december revision information re.vision #10 …december 9,2003 page-1 index page october 15,2002...

151
December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page GS-5 November 3,2003 REVISION INFORMATION - Re.vision #10 Addition of Segmental Retaining Wall Project Signs - Addition of Retaining Wall Spec SUMMARY OF REVISIONS TO THE CITY OF LONDON STANDARD CONTRACT DOCUMENT FOR MUNICIE’AL CONSTRUCTION PROJECTS REVISION 10 The City of London Standard Contract Document for Municipal Construction Projects is revised as follows: REVISEDAVEW INSERT REMARKS SUPERCEDED/CANCELLED REMOVE I SECTION SECTION I DATED I B- Part I Supplemental Standards for Roads 1 October 15.2002 November 3.2003 Spec. 3 10.09/3 10.10 page no. change Addition of Selected 0.P.S.D’ for curb and gutters Revised O.P.S.S. met. numbers Index Page 1 Index Page 1 Index Page 2 October 15,2002 November 3,2003 November 3,2003 Page SR-1 Page SR-2 Page SR-3 February 29,2000 Page SR-1 -Revised O.P.S.S. spec. numbers -Tack Coat Spec Revised to 3 10.07.03 -Remove Tolerance and replaced with Cores and 310.07.02.13 revised to 3 10.07.05.02.05 -Widening and Irregular Section 3 10.07.02.09 revised to 310.07.08 -Asphalt Pavement Reinforcement paragraph 1 revised paragraph to clarify Price Adjustment for Asphalt Cement Content 310.08.03 removed -Basis of Payment moved from SR-6 -Glas Grid Pavement Reinforcement 310.09.05 revised to 310.09.01.04 -Widening and Irregular Secions 310.10.01.04 revised to 310.10.04 -Remove 310.10.01.05 Tolerance and replace with 310.10.05 Core Samples and 3 10.10.06 Asphalt cement Payment Adjustment Portion of Basis of Payment 3 10.10 spec moved to Page SR-5 O.P.S.S. 350 moved from Page SR-8 Page number changed Page number changed January 16,2003 Page SR-2 November 3,2003 January 16,2003 Page SR-3 November 3,2003 January 16,2003 Page SR-4 November 3,2003 January 16,2003 Page SR-5 November 3,2003 7 Page SR-6 January 16,2003 Page SR-6 November 3,2003 November 3,2003 November 3,2003 November 3,2003 November 3.2003 October 15,2003 January 16,2003 Page SR-7 Page SR-8 Page SR-9 October 15,2003 October 15.2003 Page SR-IO Page number changed - Page SR-1 1 Page SR-12 October 15,2003 October 15,2003 November 3,2003 November 3,2003 Page number changed Page number changed -0.P.S.S. 353 moved from Page SR-14 -Clean up wording in the I’ sentence of the last paragraph O.P.S.S. 501 moved from page SR-15 -0.P.S.S 506 moved fi-om page SR-16 -Subsection 506.07.03 revised to 506.07.02.01 October 15,2003 Page SR- 13 November 3,2003 Page SR-13 I October 15,2003 Page SR- 14 November 3,2003 November 3,2003 January 16,2003 Page SR- 1 5 Page SR-15 I I

Upload: others

Post on 06-Jun-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

December 9,2003 Page-1

Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003

Page GS-5 November 3,2003

REVISION INFORMATION - Re.vision #10

Addition of Segmental Retaining Wall Project Signs - Addition of Retaining Wall Spec

SUMMARY OF REVISIONS TO THE CITY OF LONDON STANDARD CONTRACT DOCUMENT FOR MUNICIE’AL CONSTRUCTION PROJECTS

REVISION 10

The City of London Standard Contract Document for Municipal Construction Projects is revised as follows:

REVISEDAVEW INSERT REMARKS SUPERCEDED/CANCELLED

REMOVE I SECTION SECTION I DATED I

B- Part I Supplemental Standards for Roads 1

October 15.2002 November 3.2003 Spec. 3 10.09/3 10.10 page no. change Addition of Selected 0.P.S.D’ for curb and gutters Revised O.P.S.S. met. numbers

Index Page 1 Index Page 1

Index Page 2 October 15,2002 November 3,2003

November 3,2003 Page SR-1

Page SR-2

Page SR-3

February 29,2000 Page SR-1 -Revised O.P.S.S. spec. numbers -Tack Coat Spec Revised to 3 10.07.03 -Remove Tolerance and replaced with Cores and 310.07.02.13 revised to 3 10.07.05.02.05 -Widening and Irregular Section 3 10.07.02.09 revised to 310.07.08 -Asphalt Pavement Reinforcement paragraph 1 revised paragraph to clarify Price Adjustment for Asphalt Cement Content 310.08.03 removed -Basis of Payment moved from SR-6 -Glas Grid Pavement Reinforcement 310.09.05 revised to 310.09.01.04 -Widening and Irregular Secions 310.10.01.04 revised to 310.10.04 -Remove 310.10.01.05 Tolerance and replace with 310.10.05 Core Samples and 3 10.10.06 Asphalt cement Payment Adjustment Portion of Basis of Payment 3 10.10 spec moved to Page SR-5 O.P.S.S. 350 moved from Page SR-8 Page number changed Page number changed

January 16,2003 Page SR-2 November 3,2003

January 16,2003 Page SR-3 November 3,2003

January 16,2003 Page SR-4 November 3,2003

January 16,2003 Page SR-5 November 3,2003

7 Page SR-6 January 16,2003 Page SR-6 November 3,2003

November 3,2003 November 3,2003 November 3,2003 November 3.2003

October 15,2003 January 16,2003

Page SR-7 Page SR-8 Page SR-9 October 15,2003

October 15.2003 Page SR-IO Page number changed - Page SR- 1 1 Page SR-12

October 15,2003 October 15,2003

November 3,2003 November 3,2003

Page number changed Page number changed -0.P.S.S. 353 moved from Page SR-14 -Clean up wording in the I’ sentence of the last paragraph O.P.S.S. 501 moved from page SR-15 -0.P.S.S 506 moved fi-om page SR-16 -Subsection 506.07.03 revised to 506.07.02.01

October 15,2003 Page SR- 13 November 3,2003 Page SR-13 I

October 15,2003 Page SR- 14 November 3,2003

November 3,2003 January 16,2003 Page SR- 1 5 Page SR-15 I

I

Page 2: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

REVISION INFORMATION - Revision #lo

Page SR-22

Page SR-23

Page SR-24

December 9, 2003 Page-2

October 15,2003

October 15,2003

January 16,2003

SUMMARY OF REVISIONS TO THE CITY OF LONDON STANDARD CONTRACT DOCUMENT FOR MUNICIPAL CONSTRUCTION PROJECTS

SR-2.0 SR- 1 3 .O

SUPERCEDED/CANCELLED REMOVE

November 14,2002 SR-2.0 September 18,2003 Note 3 revised November 6,2002 SR-13.0 October 17,2003 Section A-A now shows the 40mm

I SECTION I DATED

SR- 1 4 .O

Page SR-17

HL8 continuous New Drawing - Matching Cut Guidelines

November 3,2003

October 15,2003

Page SR-19 January 16,2003

Page SR-20 January 16,2003

Page SR-2 1 I

October 15,2003

1 PageSR-26 1 October 15,2002

REVISED/NEW INSERT

SECTION

Page SR-16

Page SR-17

Page SR-18

Page SR-19

Page SR-20

Page SR-2 1

Page SR-22

Page SR-23

Page SR-24

DATED

November 3,2003

November 3,2003

November 3.2003

November 3,2002

November 3,2002

November 3 , 2002

November 3,2002

November 3,2003

November 3,2003

REMARKS

-0.P.S.S. 510 moved from SR-17 -Reorganize subsections due to revised O.P. S .S . -510.07.01.02 Removals has been removed -510.07.01.03 revised to 510.07.10 -Management of Excess Unsuitable Material - revised I" sentence -Replaced title of subsection 510.07.06.04 -Measurement for Payment moved fiom page SR-18 -510.09.02.02.02 revised to 5 10.09.01.02.02 0.P.S.S.532 moved fiom page SR-19 -0.P. S . S . 532.07 Construction moved fiom page SR-20 -Paragraph 4 1 St line clean up words O.P.S.S.570 moved fiom page SR-21 -O.P.S.S571 moved fiom page

-571.07.05 Title changed and 1'' paragraph replaced -Qualify Assurance 571.08 now includes subsection 571.08.01 Performance Measure -subsection 571.09.02 Water for Sod (ref.571.08.01) and (ref.571.09.01) revised to (ref571.07.05) and (ref57 I .09.0 1 .O 1) respectively -0.P.S.S 2501 moved from page

-subsection2501.09 title changed

SR-22

SR-23

-Page number changed -Changes made to SR-2.0 -Corrected dates on Drawings SR- 1.2, 5.0,5.1 and 7.0 -Page number changed -Corrected dates on SR-13 -Addition of new SR-14 Tnformation has been included on page SR-13

Page 3: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

December 9, 2003 Page-3

SECTION

REVISION TNFORMATION - Revision #10

DATED

Page SW-2

Page SW-3

Page SW-4

November 3,2003

November 3,2003

November 3,2003

Page SW-7

Page SW-9

November 3,2003

November 3,2003

Page SW-10 to SW-42 November 3,2003

Page SW-44 Page SW-45

November 3,2003 November 3,2003

SW-3.1

W-CS-69 (Sheet 1)

W-CS-69 (Sheet 2)

W-CS-69 (Sheet 3)

November 3,2003

September 16, 2o03

September 16,2003

Catch Basin Pipe Subdrain Detail 450m and up Typical Watermain Support Detatil Typical ReinstatementfBedding Detail for 4501nm and up Watermain

General Submission and Design

S~pport and Bedding Reinstatement

SUpQOrt

September 16,2003 Requirements for Watermain

SUMMARY OF REVISIONS TO THE CITY OF LONDON STANDARD CONTRACT DOCUMENT FOR MUNICIPAL CONSTRUCTION PROJECTS

B - Part I1 Supplemental Standards for Sewer and Water ( S W

SUPERCEDED/CANCELLED REMOVE

REVISEDNEW INSERT REMARKS

SECTION ~

DATED -0.P.S.S. 410 Basis of Payment page SW-6 changed to SW-7 -Addition of O.P.S.S. 538 -0.P.S.S. 701 pages SW-9 to SW-42 changed to SW-10 to SW-42 -0.P.S.S. 1010 page SW-44 missing -Addition of selected O.P.S.D. to be

Remove paragraph a) and b) and replace with new description -0.P.S.S. 407 title change -remove cc~nanhole” throughout spec and replace with “maintenance hole” Subsection 410.03 Definition paragraph 1 revised Subsection 410.07 Construction - paragraph 1 clean up words Second last paragraph - clean up

used (SW-49)

October 15,2002 & January 16,2003 Index Pages Index Pages November 3,2003

Page SW-1 February 29,2000 Page SW-1 I November 3,2003

February 29,2000 Page S W-2

Page SW-3 January 16,2003

Page SW-4 January 16,2003

January 16,2003

Febi-uarv 29,2000

Page SW-7

Page SW-9 words -New Section O.P.S.S. 538 -Replace with revised O.P.S.S.701 -S%-16: New Sub&ttal Required by Pipe Manufactures, paragraph 3 a), b) and c) -SW-35: New Paragraph, paragraph 1 to subsection 70 1.07.18 .O 1 Installation of New Service Connections -SW-37: 701.07.02 -paragraph 7

Page SW-10 to SW-42 All Dates

addition of last sentence Missing from original Page SW-44

Page SW-45 February 29,2000 October 15,2002 Revised Drawing SW-3.1

Organization of information -Organization of information -Removal of Selected 0.P.S.D’s

Page SW-46 October 15.2002 Page SW-46 I November 3.2003

Page SW-47 October 15,2002 Page SW-47 1 November 3,2003

-Result of reorganizing pages -New drawings: W-CS-69 sheets 1 ,2 and 3 Selected O.P.S.D.’s

Page SW-48 November 3,2003

Page 4: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

REVISION INFORMATION - Revision #lo

SUPERCEDED/CANCELLED REMOVE

December 9,2003 Page-4

REMARKS REVISED/NEW INSERT

SUMMARY OF REVISIONS TO THE CITY OF LONDON STANDARD CONTRACT DOCUMENT FOR MUNICIPAL CONSTRUCTION PROJECTS

Page STS-1

Page STS-2

Page STS-5

Page STS-6

Page STS-9

October 15,2002 Page STS-1 November 3,2003

October 15,2002 Page STS-2 November 3,2003

October 15,2002 Page STS-5 November 3,2002

October 15,2002 Page STS-6 November 3,2002

January 16,2003 Pages STS-9 November 3,2003

SECTION I DATED 1 SECTION I DATED I

Februaiy 29,2000 Index Page 2 Index Page 2

October 15,2002

February 29,2000

Index Page 3 Index Page 3 November 3,2003

Page SGC-I November 3,2003 Page SGC-I

February 29,2000 Page SGC-2 Page SGC-2

Page SGC-3 Page SGC-4

Februaiy 29,2000 February 29,2000 February 29,2000 October 15,2002

- Page SGC-5 Page SGC-6

Page SGC-3 November 3,2003 Page SGC-4 November 3,2003 Page SGC-5 November 3,2003 Page SGC-6 November 3,2003

Page SGC-8 February 29,2000

Page SGC-9

Page SGC-8

Page SGC-10 February 29,2000

All Dates Pages SGC-1 I to SGC-23-

Page SGC-10 November 3,2003

Pages SGC-1 I to SGC-24 November 3,2003

November 3,2003

I

November 3,2003

November 3,2003

February 29,2000 1 Page SGC-9 1 November 3,2003

-Parargmph 3 revised with Parking and Traffic Signal Division -Last paragraph revised with Parking and Traffic Signal Division Parargraph 2 revised with Parking and Traffic Signal Division Revised subsection 609.07.03.05 for Ground Wire Connections and 609.07.04.01 for Ground Rods Subsection 616.07.01.02 Sleeves and Duct paragraph 3 revised with Parking and Traffic Signal Division Subsection 620.07 Construction paragraph 4 and 6 revised with Parking and Traffic Simal Division

-GC7.15 page changed to SGC-12 -GC8.01.02 page changed to SGC-12 -GC8.02.02 page changed to SGC-13 -GC8.02.03 page changed to SGC-13 All pages from GC8.02.03.01 to GC8.02.09 have changed Paragraphs 1 1 , 12 and 13 correct spelling errors -Correct Spelling mistakes -Included SPO - -Paragraph 10 and 11 include General Manager of Planning and Develowment

Corrected spelling mistakes Corrected swell in^ mistakes - lst paragraph added clause .17 -Added clause .17 Technical Standards and Safety Authority Act Addition of paragraphs . 1 1, .12 and .I3 -As a result of additional paragraphs Underground Utilities Tolerances moved to page SGC-11 -Last line of last paragraph revised to read (see page SGC-11) Page numbers chanced

Page 5: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

REVISION INFORMATION - Revision #10

SUPERCEDED/CANCELLED REMOVE

SECTION DATED

December 9,2003 Page-5

REMARKS REVISEDNEW INSERT

SECTION DATED

SUMMARY OF REVISIONS TO THE CITY OF LONDON STANDARD CONTRACT DOCUMENT FOR MUNICIPAL CONSTRUCTION PROJECTS

Page SPO-3 Page SPO-4

January 10,2003 Januaiy 10,2003

B - Part VI Supplemental Standards for Parks and ODen Spaces (SPO)

Page SPO-8 Page SPO-9

Index Page 2

January 10,2003 January 10,2003

January 10,2003

Page SPO-11 Page SPO-12

Page SPO-2

January 10,2003 January 10,2003

Januaiy 10,2003

Page SPO-5 January 10,2003

Page SPO-6 January 10,2003 , SPO-7 Page January 10,2003

Page SPO-IO January 10,2003

Index Page 1

Index Page 2

Page SPO-2

Page SPO-3 Page SPO-4

Page SPO-5

Page SPO-6 Page SPO-7

Page SPO-8 Page SPO-9

Page SPO-10

Page SPO- 1 1 Page SPO-12

November 3.2003

November 3,2003

November 3,2003

November 3,2003 November 3,2003

November 3,2003

November 3,2003 November 3,2003

November 3,2003 November 3,2003

November 3,2003

November 3,2003 November 3,2003

0.P.S.S 353 page numbers changed -0.P.S.S. 405 page number changed -0.P.S.S. 570 remove Measurement for Payment and page number changed -0.P.S.S. 571 Remove Quality Assurance and page number changed -0.P.S.S. 572 Dage number changed -Title changed -subsection3 10.07.02.13 revised -subsection 310.07.03 has been deleted and redaced with 3 10.07.14 Subsection 3 10.07.14 continued -Revised subsection 350.07.03, 350.07.03.01 to 350.07.02 and 3 50.07.02.0 1 respectively -Removed subsection3 50.07.04 -Miscellaneous Proctection from the old SPO-5 now appears on the new

-0.P.S.S. 353 page number changed -subsection 353.07.01 paragraph 2 last sentence revised. Page number changed -Page number changed -Subsection 570.07 moved to SPO-8

SPO-5

Continuation of 570 O.P.S.S. 571 moved here and subsection 571.08 Quality Assurance has been removed 0.P.S.S 572 moved here and removed subsections 572.05 and 572.09 Continuation of subsection 572.07 Addition of Tables 1 and 2

Page 6: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

REVISION INFORMATION - Revision #10

SECTION

December 9,2003 Page-6

DATED SECTION DATED

SUMMARY OF REVISIONS TO THE CITY OF LONDON STANDARD CONTRACT DOCUMENT FOR MUNICIPAL CONSTRUCTION PROJECTS

Payment Certificate Checklist Tender and Proposal Ad Time and Material Change Order Summary Forms

SUPERCEDED/CANCELLED REMOVE

October 15,2002 Payment Certificate checklist November 3,2003 Revised Clause 3

Tender and Proposal Ad Time and Material Change Order Summary Forms

Revised to indicate 2004 Revised to Environmental and Engineering Services Department

REVISED/NEW INSERT

Tender Document Title PaEe January 2003

REMARKS

Tender Document Title Page November 2003 Division name change

Data Sheet Change open for acceptance fiom45 February 29,2000 Date Sheet November 3> 2003 days to 60 days

Section E - SamDle Tender Document I

Page FT- 1

Page FT-2

-Title at top of page replaced -Added SPO in clause 1 November 3' 2003 January 3 1,1998 Page FT-1

October 15,2003 Page FT-2 November 3,2003 Title at top of page replaced

Page IT-1

Page IT-3

Clause 1 paragraph land 6 name change and address change Clause 10 change the irrevocable

Coirect spelling clause 13 paragraph

November 3' 2003 October 15,2003 Page IT-I

February 29,2000 Page IT-3 November 3,2003 period

Page IT-5

Page IT-7

Page IT-8 I revisiodamendment dates

, - --, Clause 17 paragraph 2 change the

Clause 23 paragraph 4 removed last November 3y 2003 irrevocable period February 29,2000 Page IT-5

October 15,2002 Page IT-7 November 3,2003 sentence

January 16,2003 Page IT-8 November 3,2003 Clause 24 corrected

I I I I

Form of Aneement Page FA-I Page FA-2

Page FA-3

Febmaiy 29,2000 Page FA-I November 3,2003 Replace title on top of page January 3 1,1998 Page FA-2 November 3,2003 -Replace title on top of page

-Clause 3 paragraph 8 added SPO January 3 1,1998 Page FA-3 November 3,2003 -Replace title at the top of te page

-Clause 6 revised

Page FA-4 -Article 7 added SPO

March 1, 1998 Page FA-4 November 3,2003 Replace title on top of the page

Page 7: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003

London C A N A D A

CITY OF LONDON

GENERAL SPECIFICATIONS (GS)

J

I N D E X

1. General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . , . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . GS- 1

2. Recovered Concrete As Granular Materials Granular ‘A’, Granular ‘B’ - Select, and Granular ‘C’. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .GS-1

3.

4.

5.

6.

7.

8.

Recovered Bituminous Pavement For Blending With Granular ‘A’. . . . . . . . . . . . . . . . . . . . . . . . . . .GS-1

Contract Administrator’s Field Office . . . . . . . - . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .GS-1

Project Sign Boards.. . . . .. . . . . . . . . . . .. . . . . .. . . . . . . . . . . . . . .. . . . . .. . . . . . . . . . . . . . . . . . . . .. . . . . .. . .. . . . . ... GS-3

Advanced Warning Construction Signs.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .GS-4

Raised Maintenance Covers Ahead Signs . . . . . . . . . . , . . . . . . . . . . . . . . . .. . . . . . . . .. . . . . .. . . . . .. . .. . ... GS-4

Construction of Segmental Retaining Wall.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. GS-5 .

Page 8: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 GS-3

I

CITY OF LONDON NAME OF PROJECT

CONTRACTOR’S NAME DATE OF COMPLETION 20

London C A N A D A

City Engineer or (General Manager of Planning & Development) P. W. StebIin, P. Eng.

“INVESTING IN OUR COMMUNITY”

Consultant

Front Face of Project Sign Board

London C A N A D A

THE CITY OF LONDON

~ “INVESTING IN OUR COMMUNITY”

Reverse side of Project Sign Board

Page 9: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 5,2003 GS-5

8. Construction of Segmental Retaining Wall

The construction of new segmental retaining walls on the City of London road allowances or City projects by the Owner shall be constructed of units with a minimum weight of 200 kg/unit (typical), and a minimum product weight per square metre of 11 00 kg/m2 wall face.

The following is an overall list of segmental retaining walls approved for use on the City of London road allowances.

- Split Face Finish Walls (a.) Nava Stone - Wallstone Grande (b.) Unilock - Sienna Stone

- Smooth Face Walls (a) Unilock - Dura-Hold

Page 10: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

London C A N A D A

SUPPLEMENTAL STANDARDS FOR ROADS (SR)

The Ontario Provincial Standards (OPSS) are amended as follows:

I N D E X

Section

206.07 206.09 206.10

310.07 3 10.08 3 10.09 310.10

350.05 350.07 350.08 350.09 350.10

351.07 35 1.09 351.10

Description

O.P.S.S. 206 - CONSTRUCTION SPECIFICATION FOR GRADING

Page

Construction ....................................................................................................................... SR-1 Measurement for Payment .................................................................................................. SR- 1 Basis of Payment ............................................................................................................... .SR-l

O.P.S.S. 310 - CONSTRUCTION SPECIFICATION FOR HOT MIXED, HOT LAID ASPHALTIC CONCRETE PAVING AND HOT MIX PATCHING

Construction SR-2 SR-4

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Quality Assurance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Measurement for Payment ................................................................... Basis of Payment, . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SR-5

SR -3 I

O.P.S.S. 350 - CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE

Materials ............................................................................................................................. SR-7 Construction ....................................................................................................................... SR-7

Measurement for Payment .................................................................................................. R-. Basis of Payment ...................................................................................................................

Quality Assurance.. ........................................... .:. ................................................................ SR-9

0.P.S.S. 351 - CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK

Construction ..................................................................................................................... SR-11. Measurement for Payment ................................................................................................ SR-12 Basis of Payment ..............................................................................................................SR-l~

Page 11: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

-2- November 3,2003

I N D E X (cont'd)

Section Description Page

353.09 353.10

501.07 1 501.08

I 506.07

5 10.03 5 10.07 5 10.09

532.04 532.05 532.07 532.09

570.07 I 570.09

57 1.07 571 -08 571.09

O.P.S.S. 353 - CONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS

Measurement for Payment ................................................................................................ SR-13 - Basis of Payment .............................................................................................................. SR-13 Selected Ontario Provincial Standard Drawings for Concrete Curb and Gutters. ........... SR- 13

-

O.P.S.S. 501 - CONSTRUCTION SPECIFICATION FOR COMPACTION

Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SR-lg QualityAssurance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SR-14

O.P.S.S. 506 - CONSTRUCTION SPECIFICATION FOR DUST SUPPRESSANTS

Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

0.P.S.S. 510 - CONSTRUCTION SPECIFICATION FOR THE DEMOLITION AND REMOVAL OF STRUCTURES

Definitions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Measurement for Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

0.P.S.S. 532 - CONSTRUCTION SPECIFICATION FOR PAVEMENT MARKING

SR-19;

SR-16 SR-16 SR-12

Submission And Design Requirements ............................................................................ SR-1& Materials ........................................................................................................................... SR- 18 Construction ..................................................................................................................... SR-@ Measurement for Payment ................................................................................................ S R - ~ 9

O.P.S.S. 570 - CONSTRUCTION SPECIFICATION FOR TOPSOIL

Construction ..................................................................................................................... SR-28 Measurement for Payment ................................................................................................ S R - 2 ~ -

-

O.P.S.S. 571 - CONSTRUCTION SPECIFICATION FOR SODDING

Construction ..................................................................................................................... SR-21 Quality Assurance.. ........................................................................................................... SR-29 Measurement for Payment ................................................................................................ SR-2~ -

Page 12: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

Section

-3-

I N D E X (cont'd)

Description

November 3,2003 I

Page

O.P.S.S. 2501 - MATERIAL SPECEICATION FOR CALCIUM CHLORIDE FLAKE AND SOLUTION

250 1.09 Owner Purchase Of Material . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . SR-22 1 STANDARD DRAWINGS FORROADS ....................................................................... SR-23 I

Page 13: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SR-11

351.07

35 1.07.0 1

O.P.S.S. 351 CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK

CONSTRUCTION

General

Subsection 35 1.07.01 is amended by the addition of the following:

For contracts dealing with the construction of sidewalks only, excavation outside of the nominal two meter limit centered along the proposed sidewalk location will be a separate item in the Form of Tender termed "LANDSCAPE GRADING". This excavation will consist of landscape grading of lawns, boulevards or any other area adjacent to the proposed sidewalk.

351.07.02.02 Granular Base

Subsection 35 1.07.02.02 is amended by the addition of the following:

Granular Base shall be a minimum of 100 mm for the construction of new or replacement sidewalks.

351.07.06 Utility Adjustment

Subsection 35 1.07.06, second paragraph, frst sentence is amended to read:

Appurtenances maintained and owned by utility companies other than the Owner shall either be adjusted by the utility company concerned or by the Contractor (with approval from the applicable utility company). All arrangements to adjust the utility appurtenance shall be approved by the Contract Administrator.

