decam in chile
DESCRIPTION
DECam in Chile. Intro to Dark Energy Survey & DECam Project Status of arrivals in Chile Instrument checkout in Chile Schedule for first light. The Dark Energy Survey. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/1.jpg)
1
DECam in Chile
• Intro to Dark Energy
Survey & DECam Project
• Status of arrivals in Chile
• Instrument checkout in Chile
• Schedule for first light
![Page 2: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/2.jpg)
The Dark Energy Survey
• Science goal : Measure the time dependence of the dark energy equation of state, improving the figure of merit defined by the Dark Energy Task Force by a factor of 4-5 compared to present knowledge.
• Method: Conduct a 5000-square degree survey in 5 optical/near IF wavelengths in the Southern Hemisphere, down to ~21st -24th magnitude. Will observe 3 x 108 galaxies and 3 x 104 galaxy clusters, plus 4 x 103 Type Ia supernovae.
• Time scale: Requires ~ 500 observing nights over 5 years on a 4-meter telescope.
2
![Page 3: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/3.jpg)
The DECam Project
• 519 Megapixel CCD camera with 3sq deg FOV
• Low noise readout system• DAQ system• Support systems: cooling,
mirror handling, instrument handling
3
![Page 4: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/4.jpg)
A reminder of the site in Chile
• Cerro Tololo Inter-American Observatory• 2215 m elevation• V.M. Blanco Telescope – 4 meter mirror,
completed in early 1970’s• Excellent astronomical ‘seeing’
4
Merritt All Experimenters Meetting Dec 12 2011
![Page 5: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/5.jpg)
Shipping I.
• 2,501 emails directly related to shipping • 1,034 emails related to coordinating and allowing
shipments• 62 people who have been directly involved. There are • 45 shipments listed (including 5 which have not yet
arrived at CTIO)• Stats (lower limit):
89 boxes17,069 cubic feet147,089 pounds$7,227,159 in shipping value
Merritt All Experimenters Meetting Dec 12 2011
5
![Page 6: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/6.jpg)
Shipping II.
Large heavy parts were shipped by boat
• Oct 2010 F/8 handling system
• June 2011 Cooling system parts
• Aug 2011 Cage, NW platform, etc.
•Dec 2011 Final cooling sys parts
6
Flaugher July 2011
More delicate pieces by truck and air
•May 2011 RASICAM•June 2011 Hexapod, Filter Changer and Shutter•June 2011 Parts of LN2 Cooling system•July 2011 i and z filters (from Japan to Chile) [delayed by volcano eruption]•Aug. 2011 r and y filters (from Japan to Chile)•Nov 2011 The Imager (with CCDs installed!)•Dec 2011 The corrector (enroute now!)
![Page 7: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/7.jpg)
Imager with all Science grade CCDs. Testing completed at Fermilab at end of July
![Page 8: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/8.jpg)
Cooling installation at CTIO July 2011
• Herman, Andy, Rolando, Brenna and Tom went to Chile
• July 7-21 LN2 tank and piping was installed on console roof,
• LN2 circulated to Coude room (where imager will be serviced and tested)
July 7th
July 20th
![Page 9: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/9.jpg)
July 25-Aug. 5: Shutter, FCM, HexapodKen Schultz and Cheryl Jackson replace Herman Andy and Rolando
• Tom Diehl exercising the shutter
• Filter changer operating in the Coudé room
Flaugher July 2011
9
• Hexapod operating at CTIO
• Limit switch issues with hexapod – now resolved
Hexapod
![Page 10: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/10.jpg)
August 3, 2011
• The boat shipment with the prime focus cage, cage cart, imager handling system etc … arrived on the mountain top
• It had been unloaded from the shipping container onto the flatbed shortly after it was taken off the ship, making it possible for Gale & co. to unload the boxes using a forklift.
![Page 11: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/11.jpg)
•Installing Barrel in cage (no shroud on barrel)Barrel weighed (2200 kg)
11
September Trip for Cage Assembly
DECam cage complete!
![Page 12: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/12.jpg)
Training
12
Troublemaker in the Coude room, tests debugging skills of trainer and trainee
![Page 13: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/13.jpg)
The Imager’s Trip
Merritt All Experimenters Meetting Dec 12 2011
13
• Left Fermilab Nov 17• Arrived CTIO Nov 23• Unpacked Nov 30• Under vacuum Dec 2• Cooled down Dec 5• Good full image Dec 6 !!
![Page 14: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/14.jpg)
Shock Logger from Imager Trip
14
Left Ferm
ilab
Landed Santiago
Unloaded at C
TIO
![Page 15: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/15.jpg)
Imager Checkout Team
Merritt All Experimenters Meetting Dec 12 2011
15
![Page 16: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/16.jpg)
Cooled down & Reading Out!
Merritt All Experimenters Meetting Dec 12 2011
16
Dec 5 18:10
Later on Dec. 5
Dec. 6: Beautiful flat field Image!!
