Contents
Background Project Highlight Power Allocation Project Location Gas Supply Network of ONGC Project Status : Clearances & Permits Project Status : Supply and Construction Logistics Status of Inputs Areas of Concern Assistance Required
2
Background
Unutilized gas reserves in Tripura
Transportation of gas to mainland not economically viable
Possible Option – Gas head generation & transmission of electricity
Government of Tripura, ONGC and IL&FS join hands to set-up Power Plant
to provide good quality energy in NER: stimulating economic growth
Hon’ble Prime Minister laid the foundation stone in October, 2005
10
Project Highlight
Capacity: 2 x 363.3 MW
Type: Gas Based Combined Cycle
Location: Palatana, Tripura
Project Cost: Rs 3,429 Crore
Source of Fuel: ONGC’s Gas Field in Tripura
Type of Fuel: Natural Gas
Quantity of Fuel: 2.65 MMSCMD
Source of Water: River Gumti
Quantity of Water: 125 MLD
Promoters: ONGC (50%), IL&FS (26%), GOT (0.5%).
11
Project Highlight …… Contd
EPC Contractor: Bharat Heavy Electricals Limited (BHEL)
Award of Contract: 23-Jun-08
Commissioning: Unit-1: 22-Dec-11,
Unit-2: 22-Mar-12
Evacuation: 650 KM 400 KV D/C Palatana – Bongaigaon Line
12
Power Allocation
Power Allocation by MoP
Beneficiary State Pro-rata allocation in MW based on actual capacity of 726.6 MW
Tripura 196
Assam 240
Arunachal Pradesh 22
Nagaland 27
Mizoram 22
Manipur 42
Meghalaya 79
Power allocated to OTPC 98
13
Konaban GGSKunjaban Manifold
Nimbutali
Sonamura GGS
Agartala Dome GGS(ADB)
Palatana
Sundalbari Manifold
16” 12km Pipeline
(Sector–II)
8” 19.5km Pipeline
(Sector-IV)
6” 19.5km Pipeline
(Sector-V)
20” 41km Pipeline (Sector-I)
20” 12km Pipeline
(Sector –I)
8” 12.5km Pipeline
(Sector –VI)6” 12.5km
Pipeline(Sector-VII)
16” 22km Pipeline
(Sector – III)
BagabasaSectionalizing Valve Station
F1A : Facility F1 (Early)F1B : Facility F1 (as per NOA)F 2 : Facility F2
Gas Supply from ONGC – Tripura Asset
15
Project Status: Clearances and Agreements
Clearance received from MOEF, TSPCB, AAI, MOD
State Support Agreement Signed
206 Acres of Land Acquired for the project
Shareholders Agreement, Gas Sale & Purchase Agreement and Power
Purchase Agreement signed.
Long Term Service Agreement signed with OEM (GE) for Gas Turbine
16
Project Status : Supply & Construction
SUPPLIES
Dispatch of ODCs to be transported through Bangladesh started in May-10 and last dispatch from BHEL works for Unit-1 & Unit-2 is expected by end Feb-11.
Supplies of non-ODCs to be transported via Gauhati started in Mar-10 and last dispatch from BHEL works for Unit-1 is expected by Apr-11 and for Unit-2 by Aug-11.
CIVIL CONSTRUCTION
Piling and foundation of major buildings for Unit-1 completed and main plant equipment erection shall start in Jan-11.
Major structures for Unit-2 are likely to be ready for erection by Apr-11.
Work for Cooling Tower and Water Treatment System has commenced. CT-1 is likely to be commissioned in Sep-11 and Water Treatment System is likely to be commissioned in Jul-11
Construction of River Water Intake Pump house and pipeline has commenced and likely to be commissioned by Jul-11.
17
Project Status : Erection
ERECTION
Erection contract has been awarded and erection of Main Plant equipment shall start in Jan-11
Milestone Target Date
Mechanical Completion Aug-11
Hydro test Completion Oct-11
Readiness for commissioning Dec-11
18
Routes for transportation of ODCs from Kolkata: There are two routes available for transportation of ODCs to Palatana site:
Via Karimganj: 1318 KM (river) + 320 KM (road - India)
Via Ashuganj (Bangladesh): 856 KM (river) + 115 KM (road – India + B’dsh)
Ashuganj route has been selected because river route is navigable through out the year and road route passes through generally plain land leading to less risk in transportation.
Hon’ble Prime Minister of Bangladesh during her visit to India in Jan-10 agreed to allow movement of ODC through Ashuganj in Bangladesh. Since then, Ashuganj has been included in Indo-Bangla Water Transport Proto-call and MOU has been signed with GOB formally allowing movement of ODCs through Bangladesh territory.
96 ODCs shall be transported through Bangladesh for which construction of RO-RO jetty at Ashuganj and bypasses between Ashuganj and Palatana has started.
Movement of ODC from Kolkata to Ashuganj shall start from jan-11 and from Ashuganj to Palatana site shall start in Feb-11.
Logistics – Overview
24
PROJECT – STATUS OF INPUTS
Commissioning Gas Start-up Power Evacuation System
Responsible agency ONGC TSECLNETCL / POWERGRID /
NER STATES
Latest required – to meet commissioning schedule
August ’11 May’11 November’11
Current StatusConstruction has
started
Line construction contract yet to be
awarded
Construction started but moving at tardy
pace.
OTPC assessment No delay Delay of 3 Months
Delay of 3 months (up to Silchar)
Delay of 6-9 months (up to Bongaigaon)
Impact on unit#1 No impact Delay of 3 monthsLikely delay of 3
months
Impact on Unit#2 No impact No impactLikely delay of 6/9
months
25
PALATANA – SILCHAR TRANSMISSION LINE
Delay in Forest Clearance in Assam (4 KM)
SILCHAR – BONGAIGAON TRANSMISSION LINE
Delay in Forest Clearance in Meghalaya (25 KM) and Assam (22 KM)
EVACUATION CONSTRAINT: PALATANA – BONGAIGAON
Delay in construction of Azara and Byrnihat sub-station
DOWNSTREAM NETWORK BY BENEFICIARY STATES
Work yet to commence by States i.e. Assam, Tripura, Mizoram etc for absorption of power. Unit-1 commissioning may be delayed on this account.
AREAS OF CONCERN
26
Immediate Forest Clearance in Assam (26 KM) and Meghalaya (25 KM) required.
State governments to expedite development of Azara and Byrnihat sub-station and downstream network to match Unit-1 commissioning in Dec-11
States to advise POWERGRID to install series-compensation facility at Bongaigaon sub-station.
Government of Tripura to expedite construction of 132 KV line and provide startup power by May-11
ASSISTANCE REQUIRED