351.07.11 Identification Stamp

Subsection 35 1.07.1 1 is deleted in its entirety and replaced by the following:

Under the direction of the Contract Administrator, the Contractor shall clearly and legibly; mark with an approved stamp only at each end of the work. The stamp shall be located on the centre of the bay, next to and parallel to a transverse joint .

351.07.14 Protection of New Sidewalk

Subsection 35 1.07.14 is deleted in its entirety and replaced by the following

New sidewalk surfaces shall be protected fiom damage of any kind. Vehicular and pedestrian traffic will not be permitted to travel on or across the new sidewalk surfaces until approved by the Contract Administrator.

Page 14: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SR-12

351.09 MEASUREMENT FOR PAYMENT

351.09.01.02 Excavation

Subsection 35 1..09.01.02 is deleted in its entirety and replaced by the following:

For contracts dealing with the construction of sidewalks only, measurement of concrete sidewalk excavation will be contained within a nominal width of two meters centered on the proposed sidewalk location. All materials actually excavated in cut will be measured in cubic meters from the existing ground profile down to the earth sub-grade. All sidewalk earth excavation will be constructed in accordance with O.P.S.S. 206.

The areas of "LANDSCAPE GRADING" beyond the two meter limit will be measured and computed in square meters for any depth required to establish grade, to the satisfaction of the Contract Administrator.

351.10

351.10.02

BASIS OF PAYMENT

Excavation

Subsection 35 1.10.02 is amended by the addition of the following:

Payment at the contract price for the tender item(s) "EARTH EXCAVATION, LANDSCAPE GRADING AND/OR ROCK EXCAVATION" shall be full compensation for all labor, equipment and material to do the work, including placement and disposal of surplus acceptable and unacceptable material.

Page 15: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

O.P.S.S. 350 CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND

CONCRETE BASE

350.05

350.05.01

MATERIALS

Concrete

Subsection 350.05.01, paragraph a) is deleted in its entirety and replaced by the following:

(a) The nominal maximum size of the coarse aggregate for concrete pavement shall be 19.0 mm with gradation requirements as per Table 3 of O.P.S.S. 1002.

350.07 CONSTRUCTION

350.07.02 Joints

350.07.02.01 General

Clause 350.07.02.01, f ist paragraph, is deleted in its entirety and replaced by the following:

Although the joint types and locations may be shown on the Contract Drawings, the Contractor shall submit a joint layout for approval prior to placing either curb and gutter or concrete pavement or both.

Clause 350.07.02.01 is amended by the addition of the following:

Transverse joint layout should begin by planning joints to intercept roundouts for CB’s and MH’s. The centre line of road distance between ends, shall be divided into panels with a maximum length of either 30 times the pavement thickness or 4.5m, whichever is less.

Transverse joints shall have a depth not less than l/4 the slab thickness and be continuous through the curb.

Longitudinal joint spacing shall not exceed 3.8m. Sawn longitudinal joints should be cut to 1/3 the pavement thickness.

350.07.02.04 Position and Alignment Tolerances

350.07.02.04.02 Joints

Clause 350.07.02.04.02 Joints is deleted in its entirety and replaced by the following:

All joints shall be placed within a tolerance of +/-15mm from the design location shown on the sawcut construction drawing, or from some other location required by the Contract Administrator.

Page 16: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

350.07.03.02

350.07.05

350.07.05

350.07.08

350.07.08.01

350.07.08.02

350.07.08.05

Finishing

Clause 350.07.03.02 is amended by the addition of the following:

Following strike-off and consolidation, the concrete pavement shall be scraped with an aluminum or magnesium straight-edge, 3 meters wide, equipped with a handle to permit operation from the edge of pavement. Any excess water or latence shall be removed from the surface before scraping.

Joint Sealing

General

Section 350.07.05 is amended by the addition of the following:

Cold Poured Joint Sealant: Apply joint sealant Dow 888 or equivalent in accordance with the manufacturer's recommendations.

Use Cold Poured Joint Sealant for the construction of concrete pavement.

Sampling and/or Testing

Slump and Air Content

Clause 350.07.08.01 , fist paragraph, is deleted in its entirety and replaced by the following:

. Field sampling and testing of plastic concrete for conformance to surface tolerance, slump and air content shall be undertaken by the Owner.

Coring

Clause 350.07.08.02 is deleted in its entirety and replaced by the following:

When required or directed by the Contract Administrator, coring shall be carried out when the concrete or lean concrete is 28 to 35 days old.

The Contractor shall cut a core in the location(s) designated by the Contract Administrator. The core shall be 100 mm in diameter and shall be drilled through the complete depth of concrete pavement, concrete base or lean concrete base, perpendicular to the surface of the slab.

Transportation of Cores

Clause 350.07.08.05 is deleted in its entirety and replaced by the following:

The concrete cores shall be delivered by the Contract Administrator to a laboratory designated by him on the same day they were obtained.

Page 17: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SR-9

350.08

350.08.01

350.08.01.01

350.08.01.03

350.08.01.03.01

QUALITY ASSURANCE

Acceptance Criteria for Strength and Thickness

General

Clause 350.08.01.01 is deleted in its entirety and replaced by the following:

Slab thickness and core and/or cylinder compressive strength shall be the basis for acceptance of concrete pavement, concrete base and lean concrete bases.

Lot Size

Clause 350.08.01.03 is deleted in its entirety.

Compressive Strength and Thickness

Clause 350.08.01.03.01, fmt and second paragraph is deleted in its entirety and replaced by the following.

When concrete cylinders are tested for compression, the compressive strengths will be calculated in accordance with CAN/CSA-A23.1 -M90 Section 17.5.7.1.

17.5.7

17.5.7.1

Notes:

(1)

(2)

Compressive Strength Requirements

Standard Cured Cylinders

The strength level of each class of concrete shall be considered satisfactory if the averages of all sets of three consecutive strength tests for that class at one age equal or exceed the specified strength, and no individual strength test is more than 3.5 MPa below the specified strength. These requirements shall not apply to field-cured specimens.

With the standard deviation designated “sf’, these criteria can be expected to be met 99% of the time if the concrete is proportioned to produce an average strength as follows:

(a)

(b)

1.4 times the standard deviation (1.4 s) above the specified strength when the standard deviation (s) is not more than 3.5 MPa; and 2.4 times the standard deviation minus 3.5 MPa (2.5 - 3.5 m a ) above the specified strength when the standard deviation (s) is not more than 3.5 MPa.

The standard deviation used in Note 1 should be based on at least 30 consecutive strength tests, representing concrete whose design strength is within 7 MPa of that required for the work made with sirnilar materials and under similar conditions to those expected.

Page 18: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SR-10

(3) Individual tests from concrete meeting these requirements can be expected to be below specified strength about 10% of the time.

(4) For high-strength concrete different acceptance criteria will be specified by the Owner.

350.08.01.05 Removal of Unacceptable Concrete

Clause 350.08.01.05, fust paragraph, is amended to read:

If the mean core compressive strength and/or deficiency in the thickness of the concrete pavement slab dictates removal or replacement, the Contractor will receive written instruction from the Contract Administrator to correct the deficient area( s).

Clause 350.08.01.05, second and fourth paragraphs are deleted in their entirety.

350.09 MEASUREMENT FOR PAYMENT

350.09.01 Actual Measurement

350.09.01.01 Concrete Pavement, Concrete Base and Lean Concrete Base

Clause 350.09.01.01 is amended by the addition of the following:

If the concrete curb and gutter is poured monolithically (as part of the road slab), width measurements will be taken from back of curb to back of curb minus two times the width of the specified type curb and gutter.

The curb and gutter area will be measured in accordance with O.P.S.S. 353.09.01 -01.

350.09.02 Plan Quantity Measurement

Clause 350.09.02.01 is deleted in its entirety.

350.10 BASIS OF PAYMENT

350.10.01 Concrete Pavement - Item Concrete Base - Item Subsection 350.10.01 is deleted in its entirety and replaced by the following:

Payment at the contract price for the above items shall be -full compensation for all labor, equipment and material required to do the work.

350.10.01.01 Compressive Strength and Slab Thickness

Clause 350.10.01.01 is deleted in its entirety.

Page 19: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SR-1

206.07

206.07.03.03

206.09

206.09.01 206.09.01.01

O.P.S.S. 206 CONSTRUCTION SPECIFICATION FOR GRADING

CONSTRUCTION

Excavation Below Subgrade

Clause 206.07.03.03 is deleted in its entirety and replaced by the following:

Unsuitable materials, other than material excavated from swamps, shall be removed below the subgrade to the lengths, widths and depths specified either in the contract or as directed by the Contract Administrator during the time of construction. The resulting excavation shall be backfilled with acceptable material which shall be compacted.

MEASUREMENT FOR PAYMENT

Actual Measurement Earth Excavation (Grading)

Clause 206.09.01.01 is amended by the adition o the following:

"EARTH EXCAVATION BELOW SUBGRADE", may also be measured in tomes of Provisional Granular 'C'.

206.10

206.10.01

BASIS OF PAYMENT

Subsection 206.10.0 1 is amended by the addition of the following:

When earth excavation below subgrade is paid by the tonne under the item in the Form of Tender "EARTH EXCAVATION BELOW SUBGRADE (INCLUDING PROVISIONAL GRANULAR 'C' BACKFILL)", the Contractor will comply with the requirements of O.P.S.S. Clause 206.07.03.01. It will include the supply, backfill and compaction of Provisional Granular 'C' to fill the sub-excavation void under the Direction of the Contract Administrator.

Page 20: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SR-6

Each Asphalt Cement Payment Adjustment required after July lSt. shall be made on the cut off date for each payment certificate issued (typically at the end of each calendar month).

The payment adjustment shall be calculated based on the ACPI and the asphalt cement content as determined by testing during placement of the asphalt. If test results are unavailable then approved mix design will be used for the calculation. For mixes containing reclaimed asphalt, the payment adjustment shall apply to new liquid asphalt only and the contractor shall show the percentage of new asphalt to be used in the mix design submission.

In all cases, the payment adjustment shall be based on the following calculation:

Payment Adjustment = (ACPIasphalt placed- ACPItender close) x Weighted Ave. of asphalt cement x Quantity of asphalt placed.

Payment adjustment may result in additional compensation to the contractor or a rebate to the Owner.

Page 21: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SR-2

Difference in Thickness Between Specified and Actual

0 to 5 millimetres 5 to 10 millimetres 10 to 15 millimetres

> 15 millimetres

O.P.S.S. 310 CONSTRUCTION SPECIFICATION FOR HOT MMED, HOT LAID ASPHALTIC CONCRETE

PAVING AND HOT MM PATCHING

Price Adjustment to Contract Price for Tender Item Hot Mix Placed on

Binder on Granular Existing Asphalt Nil Nil Nil 10% (penalty)

10% (penalty) rejectable rejectable rejectable

310.07

3 10.07.03

310.07.05.02.05

CONSTRUCTION

Tack Coat

Clause 3 10.07.03 is deleted in its entirety and replaced by the following:

The work required for this item shall be carried out on all milled surfaces. Tack coating of pavements shall conform to clause 3 10.07.02.02 .

Cores

Subsection 310.07.05.02.05 is deleted in its entirety and replaced by the following:

Core Samples

The minimum thickness of the compacted hot mix layer(s) should be as specified on the contract drawings and / or in the tender document. The surface of the hot asphalt mix shall conform to the grades shown on the contract drawings. The owner may, at his option and expense, require the contractor to obtain 1 O O m m diameter cores of the compacted hot mix to verify the thickness of the layer(s). Holes made by the removal of such samples shall be filled with the specified hot mix and compacted.

If the average thickness of the hot mix layer on a lot by lot basis varies from that specified, the contract price of that portion of the hot mix shall be adjusted down as shown below. It should be noted here that price adjustment for hot mix asphalt on cold-in-place asphalt shall follow the adjustments noted for “Binder on Granular” in the following table:

At least three cores shall be obtained for each lot.

These calculations will be made separately for each lot of hot mix.

Page 22: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SR-3

Number of Tomes in Items < 500

500 to 1000 1000 to 1500

>1500

310.07.08

Number of Lots 1 2

2 or 3* 3+

The Contract Administrator will determine the number and location of the cores within the lots after discussion with the Contractor. Guidelines for the breakdown of the tender item quantity into lots are as follows:

*As Determined by Contract Administrator in consultation with the Contractor.

Widenings and Irregular Sections

Subsection 3 10.07.08 (a) is deleted in its entirety and replaced with the following:

(a) Widenings

The Hot Mix Asphalt (HMA) shall be placed in widenings such that the top of the compacted HMA is flush with the top of the existing pavement. The new asphalt shall be keyed into the existing asphalt by either stepped joint or by asphalt reinforcement, as noted below in subsection (c). The type of joint required shall be confirmed with the Transportation Division prior to undertaking the work.

Subsection 310.07.08 is also amended by the addition of the following:

(c.) Asphalt Pavement Reinforcement

The use of pavement reinforcement shall be used on all joints, where new asphalt meets existing asphalt, in good condition, on all road widenings and full road reconstructions where sufficient existing asphalt depth exist (a minimum of 150im). Asphalt milling will be to a depth of 9Omm and to a width 850mm for the length of the joint; the base asphalt layer shall be at a 40mm depth and shall extend across the milled area and across the widening to ensure one continuous layer of base asphalt. The requirements as noted in the City of London Drawings SR-13 (amended October 2003) shall be adhered to. The use of Bayex 8502 GlasGrid (or approved equivalent) reinforcement shall be used. Joints should be out of the general alignment of the wheel path whenever possible. Any asphalt widening or irregular section with or without pavement reinforcement, the pavement and granular base structure for the new work shall be identical or greater than the existing road structure. As a minimum, there should be 15Omm of compacted granular ‘A’ and a minimum of 1 0 0 m of compacted hot mix asphalt. Where there is excessive truck traffic or as requested by the contract administrator, the minimum thickness of granular ‘A’ shall be increased to 200mm.

For utility cuts greater than 3 meters in length and greater than 1 meter wide shall utilize the City of London Drawings SR-13. The contractor shall mill the existing asphalt on either side of the utility cut to accommodate the two - 1.5 meter width of the Glas-Grid roll (overlap of 25Omm. is required). Ensure the width of the milled asphalt on either side of the cut is a minimum of 750mm. to accommodate the Glas-Grid (ie. 750m1n. on the new asphalt base and 750mm. on the padded asphalt in the milled area).

Page 23: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SR-4

For utility cuts less than 3 meters in length andlor less than 1 meter in width, the contractor shall mill a 300mm width along the cut at a depth of a minimum of 50m.m. The hand laid asphalt and granular base structure within the utility cut shall be replaced identical to or greater than the existing road structure. As a minimum there should be 150mm of compacted granular ‘A’ and 1 O O m m . of compacted hot mix asphalt. If the asphalt is in poor condition, replace the utility cut with new hot mix asphalt upto a sound joint or as directed by the contract administrator. The use of Glas-Grid will be confi ied by the Transportation Division prior to the work being completed.

310.07.1 1 Longitudinal and Transverse Joints

310.07.11.01 General

Subsection 3 10.07.1 1.01 paragraph 2 is deleted in its entirety and replaced by the following:

Longitudinal and transverse butt or stepped joints between the new €€MA pavement and the existing pavement shall be constructed by trimming or milling the existing pavement edge to a straight clean vertical surface of at least 501nm. When matching new asphalt to existing asphalt, consideration must be given to ensuring that all joints will not be located in the vehicular running tracks and that any cut areas can be restored with conventional paving equipment and rollers. All cuts shall be squared off to avoid any hand placed areas. The guidelines as shown in the City of London Drawing SR- 14 shall be followed.

3 10.08

310.08.01

QUALITY ASSURANCE

Pavement Sampling

Subsection 310.08.01 is amended by the addition of the following:

When initial representative hot mix samples fail to meet the requirements of its mix design, the Owner will investigate further with a second representative sample for re- testing. All costs associated with initial testing, and successful testing on the second representative sample are bourne by the Owner. All costs associated with the failed second sample re-testing, further investigation (testing and subsequent testing), and remedial measures to correct outstanding deficiencies, will be charged to the Contractor.

310.08.05.03 Compaction Requirements

Subsection 3 10.08.05.03 is amended by the addition of the following:

All costs associated with successful fEst and second attempt hot mix compaction testing shall be bourne by the Corporation. Costs associated with unsuccessful second attempt compaction tests and all subsequent testing will be charged to the Contractor.

Page 24: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SR-5

310.09 MEASUREMENT FOR PAYMENT

Subsection 310.09 is amended by the addition of the following:

310.09.01.04 Glas-Grid Pavement Reinforcement

Glas-Grid pavement reinforcement shall be paid for by the unit square meters.

310.09.01.05 Core Samples

Core samples taken shall be paid for by the unit each.

310.10

310.10.01

310.10.04

310.10.05

3 10.1 0.06

BASIS OF PAYMENT

Section 3 10. IO. is amended by the addition of the following:

Widenings and Irregular Sections

Asphalt Pavement Reinforcement

Payment at the contract price for the above item shall be full compensation for all labor, equipment and material required to place the pavement reinforcementzhe hot mix asphalt for base and top asphalt shall be paid for under the appropriate hot mix asphalt item.

Core Samples

Payment at the contract price for the above item shall be full compensation for all labor, equipment and material required to do the work.

Asphalt Cement Payment Adjustment

The Contract Administrator shall make a payment adjustment relative to price changes in asphalt cement generally in accordance with Ministry of Transportation's (MTO) policy as amended herein.

The price adjustment will be based on the MTO published price index. The MTO publishes a price index for asphalt cement, F.O.B. the Depots in the Toronto area for PG Grade 58-28 each month in its contract bulletins which may be found at the following web site: http://www.raqs.mto.gov.on.ca .

Tender prices shall remain fm from closing of tender to July lS*. of the same year. No price adjustment will be made for works completed prior to July lSt. of the same year as the tendering closing.

Payment adjustment will only be made if the variation in the Asphalt Cement Price Index (ACPI) is greater than 15% compared to the ACPI in effect at the tender close. If no ACPI is available at the tender close then the May ACPI of that year will be used.

Page 25: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SR-13

353.09

353.09.0 1

353.09.01.01

353.09.01.01

353.10

353.10.01

O.P.S.S. 353 CONSTRUCTION SPECIFICATION FOR

CONCRETE CURB AND GUTTER SYSTEMS

MEASUREMENT FOR PAYMENT

Actual Measurement

Concrete Curb and Gutter

Clause 353.09.01.01 is amended by the addition of the following:

Concrete Curb and Gutter Concrete Curb Setbacks

Measurement for the item “CONCRETE CURB SETBACKS” in the Fom of Tender will be for the actual number of curb setbacks constructed (each).

BASIS OF PAYMENT

Concrete Curb and Gutter - Item Concrete Spillways - Item Concrete Gutter Outlets - Item

Subsection 35 3.10.0 1 is amended by the addition of the following:

Concrete Curb Setbacks - Item

Note:

The following Ontario Provincial Standard Drawings for Concrete Curb and Gutter have been selected for use on all design, construction and reconstructive maintenance projects of the City’s infi-astructure, including new subdivisions and developments, unless specified on Contract Drawings and Special Provisions.

OPSD 600.01 Concrete Barrier Curb with Wide Gutter OPSD 600.04 Concrete Barrier Curb with Standard Gutter OPSD 600.06 Concrete Semi-Mountable with Standard Gutter

Note: The construction note “thickness of adjacent sidewalk” made to the dimension between the top of curb and the top of the concrete key, on the back of the curb, should read “thickness of adjacent sidewalk and island cap” for OPS drawings 600.01 and 600.04 noted above.

Page 26: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SR-14

O.P.S.S. 501 CONSTRUCTION SPECIFICATION FOR COMPACTION

501.07 CONSTRUCTION

501.07.01 GENERAL

Subsection 501.07.01 is amended by the addition of the following:

“Jetting” is not an approved method of compaction unless it is carried as a “Special Provision” in the Contract Document, or as directed by the Contract Admini strat or.

501.08

501.08.01

501.08.02

QUALITY ASSURANCE

General

Subsection 501.08.01 is amended by the addition of the following.

All costs associated with successful fxst and successful second attempt compaction testing shall be bourn by the Corporation. Costs associated with unsuccessful second attempt compaction tests and subsequent testing will be charged to the Contractor.

Method A

Subsection 501.08.02 is amended by the addition of the following to the fxst paragraph:

Trench backfill material placed in a zone ffom 1 .O meters below road sub-grade, to road sub-grade, shall be compacted to a minimum density of 98% of the maximum dry density.

Page 27: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003

O.P.S.S. 506 CONSTRUCTION SPECIFICATION FOR DUST SUPPRESSANTS

506.07 CONSTRUCTION

506.07.02.01 Calcium Chloride Flake

Subsection 506.07.02.01, second paragraph, is deleted in its entirety and replaced by the following:

Calcium chloride flake shall be applied in locations and such times as the Contract Administrator may require.

Page 28: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SR-16

510.03

O.P.S.S. 510 CONSTRUCTION SPECIFICATION FOR THE

DEMOLITION AND REMOVAL OF STRUCTURES

DEFINITIONS

"Asphalt Pavement" means all bituminous surface treated materials, and Hot Mix H.L. materials (all types).

510.07 CONSTRUCTION

510.07.06.04 Removal of Pavement, Treated Base and Concrete Base

Subsection 5 10.07.06.04, first paragraph, last sentence, is deleted and replaced by the following:

Such materials shall be removed from the contract site and disposed of outside the right-of-way at locations arranged for by the Contractor at the Contractor's expens e

510.07.06.05 Removal of Asphalt Pavement - Partial Depth

Subsection 5 10.07.06.05, fust paragraph, second sentence, is deleted in its entirety and replaced by the following:

510.07.10

Such materials shall be removed from the contract site and disposed of outside the right-of-way at locations arranged for by the Contractor at the Contractor's expense.

Management and Disposal of Excess Material

Subsection 510.07.10 is amended by the addition of the following:

Excess materials or materials unsuitable for the Contract will be removed from the contract site and disposed of outside the right-of-way at locations arranged for by the Contractor. Payment will be in accordance with G.C.8.02.01, paragraph 02).

Page 29: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

510.09

510.09.01.02.02

510.09.01.02.02

November3,2003

MEASUREMENT FOR PAYMENT

Removal of Maintenance Holes, Catch Basins, Ditch Inlets and Valve Chambers

510.09.01.02.02 is deleted in its entirety and replaced by the following:

Removal and Relocation of Maintenance Holes, Catch Basins, Ditch Inlets and Valve Chambers

For the purpose of removing and relocating existing catch basins, manholes and ditch inlets measurement for payment will be paid by the unit each under the appropriate items in the Form of Tender.

Page 30: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SR-18

532.04

532.04.01

532.05

532.05.03

532.05.04

532.05.05

O.P.S.S. 532 CONSTRUCTION SPECIFICATION FOR PAVEMENT MARKING

SUBMISSION AND DESIGN REQUIREMENTS

General

Subsection 532.04.01, fEst paragraph, is deleted in its entirety and replaced by the fOll0 wing:

At the request of the Contract Administrator, the Contractor shall supply and deliver a sample of the pavement marking material specified in the contract to a designated lab for testing.

An adequate amount of binder, activator, pigment, inert filler content and reflectorizing glass beads to produce a one-litre sample of extruded hydrocarbon thermoplastic or extruded two-component cold plastic; a one-litre sample of solvent-based and/or water-borne paint; one metre sections of preformed pavement tape as specified in the contract shall be delivered to the designated lab at the Contractor’s expense.

MATERIALS

Thermoplastic Pavement Marking Materials

Subsection 532.05.03 is amended by the addition of the following:

Thermoplastic pavement marlung shall also conform to the requirements of Lafrentz “300 Series”.

Field Reacted Polymeric Pavement Marking Materials

Subsubsection 532.05.04 is amended by the addition of the following:

Field reacted polymeric pavement marking material shall also conform to the requirements of Lafi-entz “System 400”.

Preformed Plastic Pavement Marking Tape

Subsection 532.05.05 is amended by the addition of the following:

Preformed plastic pavement marlung tape shall also conform to the requirements of 3M Stamark Series “440, 5730 and 5731.”

Page 31: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003

532.07 CONSTRUCTION

532.07.08 Selection of Materials

Subsection 532.07.08, paragraphs one to four inclusive, is deleted in its entirety and replaced by the following:

When the item “Permanent Pavement Marking” is called for in a contract, the Contractor shall choose from one of the following:

a) b) c)

d)

e)

Lafrentz “System 400” cold plastic Lafrentz “300 Series” inlaid therm0 3M Stamark Series 5730 and 5731 for lane lines, edge lines, and channelizing lines 3M Stamark Series A440 for stop bars, pedestrian crossings at intersections, and pedestrian crossovers (PXO) 3M Stamark Series 5730 for legends and symbols

unless otherwise specified by the Contract Administrator.

532.09 MEASUREMENT FOR PAYMENT

532.09.01 Actual Measurement

532.09.01.01 Pavement Marking Pavement Marking, Durable Pavement Marking, Temporary Pavement Marking, Temporary - Removable Pavement Marking Obliterating

Subsection 532.09.01.01, fKst paragraph, is deleted in its entirety and replaced by the following:

All pavement marking lines shall be paid by the horizontal length in metres (excluding gaps) for the following line widths:

TYPE

Lane lines (solid/broken), edge lines, channelizing lines

Pedestrian crossing lines at signalized intersections

Pedestrian crossings at all way stop intersections, school crosswalks and pedestrian crossovers (PXO)

Stop bars

WIDTH

100 m

100 mm

150 mrn

300 mm

Page 32: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

O.P.S.S. 570 CONSTRUCTION SPECIFICATION FOR TOPSOIL

570.07 CONSTRUCTION

5 70.0 7.03 Placement of Topsoil

Subsection 570.07.03, f ist paragraph, is deleted in its entirety and replaced by the following:

570.09

570.09.02

5 70 .O 9.03

Topsoil shall be spread to a uniform depth of 100 mm on designated areas.

MEASUREMENT FOR PAYMENT

Topsoil from Stockpiles

Subsection 570.09.02 is deleted in its entirety and replaced by the following:

Where topsoil is to be placed and drawn from stockpiles built by the Contractor or fiom existing stockpiles designated in the Contract, measurement will be made in square metres of topsoil placed.

Topsoil, Imported

Subsection 570.09.03 is deleted in its entirety and replaced by the following:

Where topsoil is to be imported and placed, measurement will be made in square metres of topsoil placed.

