calls to the QSEs

• Advisory – PRC below 3000 MW• Watch – PRC below 2500 MW• EEA 1 – PRC below 2300 MW

o Deploy ERS – ERS-30 and / ERS-30 weather-sensitive (June – September, during BH2 or BH3)

o HASL Release (HASL-(Gen+ 5 min load ramp) < = 200 MW manually deploy 500 MW of RRS 10 min. < = 200 MW manually deploy another 500 MW PRC < = 2000 MW deploy remaining RRS

• EEA 2 – Maintain 60 Hz or PRC below 1750 MW o Deploy ERS – ERS-10 and / ERS-10 weather-sensitive (June – September,

during BH2 or BH3) o Deploy Load Resources

• EEA 3 – Maintain 59.8 Hz

Real-Time Operator – Response to a Capacity Shortage

13

Posts the notifications on the MIS Public for each step

• Advisory, Watch, EEA 1, EEA 2 & EEA 3

• Send the XML deployments for Off-line Non-Spin, ERS-30, ERS-10, including weather sensitive ERS and Load Resources

• As Business Hours change, additional services may be deployed

Resource Operator – Response to a Capacity Shortage

14

5 DC-Ties

East – 600 MW

North – 220 MW

Laredo – 100 MW

Railroad – 170 MW

South – 30 MW

Curtail all exports (expect Oklaunion exemption)

Request emergency energy if any available capacity on DC-Ties:• Southwest Power Pool (SPP) for the East or North DC-Ties. • Comision Federal de Electricidad (CFE) through AEP TO for the

South DC-Tie and Laredo VFT and Sharyland for the Railroad DC-Tie.

DC-Tie Operator – Response to a Capacity Shortage

15

Makes the Hotline calls to the TOs

• EEA 1 – PRC below 2300 MWo Deploy Load Management Program - Only on weekdays (except

holidays) during June to September between 1330 and 1900 hours.o Block Load Transfers can be utilized

• EEA 2 – PRC below 1750 MWo Reduce customer loads by using distribution voltage reduction

measures, if deemed beneficial

• EEA 3 – Maintain 59.8o Shed firm load

• Works with Shift Engineer and coordinating with Local Transmission Operators to determine which actions should be taken for constraints that are limiting generation output (effective 5/1/15)

Transmission Operators – Response to a Capacity Shortage

16

• NPRR 642/NOGRR135 – Constraint Management in EEAs (effective 5/1/15)o Evaluate constraints active in SCED, determine which constraints have

the potential to limit generation output Restore transmission elements that are out of service Reconfiguring the transmission system Adjustments to phase angle regulator tap positions 15-minute rating available Determine whether double-circuit failures are at a high risk of

occurring due to system conditions

• Send message from Emergency Notification System• Start internal event reporting

Shift Engineer – Response to a Capacity Shortage

17

• Coordinates and makes sure all steps are completed

Shift Supervisor – Response to a Capacity Shortage

18

EEA Dashboard in EMS

19

Protocol Section 6.5.9.4.2

Operating Guide Section 4.5.3.3

ERCOT Operator Procedures

ERCOT.com

Grid Information>Operating Procedures

Transmission Operators – Transmission and Security Operating Procedure

QSE’s – Real Time Operating Procedure

ERCOT Operator – Response to a Capacity Shortage

20

Market Notice M-C041114-01 was sent out on 4/11/2014

Texas Commission on Environmental Quality (TCEQ) will use its enforcement discretion for power generating facilities when ERCOT is in an EEA situation.

Any Generator who will exceed its air permit limits during an EEA should provide notice of this to the Director of Critical Infrastruction Division of TCEQ by e-mail. No response from them is needed.

Notice of Enforcement Discretion on Air Permitting

21

Extreme Cold Weather

22

• Extreme cold weather notifications will be issued when temperatures and/or wind chill is expected to be below freezing for sustained periods and may abnormally impact load levels or generation availability.