![Page 17: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/17.jpg)
Corrector Leaving UCL Earlier Today
• Barrel travels in two pieces: Body with C2,C3,C4,C5Cone with C1
• Left UCL this morningArr Santiago Thurs, CTIO Fri-Sat
17
![Page 18: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/18.jpg)
Still to Do
18
Corrector needs to arrive and have alignment of lenses checked at CTIO
Final filter needs to be completed – 4 of the 5 filters have been manufactured by Asahi in Japan and are at CTIO.
C1 lens in the cone – Nov 29 at UCL
![Page 19: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/19.jpg)
Filters
19
Asahi Filter Plant
50 Mile zone
![Page 20: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/20.jpg)
Safety Issue
Merritt All Experimenters Meetting Dec 12 2011
20
![Page 21: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/21.jpg)
Summary of Current Status
The Imager has arrived undamaged. It is cold and reading out. The Corrector is enroute to CTIO.
By late January the imager and corrector should be reassembled and checked out completing the DECam Project after only 8 years!
![Page 22: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/22.jpg)
Next: The Stars (and Galaxies)!
• CTIO will take the telescope out of service in February.• The old cage will be removed and the new cage (empty) will
be installed/uninstalled to check its fit and the installation procedure
• Next the DECam corrector, hexapod and dummy imager will be put in the cage and it will be reinstalled on the telescope.
• Finally the Imager will be installed, and we will be ready to observe the Southern sky – probably late Spring/early Summer.
• The Dark Energy Survey will start its 5-yr run this Fall.
Merritt All Experimenters Meetting Dec 12 2011
22
![Page 23: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/23.jpg)
DECam Shipping Status
23
En route to CTIO At CTIO Being Packed
Category Shipment Carrier % of total Forecast Date StatusReady for
CD4Filters 1st 2 filters (i, z) Air 40% done At CTIO Y
2nd 2 filters (r,Y) Air 40% done At CTIO YLast filter (g) Air 20% 1/31/2012 In production
RASICam RASICam Air 100% done At CTIO Y
Corrector BarrelCorrector
Air 100% 12/12/2011En route to CTIO Y
SISPI SISPI hardware n/a 90% n/a At CTIO YRemaining S-Links Air 10% done At CTIO Y
Imager Imager & full focal plane Air 100% done At CTIO YFEE Boards & Cables Air 100% done At CTIO Y
Camera Support Equipment
May Boat/CSE 1 Boat 8% done At CTIO Y
May Air/CSE 1/Hexapod Air 25% done At CTIO YBoat/CSE 2 Boat 56.5% done At CTIO Y
May Air CSE 1/Shutter Air 10% done At CTIO YAir/CSE 3 / Crate Cooling Air 0.5% done At CTIO Y
F/8 F/8 Platform Boat 100% done At CTIO Y
CCDs Full focal plane Air 100% doneAt CTIO
Y
Spare CCDs Air? ?LN2 Cooling June Air/LN2 Cooling Air 45% done At CTIO Y
May Boat/LN2 Cooling 1 Boat 25% done At CTIO YAir/ Telescope Utils for LN2 Air 20% done At CTIO Y
Boat/ Telescope Utils for LN2 Boat 20% done At CTIO Y
DECal Shipment 1 Air 10% done At CTIO Y
Shipment 2Air 90% done
En route to CTIO Y
PreCam PreCAM & assoc equip Air 100% done At CTIO done
DECam Shipment Acceptance Status
12/12/2011Acceptance for Export
![Page 24: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/24.jpg)
RASIcam in Action at CTIO
Merritt All Experimenters Meetting Dec 12 2011
24
![Page 25: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/25.jpg)
f/8 Handling System at CTIO
• f/8 Handling System shipped to Chile in Sept. 2010 – first large DECam system completed
• Designed and built at Argonne
25
![Page 26: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/26.jpg)
Cooling Installation – July 2011
![Page 27: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/27.jpg)
July 20, 2011
• Training in shifts on cool down.
• LN2 reached the Coude room and the Jorge/Rolando copper by pass frosted up as planned.
Congratulations to everyone!!
![Page 28: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/28.jpg)
More Scenes from Imager Checkout at CTIO
Merritt All Experimenters Meetting Dec 12 2011
28
![Page 29: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/29.jpg)
Alignment Frame for Corrector Completed at UCL
• Ken Schultz• David Brooks• Brenna
![Page 30: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/30.jpg)
Rotary table alignment frame and laser system in UCL Optics Lab
Plates added for precision x-y motions required for installing lenses in corrector barrel
![Page 31: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/31.jpg)
Oct. 5: C2/C3 are installed in the Body!
C2/C3Next week C4 goes in (from the top) then C5.At that point we will know if our mechanical alignment and pins produce acceptable optical alignment. If so, shipping in early Nov. is on track. Ken and I go back to UCL Oct 24th in case we can help.
![Page 32: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/32.jpg)
DECal part 1: the new flat field screen from TAMU is installed
It was installed by CTIO in October and has been tested with Mosaic – the new screen has 5 times more reflectance in u-band than the old screen.
![Page 33: DECam in Chile](https://reader030.vdocument.in/reader030/viewer/2022032805/56813146550346895d97c460/html5/thumbnails/33.jpg)
ConeC1 lens is protected
behind this coverDec. 5
C1 lens