Page 33: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SR-2A

571.07

571.07.04

571.07.05

571.08

571.08.01

571.09

571.09.02

O.P.S.S. 571 CONSTRUCTION SPECIFICATION FOR SODDING

CONSTRUCTION

Placement of Sod

Subsection 57 1.07.04 is amended by the addition of the following:

Butt joints will be used where new sod blends with existing grass; lap joints will not be permitted.

Maintenance of Completed Sodding

Subsection 57 1.07.05 is deleted in its entirety and replaced by the following:

The Contractor shall apply maintenance watering and shall repair any break or displacement of sod, until 60 days after sod placement.

At the end of the 60-day period, the sod shall be green and succulent, and show evidence of rooting into the underlying soil. Any area of sod which fails to meet these requirements shall be replaced by the Contractor, and shall be subject to a further extension of a sixty day maintenance period.

QUALITY ASSURANCE

Performance Measure

Subsection 57 1.08.01 is deleted in its entirety and replaced by the following:

At the end of the 60 consecutive day maintenance period, an inspection of all the sod placed shall be made by the Contract Administrator. All placed sod shall be green and succulent, and show evidence of rooting into the underlying soil. All sod shall be in the same location as originally placed and shall not have moved, eroded, slipped or sloughed. Any areas which fail to meet these requirements shall be replaced by the Contractor, and shall be subject to a further extension of a 60 day maintenance period.

MEASUREMENT FOR PAYMENT

Water for Sod

Subsection 571.09.02 is deleted in its entirety and replaced by the following:

Water to establish sod growth throughout the 60 day period (ref. 571.07.05) is included in the price per square metre of sod placedheasured (ref.571.09.01.01).

Page 34: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SR-22

O.P.S.S. 2501 MATERIAL SPECIFICATION FOR

CALCIUM CHLORIDE FLAKE AND SOLUTION

2501.09 OWNER PURCHASE OF MATERIAL

2501.09.01 Measurement and Payment

Subsection 2501.09.01 is amended by the addition of the following:

Measurement for payment may also be measured by the number of 25 or 40 kg bags used on the construction site. The unit 25 or 40 kg bag shall be indicated in the Form of Tender.

Page 35: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SR-23-

CITY OF LONDON

STANDARD DUWINGS FOR ROADS

TITLE OF DATED DRAWING

Volume 3 of the Ontario Provincial Standard Drawings (OPSD), and the current City of London Standard Contract Drawings are amended as follows:

OPSD

SUPERSEDEDlDELETED (REMOVE)

I I CITY OF TITLE OF LONDON DATED DRAWING

310.010

3 10.020

310.030

351.010

1993- 1 0-0 1

1 993- 1 0-0 1

Concrete Sidewalk SR- 1 .O 1996-03- 15 Concrete Sidewalk

Concrete Sidewalk Adjacent to Curb and Gutter

SR-1.1 1997-02- 15 Concrete Sidewalk Adjacent to Curb and Gutter

1993-1 0-01 Concrete Sidewalk Ramp at Intersection

. SR-1.2 2002-1 1-13 Concrete Sidewalk Ramps

Sidewalk

Face Sidewalk at Driveways

SR-1.3 1997-02-15 Combination curb Face

SR- 1.4 1996-03-1 5 Combination Curb

1992-05-01 Urban Residential Entrance with

SR-1 .O 1997-02-1 5 Concrete Sidewalk

SR-1.1 1999-01 -30 Concrete Sidewalk Adjacent to Curb and Gutter

SR- 1.2

~~

2003-0 1 - 17 Concrete Sidewalk Ramps

SR-2.0 Boulevard

Mu@-Family Driveway 2002-1 1-14 Single, Double and

500.020

5 12.020

SR-1.3 1998-03-01 Combination Curb Face Sidewalk

SR- 1.4 1997-02-1 5 Combination Curb Face Sidewalk at Driveways

SR- 1.5 1996-03- 15 Sidewalk Driveway Entrance t Detail

Entrances with Boulevards

SR-3-0 1 997-02-1 5 Concrete Curb Setbacks

SR-4.0 1996-03-1 5 Asphalt Bicycle Path Turning Basins for Terminated urban

Roadways

Cul-de-S ac

Cul-de-sac

Circle

Footings

199 1-04- 15

SR-5.0 2002-03-20 Standard For Circular

SR-5.1 2002- 1 1-06 Standard For Industrial

SR-5.2 1996-03-15 Temporary Turning

SR-6.0 1996-03-1 5 Concrete Steps with

SR-6.1 1996-03- 15 Concrete Steps without

with Boulevards

SR-5.0

SR-5. l

SR-5.2

SR-6.0

SR-6.1

SR-7.0

SR-8.0 SR-9.0

SR-9.1

2003-0 1 - 17

2003-0 1 - 17

2002-03-20 Temporary Turning Circle

2002-1 1-06

2002- 1 1-06

2003-01-17 Standard Pedestrian Walkway

1996-03-15 Removable post Detail 1998-03-01 Steel Beam Guide Rail

1998-03-01

Standard For Circular Cul-de- Sac

Standard For Industrial Cul- de-Sac

Concrete Steps with Footings

Concrete Steps without Footings

Assembly Detail Steel Beam Guide Rail Post

and Offset Block Detail

SR-7.0 k ootings

Walkway 2002-03-20 Standard Pedestrian

902.090 1992-12-15 Steel Beam Guide Rail Embedded Connection

SR-10.0 for New Structures

1999-01-30 Steel Beam Guide Rail Embedded Connection

for New Structures

SR-10.0 2000-02-29 Steel Beam Guide Rail Embedded Connection for

New Structures

Page 36: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003

fl

SUPERSEDEDDELETED AMENDED/NEW/CURRENT

STANDARD DRAWINGS FOR ROADS

SR-11 .O SR- 12.0

SR-13.0

SR-14

Volume 3 of the Ontario Provincial Standards Drawings (OPSD), and the current City of London Standard Drawings are amended as follows:

2000-02-29 Concrete Island Bullnose 2000-02-29 Existin Gravel Driveway

kes t orat ion 2003-10-17 Pavement Reinforcement

Detail for Road Widenings 2003- 1 1-03 Pavement Cut Guidelines

Matching New Construction to Existing Asphalt

(REMOVE) I

1 OPSD I LONDON CITYOF

I 1~ SR-13.0

TITLE OF DATED 1 DRAWING

(INSERT) II CITYOF 1 1 LONDON DATED I/ TITLE OF

DRAWING

Page 37: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

Driveway St ruc tu re

Single F a m i l y ( S e e Note 3 1 Single Fami l y

225

1.50m - 1 . 5 0 m 3.Om - L

,!" I

DWG SR-2,O

SECTION Z-Z FOR NEW SUBDlVlSlONS

RATE APPROVED BY 2003 09 1 8 CITY ENGINEERP'

Varies A . ALL DIMENSIONS ARE (preferred) 1 . 5 m

1.50m Var i es I"

MILLIMETRES UNLESS OTHERWISE SHOWN

IN

NOTES: SECTION 2-Z FOR EXISTING R.O,W.'S

1 . For developments w i t h commercial or 3. For single detached dwellings perm i t ted i n mu l t i - f am i l y driveway entrances: the Res ident ia l Zones w i t h a l o t f ron tage o f less v e r t i c a l grades of access driveways s h a l l be 2% f o r a m i n i m u m d is tance of 6.0m than 12 metres ( 3 9 . 4 fee+), t h e m a x i m u m d r i ve - back o f p roper t y I ins. way w id th leading t o a l l o r Q p o r t i o n o f a

Darkina areat s h a l l NOT exceed 50% o f the 2. HL3 can be s u b s t i t u t e d w i t h o ther hard

surfaces ( i e. paving stone, concrete 1 QS approved by t h e Contract Admin is t ra to r .

- lot f ron tage or a maxinwm of 6.0 metres

(19 .7 -Feet)* whichever is LESS. (2-1-007591

CITY OF LONDON STANDARD DRAWING

SINGLE FAMILY AND MULTI-FAMILY DRIVEWAY ENTRANCES WITH BOULEVARD

Page 38: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

A

L

DWG SR-13

1500 CONTINUOUS S T R I P -.....A OF 8 5 0 2 GLASGRID OR E Q U I V A L E N T (SHADED A R E A )

FA- DATE APPROVED BY *003-10-17 CITY ENGINEER ple &

M I L L TO S P E C I F I E D DEPTH /-

A

3

OPSD CONCRETE CURB AND GUTTER

\

r S P E C I F I E D HOT M I X MATERIALS AND DEPTHS

M I L L TO M I N I M U M ---T

DEPTH OF 90rnrn /i A S P E C I F I E D GRANULAR TYPES AND DEPTHS

50rnm M I N . S P E C I F I E D - HOT M I X M A T E R I A L

40 mm H . L . 8 COURSE

WIDENING TO MATCH LAYER IN . . - _ v?; . , , . . . . , - . v . , - .

P '0 0,' 0 '0 0: 0 -0 .&): 9 '0 0: 0 '0 .& 0 '0 .o,s 0 '.I 8502 GLASGRID OR APPROVED EQUAL

\-EXISTING GRANULAR B E D D I N G

SECTION A - A NOTES:

1 . A L L DIMENSIONS ARE IN M I L L I M E T R E S 2' M I N . DEPTH OF E X I S T I N G UNLESS OTHERW I SE SHOWN ASPHALT MUST BE 150mm

CITY OF LONDON STANDARD DRAWING

Page 39: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

EXISTING ROAD

A i

I

300

JOINTS SQUARE OFF NOT I N CUTS I N WHEEL PATHS EX ASPHALT

(NO IRREGULAR SHAPES 1 I r---------

MATCH TO EX1 S T I NG

NOTES:

1 . MIN. 3 0 0 m CLEARANCE NEEDED FOR CURB MACHINE ON MATCH POINTS TO EXIST ING

2. SQUARE OR CUTS-NO IRREGULAR SHAPES. TO ALLOW USE OF CONVENTIONAL PAVING EQUIPMENT.

3 .JOINTS TO MATCH NEW ASPHALT TO E X I S T I N G TO FOLLOW OPSS 310 (C.0.L. SR)

EX STORM MH

EX SAN MH

I

z: 3:

Z 0

I- o 3 Ly: t- Ln

w

Z 0 0

3 w Z

JOINTS NOT I N WHEEL PATHS

CITY OF LONDON

PAVEMENT CUT GUIDELINES MATCHING NEW CONSTRUCTION TO EXjSTING ASPHALT

Page 40: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003

London CITY OF’ LONDON

SUPPLEMENTAL STANDARDS FOR SEWER AND WATER (SW)

The Ontario Provincial Standards (OPSS) are amended as follows:

I N D E X

Section

405.07

407.07 407.09 407.10

410.03 410.05 410.07 410.09 410.10

5 14.05 514.07

538.07 538.08

Description Page

O.P.S.S. 405 - CONSTRUCTION SPECIFICATION FOR PIPE SUBDRAINS Construction ......................................................................................................... SW-1

O.P.S.S. 407 - CONSTRUCTION SPECIFICATION FOR MAINTENANCE HOLE, CATCH BASIN, DITCH INLET AND VALVE CHAMBER Construction ......................................................................................................... S W -2 Measurement for Payment.. ................................................................. i.. .............. SW-2 Basis of Payment .................................................................................................. SW-2

O.P.S.S. 410 - CONSTRUCTION SPECIFICATIONS FOR P P E SEWER CONSTRUCTION BY OPEN CUT METHOD Definitions.. .......................................................................................................... SW-3 Materials.. .................................. ..; ........................................................................ SW-3

Measurement for Payment. ................................................................................... SW-6 Basis of Payment .................................................................................................. SW-7

Design And Construction ..................................................................................... SW-4

0.P.S.S. 514 - CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING AND COMPACTION Materials ............................................................................................................... SW-8 Construction ......................................................................................................... SW-8

O.P.S.S. 538 - CONSTRUCTION SPECIFICATIONS FOR SUPPORT SYSTEMS Construction. ............................................................................. S W - 9 Measurement for Payment. ............................................................. SW-9

Page 41: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003

I N D E X (cont'd)

Description Section

701.01 70 1.02 70 1.03 70 1.05 70 1.07 701 -09 701.10

1003.05

101 0.05

O.P.S.S. 701 - CONSTRUCTION SPECIFICATION FOR WATERMAIN .

CONSTRUCTION BY OPEN CUT METHOD Scope.. ................................................................................................................ S W- 1 0 References .......................................................................................................... S W- 1 0 Deftnitions ....................................................................................................... :.. SW-13 Materials.. .............................................................................. SW-13 Construction ........................................................................................... .. ........... S W -2 8 Measurement For Payment.. .................... .:. ........................................................ SW-41 Basis Of Payment ............................................................................................... SW-42

O.P.S.S. 1003 - MATERIAL SPECIFICATION FOR AGGREGATES - HOT MIXED, HOT LAID, ASPHALTIC CONCRETE Materials ............................................................................................................. SW-43

O.P.S.S. 1010 - MATERIAL SPECFICATION FOR AGGREGATES - GRANULAR A, B, M AND SELECT SUBGRADE MATERIAL Materials.. ........................................................................................................... SW-44

STANDARD DRAWINGS FOR ROADS .......................................................................................... SW-45

SELECTED ONTARIO PROVINCIAL STANDARD DRAWINGS TO BE USED ON ALL DESIGN, CONSTRUCTION AND RECONSTRUCTION MAINTENANCE PROJECTS ....................................................... SW-49

Page 42: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3, zuw sw-1

405.07

405.07.01

O.P.S.S. 405 CONSTRUCTION SPECIFICATION FOR PIPE SUBDRAINS

CONSTRUCTION

General

Subsection 405.07.01, paragraphs a) and b) are deleted in their entirety and replaced by the following:

Pipe subdrains shall be provided on both sides of all catch basins installed in hard surface areas. Subdrains are not required in rear lot catch basins or in catch basins located in grassed areas.

All subdrains shall be 1 50mm diameter, minimum 3 .Om long wrapped in terrafuc 270R or approved equal, either of perforated corrugated steel pipe or PVC pipe. Perforations shall consist of 6 m holes in four rows positioned at 4, 5 , 7 and 8 o’clock and 75mm apart longitudinally in both materials.

Pipe subdrains shall be connected to the 200mm knockout provided in the catch basin pot, typically at subgrade elevation, shall be laid parallel with the curb and at the same grade as fmished road grade. Pipe subdrains shall be capped at the upstream end with a pre-manufactured end cap or with cement brick and non shrink grout.

Page 43: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-2

407.07

4 07.07.2 0

407.09

407.09.01.01

407.10

407.10.01

O.P.S.S. 407 CONSTRUCTION SPECIFICATION FOR MAINTENANCE HOLE, CATCH BASIN, DITCH INLET AND VALVE CHAMBER

CONSTRUCTION

Installation of Extension Stems and Boxes for Valve Chambers

Subsection 407.07.20 is amended by the addition of the following:

All service boxes that fall within a concrete sidewalk or driveway shall have a 1 O O r n m piece of 10M (#3 bar - 0.375 dia.) rod welded horizontally to the underside of the service box cover, approximately 40mm below the surface, to prevent frost heave.

MEASUREMENT FOR PAYMENT

Maintenance Hole, Catch Basin, Ditch Inlet and Valve Chamber

Clause 407.09.01.01 is amended by the addition of the following:

For the purpose of relocating existing catch basins, the requirements of O.P.S.S. 407 and 5 10 shall apply and will be paid under the appropriate item in the Form of Tender. Measurement for payment of the installed salvaged catch basin will be paid by the unit (each).

BASIS OF PAYMXNT

Maintenance Hole - Item Catch Basins - Item Ditch Inlets - Item Valve Chambers - Item Manhole Leakage Testing - Item

Subsection 407.10.0 1 is amended by the addition of the following:

Relocate Existing Catch Basin - Item Relocate Existing Ditch Inlet Catch Basin - Item

Page 44: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-3

410.03

410.05

410.05.01 410.05.01.01

O.P.S.S. 410 CONSTRUCTION SPECIFICATIONS FOR

PIPE SEWER CONSTRUCTION BY OPEN CUT METHOD

DEFINITIONS

Section 410.03 is amended by the addition of the following definitions:

Bedding Material: means the material placed from the earth subgrade to the springline of the pipe.

Cover Material: means the material placed from the springline of the pipe to 300 mm above the pipe.

Granular 'C' Provisional Quantity: means the material to be used as trench bacKill between the cover material and the road or earth subgrade, as a substitute for unsuitable native bacHi11, as directed by the Contract Administrator.

MATERIALS

PIPE MATERIALS General

Subsection 410.05.01.01, fxst paragraph, is deleted in its entirety and replaced by the following:

Pipe size, class, material and type shall conform as shown in the contract. The following is an overall list of sewer pipe approved for use on City projects by the Owner for sizes certified by CSA. A substitution from that specified in the contract may be considered in accordance with the General Conditions.

(a) polyvinyl chloride (P.V.C.) pipe - smooth wall (CSA B182.2) - l O O m r n - 600mm inclusive 1. Ipex 2. Royal

(b) polyvinyl chloride (P.V.C.) pipe - smooth wall (CSA B 182.2) - 1 0Omm - 375mm inclusive 1. REHAU DURALOC

(c) ribbed polyvinyl chloride (P.V.C.) pipe - 200 m to 600 ~lllzl inclusive (CSA B 182.4) 1. Loc-Pipe 2. IPEX 3. Royal Pipe Co. (KOR-FLO) - 200mm to 450mm inclusive 4. Rehau RauRib ribbed PVC pipe - 375mm, 450mm, and 600mm

Page 45: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 s w - 4

410.07

410.07

410.07.02

410.07.12

All PVC fabricated and moulded fittings shall be C.S.A. certified.

(d) high-density polyethylene (HDPE) annular profile pipe - for use on storm sewers only, 200mm. to 600m1n. inclusive with integral bell and spigot (CSA B182.6) 1)Big 0 - Boss Poly-Tite 2)Soleno - Solflo Max

All HDPE fabricated pipe and moulded fittings shall be CSA certified.

Concrete pipe material must comply with the following C.S.A. requirements.

(1) (2) Reinforced - CANKSA257.2

Non-Reinforced - CANKSA257.1 lOOmm - 600mm

CONSTRUCTION

The title “Construction” for Section 410.07 is deleted in its entirety and replaced by the following:

DESIGN AND CONSTRUCTION

Preservation and Protection of Existing Facilities

Clause 410.07.02 is deleted in its entirety.

Service Connections

Except for paragraph 4, Subsection 410.07.12 is deleted in its entirety, and replaced by the following:

1 .Service Connections For New Sewer Construction

Concrete Pipe

Where applicable, concrete pipe main may be core drilled and fitted with a KOR - N -TEE Flexible Connector or a Core Bell Concrete Adaptor (for sizes 1OOm - 250mm only).

Factory tees for PVC pipe connections shall be manufactured with a two step/gasket system and grouted around the PDC on the outside of the tee after the connection is made.

Approved factory tees for 300mm - 600mm pipe diameters are:

Centennial Concrete Pipe & Products Inc. “FILLET PVC TEE” or approved equivalent.

Approved factory tees for 675mm - 1800mm pipe diameters are:

Centennial Concrete Pipe & Products Inc. “QUK TEE” or approved equivalent.

Page 46: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SW-7

Substitutions. The volume of granular material substituted will be based on actual field measurements.

410.09.02 Plan Quantity Measurement - Delete

410.10 BASIS OF PAYMENT

Subsection 410.10.01, second paragraph is deleted in its entirety. Subsection 410.10.01 is amended by the addition of the following:

410.10.01 Pipe Sewers - Item Utility Supports - Item Infiltr a ti0 n Exfiltration Tests - Item Testing with Water - Item Low Pressure Air Testing - Item Deflection Testing of Pipe Sewers - Item Low Pressure Air Tests - Item

If the average manhole or sewer depth (invert to design grade), differs fkom those shown in the Form of Tender for any reason, an adjustment will be made to the Contract Price only if the difference is more than 0.30m (1 2").

When pre-qualification leakage, infiltration, exfiltration, deflection and low pressure air tests are required, payment will be made under the appropriate item in the Form of Tender.

When imported Granular 'C' trench backfill is specified in a Special Provision, and the Contract Administrator directs that native, selected native material, and/or selected native site material be used as trench backfill, the credit to the Corporation shall be based on the current market price of Granular 'C' materials delivered to the job site, and the volume in tonnes of native materials that is substituted.

Associated costs to complete the video inspection are included under the item "Pipe Sewers".

Partial payment will be made on pipe sewer installed only.

Page 47: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-9

538.07 53 8.07.0 1

538.07.03

538.09

538.09.01

O.P.S.S. 538 CONSTRUCTION SPECIFICATION FOR

SUPPORT SYSTEMS

CONSTRUCTION General

Subsection 538.07.01 is amended by the addition of the following requirements:

The requirements stated on the Supplemental Standard Drawings W-CS-69, sheets #1 and #3 shall be adhered to.

Removal, Backfilling and Compacting

Subsection 538.07.03 is amended by the additional requirements stated on Drawings W-CS-69, sheets #2 and #3 in the Standard Drawings for Sewer and Water.

MEASUREMENT FOR PAYMENT

Support System Left in Place

Subsection 538.09.01 is deleted in its entirety.

Page 48: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-10

O.P.S.S. 701 CONSTRUCTION SPECIFICATION FOR

WATERMAIN INSTALLATION BY OPEN CUT METHOD

701 . O l SCOPE

This specification covers the requirements for constructing watermains, service connections and appurtenances in open cut.

701.02 REFERENCES

Clause 701.02 is amended by adding the following:

City of London

City of London General Requirements and Design Specifications for the Water Distribution System

Ontario Provincial Standard Specifications, Construction:

OPSS 501 Compacting

Canadian Standards Association Standards:

B137.2 - PVC Injection - Moulded Gasketed Fittings for Pressure Applications

B137.3 - Rigid Polyvinyl Chloride (PVC) Pipe for Pressure Applications

CAN/CSA-A5/A8/A362-M88-Portland CemenVMasonry Cement/Blended Hydraulic Cement

American Society for Testing and Materials Standards:

A 183-89(R90) - Carbon Steel Track Bolts and Nuts

A 276-90 - Stainless and Heat-Resisting Steel Bars and Shapes

B 88-M89 - Seamless Copper Water Tube

B 766-86 - Electrodeposited Coatings of Cadmium

C 361 M90 Reinforced Concrete Low-Head Pressure Pipe (Metric)

D 1784 - Rigid Poly(Viny1 Chloride) (PVC) Compounds and Chlorinated Poly(Viny1 Chloride) (CPVC) Compounds

D 3035-89a - Polyethylene (PE) Plastic Pipe (SDR-PR) Based on Controlled Outside Diameter

D 31 39-89 - Joints for Plastic Pressure Pipes Using Flexible Elastomeric Seals

D 3350-84 - Polyethylene Plastics Pipe and Fittings Materials

Page 49: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-11

F 1674 - Test Method for Joint Restraint Products for Use with PVC pipe

American Water Work Association

C104/A21.4-95 - ANSI Standard for Cement-Mortar Lining for Ductile-Iron Pipe and Fittings for Water

C105/A21.5-99 - ANSI Standard for Polyethylene Encasement for Ductile Iron Systems

C l 1 O/A21 .I 0-98 - ANSI Standard for Ductile-Iron and Gray-Iron Fittings, 3in. Through 48 in., for Water

C11 llA21 .I 1-00 - ANSI Standard for Rubber - Gasket Joints for Ductile-Iron and Gray-Iron Pressure Pipe and Fittings

C116lA21 . I648 -ANSI Standard for Protective Fusion Bonded Epoxy Coatings for the Interior and Exterior Surfaces of Ductile Iron and Grey Iron Fittings for Water Supply Services

C151/A21.51-02 -ANSI Standard for Ductile-Iron Pipe, Centrifugally Cast, for Water

C153/A21.53-00 -ANSI Standard for Ductile-Iron Compact Fittings, 3" through 24" for Water Service

C200-97 - Steel Water Pipe 6 inches and Larger

C205-00 - Cement Mortar Lining of Pipe and Fittings

C206-97 - Field Welding of Steel Water Pipe

C207-01 - Steel Pipe Flanges for Waterworks Service - Sizes 1OOmm Through 3600mm

C208-01 - Dimensions for Fabricated Steel Water Pipe Fittings

C209-00 - Cold Applied Tape Coatings for the Exterior of Special Sections, Connections, and Fittings for Steel water Pipelines

C210-97 - Liquid Epoxy Coating Systems for the Interior and Exterior of Steel Water Pipelines

C213-01 - Fusion Bonded Epoxy Coating for the Interior and Exterior of Steel Water Pipelines

C214-00 - Tape Coating Systems for the Exterior of Steel Water Pipelines

C301-99 - Prestressed Concrete Press Pipe, Steel Cylinder Type

C302-95 - Reinforced Concrete Pressure Pipe, Non-Cylinder Type

C500-02 - Metal Seated Gate Valves for Water supply Services

Page 50: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-12

C502-94 - Dry-Barrel Fire Hydrants

C504-00 - Rubber-Seated Butterfly Valves

C509-01 - Resilient-Seated Gate Valves for Water Supply Service

C550-01 - Protective Epoxy Interior Coatings for Valves and Hydrants

C600-99 - Installation of Ductile Iron Watermains and Their Appurtenances

C602-00 - Cement Mortar Lining of Water Pipelines in Place - 100mm andLarger

C605-94 - Underground Installation of Polyvinyl Chloride (PVC) Pressure Pipe and Fittings for Water

C651-99 - Disinfecting Watermains

C800-01 - Underground Service Line Valves and Fittings

C900-97 - Polyvinyl Chloride (PVC) Pressure Pipe, and Fabricated Fittings, 1 OOmm Through 300mm for Water Distribution

C903-02 - Polyethylene-Aluminum-Polyethylene & Crosslinked Polyethylene Composite Pressure Pipes, 12mm Through 50mm for Water Service

C905-97 - Polyvinyl Chloride (PVC) Pressure Pipe, and Fabricated Fittings, 350mm Through 1200mm for Water Transmission and Distribution

C907-91 - Polyvinyl Chloride (PVC) Pressure Fittings for Water 1OOmm Through 200mm

M9 - Concrete Pressure Pipe

M I 1 - Steel Pipe - A Guide for Design and Installation

M23 - PVC Pipe - Design and Installation

M41 - Ductile Iron Pipe and Fittings

Canadian General Standards Board Standards:

41-GP-25M - (October 1977) - Pipe, Polyethylene, for the Transport of Liquids

NS F In ternationa I

NSF Standard No. 60 - Drinking Water Treatment Chemicals - Health Effects

NSF Standard No. 61 - Drinking Water System Components - Health Effects

UNI/BELL Plastic Pipe Association

UNI-Bell Handbook of PVC Pipe - Design and Construction

Page 51: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SW-13

701.03

701.05

701.05.01

701.05.02

DEFINITIONS

Clause 701.03 is amended by the addition of the following:

Centre Line: means a line horizontally bisecting the pipe.