Extreme Cold Weather

23

Makes the Hotline calls to the TOs

• Issue an OCN - when approaching extreme cold weather is approximately 5 days away

o Review Planned outages and existing outages for the possibility of canceling or restoring equipment

o Review and implement winterization procedures o Notify ERCOT of any changes or conditions that could affect reliability

• Issue an Advisory - when approximately 3 days away

• Issue a Watch - when approximately 1 day away with concerns that this event could abnormally impact load levels or generation availability

• Issue an Emergency – only if weather is having an adverse impact on the system (EEA or local transmission emergency)

Transmission Operator – Extreme Cold Weather

24

Makes the Hotline call to the QSEs

• Issue an OCN - when approaching extreme cold weather is approximately 5 days away

o Review fuel supplies and notify ERCOT of any known or anticipated fuel restrictions

o Review Planned Resource outages and consider delaying maintenance or returning form outage early

o Review and implement winterization procedures o Notify ERCOT of any changes or conditions that could affect reliability

• Issue an Advisory - when approximately 3 days away

• Issue a Watch - when approximately 1 day away with concerns that the event could abnormally impact load levels or generation availability

• Issue an Emergency – only if weather is having an adverse impact on the system (EEA or local transmission emergency)

Real-Time Operator – Extreme Cold Weather

25

• Determine if additional Ancillary Services are needed for one or more Operating Hours than were procured in the Day-Ahead

• Guideline for that determination:o Look at Self-Scheduled HSL Margin after DRUC is complete

o When wind chill is expected to be below freezing, a minimum of 600 MW is required for those hours, OR

o When wind chill is expected to be below 20°F, a minimum of 1300 MW is required for those hours.

• Issue a Watch to increase the system-wide A/S requirement above what was procured in the Day-Ahead, give the 30 minute notice for QSEs to update A/S Offers

Resource Operator – Extreme Cold Weather

26

Operator Authority

27

NERC Standards:

• EOP-002-3.1 R1 Each BA and RC shall have the responsibility and clear decision-making authority to take whatever actions are needed to ensure the reliability of its respective area and shall exercise specific authority to alleviate capacity and energy emergencies

• IRO-001-1.1 R3 The RC shall have clear decision-making authority to act and to direct actions to be taken by TOPs, BA, GOP, TSP, LSE, PSE within its RC area to preserve the integrity and reliability of the BES. These actions shall be take without delay, but no longer than 30 minutes

Operator Authority

28

NERC Standards:

• PER-001-0.2 R1 Each TOP and BA shall provide operating personnel with the responsibility and authority to implement real-time actions to ensure the stable and reliable operation of the BES

• TOP-001-1a R1 Each TOP shall have the responsibility and clear decision-making authority to take whatever actions are needed to ensure the reliability of its area and shall exercise specific authority to alleviate operating emergencies

Operator Authority

29

Protocols• 6.5.1.1 – ERCOT Control Area Authority

Operating Guides• 4.5.2 - The ERCOT System Operators have the authority to make

and carry through decisions that are required to operate the ERCOT System during emergency or adverse conditions

Operator Authority

30

QUESTIONS

31

Question 1

1) Which ERCOT desk Operator is monitoring the PRC?

a) ERCOT Shift Engineer

b) ERCOT Shift Supervisor

c) ERCOT Real-Time Operator

d) ERCOT RUC Operator

32

Question 2

2) Identify the current procedure for TCEQ enforcement discretion during an EEA event:

a) Call ERCOT Shift Supervisor

b) Call ERCOT Account Manager

c) Send e-mail to TCEQ

d) Send e-mail to ERCOT CEO

33

Question 3

3) Identify which action TO’s and QSE’s should prepare for an extreme cold weather event:

a) Call in sick during the event

b) Review and implement weatherization and emergency operating procedures

c) No action needed

d) Ask the Texas Regional Entity

34

Question 4

4) What Market Notifications could be issued by ERCOT in preparation for an extreme cold weather event?

a) OCN, Advisory, or Watch

b) Market Bulletin

c) News release

d) E-mail from ERCOT CEO

35

Question 5

5) Identify where Market Participants can locate the ERCOT operator desk procedures

a) Protocols

b) Operating Guides

c) NERC Standards

d) ERCOT.com

36

Question 6

6) Identify Operator Authority:

a) Responsibility and authority to implement real-time actions to ensure the stable and reliable operation of the BES

b) Responsible for saying who can come into the control room

c) Authority to operate transmission equipment

d) Don’t have to listen to my Manager

37

QuestionsQuestions

?