Watermain: means an installation designed for the conveyance of potable water under pressure, using pre-formed or pre-cast pipe sections, circular in cross-section, laid end to end using suitable jointing materials.

Weakly Cemented Fill: means any combination of granular material with low percentages of cement and/or other cementitious material such that the strength is in the order of 0.4 MPa at 28 days.

MATERIALS

Genera I

Clause 701.05.01 is amended by the addition of the following:

Unless otherwise specified, watermain test pressure shall be 1030 KPa (I 50 p.s.i.).

Ductile Iron Pipe Products

Clause 701.05.02 is deleted in its entirety and replaced by the following:

Ductile iron (DI) with cement mortar lining and polyethylene encasement. Pipe shall be new and shall conform to AWWA C151 up to and including 450 mm diameter. Cement mortar lining shall conform to AWWA C104. Polyethylene encasement shall conform to AWWA ClO5. Hyprotech coating for 600 mm diameter and larger shall be a fibre reinforced polymer concrete or as specified by the Contract Administrator.

Pipe shall have push-on joints. Thickness class shall be class 52 for all diameters up to and including 300 mm diameter and Class 51 for 400 mm and 450 mm diameter. Joint gaskets and lubricants shall conform to AWWA C111. Copper strips, wedges or other approved devices to provide electrical continuity shall be supplied by the pipe manufacturer and approved by the Contract Ad mi n i stra to r.

All cast iron (CI) and ductile iron (DI) fitting (including fire hydrant boots) shall have a 17 pound Magnesium Anode. Anode must be attached to fitting using a CADW ELD and coated with mastic. Anodes and installation must be approved by the Contract Administrator.

DI fittings shall have distinctly cast on them. the pressure rating, nominal diameters of openings, manufacturers identification and have "DI" or "Ductile" cast on them in accordance with ANSVAWWA C l 10-871A21 .I 0.-87.

Push-On Joint Ductile Iron Fittings produced in strict accordance with all applicable terms and provisions of ANSVAWWA C153/A21.53. Joints shall be

Page 52: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SW-14

in accordance with C11 UA21 .I I with bell sockets designed to receive pressure pipe O.D.=s as specified in C151/A21.51 and (3900. The working pressure rating shall be 350 psi. Rubber rings shall be furnished by the fitting manufacturer.

Fittings shall be:

(a) ductile iron (DI) conforming to ANSVAWWA C1 IO-871A21 .I 0-87 with a minimum class of 350. DI fittings shall be cement mortar lined in accordance with ANSVAWWA C1041A21.4;

(b) gray iron (CI) push-on joints conforming to AWWA CI IO-87 with joints conforming to AWWA Cl11. CI fittings are not required to be lined;

Approved Joint Restraints are:

(a) Joint Restraint Device for DI Pipe To Mechanical Joint Fittings: 1 OOmm(4”) to 300mm(l2”)-Smith Blair Model 981 (colour code blue) 1 OOmm(4”) to 300mm( 12”)-Romac “Grip Ring” (with black grip ring) 1 OOmm (4”) to 300mm (1 2”) - EBAA Iron Series I I00 Megalug 1 OOmm (4”) to 300mm (1 2‘7 - Star Series 1000 Tie Rod System

Restraining glands shall be manufactured of high strength ductile iron conforming to the requirements of ASTM A536, Grade 65-45-1 2 (minimum) , (400 mm to 600 mm) shall be manufactured of structural steel conforming to the requirements of ASTM A36.

(b) Joint Restraint Device for DI Pipe to Push On Fittings 1 OOmm (4“) to 300mm (1 2”) - Uniflange Series 1300 1 OOmm(4”) to 300mm( 12”)-Smith Blair Model 982 (colour code blue) I OOmm(4”) to 300mm( 12”)-Clow Series 300

701.05.03 Concrete Pressure Pipe Products Clause 701.05.03 is deleted in its entirety and replaced by the following:

Manufacture: to AWWA C30 1 Joints : Fittings: to AWWA C301. Pipe class:

bell and spigot to AWWA C301 and bonded together.

as specified elsewhere with minimum of Class 14

Outlets are to be fabricated such that there is no increase in the outside diameter of the pipe. Outlets are to be shop fabricated by the supplier.

Flanges: to AWWA C207, Class D unless otherwise noted

Protective coating on exposed portion of joint rings, two coats of Rust-Oleum No. 745 or approved equal.

Submissions: Affidavit of Com p I iance Des i g n ca I cu la t io n s Details of specials and fittings Details of materials and methods of welding Rubber Gasket Material Test Reports Steel Test Reports

Page 53: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SW-15

Ag g reg ate samples Tabulated La you t Schedule

Type of Cement: use Type 20 cement on the outside of all manufactured pipes and fittings and use Type 10 cement on the inside of all manufactured pipes and fittings.

Restrained Joints: Restrain all joints as determined by the manufacturer and approved by the Contract Administrator.

Joints shall be designed for the same design, test and surge pressure ratings as the pipeline in accordance with AWWA - M9 Concrete Pressure Pipe.

Restrained joints to be snap-ring type, hold fast coupling or flexible welded joints.

Increase pipe reinforcement as required to transmit thrust forces. Advise Contract Administrator if increase pipe reinforcement length extends beyond last restrained joint shown on the Contract Drawings.

Adaptors, make-up pieces and spacers: fabricate from steel pipe and line, in accordance with this Specification.

Closures: two fabricated short pipes with plain steel ends connected by a split welding sleeve coupling.

All joints to be grouted and encapsulated with diaper provided by the manufacturer.

A solid 12 gauge TWU copper wire must be supplied along the full length of the pipe to provide electrical continuity for location purposes.

701.05.04 Polyvinyl Chloride Pipe Products

Clause 701.05.04 is deleted in its entirety and replaced by the following:

Polyvinyl Chloride (PVC) pipe up to and including 300 mm diameter shall conform to AWWA C900, to be certified by the Canadian Standards Association to CSA Standard B137.3, and shall be Class 150, DR18, with Cast Iron O.D. dimensions.

Polyvinyl Chloride (PVC) pipe 400 mm diameter to 600 mm diameter shall conform to AWWA C905 Class 165, DR25, to be certified by the Canadian Standards Association to CSA Standard 9137.2 and have Cast Iron O.D. dimensions. Polyvinyl Chloride (PVC) pipe greater than 600 mm diameter shall be as specified elsewhere.

A solid 12 gauge TWN copper wire must be supplied along the full length of the pipe to provide electrical continuity for location purposes.

All PVC pipe and fittings shall be blue in colour.

Page 54: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SW-16

All cast iron (CI) and ductile iron (DI) fittings shall have a 17 pound Magnesium Anode. Anode must be attached to fitting using a CADWELD and coated with mastic.

Anodes and installation must be approved by the Contract Administrator.

Submittals by the pipe manufacturer in the form of a Construction Report will include the following:

(a) Letter of Compliance (b) (c)

Summary of fittings and specials Restrained length calculations and drawings

Fittings shall be:

PVC injection moulded fittings in sizes up to and including 200 mm with push on joints (for use with Class 150 DR18 PVC pressure pipe conforming to AWWA Standard C900 and to CSA Standard B137.3 having cast iron O.D)., shall conform to AWWA Standard C907, shall be UL listed and FM approved, and shall be certified by the Canadian Standards Association to CSA Standard B137.2;

PVC fabricated fittings in sizes 300mm (12") to 750mm (30") with push on joints (for use with Class 165 DR25 PVC pressure pipe conforming to AWWA C905 and CSA Standard 6137.3 having cast iron O.D.) shall be UL listed and FM approved, and shall be certified to CSA Standard B137.3;

Ductile Iron (DI) conforming to C153 with a minimum class of 350. DI fittings shall be cement mortar lined in accordance with ANSVAWWA C104/A21.4. DI fittings shall have distinctly cast on them the pressure rating, nominal diameters of openings, manufacturer's identification and have "DI" or "Ductile" cast on them in accordance with C153;

Cast Iron (CI) push-on joints conforming to AWWA C110-87 with joints conforming to AWWA C111. CI fittings are not required to be lined.

Joint Thrust Restraints:

All joint thrust restraint devices must meet or exceed the minimum requirements of ASTM F 1674-96 (Standard Test Method for Joint Restraint Products for use with PVC Pipe), be UL listed and FM approved. Restraining glands (100 mm to 300mm) shall be manufactured of high strength ductile iron conforming to the requirements of ASTM A536, Grade 65-45-12 (minimum), (400 mm to 600 mm) shall be manufactured of structural steel conforming to the requirements of ASTM A36.

Page 55: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-17

All fittings and joints must be restrained as determined by the Manufacturer and approved by the Contract Administrator.

Approved Restrainers are:.

a) Restraining PVC Pipe to Mechanical Joint Fitting (ie. tees, bends, etc.) 100 mm (4“) to 600 mm (24“) - Uni-Flange Series 1300 100 mm (4”) to 600 mm (24“) - Clow Series 300 100 mm (4”) to 300 rnm (12”) - EBAA Iron Series 1500 100 mm (4”) to 300 mm (1 2”) - Smith Blair Model 981 (colour code blue) 100 mm (4”) to 300 mm (12”) - Sigma PV-LOC Model PVM 100 mm (4”) to 200 mm (8”) - Romac Series 600 100 mm (4”) to 300 mm (1 2”) - Romac “Grip Ring” (with BLACK grip ring) 400 mm (16”) to 600 mm (24”) -EBAA Iron Series 2000PV 400 mm (16”) to 600 mm (24”) - Romac Series 470MJ

b) Restraining PVC Pipe to PVC Injection Moulded Fittings(ie.tees, bends, etc.) 100 mm (4”) to 200 mm (8“) - Uni-Flange Series 1360 100 mm (4”) to 200 mm (8”) - Clow Series 360 100 mm (4”) to 200 mm (8”) - EBAA Iron Series 2500 100 mm (4”) to 200 mm (8”) - Sigma PV-LOC Model PVPF

c ) Restraining PVC Pipe to PVC Fabricated Fitting (ie. tees, bends, etc.) 250 mm (1 0”) to 600 mm (24”) - Uni-Flange Series 1360 100 mm (4”) to 200 mm (8”) - Clow Series 360

d) Restraining PVC Pipe Standard Bell and Spigot Push On Joints 100 mm (4”) to 600 mm (24”) - Uni-Flange Series 1390 100 mm (4”) to 300 mm (1 2”) - Smith Blair Model 982 (colour code blue) 100 mm (4”) to 300 mm (12”) - Sigma PV-LOC Model PVP 400 mm( 16”) to 600mm (24”) - Romac Series 470SJ 100 mm (4”) to 600mm (24”) - Clow Series 390

701.05.05 Polyethylene Pipe Products

Clause 701.05.05 is deleted in its entirety and replaced by the following:

Approved in special applications only. Polyethylene (PE) pressure pipe shall conform to CSA B 137.1, ASTM D3035 and D3350, and CGSB 41-GP-25 M.

Joints shall be thermal butt fusion type.

Fittings shall be gray or ductile iron and shall conform to AWWA C11 OIA21 .I 0, flanged.

701.05.06 Steel Pipe Products

Clause 701.05.06 is deleted in its entirety and replaced by the following:

Manufacture to: AWWA C200 manufactured to meet the requirements of ASTM A139C, Steel plate: to ASTM A572, Grade 42.

Page 56: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SW-18

Nominal pipe sizes: to be actual inside diameters after cement mortar lining, for watermains inside diameter for chamber piping 300 mm and under, and outside diameter for chamber piping 350 mm and over.

Watermain: Bell and spigot joints, push-on, with rubber gaskets to AWWA C200.

Joints to have a safe working pressure equal to the pipe class.

Bends forming each bell and shall have a radius of at least 12 times the pipe wall thickness.

Rubber qaskets to: AWWA C200.

Rubber gasketed joints to be bonded with electrical cables in accordance with the manufacturer's recommendations.

Restrained : Flexible welded joints or harness fabricated by pipe manufacturer in accordance with AWWA Manual M I 1, Steel Pipe, Chapter 13.

Watermain Field Welded Joints: Bevel end, lap joint or butt-strap to the requirements of AWWA C206.

Fitti nqs to:

Flanges to:

Design stress:

Chamber pipinq:

AWWA C208.

AWWA C207, Class D unless otherwise noted

50% of minimum yield point.

a) 300 mm diameter and smaller shall be schedule 40. b) 350 mm diameter and larger shall be 10 mm. c) Paint interior of pipes and fittings to AWWA C210. d) Coat exterior pipes and fittings with two coats

Rustoleum No. 745 or approved equal.

Cement mortar interior lining of pipe and fittings to AWWA C205.

Tape coating of exterior surfaces of pipe to AWWA C214.

Coating thickness to be 80 mils, consisting of primer, 20 mils inner layer and two 30 mils outer layers.

Tape coating of exterior surfaces of joints, specials and fittings to AWWA C209.

Coating thickness to be 70 mils, consisting of primer and two 35 mils layers.

Page 57: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-19

Field Repairs: Cement mortar lining of interior surfaces to Appendix A of AWWA C205.

Tape coating of exterior surfaces to AWWA C209.

Submissions Required:

Affidavit of Compliance. Design Drawings and calculations for pipe wall thickness and restrained joint system. Details of materials and methods of welding. Rubber gasket material test reports. Length of pipe ends. Details of specials and fittings. Hydrostatic proof-test reports.

705.05.07 Po I yb utyle ne Plastic Pipe

Clause 701.05.07 is deleted in its entirety.

701.05.09 Composite Pipe

Clause 701.05.09 is deleted in its entirety and replaced by the following:

Polyethylene-Aluminum-Polyethylene Pressure Pipe shall conform to AWWA C903-02, CSA B137.10, ASTM F1281 and NSF 61 and shall be Blue in colour.

Approved Pol yet h ylene-AI u mi nu m- Pol ye th ylene pipe:

Blue KlTEC as manufactured by IPEX

701.05.1 0 Valves

701.05.10.01 General

Clause 701.05.10.01 is deleted in its entirety and replaced by the following:

Valves shall be capable of a seat differential test pressure equal to the Design Pressure and to a hydrostatic shell test pressure at least 50% in excess of the design pressure.

Valves for buried installation shall have mechanical or bell ends as required.

Shaft spindles shall have O-ring seals of resilient materials.

Valves shall open clockwise.

Page 58: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-2 0

701.05.10.02 Service Line Valves

701.05.10.03 Gate Valves

Clause 701.05.1 0.03 is deleted in its entirety and replaced by the following:

Valves shall be gate valves conforming to AWWA C500 or resilient seat gate valves conforming to AWWA C509.

All valves must be thrusted as per W-CS-43 SH7-1.

Epoxy coated gate valves do not require anodes.

All valves up to 300 mm diameter must be push-on joint and epoxy coated inside and out (minimum of 3 mm thickness) and conforming to AWWA C-550. All valves must open right (Clockwise) and have stainless steel nuts and bolts. Valves shall work equally well with full pressure applied on either side of valve.

Approved gate valves are: Approved resilient seat gate valves are:

Mueller A2380-21 Darling (Canada Valve) No. 55 Kennedy Fig. 571X Clow F5000 Series Bibby NRS

Clow RIW F-6100 and F-6112 Mueller A2370-21 AVK for PVC and DI

Valve boxes shall be CI 130 mm screw type.

Approved boxes are:

For 1.2 m to 1.65 m depth Bibby Code 7130

For 1.5 m to 1.9 m depth Bibby Code 7135

Extension pieces must be used for depths greater than 1.9 m.

Valve rods shall be made by the Corporation according to Drawing Number W- CS-6.

There will be a charge for labour and material.

Geared operators shall consist of carburized alloy steel spiral bevel gears with shafts operating in anti-friction bearings. Geared operators are to be self- contained units, permanently lubricated and totally enclosed in an impact resistant cast iron housing.

Page 59: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-2 1

701.05.10.04 Butterfly Valves

Clause 701.05.1 0.04 is deleted in its entirety.

701.05.10.05 Air Release Valves

Clause 701.05.10.05 is deleted in its entirety and replaced by the following:

Air release valves to be combination air release valves, employing Kinetic opera t i n g p ri n ci p I e.

Shall be flanged faced and drilled.

Shall have a cast iron body.

Shall have stainless steel or plastic balls.

Shall be epoxy coated inside and out.

Each air release valve shall be provided with an isolation gate valve with bevel gear.

Bolts and nuts shall be stainless steel Type 304.

Approved Air Release Valves are:

G. A. Industries Inc. Crispin

701 . O M 0.06 Tapping Valves

Tapping valves shall conform to AWWA C500 and must open right. (Clockwise)

Approved Resilient Seat Tapping Valves may be substituted by Resilient Seat Gate Valves.

Approved tap pi nq valves are: Approved resilient seat tappinq valves:

Mueller - H667 Darling (Canada Valve) - No. 565

McAvity No. 20675R Mueller A2370-I 6

Kennedy - 950X CIOW RMI F-6114

Approved tapping sleeves for DI, CI and PVC pipe are:

Ford Model No.FTSC Meuller Model No. H-604 Smith Blair Model No. 622 Robar Model No. 6606 Romac Model No. FTS420 (not for use on PVC pipe) Romac Model FTS419

Page 60: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-2 2

701.05.1 1 Hydrants

Clause 701.05.1 1 is deleted in its entirety and replaced by the following:

Refer to W-SC-I for installation specifications.

Hydrants shall conform to AWWA C502 for dry barrel hydrants.

Hydrants must open right (Clockwise).

Hose connections threads and operating nut to be to Ontario Provincial Standard Specifications and comply to all ULC Standards.

Pumper connection waterway to be 1 14 mm nominal size with four (4) threads per 25 mm at an O.D. of 146 mm.

Seats, seat rings and seat casings for valves and drain valves shall be bronze.

Fire hydrants shall have a minimum bury of 1.7 m and maximum bury of 1.9 m, measured from the base of the fire hydrant boot to finish grade.

Fire hydrant extensions as required for deeper bury are to be obtained from the fire hydrant manufacturers. A maximum of one (1) 300mm extension is permitted per hydrant.

Fire hydrants shall have a chrome yellow high gloss exterior paint over quick dry red oxide primer.

Hydrants shall be installed a minimum of I .5m from the edge of a driveway.

The hydrant shall have push-on joints conforming to ANSVAWWA G I 1 '!/A21 .I I.

All new fire hydrants shall be three-way with two (2) standard hose connections and one (I) STORZ connection with blue cap. STORZ nozzle to be bronze ASTM B584, nozzle cap to be cast iron and painted Multiguard No. 2500 Blue 50005.

The City of London Fire Department reserves the right to select the required hydrant(s), appurtenances, and location of hydrant(s) depending on the fire risk of the area.

Approved hydrants are:

Canada Valve Century McAvity M-67 with break flange AVK

Page 61: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-2 3

701 .OM2 Service Connections Fittings and Appurtenances

Clause 701.05.12 is deleted in its entirety and replaced by the following:

701.05.12.01 Service Saddles:

20 mm and 25 mm services may be direct tapped into all sizes of DI and CI mains except a service saddle must be used for a 25 mm service into a 100 mm main. Service saddles must be used for all sizes of service into PVC pipe and for 40 mm and 50 mm services into CI and DI pipe.

All saddles shall have AWWAthread outlet. Saddles for DI and CI and AC pipe shall have ductile iron epoxy body with electro galvanized steel double straps and bolts.

Saddles for PVC pipe shall be full circumference wide band with stainless steel band, nuts, bolts and outlet. Band shall be Type 304 Stainless Steel of minimum 18 gauge thickness.

Approved service saddles are:

Romac style 304 for 20 to 25 mm outlets Romac style 306 for 40 to 50 mm outlets Cambridge Brass Double Bolt Series 403 for 20 to 50mm Ford FS 303 Mueller 521 - 529 Servi-Seal Clamps for 100 mm to 300 mm main Rockwell 372 for 20 to 50mm outlets Robar Series 2616 for 20 to 50 mm outlets (double bolt)

Approved PVC Injection Moulded Tap Tee for 150 mm and 200 mm PVC C900 CLEO Dr 18 pipe are:

lpex C907 for 20 to 50 mm outlets

Connections to steel mains for 100 mm and larger services and private mains shall be made using Maloney Insulating sets. Refer to Standard Drawings W-CS- 24.

701.05.12.02 Main Stops:

Main stops shall be brass with inlet AWWA thread and outlet flared or compress ion .

Approved main stops for copper are:

Co m press ion Flared

Cambridge Brass, Series 102 20 mm - Code A070 430 25 mm - Code A070 440 40 mm - Code A070 460 50 mm - Code A070 470

Cambridge Brass, Series 102 20 mm - Code A0700730 25 mm - Code A0700740 40 mm - Code A0700760 50 mrn - Code A0700770

Page 62: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-2 4

Ford All sizes - FI000

Mueller All sizes - H-15008

Ford All sizes - F600

Mueller All sizes A-220

Approved main stops for PEX-AL-PEX:

Cambridge Brass 20mm - Number 070137A 25mm - Number 070145A

Mueller All sizes - K15008

For services connected to private mains, main stops may be replaced by Ford F60 main stop replacements with AWWA thread inlet and flared copper outlet.

For connecting to steel mains approved insulated stops are:

1. Cambridge Brass - Series 103 - Compression only - 20mm and 25mm

2. Ford Copper Service Insulator - all sizes must be used with Ford FIOOO flared outlet main stop.

3. Insulators have flared outlets and 20 mm and 25 mm also are available with compression outlets.

701.05.12.03 Curb Stops:

Curb stops shall be brass ball or plug valves with both inlet and outlet flared or compression.

Approved curb stops for copper are:

Compress ion Flared

Cambridge Brass, Ball Valves Cambridge Brass, Ball Valves 20 mm-- Code 070021A 25 mm - Code 070022A 40 mm - Code 070024A 50 mm - Code 070025A

20 mm - Code E16402 25 mm - Code E16403 40 mm -Code E21016 50 mm - Code E21027

Ford Ford 20 mm - B44 - 333 25 mm - B44 - 444 40 mm - B44 - 666 50 mm - B44 - 777

20 mm - B22 - 333 25 mm - B22 - 444 40 mm - B22 - 666 50 mm 0 B22 - 777

Mueller Mueller All sizes - H I 5209 All sizes - H I 5204

Page 63: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 5w-2 5

Approved curb stops for PEX-AL-PEX:

Cambridge Brass, Ball Valves Cambridge Brass, Ball Valves 20 mm - Number 070207A 25 mm - Number 070209A

20 mm - Number 070138A 25 mm - Number 070146A

Mueller All sizes - K15209

701.05.12.04 Couplings:

Couplings shall be brass with both inlet and outlet flared or compression.

Com pression Flared

Cambridge Brass, Series 118 Cambridge Brass, Series 118 20mm-CodeA0703330 20mm-CodeA0703150 25 mm - Code A0703340 25 mm - Code A0703180 40 mm - Code A0703370 40 mm - Code A0703210 50 mm - Code A0703390 50 mm - Code A0703230

Ford Ford 20 mm - C44 - 33 25 mm - C44 - 44 40 mm - C44 - 66 50 mm - C44 - 77

20 mm - C22 - 33 25 mm - C22 - 44 40 mm - C22 - 66 50 mm - C22 - 77

Dresser 20,25 and 40 mm - Style 88

Mueller Mueller All sizes - H I 5403 All sizes - A319

Approved couplings for PEX-AL-PEX are:

Cambridge Brass, Series 102 Cambridge Brass, Series 102 20 mm - Number 070164A 25 mm - Number 070150A

20 mm - Number 070205A 25 mm - Number 070206A

Mueller All sizes - K15070

701.05.12.05 Service Boxes and Rods:

Shall be CI type to suit curb stop and shall have 20 mm hexagonal brass lid plug. Length shall be adjustable to suit depth of service.

Approved boxes for 20 and 25 mm curb stops are:

I. Mueller A726 2. 3. BibiVSBl

Domestic Style No. DF 900

Page 64: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SW-2 6

Service rods shall be stainless steel of minimum 13 mm diameter.

Approved boxes for 40 mm and 50 mm curb stops are:

I.

2. Bibi VSB2 3.

Mueller A728 - Operating rod to have modified top to enable use of same key as used on the A726 box.

Cambridge Brass - Series 161-1

Service rods shall be stainless steel of minimum 20 mm diameter. Bottom boards shall be made according to Drawing W-CS-8, Sheet 3.

701.05.14 Straps, Tie-Rods, Angles, Nuts and Bolts and Sleeve Couplings

Clause 701.05.14 is deleted in its entirety and replaced by the following:

Stainless steel straps, tie-rods, angles, nuts and bolts used in concrete thrust blocks shall conform to ASTM A276, Type 316 stainless steel.

Bolts and Nuts: For flanged joints: to AWWA C207. For mechanical joints: to AWWA C11 I/A21 .I 1.

All bolts and nuts to be stainless steel Type 304.

Approved Sleeve Couplinas are:

Dresser style 253 Rockwe I I Straub

Sleeves shall be: ductile iron to ASTM A-536

fusion bonded epoxy to an average 0.3 rnrn thickness, suitable for potable water system.

Followers shall be: malleable iron ASTM A-47 ductile iron ASTM A-536, or steel.

shop coat enamel

Gaskets shall be:

Bolts and Nuts shall bestainless steel Type 304

rubber suitable for cold water service.

Page 65: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SW-2 7

701 -05.1 5 Corrosion Protection:

701.05.1 6

701.05.1 7

701.05.1 8

Material used to electrically insulate connections to steel mains shall be as listed and applied per suppliers recommendation.

ITEM DESCRIPTION SUPPLIER

Flange Gasket "Maloney" Corrosion Service Sets

Protective Coating Denso Paste Denso of Canada Denso Tape

Mastic Coating Ta pecoa t Mastic

Mastic Coating Royston A51 Corrosion Service Mastic

Po lye t h y I e ne 8 mil thickness Pipe Supplier per AWWA C105

All Cast iron (CI) and Ductile Iron (DI) fittings must have a 17 pound magnesium anode. Anode must be attached to fitting using a CADWELD and coated with mastic. Anodes and installation must meet the requirements of OPSS 702 and be approved by the Contract Administrator.

Thermal Insulation:

Material used to thermally insulate mains and services shall have a minimum compressive strength of 690 kPa. Approved material is STYROFOAM HI 100 BRAND by Dow Chemical or approved equal. Installation as per W-CS-68.

Blow Offs:

Blow off curb valves shall be stop and drain with inside I.P. thread on inlet and outlet. Refer to W-CS-5 for the Standard 50mm Blow Off Installation.

Approved curb stops are:

Mueller H - 10284 Cambridge Brass Series 1121 - 7 - 08670 Ford No. B11 - 677 SW

Pipe Bedding Materials

Granular materials greater than I 9 mm in size shall not be used for pipe bedding.

Bedding material shall be as specified in the Contract.

Concrete for bedding shall conform to OPSS .

Page 66: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SW-2 8

701.07 CONSTRUCTION

701.07.03 Preservation and Protection of Existing Facilities

Clause 701.07.03 amended as following:

Where it is required that a trench must cross under an existing main or where an existing main will be undermined during excavation, the Contract Administrator shall specify the method to be used. In general, the following methods may be used:

1. Where the main is cast iron crossing a trench it shall be cut back I .2 m into solid ground on either side of the trench and be replaced with new ductile iron pipe with exceptions as specified below.

The maximum unsupported length of cast iron watermain that can be allowed with no joint exposed before replacement with ductile iron pipe is required may be selected from the following tables:

STABLE SOIL (CLAYS AND CLAYEY SOILS)

MAXIMUM ALLOWABLE UNSUPPORTED LENGTH OF WATERMAIN (NO JOINT

EXPOSED)

W.M. at W.M. at W.M. 1.5 m Cover 2.5 m Cover

100 mm 1.37 m 1.07 m

Diameter

150 mm 1.68 m 1.37 m

200 mm 1.98 m 1.68 m

250 mm 2.44 m 1.83 m

300 - 450 mm 2.74 m 1.98 m

Page 67: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-2 9

2.

3.

4.

5 .

UNSTABLE SOIL (FILL, GRAVEL, SAND, SILT AND GRANULAR SOILS)

MAXIMUM ALLOWABLE UNSUPPORTED LENGTH OF WATERMAIN (NO JOINT

EXPOSED)

W.M. at W.M. at - W.M. 1.5 m Cover 2.5 m Cover

1.07 m 0.84 m 100 mrn

150 mm 1.37 m 1.14 m

1.68 m 1.45 m 200 rnm

1.98 m 1.68 m 250 mm

2.13 m 1.52 m 300 - 450 mm

Diameter

Allowable unsupported lengths for depth of watermain between 1.5 m and 2.5 m may be interpolated from the tables. For depth of watermain greater than 2.5 m, the Contract Administrator will specify the method to be used.

In the foregoing, if a joint is within the unsupported watermain length, the allowable length is to be reduced by 50%.

Where a cast iron main running parallel to a trench is undermined it shall be replaced with new ductile iron pipe in its original location or in a new location as approved by the Contract Administrator.

Where the main outlined above is ductile iron or PVC it must be temporarily supported during excavation and the trench may be backfilled with well compacted granular fill.

In hard stable soil tunnelling under watermains is acceptable. The minimum length of tunnel is to be 1.5 m, the vertical separation from tunnel roof to watermain is to be a minimum of 1.0 m and the void in the tunnel is to be filled with I 9 rnm crushed stone. Tunnelling in soft, loose and unstable soil is not acceptable.

Large cast iron, ductile iron, asbestos cement and concrete mains may require special supports, concrete support beams or trench sheeting or shoring. These cases will be treated individually as approved by the Contract Ad mi n is t ra tor.

In all cases where pipe is laid on backfilled material, the backfill shall consist of granular material compacted in 150 mm layers to 95 percent Standard Proctor Density.

Page 68: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-3 0

701.07.06 Transporting, Unloading, Storage and Handling Pipe

70 .07.1 I

Clause 701.07.06 is deleted in its entirety and replaced by the following:

Delivery and unloading of pipes and fitting at the job site shall cause the least possible delay to traffic.

All pipes, specials, fitting and gaskets that are unsound or damaged shall be removed from the site and replaced.

Mechanical equipment shall be used to unload the pipe.

Materials shall be placed in safe storage.

Manufacturer's handling and storage recommendations shall be followed.

Bac kf i I I i n g a n d Compact i ng

Clause 701.07.1 1 is amended as follows:

Where concrete or weakly cemented fill bedding is specified, the pipe shall be supported on grade and aligned by solid concrete blocks having the same minimum compressive strength as the specified bedding, spaced so that no movement of the pipe occurs during concrete or weakly cemented fill placing.

If necessary, concrete bedding may be placed in two pours. The level of the first pour shall not be higher than 75 mm below the bottom of the pipe. The first pour shall be cured a minimum of 24 hours before the second pour is started.

At pipe joints, bedding materials shall be left clear of the joints to permit their completion as specified elsewhere. After the connection has been completed, approved bedding material shall be placed under the joint and thoroughly tamped to the compaction specified. Bedding material shall not be taken from completed portions of the trench for this purpose.

Granular bedding shall be dimensioned as shown on Drawing SW-1. Granular bedding shall be uniformly compacted in layers not exceeding 150 mm in thickness. Compaction shall conform to OPSS 501 with a density of not less than 95 percent of the maximum dry density.

701.07.12 Installation of Pipes

Clause 701.07.12 shall be amended to include the following:

Pipes shall be handled with special care during temperatures below freezing. Pipes shall not be exposed to localized high temperatures except as required for the jointing process.

Pipe shall be lowered into the trench carefully.

Page 69: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-3 1

701.07.13

701.07.13.02

Pipes shall be laid on the prepared bed, true to the line and grade as shown on the contract drawings. The barrel of each pipe shall be in contact with the shaped bed throughout its full length. The ends of the pipe shall abut against each other so that there is no unevenness along the inside.

Pipe shall be kept clean as work progresses. Water shall not be allowed to flow through pipe during construction. A removable watertight bulkhead shall be installed at the open end of the last pipe laid whenever work is suspended. Pipe shall not be laid until the preceding pipe joint has been completed and the pipe carefully embedded and secured in place.

For DI pipe refer to AWWA C600 (Installation of Ductile Iron Wateramin and Their Appurtenances) and AWWA M41 (Ductile Iron Pipe and Fittings). For PVC pipe refer AWWA C605 (Underground Installation of Polyvinyl Chloride (PVC) Pressure Pipe and Fittings for Water), AWWA M23 andUNI-B-3.

Pipe shall be laid with the bell ends facing in the direction of laying.

At grades above 10 percent for PVC and DI pipe and 5 percent for concrete pressure pipe and steel bell and spigot pipe, laying shall start at the bottom with the bell ends facing upgrade.

Pipe shall not be laid when, in the opinion of the Contract Administrator, trench conditions are unsuitable.

Offsets must be made according to Drawing W-CS-12. Use of offsets must be indicated on the approved plans or in the case of unforeseen obstructions written approval of the Contract Administrator must be obtained.

Where joint deflections or offsets require pipe to be laid with less than specified cover insulation shall be placed to prevent freezing. Refer to Drawing W-CS-68, for insulation requirements.

For the purpose of locating PVC and concrete pressure pipe, a solid 12 gauge T.W.U. copper wire must be installed along the top of the pipe, strapped to it at six (6) metre intervals. The wire must be installed between each valve andlor the end of the watermain. Joints in the wire between valves will not be allowed. At each valve a loop of wire must be brought up inside the valve box to the top of the box. The Inspector may test the tracing wire for conductivity. If it is not continuous from valve to valve, the Contractor shall, at his expense, replace or repair the wire.

Jointing

Jointing Ductile Iron Pipe

Clause 701.07.13.02 shall be amended as follows:

Section a) Mechanical Joints shall be deleted in its entirety.

Refer to AWWA C600 - Section 3.4.

Page 70: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-3 2

701.07.1 3.03 Jointing Concrete Pressure Pipe

Clause 701.07.1 3.03 is deleted in its entirety and replaced by the following:

Refer to AWWA M9 (Concrete Pressure Pipe.

Bell and Spigot Joints:

Cement mortar consists of one part Portland cement conforming to CAN3-A5-M and three parts mortar sand conforming to OPSS 1004 shall be poured around the assembled joint. Ensure that the diaper is carefully placed around joint recess.

Grout internal joints coincident with the pipe laying operation.

Restrained Joints:

Restrained joints to be hold fast coupling, snap-ring type or flexible welded joints.

Install joints to manufacturer's instructions.

Installation of Flanged Joints:

Flange faces to bear uniformly on the gasket.

Tighten bolts uniformly.

Take care to prevent bending or torsional strains on the flanges.

Align accurately and properly restrain connecting pipes and flanged fittings, valves and specials.

Clean all bolts, nuts, couplings, gaskets and connecting pieces thoroughly before i n s ta I la t i on.

Support all flanged joints.

701.07.1 3.04 Jointing Polyvinyl Chloride Plastic Pressure Pipe

Clause 701.07.1 3.04 is deleted in its entirety and replaced by the following:

a) Bell and Spigot Joints:

Joint Pipe in accordance with UNI-B-3-92 and manufacturer's specifications.

If elastomeric gaskets are supplied separately, they shall be inserted into the groove of the bell end of the pipe.

Clean the gasket, the bell, the groove area (except when gasket is permanently installed) and the spigot area with a clean rag to remove any dirt or foreign material before assembling.

Page 71: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-3 3

Insert the gasket into the groove and seal it firmly.

701.07.1 3.05

701.07.1 3.06

Apply lubricant to bevelled spigot end.

Push the lubricated end past the gasket into the bell until reference mark is even with. bell.

b) Restrained Joints and Thrust Blocking:

Thrust block and joint restraining as per UNI-B-3-92, UNI-B-I 3-92 and manufacturer's specifications.

Restraining collars shall be attached to the fitting bell behind the gasket face.

Tie-rods can be run from the collar to a suitable collar on the connecting pipe.

Tie-rods and collars to be Denso wrapped.

Jointing Polyethylene Plastic Pressure Pipe

Clause 701.07.13.05 shall be amended as follows:

Approved only in special applications.

Jointing Steel Pipe

Clause 701.07.1 3.06 is deleted in its entirety and replaced by the following:

Joint pipe in accordance with AWWA Manual M I 1, Steel Pipe, Chapter 12.

Bell and spigot joints:

Follow procedure recommended by pipe manufacturer.

Field welded joints:

To AWWA C206

Expansion and contract joints in accordance with AWWA Manual M I 1, Steel Pipe, Chapter 8.

Restraint:

Flexible welded joints or harness fabricated by pipe manufacturer in accordance with AWWA Manual M I 1, Steel Pipe, Chapter 13.

Conform to AWWA C206, for field welding.

Page 72: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-3 4

701.07.1 6

701.07.16.01

701.07.17

Installation of Flanged Joints:

Flange faces to bear uniformly on the gasket.

Tighten bolts uniformly.

Take care to prevent bending or torsional strains on the flanges.

Align accurately and properly restrain connecting pipes and flanged fittings, valves and specials.

Clean all bolts, nuts, couplings, gaskets and connecting pieces thoroughly before installation.

Support all flanged joints.

Cement mortar lining for field joints to AWWA C205, Appendix A.

Installation of Valves

General

Clause 701.07.16.01 is deleted in its entirety and replaced by the following:

The work of installing valves shall include the valves, valve boxes and'rods. Valves shall be installed at the locations shown in the Contract. Valves and connecting pipes shall be aligned accurately and supported as specified.

Damage to Epoxy coating shall be repaired prior to installation, as per man ufact u rer's recom mend a tions .

Installation of Hydrant Sets

Clause 701.07.17 is deleted in its entirety and replaced by the following:

The work of installing hydrant sets shall include the placing of hydrants, hydrant isolations valves, hydrant leads and restraining devices.

Hydrants shall be installed at locations as shown in the Contract or as directed by the Contract Administrator.

Fire hydrants are to be installed at a grade, whereby the fire hydrant boot has a minimum bury of 1.7m to a maximum bury of I .9m, measured from the base of the fire hydrant boot to finished grade.

In cases where the depth of the watermain is greater than 1.9m, bends may be used to offset the hydrant lateral (past the gate valve) to achieve the standard fire hydrant boot depth.

A 300mm (maximum) fire hydrant barrel extension may also be used.

All offsets and extensions must be approved and inspected by the Contract Ad mi n istrato r.

Page 73: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-3 5

701.07.1 8

The hydrant shall be plumb with the nozzles parallel to the edge of pavement or curb line and the pumper connection facing the roadway.

Damage to the fire hydrant paint coating shall be repaired prior to installation, as per manufacturer's recommendations.

Hydrant installation shall be according to Drawing W-CS-1.

Hydrants shall be set at a grade whereby the final grading of the street or area shall be 75mm from the break flange of the hydrant. Grading which results in a depression or ponding at the hydrant will not be accepted.

Hydrant leads shall be constructed of the same material as the main line.

Installation of Services Connections

Clause 701.07.1 8 is deleted in its entirety and replaced by the following:

701.07.1 8.01 General

All watermain tapping to commissioned City of London watermain shall be made by City of London forces only.

Competent contractors may tap watermain that is not yet in service.

A service connection shall consist of a service connection pipe and a service connection appurtenance set and shall be installed at all specified locations.

All connections must be approved and inspected by the Contractor Administrator.

Water service connections shall be installed from the watermain to the property line at locations as shown in the Contract or as directed by the Contract Ad m in is tra to r.

A surface stake painted blue, 40mm X 90mm X 450mm long (standard 2"x 4'7, shall be placed after trench restoration to mark the termination of a water service.

Curb stop valve and boxes shall be installed vertically and flush with final grade elevation.

All service boxes that fall within a concrete sidewalk or driveway, shall have a 1 OOmm piece of 1 OM (#3 bar-0.375dia.) reinforcing-rod welded horizontally to the under side of the service box cover, approximately 40mm below the surface, to prevent frost heave.

Page 74: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SW-3 6

701.07.18.02

701.07.18.03

701.07.18.04

701.07.19

No service extensions to any users or use of the water from a main will be permitted until the main has been cleaned and passed pressure, leakage and disinfection tests.

All tapping must be undertaken by competent workmen equipped with tapping machines and other required equipment satisfactory to the Contract Administrator.

If PEX-AL-PEX (KITEC) water services are installed, this material must be used continuously from the main to the water meter.

Service Connections of 20mm to 25mm Diameter

Services of 20 mm and 25 mm diameter shall be installed according to Drawing W-CS-8, Sheets 1 to 3.

Service Connections of 40mm and 50mm Diameter

Services of 40 mm and 50 mm diameter shall be installed according to Drawing W- cs-22.

Service Connections of 100mm in Diameter and Larger

For services of 1 OOmm in diameter and larger, the method of connection shall be prescribed by the Contract Administrator. The method shall either cut out and install a tee, or use a tapping sleeve and valve.

The Contractor shall supply and install the tapping sleeve and valve for the City of London forces to complete the tap to the existing watermain.

In all cases, the City of London forces shall make the tap to the commissioned watermain at the Contractor’s expense, unless an agreement is made in writing between the Contract Administrator and the Contractor.

Shutting Down or Charging Mains

Clause 701.07.19 is deleted in its entirety and replaced by the following:

At no time shall watermains that are in service be shut down or charged, or operate any gate valve or other control for any purpose. Operation of valves, hydrants, blow-offs and curb stops shall be performed solely by the City of London forces.

At least 24 hours notice must be given to the Corporation when valves which will shut off services to consumers are required to be operated.

The Contractor shall give notice of interruption of service to consumers at least twelve (I 2) hours before the interruption occurs. The Contractor shall obtain notice cards from the Corporation and shall distribute them at no expense to the City of London.

Page 75: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-3 7

701.07.20 Connection to Existing Watermains

701.07.21

Clause 701.07.20 is deleted in its entirety and replaced by the following:

All connections to existing watermains shall be made under the supervision of the Contract Administrator. Dewatering and removal of any plugs, caps, blow offs andlor thrust blocks from an existing watermain or fitting and reconstruction of the joint will be considered part of the work of constructing the new watermain.

Where connections are to be made to steel mains, approved insulated flange insulation kits shall be used according to Drawing W-CS-25. All disturbed coating shall be replaced and all bare metal between the insulator and the steel main shall be'given a protective mastic coating and the entire assembly shall be encased with 8-mil thick loose polyethylene film in accordance with AWWA C105.

Where connections are to be made to DI pipe using steel tapping sleeves the installation must be mastic coated. Clean sand bedding shall be used at least 300 mm above and 150 mm beneath the installation. Tapping of PVC pipe must be done as recommended by the pipe manufacturer. The sleeve must be supported and blocked during tapping and supports for the sleeve and valve must be left in place. Thrust blocks must be used.

Connecting to PVC Water Mains: Refer to UNI-B-3 - Section 5.3.6. Direct tapping is not permitted.

The method of connecting to existing mains shall be prescribed by the Contract Administrator. The method shall either cut out and install a tee, or use a tapping sleeve and valve.

The Contractor shall supply and install the tapping sleeve and valve for the City of London forces to complete the tap to the existing watermain. Connections to a fully commissioned watermain are not to be made by the Contractor.

In all cases, the City of London forces shall make the tap to the existing main at the Contractor's expense, unless an agreement is made in writing between the Contract Ad mi n is tra to r and the Contractor.

In special cases the Contractor may be allowed to tap a commissioned main on written approval by the Contract Administrator on site before any tapping begins.

Thrust Restraints

Clause 701.07.21 is deleted in its entirety and replaced by the following:

Thrust restraint shall be provided at all connections, fittings, bends as well as at tees, valves, hydrants, reducers and plugged or capped dead-ends that are liable to "draw" or blow-off. All valves shall me mechanically joint restrained for a minimum of one (1) full pipe length (6m). Refer to section 7.4.6 - Thrust

Page 76: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SW-3 8

701.07.22

701.07.22.01

RestraintlBlocking of the Environmental and Engineering Services Department Design Specifications and Requirements (latest revision).

Concrete for thrust blocks shall be placed against undisturbed ground and joints and couplings shall remain free from concrete.

For DI pipe refer to AWWA C600 - Section 3.8. For PVC pipe refer to UNI-B-3 - Section 5.3.5, pipe suppliers manuals and UNI-B-I 3. Valves on PVC watermain are to be supported on concrete thrust blocks and anchored with two 15 mm diameter rods embedded in the supports.

Hydrants shall be restrained with mechanical thrust restraint (in accordance with UNI-B-13) and thrust blocks as shown on drawing W-CS-1.

Concrete thrust blocks shall be installed in accordance with Drawing W-CS-43 Sheets 1 to 3.

Tie rod and clamp assemblies shall be installed in accordance with Drawing W- cs-12.

Field Testing

Clause 701.07.22 is deleted in its entirety and replaced by the following:

Hydrostatic Testing

Hydrostatic testing shall be conducted under the supervision of the Contract Administrator upon completion of the watermain including services and backfilling.

Hydrostatic pressure and hydrostatic leakage tests may be conducted either si m ul taneo us1 y or separate I y.

Duration of test shall be two (2) hours or longer if so directed by the Contract Administrator, if tests are performed simultaneously.

If two tests are performed separately, conduct hydrostatic pressure test before hydrostatic leakage test. Duration of pressure test shall be one (1) hour or longer if so directed by Contract Administrator. Duration of leakage test shall be two (2) hours or longer if so directed by Contract Administrator.

The Contractor shall assume all responsibility when testing against existing or new line valves. The Contractor is to provide all bulkheads, taps, fittings and pipe thrust restraint necessary to undertake pre-qualification or final testing.

The Contractor is to provide means of obtaining water.

Fill test section slowly with water making sure that all air is removed from pipeline. Allow a period of 24 hours before starting test. Subject test section to continuous test pressure specified for one hour or as directed by Contract Administrator.

Page 77: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-3 9

Test pressure shall be 1035 kPa or as specified in the Contract.

701.07.23

701.07.23

Examine all parts of test section while under pressure. If test pressure is maintained with no pressure drop for specified test duration, test result is satisfactory.

If test result is not satisfactory, repair all deficient parts of section and retest until satisfactory result is attained. The leakage is the amount of water added to the test section to maintain the specified test pressure for the test duration. The measured leakage shall be compared with the allowable leakage as calculated for the test section. The allowable leakage is 2.22 L per mm of pipe diameter per km of pipe per day.

If the measured leakage exceeds the allowable leakage, all leaks shall be located and repaired and the test section shall be retested until a satisfactory result is obtained.

Flushing and Disinfecting Watermains

Clause 701.07.23 is deleted in its entirety and replaced by the following:

Swabbing, Flushing and Disinfecting Watermains

Swabbing, flushing and disinfecting operations shall be under the direct control of the Contract Administrator. The Contract Administrator shall be notified at least four days in advance of the proposed date on which such operations are to co m mence.

Watermains shall be swabbed and flushed in a sequence and in accordance with procedure approved by the Contract Administrator. The contractor must submit a swabbing , flushing and disinfection procedure to the Contract Administrator for approval two (2) weeks prior to the operation for approval.

All watermains up to 300 mm diameter shall be cleaned by the use of a minimum of four (4) foam swabs introduced at hydrants or at special entry sections and forced by water pressure through the main to exit points approved by the Contract Administrator. Cleaning shall be repeated until the discharge water is clear and approved by the Contract Administrator.

Method for swabbing watermains larger than 300 mm in diameter shall be as specified in the Contract.

Foam swabs up to 300 mrn in diameter will be supplied by the Corporation. Mains shall be cleaned or flushed before hydrostatic testing and disinfection is done.

The main shall be disinfected according to instructions listed in AWWA C651 and Ontario Ministry of Environment Bulletin 65-W-4 or latest revisions. The Contractor must supply all labour and materials necessary for the sterilization of the pipe. Supervision of the sterilization procedure will be provided free by the Corporation for the initial sterilization. Places where flushing may be done, rates of flushing and location of drainage points must be approved by the Contract Administrator prior to the operation as noted above.

Page 78: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-4 0

701.07.25

701.07.25.01

701.07.25.02

i i)

The Contract Administrator may permit or require the swabbing, flushing and disinfection to be carried out in stages as sections of the system are completed. Swabbed, flushed and disinfected sections shall be protected from contamination.

The system shall be left charged with the chlorine solution for 24 hours. Samples shall be taken by the Contract Administrator. If there is indication of contamination, the disinfection procedure shall be repeated.

The system shall not be put into service until clearance has been given by the Con tract Administrator.

Management and Disposal of Excess material

Clause 701.07.25 is deleted in its entirety and replaced by the following:

General

Management and disposal of excess material shall be according to OPSS 180.

Disposal of Chlorinated Water

All chlorinated water used for testing, flushing and disinfecting watermains shall be disposed of safely. Acceptable means of disposal are by discharge to storm sewer or open environment (drainage ditch or receiving water) with a maximum chlorine residual of 0.0 mg/L (Le. no detectable level of chlorine).

Discharge of chlorinated water directly to sanitary sewer is no longer acceptable as of January 1, 2003.

When discharging to the open environment or storm sewer, it will be the responsibility of the contractor to ensure the effectiveness of the dechlorination process. The contractor shall provide a written plan for the dechlorination process which is to be submitted to the contract administrator and approved. As a minimum this shall include:

i> The chemical proposed to be used to dechlorinate, the proposed equipment and methodology for dechlorination, and the proposed point of discharge and the receiving body (Le. storm sewer, open environment, ditch, drain, watercourse).

The process proposed and how it will ensure adequate dosing and mixing of the dechlorination compound prior to d ischa rg e.

iii)

iv)

Ensuring that there are appropriate measures in place to avoid erosion at the point of discharge and downstream.

There is a location for monitoring (and a method of monitoring) to ensure no chlorine residual remains downstream of the point of discharge.

Page 79: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-4 1

Sulphur Dioxide

Sodium Thiosulphate

701 -09

701.09.01

701.09.01.01

oxygen. This will slightly lower the pH in the receiving water. Will cause some sulphur turbidity, but an excess is harmless.

701.09.01.06

701.09.01.07

701.09.01.08

The contractor shall also be responsible for documenting the dechlorination and monitoring process. These records will be made available to the contract administrator as required.

Use of Chemicals for Dechlorination of Water

There are several chemicals which can be used to dechlorinate effectively. The following comments are offered with respect to potential impacts of each on the receiving body*:

I Chemical I Hydrogen Peroxide discharging to an environmentally sensitive watercourse. An overdose will only add more

1 Sodium Sulphite 1 Excess will lower dissolved oxygen.

Sodium Pyrosulphite (sodium Metabisulphite) 1

I Excess will lower dissolved oxygen.

*the above information was taken from the former MOE Bulletin 65-W-4 "Chlorination of Potable Water Supplies".

Adequate mixing and dosage of the chemical with chlorinated water must be ensured.

MEASUREMENT FOR PAYMENT

Actual Measurement

Watermains (includes bends, 'T's and fittings)

Measurement will be in metres horizontally over the centreline of the pipe from the point of connection to a chamber, water treatment plant, or existing watermain to a point vertically above the end of the new watermain.

Wate rma i n Offsets

Measurement will be the number of offsets installed. The unit of measurement will be each.

Watermain Connections (includes bends, 'T"s and fittings)

Measurement will be by the number of connections to existing watermains.

Cut and Cap Watermain

Measurement will be by the number of watermain cut-offs.

Page 80: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SW-4 2

701.10 BASIS OF PAYMENT

701 . l O . O l

Clause 701 . I 0.01 is deleted in its entirety and replaced by the following:

Watermain (Includes bends, 'T's and fittings) - Item Valves (Includes boxes and rods) - Item Hydrant Sets (Includes valves and leads) - Item Service Connection Pipes - Item Service Connection Appurtenances - Item Watermain Offsets - Item Watermain Connections (includes bends, 'T"s and fittings) - Item Cut and Cap Watermain - Item

Payment at the contract price for the above tender item(s) shall be full compensation for all labour, equipment and material to do the work, including excavation, bedding, backfilling and compaction to subgrade.

No change in Contract Price (credit or increase) will be considered unless as- constructed location of watermain changes by more than 500 mm higher or 500 mm lower than as shown on the Contract Drawings.

Include in the prices bid in the Form of Tender: water used for testing, hydrostatic testing, cleaning, flushing, disinfecting, including, if required, water meter; closures; all temporary connections and piping; temporary bulkheads and thrust restraints required for testing purposes.

When imported Granular IC' trench backfill is specified in a Special Provision, and the Contract Administrator directs that native, selected native material, andlor selected native site material be used as trench backfill, the credit to the Corporation shall be based on the current market price of Granular 'C' materials delivered to the job site, and the volume in tonnes of native materials that is substituted.

Page 81: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-44

1oo.omm

37.5m1.11

22.41n.111

4.75mm

1.18111m

0.300111t11

0.075 III~II

O.P.S.S. 1010 - MATERIAL SPECIFICATION FOR AGGREGATES - GRANULAR A, B, M AND SELECT SUBGRADE MATERIAL

100

65-100

57-90

25-75

10-65

5-35

0-8

1010.05 MATERIALS 1010.05.03 Granular B

Subsection 1010.05.03 is amended by the addition of the following: "Granular 'B' - Select" physical requirements shall conform with "Table I Physical Requirements" Granular 'B' type I and the following gradation chart.

SIEVE SIZE

GRANULAR 'B' - SELECT

SIZE PASSING

Y O

PASSING

1010.05.04 Select Subgrade Material

Subsection 101 0.05.04 is amended by the addition of the following: The following gradation charts are specified for select subgrade material.

I 2.36- I 35-100 I

GRANULAR 'C'

SIZE PASSING

150.0nm 100

26.5 nim 50-100

4.75 111111 22- 100

1.18 imn 10-1 00

0.300mm ~ Sj: I 0.150 m

0.075 IIUX 0-10

Page 82: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-45

1998-03-01

$ % z Z ? z - Y -

2003-1 1-03

600x840 Precast Concrete Curb Inlet Catchbasin

"",-----

Catch Basin Pipe Subdrain Detail

1 998-03-0 1 Precast Concrete Catch Basin

STANDARD DRAWINGS FOR SEWER AND WATER

Volume 3 of the Ontario Provincial Standard Drawings (OPSD), and the current City of London Standard Drawings, are amended as follows:

O.P.S. Drawings 802.01 0 to 802.054 and 1 100.01 0 to 1 108.01 inclusive are deleted in their entirety.

AMENDEDINEWKURRENT II SUPERSEDEDlDELETED EMOVE)

DATED CITY OF LONDON

TITLE OF DRAWING

CITY OF LONDON OPSD

-

1003.01

1003.02

707.01 0

1006.01

1006.02

s w - 1 April 1994 s w - 1 .o Bedding Standard For Gravity And Pressure Pipe

s w - 1 .I

1988-1 2-01 Manhole Drop Structure - Tee

1988-1 2-01 Manhole Drop Structure Wye

Manhole Drop Structure - Wye

600x840 Precast Concrete Curb Inlet Catch Basin

sw-2 .0 1997-02-1 5 sw-2.0

SW-3.0 1997-02-1 5 SW-3.0

SW-3.1

SW-4.0 1997-02-1 5 Precast Concrete Catch Basin in Manhole

SW-4.0

I Maintenance Hole

SW-5.0 1997-02-1 5 SW-5.0 Manhole Adjust men t Unit Detail

Precast Concrete Maintenance Hole Tee

1998-03-01 Maintenance Hole Adjustment Unit Detail

1998-03-01 Precast Concrete Maintenance Hole

1996-09-1 5

~~

SW-5.1

SW-5.2 1998-03-01 Steps in Maintenance Hole Benchin

1 988-1 2-0 1 Sewer Service Connections for Riaid PiDe

I 988-1 2-0 I Sewer Service Connections for Rigid Pipe

Page 83: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SW-46

OPSD CITY OF TITLE OF LONDON DATED DRAWING

SW-6.0 1997-02-1 5 Private Drain Connection

SW-6.1 1997-02-1 5 PDC Riser Type I

SW-6.2 1997-02-1 5 PDC Riser Type I I

1998-03-01

I I I

Private Drain Connection

SW-7.0

UCC-I M

W-CS-1

AMENDEDINEWICU RRENT

1997-02-1 5 Standard Servicing Locations for Sin le Fa-mily A n t Semi- Detached Lots

1996-03-1 5 Standard Uti I i ty. Locations For All Streets

Hydrant and Valve Installation

1997-02-1 5 Standard

CITY OF LONDON

1998-03-01

SW-6.0

SW-6.1

SW-6.2

II Standard Hydrant And Valve Installation

SW-6.3

February 14, 1985

February 26, 1985

February 18, 1985

SW-7.0

Standard 50mm Blow Off Installation

Standard Valve Rod Extension Piece For IOOmm And Larger Valves

Standard Installation Of 16mm Water Meter

UCC-I M

w-cs-1

w-cs-5

W-CS-6

w-cs-7

W-CS-8 w-cs-8

W-CS-8

Feb.27,1985 Standard Installation Of 20mm And 25mm Water Service (Sheet 1)

W-CS-8

February 28, 1985

March 15, 1985

TITLE OF DATED DRAWING

Standard Installation Of 20mm And 25mm Water Service (Sheet 2)

Bottom Board For Standard Installation Of 20mm And 25mm Water Service (Sheet 3)

T

1998-03-01 PDC Riser Type I

1998-03-01

Cleanout

1998-03-01 Standard Servicing Locations for Sing!e Family And Semi-Detached Lots

1997-02-1 5 Standard Utility Locations For All Streets

I II

'I

March 9, 1998 Standard Installation Of 20mm And 25mm Water Service (Sheet 1)

Page 84: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-47

March 27, T pical Thrust

Watermains (Sheet

AMENDED/NEW/CURRENT ( I NSERT)

DATED

February 19, 1985

February 18, 1985

February 27, 1989

CITY OF LONDON

TITLE OF DRAWING

Standard Mechanical Joint Offset Installation Usin Tiebolt CouJings

Standard Installation Of 40mm And 50mm Water Service

CathodIc Protection Assemblies For 20mm To 50mm Water Service

w-cs-12

February 25, 1970

February 28, 1989

February 27, 1989

w-cs-22

Cathodic Protection For 100mm And Larger Water Services

Typical Installation For 20mm, 40mm, And 50mm Disc Type Water Meter

T pical Turbine dater Meter Installation For

w-cs-24

March 4, 1970

w-cs-25

T pical Vertical TKrust B!ocks For Faterrnarns (Sheet

w-cs-30

~

w-cs-30

w-cs-31

w-cs-31

w-cs-43

w-cs-43

w-cs-43

75mm To 200mm (Sheet 2)

I January 28, Schematic Layout 1985 Of 100mm And

Larger Service (Sheet 2)

January 24,

March 12, 1985

Watermains (Sheet

Page 85: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-48

CITY OF LONDON

SUPERSEDEDlDELETED

DATED CITY OF LONDON

W-CS-45

OPSD

March 7,1985

W-CS-67 W-CS-67

EMOVE)

DATED

March I, 1998 March 7, 1985

W-CS-68

TITLE OF DRAWING

March 8,1985

Remote Water Meter Re ister In s9a I I at i on

W-CS-69 Sheet1

AMENDED/NEW/CURRENT

Se tember 16, 20g3

(INSERT

W-CS-69 Sheet2

Se tember 16, 2083

W-CS-69 Sheet3

W-CS-51 March 19, 1 1975

Se tember 16, 2083

I W-CS-60 March 27, I 1985

W-CS-66 February 20, 1 1985

TITLE OF DRAWING

Standard Location For Water Valves At Intersections With 9.0m And 10.5m Curb Radii

Standard Cit Of London 29" Frame And Cover

Sterilizing Mains

Typical Service Entrances 1 OOmm to 200mm

Remote Water Meter Register Installation

Insulation Of Shallow Mains And Offsets

Typical Reinstatement / Bedding details for 450mm and Up Watermain support

General Submission and Design Re uirements for waqermain Sumort and Beddin / Reins tagernen t

Page 86: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 sw-49

SELECTED ONTARIO PROVINCIAL STANDARD DRAWINGS:

The following Ontario Provincial Standard Drawings have been selected and shall be used on all design, construction and reconstructive maintenance projects of the City=s infrastructure, including new subdivisions and developments, unless otherwise specified on Contract Drawings and in Special Provisions.

OPSD 400.02 OPSD 400.09 OPSD 401.01 OPSD 401.03 OPSD 404.020 OPSD 405.010 OPSD 701.010 OPSD 701.01 I OPSD 705.010 OPSD 705.020 OPSD 1001.01 OPSD 1001.02

Catch Basin, Cast Iron Frame and Flat Square Grate Catch Basin, Cast Iron Curb Inlet Overflow Plate Maintenance Hole, Cast Iron, Cover and Square Frame Maintenance Hole, Cast Iron, Watertight Cover and Square Frame Safety Platforms, Aluminum for Circular Manhole Manhole Steps Precast Manhole - 1200mm Diameter Precast Manhole - 1500mm and 1800mm Diameter Precast Concrete Twin Inlet Catch Basin 600mm X 1450mm Precast Concrete Catch Basin 600mm X 600mm Precast Manhole 1200mm Diameter Precast Manhole 1500mm and 1800mm Diameter

Page 87: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

300 ( TYP 1

Slope 2% TO 4% 4

DWG sw-3.1

a t a i

SECTION A-A

DATE APPROVED BY 2003 O3 CITY ENGINEER

LG* 950 per fo ra ted fllter wrapped or approved equal) subdrain ( b o t h s i I catchbasin locations c/w end caps.

( terraf i x des 1

- Curb 115 600 115

Note I/

NOTES:

Subdra ins t

. .

Granu I a r A

Granu I a r 6

Subgrads

d P L- Subdrain pipe f l 5 0 m 0 @ 3.0 m long)

0 ;!I I b A

> 1

be i n s t a l l e d on bo th sides of: c u t c h basin, a t subgrade e leva t fon . parallel t o t h e curb, a t same grade as f inished road. Subdrains to be installed into t h e 2OOm knockout provided In the catchbas i n p o t

CITY OF LONDON STANDARD DRAWING

n ~ T - 1 I n A n i k I n i n r ni innn A I L I n - 7 ~ I I

Page 88: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

- - - -

Additional supports each side of pipe joint and at each end ofexcavation Detail support system typically hardwood lumber blocldng botted together, with steel bearing plate attached.

Min 0.3m from edge oftrench

enching to comply with M.0.L guidelines.

to be measured

Trench box if

Proposed pipe to cross existing wm. labelelevation of pipe invert

label - c

DWG: W-CS-69,SHEET 1

TYPICAL SUPPORT CROSS SECTION

NTS APPROVED BY

DATE 2003 16 09 CITY ENGINEER:

SEE DRAWING W-CS-69,- SHED 3 FOR REQUIREMENTS

CITY OF LONDON STANDARD DRAWING

450mm AND UP TYPICAL WATERMAIN SUPPORT DETAIL FOR UTILITY CROSSINGS USING OPEN CUTAONSTRUCTION

Page 89: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

din 0.3m from edae of trench

-@vel ground /undisturbed surface x if disturbed, to be compacted to 100%

up to springline.Depth of unshrinlcable fillto be I determined based on size of existing wm.

3.P.M.D.D.and soil bearing capacity .o be measured A

f h \. 1 I A f

Cut into side slopes -.J 0.6m in order to place unshrinkable fi l l

Granular bedding - to be installed to City of London Standards.

Proposed pipe io cross existing w m . 1 label label elevation of pipe invert.

.rl

TYPICAL REINSTATEMENT /BEDDING DETA1L CROSS SECTION

m h i n g to comply th M.0.L guidelines.

Veriry & lablel depth i

General Notes: The watermain shall be protected by the following:

- When crossing under or over the watermain there must be a minimum separation of at least 0,6m between the outside diameters of the crossing pipes.

- A minimum 5.0m length of pipe shall be centered at the poini of crossing so thatthe watermain joints willbe equidistance and as far as possible from Ute sewer or PDC. Crossing must be absolute minimum 2.Om from watermain joint.

compaction within 0.6m of existing watermain shall be done bj hand.

- All constnrction methods including excavation and backfill

It should be noted that the support structure is to remain in place untilthe watermain is fully supported by the reinstated bedding (i.e. until unshrinkable fill is cured, or other bedding materialto supportthe watermain is in place)

SEE DRAWING W-CS-69,- SHEET 3 FOR REQUIREMENTS

TYPICAL REINSTATEMENT /BEDDING DETAIL

Page 90: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

SUPPORT DETAIL REQUIREMENTS

W-CS-69, SHEET 3

Submission and Desian Reauirements

2003 16 09 CITY ENGINEER (

When crossing below an existing watermain (450mm Dia. and greater) using open cut construction, the foilawing must be provided to the City of London Water Engineering Division for revicmhpproval a minimum of two (2) weeks prior to the proposed work taking place:

DWG DATE

A) A utility support system drawing stamped by a Professional Engineer, including the following: (See W - CS - 69, Sheet # 1 for Typical Drawing )

APPROVED BY pp@/L*

Complete pian and cross-section drawings indicating support system including all appropriate dimensions and details. Provide all structural calculations for support systems including load and deflection information for proposed beam. Provide details to confirm adequacy of support mechanism proposed to transfer loading of supported utility to supportbeam. Provide calculations forloading transferred to the end support of the beam structure and confirm adequate soil bearing capacity for the system designed for beam supports. Identify procedure for transferring load of structure to be Supported to supportbeam.

B) Contractor's work plan. The work plan shallinclude the fallowing:

(i) Identification of major activities to be carried out in association with the utility crossing.

(ii) A schedule of these works.

Under nu circumstances will the work be allowed to proceed under adverse weather conditions.

The work may not proceed until all of the above are received and approved. Please note that traffic control plans affecting the City of London Right-of-way, if required, are to be submitted for approval separately to the Transportation Engineering Division. At all times, all requirements of the Occupational HeaJth & Safety Act must be met.

BEDDINCNEINSTATEMENT DETAIL REQUIREMENTS Submission and Desian Reauirements

When crossing below an existing watermain (450mm Dia. and greater) using open cut construction, the following must be provided to the City of London Water Engineering Division for reviewbpproval a minimum of two (2) weeks priorto the proposed work taking place:

I) When crossing watermains 450mm and greater a drawing@) must be submitted indicating reinstatement and bedding is required. The drawings shall indude the following: (See W - CS - 69, Sheet # 2 for Typical Drawing)

{A) Cross - section drawingls) including all appropriate dimensions and details.

(6) If appropriate, identify insulation to be installed.

(C) To prevent settlement of watermain, install unshrinkable fill to a minimum 600mm below watermain up to the springline OR obtain recommendations reguarding watermain bedding from the watermain pipe manufacture, if any of the following apply:

0) There is less than 600mm separation between the utilities crossing each other, OR

(ii) Either structure is greater than 1000rnm in diameter, OR

fiii) Insulation is being placed between the utilities.

2) Contractor's work plan. The work plan shallinclude the following:

(A)

(6) A schedule ofthese works.

Identification of majuractivities to be carried out in association with the Irtilrty crossing.

Under no circumstances will the work be allowad to proceed under adverse weather conditions.

The work may not proceed until allof the above are received and approved. Please note that traffic control plans affecting the Crty of London Right-of-way, if required, are to be submitted for approval separately to the Transportation Engineering Division. At all times, all requirements of the Occupational Health & Safety AcA must be met.

CITY OF LONDON STANDARD DRAWtNG

Page 91: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 STS-1

601.04

601.05

O.P.S.S. 601 CONSTRUCTION SPECIFICATION FOR ELECTRICAL WORK - GENERAL

SUBMISSlON AND DESIGN REQUIREMENTS

Section 601.04 is deleted in its entirety and replaced by the following:

The Contract Administrator shall submit two (2) copies of proposed traffic installation signal and/or street light drawings to the City of London Parking and Traffic Signal Division for approval. Dimensioned drawings are required to review equipment and proposed locations.

MATERIALS

Section 601.05, second sentence is deleted in its entirety and replaced by the following:

All materials, components or completed assemblies of components shall be CSA approved and referenced in the Designated Sources for Materials published by the MTO.

601.07 CONSTRUCTION

601.07.02 Coordination With Hydro Authorities

601.07.02.01 Work To Be Inspected By Ontario Hydro

Clause 60 1.07.02.0 1 is deleted in its entirety and replaced by the following:

601.07.02.01 Work To Be Inspected By, Electrical Safety Authority @SA) and the Transportation Division

601.07.02.01.01 High Voltage Work

Clause 60 1.07.02.0 1 .O 1, first sentence is amended as follows:

The Contractor shall arrange for inspection with the applicable hydro authority, for all high voltage work, including . . .

601.07.02.01.02 Disconnecting Means

Clause 601.07.02.01.02, first sentence, is amended by the addition of Electrical Safety Authority .

60 1.07.06 Layout of Equipment

Subsection 601 -07.06 is amended by the addition of the following:

Field reviews and layout approvals may be scheduled by contacting the City of London Parking and Traffic Signal Division at 661-841 0.

Page 92: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,ZUU;J STS-2

601.07.11 Quality Control

Subsection 60 1.07.1 1 is amended by the addition of the following:

It is imperative that all underground work be inspected and approved by the City of London Parking and Traffic Signal Division prior to any placing of concrete or backfilling. This inspection is in addition to that provided by consultants and/or other City divisions.

Page 93: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3, zuw STS-5

O.P.S.S. 609 CONSTRUCTION SPECIFICATION FOR GROUNDING

609.05 MATERIALS

609.05.03 Bare Ground Wire

Subsection 609.05.03 is amended by the addition of the following:

Ground table shall be #6 copper stranded A.W.G.

609.07 CONSTRUCTION

609.07.03.05 Ground Wire Connections

Clause 609.07.03.05, second and third paragraphs, are deleted in their entirety and replaced by the following:

The ground system shall use K.P.A. style logs in poles. Plated split bolts, cadweld termination kits and plated compression ground rod clamps shall be used in providing the ground system.

609.07.04.01 Ground Rods

Clause 609.07.04.01 is amended by the addition of the following:

Every junction box shall have a 19mm X 3000mm galvanized rod or ground plate installed. The ground rod shall show 1 5 0 m above the base of the junction box after installation.

Grounding from each junction box is to be independently routed back to the grounding bed.

Page 94: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 STS-6

616.05

616.05.01

616.07

616.07.01

61 6.07.0 1.02

61 6.07.01.03

O.P.S,S. 616 CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS

FOR ELECTRICAL EQUIPMENT

MATERIALS

Concrete

Subsection 616.05.01 is amended by the deletion of "20 mpa" and its replacement with "25 mpa".

CONSTRUCTION

Concrete Footings in Earth

Subsection 616.07.01, fxst paragraph, is amended by the addition of the following:

Fibre Tube

Subsection 616.07.01 is amended by the addition of the following:

Fibre tube or approved equal shall be used to form all concrete pole bases with a minimum depth of 600mm.

When a controller cabinet base is constructed within 1.5 m of a sidewalk, they shall be connected by a 1 .O m wide concrete access walk.

Signal pole bases shall be located a minimum distance of 2.5 m behind face of curb.

Median pole bases shall be located a minimum distance of 2.0 m from the face of the bull nose, with associated junction boxes a minimum 1.0 m back of the median pole base.

All bases on islands or medians shall be installed with RichmondMelico anchors.

Sleeves and Ducts

Clause 61 6.07.01.02 is amended by the addition of the following:

All ducts shall exit the top of the concrete pole base vertically, and be centred in the template.

Some pole bases may require double duct access. The City of London Parking and Traffic Signal Division will advise the Contractor of a pole base with a double duct access in advance of construction.

Anchorage Assemblies

Clause 61 6.07.01.03 is amended by the addition of the following:

Page 95: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

novemtxr 3, LUUS

STS-9

All references to PVC junction boxes shall be deleted and replaced with reidorced concrete junction boxes.

Junction boxes shall conform to City of London Standard Drawing Nos. STS-2 and STS-3.

620.07 CONSTRUCTION 620.07.12 Junction Boxes

Subsection 620.07.12 "Junction Boxes" is a new subsection created to cover the construction requirements for junction boxes.

Junction boxes shall be located at a minimum 2.0 m distance from face of curb.

For traffic signalization, junction boxes shall not exceed a spacing of 30 m. For street lighting, junction boxes shall not exceed a spacing of 5Om unless approved by the City of London Parking and Traffic Signal Division.

At locations involving gravel shoulders, junction boxes shall be located a minimum distance of 4.5 m from the edge of pavement.

When ducts run through a signalized intersection, traffic signal junction boxes shall be used. If separate junction boxes are required for the street lighting systems, they must be Approved by the Parking and Traffic Signal Division prior to the design being approved.

All hold-down bolts shall be hex head, nickel plated or stainless steel, and 65mm in length.

Polymer concrete junction boxes shall be Synertech (traffic - Model No. S1730B18AA) or equivalent, and Synertech (street light - Model No. S 1324B18AA) or equivalent. Concrete junction boxes shall only be used when directed by the Contract Administrator.

Page 96: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3, 2003

Clause/Subsection

GC4.03

GC4.04

GC4.05

GC 4.06

GC4.07

GC5.02

GC5.04

GC 6.03

GC 6.03.01

GC6.03.02

GC7.01

GC7.02

GC7.06

GC7.08

GC7.12

’ GC7.13

GC7.15

GC8.01.02

GC8.02.02

GC 8.02.03

-2-

Description

Management and Disposal of Materials

Construction Affecting Railway Property

Default by the Contractor

Notification of Default

Contractor’s Right to Correct a Default

GC5 MATERIALS

Quality of Materials

Substitution

SECTION GC6 INSURANCE, PROTECTION AND DAMAGE

Contractor ’ s Insurance

General

General Liability Insurance

SECTION GC7 CONTRACTOR‘S RESPONSIBILITIES AND CONTROL OF WORK

General

Layout

Maintaining Roadways and Detours

Approvals and Permits

Obstructions

Limitations of Operations

Warranty Amount

GC8 MEASUREMENT AND Pa

Variation in Tender Quantities

Advance Payment for Material

Certification and Payment

Page

5gc-5

5gc-6

5cg-6

5cg-6

5gc-6

5gc-6

5gc-7

5gc-7

5gc-7

5gc-7

5gc-7

5gc-8

5gc-8

5gc-9

5gc-9

SGC-12

SGC-12

WENT

SGC-12

SGC-13

SGC-13

Page 97: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 - 3 -

ClauseiSub sec tion Description

GC8.02.03 . O l Progress Payment Certificate

GC8.02.03.02 Certification of Subcontract Completion

GC8.02.03.03 Subcontract Statutory Holdback Release Certificate and Payment

GC8.02.03.04 Certificate of Substantial Performance

GC8.02.06

GC8.02.06

GC 8.02.06

GC8.02.06

GC8 -02.06

GC8.02.06

GC8.02.08

GC8.02.09

Payment of Workers

Appendix ‘A’ - Industrial, Commercial and Institutional

Appendix ‘B’ - Roads and Structures

Appendix ‘C’ - Sewer and Watermain

Appendix ‘D’ - Building Cleaning Industry

Appendix ‘E’ - Security Guard Industry

Taxes and Duties

Liquidated Damages

Page

SGC-13

SGC-13

SGC-13

SGC-13

SGC-13

SGC-16

SGC-17

SGC-19

SGC-22

SGC-23

SGC-24

SGC-24

Page 98: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-1

SECTION GCl INTERPRETATION

GC1.04 Definitions

Add the following definitions:

"Addenda" means written information to be taken into account when bidding a project which is either bound within the Tender Package or issued to each person who had taken out a Tender Package.

''City Clerk" means the person appointed by Council to fill the office of the City Clerk of the Corporation or the person acting as such.

"City Solicitor" means the person appointed by Council to fill the office of the Deputy City Administrator and Commissioner of Legal Services and City Solicitor of the Corporation or the person acting as such.

"City Treasurer" means the person appointed by Council to fill the office of the Commissioner of Finance and Administration and City Treasurer of the Corporation or the person acting as such.

"Corporation" means the Corporation of the City of London.

"Council" means the Council of the Corporation.

"Engineer" means a professional engineer licensed in Ontario, appointed by Council to fill the office of the Commissioners of Environmental Services and City Engineer of the Corporation, or the person acting as such.

"On-site materials" means materials located in the Working Area, including native materials and Base materials.

"Owner as Constructor"

In situations where the Owner requires additional parties (utilities, City's own forces, others) to work within the Limits of Contract, the Owner may do the following:

1) assume the responsibilities of the Constructor, as defined in the Occupational Health and Safety Act for the duration of the third party Work or,

2) where appropriate, may require partitioning of the project to segregate access points (entrances and exits) from other construction operations within the Limits of Contract, in order that the City may undertake works without conflicting with other construction operations or,

3) make arrangements for the Contractor to vacate the Limits of Contract for the duration of the third party Work in order to undertake works within the Limits of Contract without conflicting with other construction operations.

Page 99: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-2

When the Owner as "Contractor" retains a third party to perform a portion of the Work, the Owner will notify the Tenderer of its intention and procedure to complete the Work in the Tender Document, Section - Special Provisions, Non Tender items pages.

In all cases the Contractor will continue to fulfil his obligations as Constructor for the Work under their control in accordance with the Occupational Health and Safety Act and regulations.

Amend the defmition of Tontract Document" as follows:

'Contract Document" means the executed Agreement between the Owner and the Contractor, the Tender, the Ontario Provincial Standards for Roads and Municipal Services, Volumes 1 - 4 inclusive, City of London Supplemental Standards for Roads (SR), City of London Supplemental Standard for Sewer and Water (SW), City of London Supplemental Standard for Traffic Signals and Street Lighting, (STS), City of London General Specifications (GS), City of London Standards for Tree Planting and Preservation (TPP), City of London Supplemental Standards General Conditions of Contract (SGC), City of London Supplemental Standards for Parks and Open Spaces (SPO), Special Provisions, Contract Drawings, addenda incorporated in a Contract Document before the execution of the Agreement, such other documents as may be listed in the Agreement, and subsequent amendments to the Contract Document made pursuant to the provisions of the Agreement.

Delete the defmition of Certificate of Substantial Perfomance and replace with the following:

Certificate of Substantial Performance means Certificate of Substantial Completion (Form 6) issued by the Contract Administrator at substantial completion of a construction pr oj ect.

Delete the defmition of "Completion Certificate" and replace with the following:

"Completion Certificate" means Final Payment Certificate issued by the Contract Administrator at the completion of a construction project.

Amend the defiiition of Tontract Administrator" as follows:

"Contract Administrator" means a person, partnership, corporation or employee in the City's Environmental and Engineering Services Department designated by City Engineer or the General Manager of Planning and Development to act as such.

For new Subdivision and Development projects, references made to Tontract Administrator" in the City of London Standard Contract Document Drawings means an employee in the City's Environmental and Engineering Services Department designated by the City Engineer or the General Manager of Planning and Developeinent.

Amend the defiition of Contract Drawings or Contract Plans as follows:

Delete the words "Any Geotechnical Report, and Subsurface Report, and other reports and"

Page 100: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-3

Amend the defiiition of "Owner" as follows:

"Owner" means the Corporation of the City of London.

Amend paragraph a) in definition of "Worlung Day".

a) Except Saturdays, Sundays and Statutory Holidays whether or not worked.

GC1.05 Amend the defmition of "Substantial Performance" subsection GC1.05 as follows:

Delete paragraph .O 1 a) and substitute the following:

a) When the work or substantial part thereof has passed inspection and testing and is ready for use and is being used for the purpose intended; and . . .

GC1.07 Final Acceptance

Subsection CG1.07 is amended by the addition of the following paragraph:

.02 Final acceptance will not occur until the work has passed all inspection and testing requirements.

SECTION GC2 CONTRACT DOCUMENTS

GC2.01 Reliance on Contract Documents

Add paragraph d) to subsection GC2.01 as follows:

d) The subsurface report is excluded from the Contract Documents.

GC2.02 Order of Precedence

Delete Order of Precedence a) to i) as set out in paragraph .01 subsection GC2.02 and replace with the following:

Agreement Addenda Special Provisions Contract Drawings City of London General Specifications (GS) City of London Supplemental Standards for Roads (SR),City of London Supplemental Standards for Sewer and Water (SW), City of London Supplemental Standards for Traffic Signals and Street Lighting(STS),City of London Standards For Tree Planting and Preservation (TPP),City of London Supplemental Standards General Conditions of Contract (SGC), City of London Supplemental Standards for Parks and Open Spaces (SPO) Ontario Provincial Standards for Roads and Municipal Services, Volumes 1 - 4 inclusive Tender Workmg Drawing

Page 101: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-4

SECTION GC3 ADMINISTRATION OF CONTRACT

GC3.01 Contract Administrator's Authority

Amend paragraph .02 of subsection GC3 .0 1 by the addition of the following in writing by the Contractor after the word Administrator.

Amend paragraph .07 of subsection GC3.01 by the addition of for the Engineer's approval following after the word Orders.

Amend subsection CG3.0 1 by the addition of the following paragraphs .16 and .17.

-16 Notwithstanding the Contract Administrator's Authority as set out in subsection CG3.01, the Engineer has the authority to overrule any decision made by the Contract Administrator with respect to the Contract.

.17 A Municipal Consent Application form must be completed by the Contract Administrator, reviewed, and approved by the Utility Coordinating Committee (U.C.C.) prior to all construction.

CG3.06 Working Area

Delete paragraph .03 of subsection CG3.06. and substitute the following:

.03 The Contractor shall not enter upon or occupy any private property outside the Working Area for any purpose unless the Contractor has received written authority fi-om the property owner prior to entering or occupying said property and provide a copy of such to the Contract Administrator. Upon completion of the project, the Contractor shall obtain a written statement from the property owner certifjring that his property has been restored to a satisfactory condition. An amount estimated by the Contract Administrator will be held back from the Contractor until such a letter is provided. It shall be the Contractor's responsibility to ensure that all necessary written approvals for disposal of surplus materials and other intended uses of private property are obtained, such as the Upper Thames River Conservation Authority, where applicable. Copies of written communications from the property owner and authority, when applicable, shall be supplied to the Contract Administrator.

GC3.10 Subcontracting by the Contractor

Delete paragraph .02 of subsection GC3.10 and substitute the following:

.02 At or prior to the start of construction, the Contract Administrator reserves the right to direct the Contractor to submit a list of subcontractors to be employed on the Contract, including the scope and estimated value of the work to be subcontracted.

Delete paragraph .03 of subsection GC3.10 and substitute the following:

.03 The list of subcontractors shall be submitted to the Contract Administrator within four (4) days from the date of notification and the Contract Administrator will

Page 102: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2Q03 SGC-5

within ten (1 0) days of receipt of such submission advise the tenderer in writing if the subcontractors are acceptable. If the intended subcontractors are not acceptable, the letter will indicate the reasons for rejection.

GC3.14.04 Negotiations

Delete the words (beginning the second last line) subsection GC3.14.04 paragraph .02 the parties may, upon ........ and replace with the following::

the disagreement will be referred to the Engineer for decision. If the Contractor does not accept the Engineer's decision, the issue may be submitted to arbitration, provided both paxties agree, in accordance with the provisions of subsection GC3.15 , "Engineering Arbitration". Where both parties cannot agree, then the appropriate judicial tribunal may be used.

SECTION GC4 OWNER RESPONSIBILITIES AND RIGHTS

GC4.01 Working Area

Delete paragraph .02 in its entity and replace with the following:

.02 Prior to the commencement of a construction project or prior to tendering in the case of a construction project to be tendered, the Owner shall determine whether any designated substances are present within the Limits of Construction The Owner shall prepare a list of known designated substances and forward the list to the applicable parties involved on the construction project including, the consulting engineer, general contractor etc. An additional copy of the list will be posted by the Contractor in a conspicuous place within the workplace, where it is most likely to come to the attention of the workers who may be affected by the use of the substances listed.

GC4.02 Approvals and Permits

Delete paragraphs .01 and .02 of clause CG4.02 and substitute the following:

.O 1 The Contractor shall obtain and pay for all necessary permits or licenses required for the execution of the Work. The Contractor shall give all necessary notices and pay all fees required by law and comply with all laws, orders of authorities, ordinances, codes, rules and regulations relating to the Work for the preservation of the public health, the environment, and for construction safety

GC4.03 Management and Disposal of Materials

Amend paragraph .01 of subsection GC4.03 as follows:

Add one additional sentence after "disposition":

Tipping fees in effect will apply for disposal of materials at W 12A landfill site.

Page 103: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-6

GC4.04 Construction Affecting Railway Property Subsection GC4.04 is deleted and replaced with the following:

.O 1 Where construction affects railway property, the Owner will pay all costs of flagging and other traffic control measures related to the Work which are required and provided by the railway company. The costs will be paid directly by the Owner to the railway company.

GC4.05 Default by the Contractor

Add paragraph c) to Subsection GC4.05 as follow

c) in the opinion of the Owner, or Owner’s agent, the Contractor fails to satisfactorily carry out the obligations and duties of an employer and constructor under the Ontario Occupational Health and Safety Act and regulations in respect of the Work.

GC4.06 Notification of Default

Add paragraph .02 to subsection GC4.06 as follows:

.02 When the Owner or Contract Administrator becomes aware of an alleged Adefault under paragraph C), subsection GC4.05, General Conditions of Contract; the Owner or Contract Administrator will give immediate written notice on City Of London form, “ NOTIFICATION OF DEFAULT.”

GC4.07 Contractor’s Right to Correct a Default

Amend paragraph .01 of subsection GC4.07 as follows:

.01 Save and except for alleged defaults under GC4.05(c) the Contractor shall have ...

Add paragraph .03 to subsection GC4.07

.03 In the case of an alleged default under GC4.05(c), the Contractor shall take action forthwith to correct the default to the satisfaction of the Owner, and or its representative; and the Owner or its representative may, in their sole discretion, stipulate a date and time by which the Contractor must have satisfactorily completed the actions necessary to correct the default. The NOTICE OF DEFAULT shall be signed off in the applicable section of the form by the Contractor, the Owner, or Contract Administrator, when both parties are satisfied with the corrective measures. Current, completed and incomplete NOTICE OF DEFAULT forms shall become part of the next Progress Payment Certificate.

SECTION GC5 MATERIALS

GC5.02 Quality of Materials

Delete paragraph .03 of subsection GC5.02 and replace with the following:

As specified or as requested by the Contract Administrator, the Contractor shall make available for inspection or testing a sample of any material to be provided by the

Page 104: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-8

Delete paragraph . 1 3 of subsection GC7 .O 1 and replace with paragraphs . 1 3, .14, . 1 5, . 1 6 and .17

.13 The Contractor shall provide the Owner a copy of the minutes of proceedings as specified in Part II-Administration, section 9, clause (22)

.14 The Contractor shall provide the Owner or Contract Administrator immediate written correspondence of any verbal or written Accident Notices and Reports submitted to a “Director”of the Ministry of Labour required by Sections 5 1 - 53 of the Occupational Health and Safety Act.

.15 The Contractor shall provide the Owner immediate written correspondence of any verbal or written reports from an Inspector or Director of the Ministry of Labour.

.16 The Contractor shall ensure that safety inspections on the project are carried out on a regular basis. More fi-equent inspections will occur for larger scale, more complex, or more hazardous projects. Through regular inspections, the Contractor will record any findings and actions taken, and provide a report on the same to the Owner.

.17 The Contractor, throughout the duration of the contract, shall also comply with the regulations and policies as set out by the Technical Standards & Safety Authority Act, TSSA Act.

GC7.02 Layout

Delete paragraph .03 of subsection GC7.02.

Delete paragraph .07 of subsection GC7.02 and replace with the following:

All stakes, marks and reference points provided by the Contract Administrator shall be carefully preserved by the Contractor. In the case of their destruction or removal, such stakes, marks and reference points shall be replaced by the Contractor at his expense. Bench marks, and survey monuments shall be protected by the Contxactor. In the case of their destruction or removal, such bench marks and survey monuments will be replaced by the Owner at the Contractor’s expense.

GC7.06 Maintaining Roadways and Detours

Delete paragraphs .04 and .05 of subsection GC7.06. Delete paragraph .01 of subsection GC7.06 and substitute the following:

.01 Unless otherwise specified in the Special Provisions Section, where an existing roadway is affected by construction, it shall be kept open to pedestrian and vehicular traffic, and the Contractor shall at his expense be responsible for providing and maintaining a route through the work, whether along the road under construction, a detour road beside the road under construction within the Working Area, or parallel to the road under construction outside the Working Area in accordance with the Manual of Unlform Traffic Control Devices (M.U. T.C.D .).

.O 1 (a) Notwithstanding paragraph .01, the Contractor may, subject to the approval of the Contract Administrator, block traffic for short periods of time to facilitate construction of the work required under the Contract.

Page 105: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-9

Delete paragraph .08 of subsection GC7.06 and replace with the following:

.08 Where, with the written prior approval of the Contract Administrator the highway is closed and the traffic diverted entirely off the highway to any other highway, the Contractor shall, at no cost to the Owner, supply, erect and maintain traffic control devices, in accordance with the M.U.T.C.D.. The Contractor shall install and maintain and remove at its expense all traffic control devices outside of the Worlung Area. Any necessary flashers, signs, barricades, etc. within the Contract Limits, outside the Contract Limits and such traffic control provisions that shall be acceptable to the City of London Transportation System Engineering Division shall be the responsibility of the Contractor. This shall include notice signs of temporary closures and associated dates. The contractor shall notify the City of London dispatcher (661-4967) to provide the location that construction is taking place and a contact person in case of emergency. The Contractor shall give the Contract Administrator at least two (2) days notice prior to removal of signs, barricades, etc.

Add paragraph . 10 as follows:

.10 The successful Contractor shall submit a plan showing a method of maintaining entrances to commercial and residential properties, detours, and construction signing in accordance with the M.U.T.C.D.. Two copies for approval are required by the City of London Transportation Division at least fourteen (14) days in advance of the commencement of work. One copy of the approved plan will be forwarded to the Contract Administrator. Construction shall not be allowed to cornmence without traffic plan approval.

Subsection GC 7.06 is amended by the addition of the following paragraphs:

- 11 The Contractor shall give the Contract Administrator forty eight (48) hours advance notice prior to any street closing, not including Saturdays, Sundays, or Statutory Holidays, in order to permit the proper notification arrangements to be made through the City of London Transportation System Engineering Division

.12 The Contractor shall notify the Fire Department at end of each worlung day in order to specify access restrictions due to construction.

.13 The Contractor shall notify the London Transit Commission forty eight (48) hours prior to closing bus bays or any work on any street that is a bus route.

GC7.08 Approvals and Permits

Amend subsection GC7.08, paragraph .02 by the addition of supplemental subsection GC4.02 paragraph .01.

Page 106: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-10

GC7.12 Obstructions

Delete paragraph -02 of subsection GC7.12.

Delete paragraph .03 of subsection GC7.12 and replace with the following:

-03 The Contractor shall ensure that arrangements are made with the appropriate utility authority for the stake out of all underground utilities, except drain connections and catch basin connections, which may be affected by the work. During the course of the

Contract, it is the Contractor's responsibility to consult with utility authorities for further information relating to the exact location of these utilities.

The Contractor's responsibility to take the necessary precautions and provide such utility supports as may be necessary to prevent damage to utilities during and after construction depends upon whether the actual locations of utilities relative to the plan locations and to the field locates are within the tolerances set out in paragraph .01 a) of subsection GC2.01 "Reliance on Contract Documents". The Contractor's responsibility is indicated in supplemental 'paragraph .04 of subsection GC7.12. ( see page SGC-11)

Page 107: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-11

Add paragraph .04 to GC7.12 as follows:

.04 Underground Utilities

T=Tolerance as set out in Para. Ol(a) of Subsection SCG2.01

Contractor Responsibility

PldActual LocatedActual Protect Temporary/ from Permanent

Damage support Inside T Outside T Inside T Outside T

A. Mainline Utilities

Case 1 d d

B. Service connections except drain connections and catch basin connections

3 .I 4 .I 5 not shown

6 not shown

7 not shown

.I .I

d .I

d not located

Case 1 not applicable .I 2 not applicable .I 3 not applicable not located

Yes

Yes

yes * yes * no ** no ** no **

Yes

no

no

C. Drain connections and catch basin connections whether or not shown on drawings

Case 1 not applicable not located Yes Yes

Note: Notwithstanding above, utilities (including service connections) requiring adjustments because of elevation conflict shall be at Owner's cost, whether actual location is inside or outside plan or Locate Tolerance.

except additional support cost and additional operation cost all associated costs at Owner's expense

* **

Page 108: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-12 --

Add paragraphs .05, .06 and .07 to subsection GC7.12 as follows:

.05 Except when a special provision item is included in the tender documents detailing specific utility support or utility protection requirements, no separate item will be included in the Form of Tender for such work. Payment for protection and utility supports shall be as set out in paragraph .02 of clause GC8.02.01 "Price for Work".

.06 Payment for utility adjustments because of an elevation conflict shall be In accordance with the tendered price for such adjustment work or at a negotiated price, if no such item is included in the Form of Tender.

.07 When the Contract Administrator directs that utilities be replaced because of hydraulic, structural or mechanical deficiencies, payment shall be in accordance with the tendered price for such replacement work or at a negotiated price, if no such item is included in the Form of Tender.

GC7.13 Limitations of Operations

Delete paragraph .01 of subsection GC7.13 and replace with the following:

.01 Except for such work as may be required by the Contract Administrator to maintain the work in a safe and satisfactory condition, the Contractor shall not carry out operations under the Contract on Saturdays, Sundays and Statutory Holidays without the permission in writing fiom the Contract Administrator.

GC7.15 Warranty

Amend paragraph .02 of subsection GC7.15 as follows:

Delete the words "prior to and".

Add paragraph .04 and .05 of subsection GC7.15 as follows:

.04 Notwithstanding paragraph .02, the warranty period for sodding shall be in accordance with OPSS 571, the Construction Specification for Sodding as amended by a supplementary specification. and,

.05 Notwithstanding paragraph -02, the warranty period on specified nursery grown vegetation including trees, plants, shrubbery etc. is two (2) years.

GC8 MEASUREMENT AND PAYMENT

GC8.01.02 Variation in Tender Quantities

Delete the last sentence in subsection GC8.01.02.01 and replace with the following:

Written requests for compensation must be received within 45 days of the Certificate of Sub st antial Completion.

Page 109: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-13

GC8.02.02 Advance Payment for Material

Delete clause GC8.02.02 in its entirety.

GC8.02.03 Certification and Payment

GC 8 .O 2.03 .O 1 Progress Payment Certificate

Amend paragraph .01 of subsection GC8.02.03.01 as follows:

Delete the words "and material supplied".

Delete paragraph .02 c) of subsection GC8.02.03.01

Add paragraph .05 to subsection GC8.02.03.01 as follows:

.05 All required documentation outlined in the Payment Certificate Contract Administrator's Checklist shall form part of each Progress Payment Certificate.

GC8.02.03.02 Certification of Subcontract Completion

Delete both the above clauses.

GC8.02.03.04 Certificate of Substantial Performance

Add paragraph .06 to subsection GC8.02.03.04 as follows:

-06 When Substantial Performance coincides with Completion, the 10% statutory holdback will be retained until 45 days from the date of publication.

GC8.02.03.09 Interest for Late Payment

Delete clauses b) and c) of paragraph .01 to subsection GC8.02.03.09

GC8.02.06 Payment of Workers

Add paragraph .04 to GC8.02.06 as follows:

.04 LABOUR CONDITIONS

The Contractor agrees to and shall observe the following:

(a) the Contractor (and each Subcontractor involved in the work) shall be governed by these requirements; the Contractor is charged with the duty of informing subcontractors of these requirements and ensuring that they are honoured.

(b) each worker shall be paid at a rate which equals or exceeds the prevailing rate applicable in the zone which incorporates the City of London under the provincial

Page 110: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-14

“Fair Wage Policy”, detailed in the Fair Wage Schedules and special provisions pertaining to:

(i) (ii) (iii) (iv) (v)

Appendix ‘A’ - Industrial, Commercial and Institutional Appendix ‘B’ - Roads and Structures Construction Appendix ‘C’ - Sewer and Watermain Construction Appendix ‘D7 - Building Cleaning Industry Appendix ‘E’ - Security Guard Industry

which apply to the type of works being done under this Contract. Such shall be obtained from:

Administrator of Fair Wage Schedules Employment Standards Branch Ministry of Labour 400 University Avenue (3rd Floor) Toronto, Ontario M7A 1V2

the working conditions and benefits specified under the Fair Wage Policy are deemed to be adopted into the employment contract between each worker and the Contractor (or his Subcontractor) as minimum standards.

the Fair Wage Policy applies to work of any person under the Contract at the job site, employed by the Contractor (or his Subcontractors) but does not apply to those persons whose sole function is to deliver materials from a supplier.

if the Fair Wage Policy is revised during the life of the Contract, the wages paid to workers shall be adjusted (where applicable) to recognize such change and any extra costs created by wage adjustments shall be borne by the Contractor.

The Contractor shall,

(9

(ii)

(iii)

at all times keep or cause to be kept a list of the names, trades and addresses of all workers providing work at the job site under the Contract, whether such workers are employed by the Contractor or through an employment agency and a record of the regular hourly wage rates, overtime hourly wage rates, hours of work, and amounts paid by the Contractor or employment agency to each such worker;

from time to time, if demanded by any authorized officer, or employee oflor designated professional accountant on behalf of the Corporation, furnish within fifteen (1 5) days after demand a certified copy of all pay sheets, lists, records and books relating to the work and keep the originals thereof open at all times for examination by such officer, employee or agent, on the understanding that such information will be considered personal information pursuant to the Municipal Freedom of Information and Protection of Privacy Act; and

upon reasonable notice furnish and disclose to any authorized officer, or employee of/or designated professional accountant on behalf of the Corporation any other information respecting wages of workers that may

Page 111: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-15

be specified by such officer, employee or agent in connection with the work.

In case of a dispute as to rate of wages to be paid under the Contract or as to the amount to be paid to any worker or workers,

the Corporation may appoint a panel of one or more persons (herein referred to as "the Panel") to adjudicate disputes between a worker or workers (or authorized representatives) and the Contractor respecting the administration of the Fair Wage Policy and the appropriate Fair Wage Schedule;

the Panel shall consider such pay sheets, lists, records and books relating to the work as the Panel considers necessary and afford the Contractor and the worker or workers (or authorized representative) a reasonable opportunity to make to make submissions with respect to the dispute;

the Panel shall as soon as practicable issue its decision and as part of its decision may, if it considers appropriate, direct that one or more of the parties pay to the Corporation its costs reasonably incurred respecting the Panel's adjudication; and

the decision of the Panel shall be fmal and binding upon all parties.

If an amount of wages is found by the Panel to be owing by the Contractor to a worker or workers at the rate called for under paragraph (b) and the Contractor fails to pay the worker or workers such wage amount within fifteen (1 5) days following the date of the Panel's decision, the Corporation may pay to the worker or workers all or a portion of the balance necessary to make up the wages that should have been paid and may,

(i) recover the amount paid by the Corporation and any of the Corporation's adjudication costs awarded by the Panel against the Contractor, together with interest and costs, as a debt due to the Corporation in a court of competent jurisdiction; and

(ii) where any money is owing by the Corporation to the Contractor, may deduct, as permitted by law, the amount paid by the Corporation and any of the Corporation's adjudication costs awarded by the Panel against the Contractor, together with an administrative fee not exceeding ffteen per cent (15%) of such balance, fiom the amount owing by the Corporation to the Contractor.

The Contractor shall have a legible copy of Clause SGC 8.02.06, paragraph .04 - Labour Conditions and Fair Wage Policy including the appropriate Fair Wage Schedule posted in open view of the workers in a prominent and accessible location at each job site throughout the duration of the Contract.

The Contractor shall include Clause SGC 8.02.06, paragraph .04 - Labour Conditions in each subcontract between the Contractor and his, her or its Subcontractor for the provision of work at the job site under this Contract.

If requested, the Contractor shall attach to all accounts rendered for payment of money upon the Contract a statutory declaration a f f i g that the requirements of Clause SGC 8.02.06, paragraph .04 - Labour Conditions have been fully complied with.

Page 112: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-16

Drywall applicators and lathers Electricians Elevator mechanics Erectors and finishers (pre-cast slab erector) Glaziers

Insulation mechanics (heat & frost) Jackhammer operators Labourers - precast Labourers - common Labourers - demolition

@ Ontario

23.20 23.92 30.37 25.06 21.53

26.56 22.49 22.94 22.94 16.69

Appendix ‘A’

Project No.: Mini~try Miiut&O

& Tram3 FAIR WAGE SCHEDULE ou

INDUSTRIAL, COMMERCLAL AND INSTITUTIONAL SECTOR OF ONTARIO’S CONSTRUCTION INDUSTRY

Zone 20: Middiesex County Urban Zone

CkssifiCEdon of Labour

Asbestos removers Boilermakers Bricklayers and stonemasons Carpenters and joiners Cement finishers Drillers (air trac, wagon, etc.)

’ Effsctivs Data: April 1,1996

$ 17.07 25.56 27.51 24.64 23.41 22.91

~ - ~

Labourers - student (registered in day school1 Marble setters Millwright Mortarmen (brick, plaster, stone) Ornamental & miscellaneous metal erectors

Painters (brush) Painters (spray) Plasterers Plumbers and pipefitters Powdermen - ~ -~

Refrigeration mechanics Riggers (general), & structural steel workers Rodmen Roofers [built-up) Sheet metal workers

15.29 25.53 26.58 22.77 25.06

23.16 23.1 6 23.20 25.70 22.9 1

30.64 25.06 23.15 24.95 26.54

Sprinkler installers Terrazzo layer or setters Terrazzo base machine operator Terrazzo floor machine operator Tile setters

Tile & linoleum layers (resilient floor layers) Truck drivers: 1. floats Truck drivers: 2. tandem axle Truck drivers: 3. single axle Watchpersons Welders and burners (acetylene or electric)

28.33 25.56 24.35

. 24.74 25.30

~~

23.40 21.61 21.51 21.41 17.17 25.06

~

Equipment Operators Licensed Operators: Engineers operating cranes, shovels, hoists, clams, gradalls, backhoes, draglines, piledrivers, mobile truck cranes, derricks, caisson boring machines over 25hp, drillers and similar equipment. Equipment Operators, Group A 1. Tuggers, side booms, man and material hoists. 2. Bullmoose equipment, steam boilers, temporary steam plants, caisson boring machines 25hp and under. Equipment Operators, Group B 1. Bulldozers, tractors, scrapers, graders, emcos, herhead and front-end loaders, trenching machines,

2. Pumps 6“ discharge and over, concrete mixers 1 &. yd. and over, well points, gas or steam driven

3. Boom trucks, A frames, compaction units, forklifts 8’and under in lifting height, forced air, gas or oil

4. Pumps under 6” discharge, and oilers.

industrial tractors with excavating attachments, concrete pumps and pumpcretes, and .post hole diggers.

generators over 50hp, fork lift trucks over 8‘ lifting height, portable air compressors.

burning temporary heating units.

24.60

23.47 21 -36

23.32

21.36

20.95

20.26

NOTE Up to 15% of the above Fair Wage rates may be in the form of benefits not required by law (for exampte: medical, demal, pension plans)

See your own employer’s posted schedule for houriy Base Wage rates p& hourly Benefits = hourly Fair Wage rates.

Page 113: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-17

7-

Appendix 'B'

Mintsnre Mirusby of du Travail

ds I'Ontarro

FAIR WAGE SCHEDULE OCCUPATION CLASSIFICATIONS

ROAD AND HIGHWAY CONSTRUCTlON

ROAD BUILDING SECTlON

LICENSED OPERATORS Operators of Shovels, Clams, Backhoes. Gradalls. Oraglines, Piledrivers, Cranes, Mobile Truck Cranes, Derricks and Dredges.

UCENSED MECHANICS AND WEL~ERS, CLASS A:

EOUIPMENT AND MAINTENANCE OPERATORS. GROUP A:

CATEGORY 1: Operators of Etulldozers (75 Drawbar HP and over, M or equivalent and over), Grader - Class A (fine grading), Front-End Loaders (l-l/Z cu. yd. and over), Ovsrhead Lodm (1-1/2 cu. yd. and over), Pitman Type (Hydra- Lift Truck Mounted Hydraulic) Crane, Farm and Industrhl Tractot. with excavating attachments (3/8 yd. capaaw and over).

CATEGORY 2 Operators of Concrete and Asphalt Pavers or Planers (1 cu. yd. or wer), Engineers on Boilers with papers, Scrapers (self-propelled), Emcos, Trenching Machines (6 and over), Mixermen on Asphalt Ptants (1 cu. yd. and over), Operators of Asphalt, Batching, and Steam Heating piants.

CATEGORY & Asphalt Rollers, Portable Compressors (210 C N and over, or two or more 110 CFh4 and over), pumps 6" and over, Portable Generators.

EOUIPMENT AND MAINTENANCE OPERATORS. GROUP 8:

CATEGORY 1: Operators of Etulldozers (under 75 drawbar HP, 1)-4 or equivalent), Graders - Class 6, Front-End Loaders (under 1-1/2 cu. yd.), Farm and Industrial Tractors with excavating attachments (under 3/8 yd. capacity), Concrete and Psphalt Plants (under 1 cu. yd.), Asphalt Spreaders (self-propelled), Asphalt Rollers - B, Mechanics and Welders - Class B, Trenching Machines (under 63, Mixermen on Asphalt Rant (under 7 cu. yd.).

CATEGORY 2: Boiler Fireman without papers, Burnerman on kphat t plants, pumps under 6, Farm and Industrial Tractors with towing compaction units, Grade Rollermen (induding sslf-propelled rubber tires), Servicemen.

CATEGOW 3: Oilers, Greasers, Compressors (less than 210 CFM). Operators of 5 or more Heaters.

SKILLED LABOURERS:

CATEGORY 1: Asphaft Raker, Form Setter, Curb Setten, Gutter &id< Setters, Manhole Valve Chamber and Catch Basin Constructors, Crawler Type Drill Man, Wire-Mesh and Rod kinforcing Man, Powderman.

CATEGORY 2: Scrsedmen. Puddlers, Floatmen, Concrote Saw Operaton. Concrete Workers, Sheeting and Shoring Man, Pipelayer, Air and Machine Tool Operator, Guard Rail Insp6ctors.

COMMON tABOUAERS: Labourers, Asphalt and Concrete Shovelers and Ironers, Asphalt and Cement Improvers, Jackhammer Breaker Operator, Fence Erectors, katerman (up to 5 heaters), Hopperman, Tamperman, Grouter. Scootmete Driver, Yard and Matsrial Men.

TRUCK DRlV%Rs

CATEGORY 1: Floats (low bed, 25 tons or more).

CATEGORY 2 Floats (low bed, under 25 tons), %mi-Float (full-timo), Semi-Double Bottom Hook-up or other Semi- Combination, Tri-Axle Dump Truck, Off-Highway Fbck Type Truck.

CATEGORY 3: Tandem M e , Load Bearing Boom Trucks, Dumpcrete Drivers, Semi-Trailers, Tandem Axle Dump Trucks, Bulk Lift Trucks, Semi-floats (part-time).

CATEGORY 4: Single &le. Single Axle +mp Trucks, Servica and Fuel Trucks, Tag Along Floats, Farm Tractor Driver, TOW Tractor Operator, Stake Trucks.

FIAGPERSONS:

WATCHPERSONS:

STRUCTURE SECT104

CARPENTERS, FORM BUILDERS

RODMEN:

CONCRETE FINISHERS:

PAINTERS

ELECTRICIANS:

LABOURERS: (on structures)

STRUCTURAL STEEL WORKERS:

Page 114: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-18

LICENSED OPERATORS

Appendix 'B' - cont'd

!6 13.83

@ Ontario

EQUIPMENT AND MAINTENANCE OPERATORS, GROUP "A"

EQUIPMENT AND h U " 3 N A N C E OPERATORS, GROUP "B"

SKCLLED LABOURERS

FAIR WAGE SCKEDULE

12.85

12.20

11.69

-

Minutty Ministke ROADS AND STRUCTURES CONSTRUCTION, ONTARIO PROVINCIAL ZONE du && Travail

TRUCK DRIVERS - Tow Tractor Operators - Rollermen (Grade)

LABOURERS FLAGPERSON

ROAD BUILDING SECTION I r i

11 -48

11.19

9 -40

Fair Wage Rate Per Hour not less than:

WATCHPERSON STUDENTS (registered in day school)

I CLASSlFICATION OF LABOUR Effective Date: April 1, 1995

9.40

9.04

r CARPENTERS, FORM BUILDERS 13.83

RODMEN. CONCRETE FINISHERS. PAINTERS 12.69

STRUCTURE LABOUR OPERATIONS I 11.34

STRUCTURAL TRAINEES 11 -48

CLASSFICATION DEFINITIONS:

Licensed Operators:

Eauiument and Maintenance Operators. Group A-

Euubment and Maintenance &erators, Group B:

Skilled Labourers:

Structure Labour Operations:

Structural Trainee:

Includes Shovel, Clam, Gradall, Backhoe, Dragbe, Piledriver Operator.

IncIudes Mechanic and Weider, Class B, Rollerman - Asphalt, Burnerman, Powerman, Boiler Engineer (wifh papers). Float Driver (over 25 tons), Concrete Paver (over 1 cu. yd.), Bulldozer (75 Drawbar HP and over), Grader, Class A (Finished Grading), Front End Loader (1-112 yds. and over), Scraper, Crusher, Asphalt Spreader Operator.

IncIudes Boiler Fireman, Mixerman, Float Driver (25 tons and under), Front End Loader (under 1-112 yds.) Grader, Class B (Gravel and other Grading), Farm and Industrial Tractor with Power Attachments, Driller (Air Track), Bulldo'zer (under 75 Drawbar HP) Operator.

Includes Air Tool Operator, Asphalt Raker, Form Setter, Pipe Layer, screedman.

Includes Labourers on Structures. ir i

Means an Employee who is enrolled in the Ontario Road Builders Association Pilot Training Programme.

Page 115: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-19 - -

Appendix 'Cy

FAIR WAGE SCHEDULE OCCUPATION CtASSiFICATlONS

SEWER AND WATERWN CONSTRUMON

OPEN CUT SECTlON

UCMSED OPERATORS: Operators of shovels, Clams, Gradalls, Backhoes, Draglines, Aledrivers, Cranes, Mobife Truck Cranes, Derricks and Dredges, Caisson &ring Machines 25hp and over.

UCENSED MECHANICS AND WELDERS, CLASS A:

EQUIPMENT AND MAINTENANCE OPEW\TORS. GROUP A:

CATEGORY 1: Operators of Bulldozers (75 Drawbar HP and over, D4 or equivalent and over), Front-End and Overhead Laaders (I-l/Z cu. yd. and mr), Pitman Type Q-tydraUt Mounted Hydmulic Truck) Crane, Caisson Boring Machines (under 2shp).

CATEGORY 2 Operators of Emas and Trenching Machines (6' and over).

CATEGOFW 3: Operaturs of Portable Compressors (210 CFM and m r , or two or more 110 CFM or over), pumps 6' and over, Drilling Machines.

EQUIPMENT AND MAINTENANCE OPERATORS. GROUP 8:

CATEGORY 1: Operators of &rlldozers (under 75 Drawbar HP. D-4 or equivalent), Front-End and Overhead Loaders (under 1-1/2 w. yd.), Farm and Industrial Tractors with excavating attachments (under 3/8 fl. wm) , Mechanics and Welders. Class 6, Trenching Machines under 6 , Boom Trucks, A Ffamss, Well points.

CATEGORY 2 Pumps up to 6, Farm and Industrial Tracton with towing compaction units, Servic%rnen.

CATEGORY 3 Oilers, Greasers. Compressors (less than 210 CFM), Qxrators of 5 or more heaters.

S K I L E D LABOURERS Fom Setters, Rpeiayers and Fitters, Air Track hillers, Powdermen, Cernenf Finishers.

COMMON LABOURERS c

TRUCK DRIVERS:

/ CATEGORY 1:

CATEGORY 2 Floats (low bed, under 25 tons), SemCRoat (full-time), Semi-Double Bottom Hoak-up or other Semi- Combination, Tri-Axle Dump Truck, Off-Highway Fmck Type Truck.

CATEGORY 3 Tandem Axle. Load Bearing Boom Trucks, Dumpcrete Drivers, Semi-Trailers, Tandem Axle Dump Trudn, &Ilk Lift Trucks, Semi-Raats (part-time).

CATEGORY 4 Single Axle, Single Axle Dump Trucks, Service and Fuel Trudcs, Tag Along Floats. Farm Tractor Wwer, Tow Tractor Operator, Stake Trucks.

floats (low bed. 25 tons or more).

WATCHPERSONS:

RAGPERSONS

Page 116: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-20

Appendix ‘C’ - cont’d

Ontario Ministere Ministry of du Travail Labour de I’Ontario

FAIR WAGE SCHEDULE OCCUPAflON CLASSlFlCATIONS

SEWER AND WATERMAIN CONSTRUCTION

TUNNEL SECTION

UCENSED OPERATORS: operaton of Shovels. &JTIS. Backhoes, Draglines, Piledrivers, GradaJls. Cranes, Mobile Truck Cranes, Derricks and Dredges, Caisson Boring Machines 25hp and mr , Hoists and Tuggers with r i n g capacity uf over 2ooo Ibs.

UCENSED MECHANICS AND WELDERS. CLASS A:

EQUIPMENT AND MAINTENANCE OPERATORS, GROUP A.

CATEGORY 1: Operators of Bulldozers (75 Drawbar HP and over, M or equivaJent and over), Fnmt-End and m r h e 8 d Loaders (1-1/2 CU. yd. and over), Pitman Type (Iiydm-uft Mounted Hydraulic Truck) Crane, Farm and Industrial Tractors with excavating attachments (3/8 yd. capacity and over). shaft Hoists and Tuggers with l i i n g capacity of XXM Ibs. or less, Locomotives (under 2ooo lbs.), Compressor House Setup Man, Campressors over 500 CFM.

CATEGORY 2 Operators of Emu?s and Trenching Machines (6’ and over).

CATEGORY 3: Operators of Portable Compressors (210 CFM and over, or two or more 110 CFM and over). pumps 6’ and over.

EQUIPMENT AND MAINTENANCE OPERATORS, GROUP B:

CATEGORY 1: Qkrators of Bulldozers (under 75 Drawbar HP. 04 or equ-Rlalent), Front-End and Overhead Loaders (under 1-1/2 cu. yd.), Farm and Industrial Tractors with excavating attachments (under 3/8 yd. capacity), M a n i c s and Welders. Class 6, Trenching Machines (under 6’).

CATEGORY 2

CATEGORY 3:

SKILLED LABOURERS:

CATEGORY 1:

CATEGORY 2

CATEGORY 3

CATEGORY 4

Pumps under C, Farm and Industrial Tractors with towing compaction attachments, Sem’cemen.

oilers. Greasers, Compressors (less than 210 CFM), Operators of 5 or more heaters.

Lead Miners.

Muckers.

Miners, Form Setters, Tunnel Mole Drivers, Mucking Machines, P o w d e w .

Underground Labourer, Loco Driver, Lodc Tender, Cage Tender, Dingy Operator.

COMMON LABOURERS:

TRUCK DRIVERS

CATEGORY 1: Floats (low bed. 25 ions or more).

CATEGORY 2 Floats (low bed, under 25 tons), Semi-Float (jull-time), Semi-Double Bottom Hookup or other Semi- Combination, Tri-Axe Dump TNC~S, Off-Highway Rodc Type Truck.

CATEGORY 3: Tandem Axle. b a d Bearing Boom Trucks, Dumpcrete Drivers, SemiiTrailers, Tandem Axie Dump Trudts, Bulk Lift Trucks, Semi-Floats (part-time).

CATEGORY 4: Single Axle, Single Axle Dump Trucks, SeMca and Fuel Trucks, Tag Along Roats, Farm Tractor Driver, Tow Tractor Operator, Stake T N ~ ~ s .

WATCHPER SONS:

FLAGPERSONS

e

Page 117: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-21

P p -aw---’wn-

LICENSED OPERATORS LICENSED MECHANICS AND WELDERS, CLASS “A“

EOUPMENT OPERATORS. GROUP “A”

Appendix ‘C’ - cont’d

$ 13.83

12.99

12.85

@ Ontario FAIR WAGE ScHEDuI;E

-~ -~ ~ ~

EQUIPMENT OPERATORS, GROUP “B”

SKILLED LABOURERS - T U M ~ Operations

SKTLLED LABOURERS

COMMON LABOURERS

Ministry MhiBLlrO SEWER AND WATERMAIN CONSTRUCTION, ONTARIO PROVINCLaL ZONE ou

&&r Travail

12.20

11.83

11.69

11.19

Fair Wage Rate Per Hour !I not less than:

TRUCK DRIVERS - Including Dump Truck and Boom Truck

FLAGPERSON

WATCHPERSON

STUDENTS (registered in day school)

Effective Date: April 1, 1995

CLASSIFICATION OF LABOUR 1 1

11.48

9.40

9.40

9.04

CLASSIFICATION DEFINITIONS:

Licensed ODexators:

Licensed Mechanics and Welders. Class A:

Equipment Operators, Group k

Equipment ODerators, Group B:

Skilled Labourers - Tunnel b r a t i o n s

Skilled Labourers:

Includes Shovel, Clam, Crane, Gradall, Backhoe, Dragline, Piledriver.

Jncludes Licensed Mechanic and Licensed Welder.

Includes Bulldozer (75 HP and over), Grader (100 HP and over),

End Loader (1-112 cu. yd. and over), Trenching Machine, Caisson Boring Machine, Pitman Type Truck, Mounted Hydradie Lift Crane, Crusher, Asphalt Spreader, Rollerman - Asphalt, Burnerman - Aspbalt, Boiler En,&er (with papers), Concrete Paver (over 1 cu. yd.), Operators and Float Driver (over 25 tons).

Includes Bulldozer (under 75 HP), Grader (under 100 EDP), Front End Loader (under 1-1/2 cn. yd.), Farm and Industrial Tractor with Excavating Attachment (up to 314 cu. yd.), Compaction roller (self- propelled), Driller-Air Track and Float Driver (25 tons and under).

Grader (75 HP Minimum and Fine Grading), Scraper, Emco, Front t

Includes Miner, Driller, Shaft Sinker, Timberman, Grout Machine Operator and any other “Skilled Labourer” as defined below who is employed in the construction of a tunel.

Includes Air Tool Operator, Boiler Fireman, Mixennan, Sheeting and Shoring, Powdennan/Blaster, Pipe Layerflop Man, Caulker, ManholeNalve Chamber/Catch Basin Constructor, Box

~1 Sewer/Culvert Constructor (including Rod Reinforcing and Fonn Setter), Well Point Installer, Asphalt Raker, Concrete Form Setter, Screedman.

Page 118: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-22

~~- - ~

AREA

EASTERN REGION

CENTRAL, REGION'

PEEL AND YORK COUNTIES

SOUTHWESTERN REGION

NORTKEASTERN REGION

NORTHWESTERN REGION

Appendix 'D'

- ~- ~

CLEANER m o w m o w CLEANER C m m R

LOW EIIGE

7.21 8.34 9 -59

7.34 8.42 9.59

8 -49 9.87 12.59

6.97 8.03 9.20

7.06 7-97 9.10',

7.06 7.90 9.26

@ Ontario FAIR WAGE SCHEDUWE

BULLDING CLEANING INDUSTRY, ONTARIO EFFECTllvE DATE - APRIL 1,1995

RATE PER HOUR ($1

excluding Peel and York counties

DescriDtion of Repions:

Eastern Region:

Central Recion:

Dundas, Stormont, Giengarry, Prescott Counties; Carleton and Russell Counties; Grenviile and Leeds Counties; Lanark County; HaIiburton and Renfrew Counties; Frontenac, Lennox and Addington Counties; Hastings and Prince Edward Counties.

'

Northumberland, Peterborough & Victoria Counties; Durham and Ontario Counties; Bruce, Dufferin, Grey, Simcoe, Huron, Manitoulin, Muskoka, Parry Sound and Perth Counties; Wellington County; Halton and Wentworth Counties; Lincofn and Welland Counties; Brant, Haldimand and Norfolk Counties; Waterloo County.

* Southwestern Reg-ion: Elgin and Oxford Counties; Middlesex County; Lambton County; Kent County; Essex County.

e Northeastern Region: Algoma District; Sudbury District; Cochrane and Timiskaming Districts; Nipissing District.

Northwestern Recion: Kenora and Rainy River Districts; Thunder Bay District.

Page 119: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-23

NORTHEASTERN REGION

NORTHWESTERN REGION

Appendix (E’

8.54

7.27

@ Ontario M~niarry Mmat*s

k r Travail du

FAIR WAGE SCmDULX SECURITY GUARD INDUSTRY, ONTARIO

EmCTIIVE DATE - APRIL 1,1995

11 CENTRAL REGION* 1 7.45 II 11 PEEL AND YORK COUNTIES I 9.34 II 11 SOUTHWESTERN REGION I 7.20 I1

* excluding Peel and York counties

Descriution of Regions:

Eastern Region: Dundas, Stonnont, Glengarry, Prescott Counties; Carleton and Russell Counties; Grenville and Leeds Counties; Lanark County; Haliburton and Renfrew Counties; Frontenac, Lennox and Addington Counties; Hastings and Prince Edward Counties.

0 . Central Region: NorthumberIand, Peterborough & Victoria Counties; Durham and Ontario Counties; Bruce, Dufferin, Grey, Simcoe, Huron, Manitoulin, Muskoka, Parry Sound and Perth Counties; WeIIington County; Halton and Wentworth Counties; Lincoln and WeIland Counties; Brant, Haldmand and Norfolk Counties; Waterloo County.

0 Southwestern Region: EIgin and Oxford Counties; Middlesex County; Lambton County; Kent County; Essex County.

Northeastern Rezion: Algoma District; Sudbury District; Cochrane and Timiskaming Districts; Nipissing District.

0 Northwestern Region: Kenora and Rainy River Districts; Thunder Bay District.

z

Page 120: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SGC-24

GC8.02.08 Taxes and Duties

Add paragraphs .05 and -06 as follows:

-05 Taxes, custom duties and excise taxes on all fuels, materials and services, except for refundable taxes and duties, shall be included in the Contract price.

.06 The Contractor shall pay all taxes, customs duties, and excise taxes on all fuels and materials with respect to the Contract. Where applicable, the Contractor shall apply for any refunds of taxes and duties to the appropriate tax levying authority.

GC8.02.09 Liquidated Damages

Delete paragraph .01 of Clause GC8.02.09 and replace with the following:

.01 If the Contractor fails to complete the work in accordance with the Contract and to the satisfaction of the Contract Administrator within the time or times specified, the Contractor shall pay the Corporation the costs incurred by the Corporation for office supervision and field inspection in addition to $100.00 (One Hundred Dollars) for each and every working day that the work or works remain unfmished after the time specified. The amount is the liquidated damages that the Corporation will suffer by reason of a delay and not as a penalty. Other than liquidated damages, the Contractor shall not be responsible for any other costs that the Corporation may incur as a result of a delay in completing the work within the time specified.

Page 121: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003

London C A N A D A

CITY OF LONDON

SUPPLEMENTAL STANDARDS FOR PARKS AND OPEN SPACES (SPO)

The Ontario Provincial Standards (OPSS) are amended as follows:

I N D E X

Section

206.07 206.10

3 10.07

350.05 350.07

353.05 353.07

Description Page

O.P.S.S. 206 - CONSTRUCTION SPECIFICATION FOR GRADING

Construction .................................................................................................................... SPO-1 Basis of Payment .............................................................................. .SPO-1

0.P.S.S. 310 - CONSTRUCTION SPECIFICATION FOR HOT MIXED, HOT LAID ASPHALTIC CONCRETE PAVING AND HOT MIX PATCHING

Construction ............................................................ SPO-2

O.P.S.S. 350 - CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE

Materials ......................................................................................................................... SPO-4 Construction.. .................................................................................................................. SPO-4

0.P.S.S. 353 - CONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS

Materials ......................................................................................................................... SPO-5 Construction.. .................................................................................................................. SPO -5

Page 122: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

Section

I N D E X

Description

November 3. 2003

Page

405.07

570.05 570.07

571.07 571.10

572.03 572.06 572.07

10 10.01 10 10.07

0.P.S.S. 405 . CONSTRUCTION SEPCIFICATION FOR PIPE SUBDRAINS

Construction ........................................................ 5p0-6

0.P.S.S. 570 . CONSTRUCTION SPECIFICATION FOR TOPSOIL

Materials ......................................................................................................................... 5p0-7

Construction .................................................................................................................... 5p0-8

0.P.S.S. 571 . CONSTRUCTION SPECIFICATION FOR SODDING

Construction .................................................................................................................... 5 p0-9 Basis for Payment ........................................................................................................... 5p0-9

0.P.S.S. 572 . CONSTRUCTION SPECIFICATION FOR SEEDING AND COVER

Definitions ..................................................................................................................... SPO-10 Equipment ......................................................................................... SPO- 10 Construction ..................................................................................... SPO-10 Table 1 ............................................................................................. SPO-12 Table 2 ............................................................................................. SPO-12

0.P.S.S. 1010 . MATERIAL SPECIFICATION FOR AGGREGATES . GRANULAR A. B. M. AND SELECT SUBGRADE MATERIAL

Scope ................................................................................................ SPO-13 Production .......................................................................................... SPO-13

STANDARD DRAWINGS FOR PARKS AND OPEN SPACES ...................................... SPO-14

Page 123: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SPO-2

O.P.S.S. 310 CONSTRUCTION SPECIFICATION FOR HOT MIX ASPHALT

310.07 CONSTRUCTION

310.01.01 Quality Control

Subsection 3 10.07.01 is amended by the addition of the following:

Hot Mix HL3 shall be used for pedestrian pathways, multi-use pathways and basketball courts, to the quantities specified on the contract drawings. A combination of Hot Mix HL 8 and HL 3 shall be used on vehicular parking areas, to the quantities specified on the contract drawings.

Surface cross slopes on pathways shall be between 1 .O% and 1.5% to ensure that there is no water ponding, while allowing existing overland drainage flows to continue. Surface cross-slopes on vehicular parking areas shall be in accordance with the contract drawings or as specified by the Contract Administrator.

All asphalt edges shall have uniform, even lines with hand pressed 45 degree angles, unless abutting curbs or structures. All rough, distorted andor ragged edges shall be re-worked to the satisfaction of the Contract Administrator.

310.07.13

310.07.14

Tolerances

Clause 3 10.07.13 is deleted in its entirety and replaced by the following:

Each course, after final compaction, shall be smooth and true to the established crown and grade and the surface of each course shall be free from deviations exceeding 3mm as measured in any direction with 1.5m straight edge (for pedestrian pathways) and 3 .Om straight edge (for vehicular parking areas and basketball courts).

Surface Appearance

Subsection 3 10.07.14 is amended by the addition of the following:

Page 124: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SPO-3

310.07.15 Surface Appearance (cont’d)

All holes and depressions of 3 m or more shall be cleaned, primed and patched. Excessively defective areas, holes andor depressions shall be marked and saw cut through the full depth of asphalt, as directed by the Contract Administrator. The material in the defective area shall be entirely removed, with all edges saw cut and painted with a thin coating of SS-1 emulsion o provide a tight waterproof bond and new asphalt shall be placed and compacted to required grades. Repairs of excessive defective areas, holes and or depressions by an asphalt overlay feathered to match existing surfaces will not be accepted.

a

Page 125: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SPO-4

350.05

350.05.01

350.06

350.07.02

O.P.S.S. 350 CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT

AND CONCRETE BASE

MATERIALS

Concrete

Subsection 350.05.01 paragraph a) is deleted in its entirety and replaced by the following:

(a) The nominal maximum size of the coarse aggregate for concrete pavement shall be 19.Omm with gradation requirements as per Table 3 of O.P.S.S. 1002.

CONSTRUCTION

Joints

350.07.02.01 General

Clause 350.07.02.01, first paragraph is deleted in its entirety and replaced by the fo 110 wing:

Joints shall be of the type and at the location shown on the contract drawings or as directed by the Contract Administrator. For concrete bench pads adjacent to play areas, one (1) continuous expansion joint shall be installed along the face of the concrete curb, and one (1) control joint shall be cut along the center of the pad, perpendicular to the concrete curb.

350.07.08 Miscellaneous Protection

350.07.08.02 Traffic

Clause 350.07.08.02 is amended by the addition of the following:

Protection against all damage to concrete paving that has not attained 75% of the specified nominal minimum 28 day compressive strength shall be the sole responsibility of the Contractor. At the discretion of the Contract Administrator, damaged or unacceptable concrete paving shall be replaced at no extra cost to the contract.

Page 126: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SPO-5

O.P.S.S. 353 CONSTRUCTION SPECIFICATION FOR

CONCRETE CURB AND GUTTER SYSTEMS

353.05 MATERIALS

353.05.05 Forms

Subsection 353.05.05 is amended by the addition of the following:

For play area curbs, flexible or rigid forms may be used provided they ensure a constant radius. When tested with a 3.0m straight edge or curved template, forms shall not deviate on the top surface more than 3 m or on the inside face more than 61nm from the testing edge of the template.

353.06 CONSTRUCTION

353.07.01 General

Subsection 353.07.01 is amended by the addition of the following:

For play area curb construction, the top of the curb shall be set level around the entire perimeter, unless other wise instructed by Contract Administrator. The radius of the play area curb shall be measured to the inside face of curb. Concrete curb to be broom finished with evenly spaced control joints (minimum every 2.0m)

For vehicular parlung area curb construction, the top of all curbs are to be set according to the grade specified on the contract drawings or as determined by the Contract Administrator during construction.

Page 127: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SPO-6

0.P.S.S 405 CONSTRUCTION SPECIFICATION FOR

PIPE SUBDRAINS

405.07 CONSTRUCTION

405.07.01 General

Subsection 405.07.01 is amended by the addition of the following:

Subdrain pipe used to drain the inside of the play areas shall be 1 O O m m diameter perforated flexible PVC drainage pipe pre-wrapped with geotextile knitted sock, or approved equal.

Subdrain pipe used to outlet play area drainage shall be lOOrnm diameter rigid PVC drainage pipe, connected to the play area subdrain with appropriate couplings.

405.07.03 Laying Pipe

405.07.03.01 General

Clause 405.07.03.01 first paragraph, is amended by the addition of the following:

Subdrain pipe used to drain the inside of play areas shall be set into 19mm clear granular stone, as per detail drawings. Filter cloth shall be used to prevent the migration of clear stone into the play area sand base. Subdrain pipe used to outlet plat area drainage shall be set onto the required excavated grade and backfilled with sufficient native soil to account for settling.

Page 128: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SPO-7

Category Herbicides

570.05

570.05.01

Fertility Requirements No detectable levels

O.P.S.S. 570 CONSTRUCTION SPECIFICATION

FOR TOPSOIL

Phosphorus Potassium Magnesium Potassium / Magnesium Ratio (WMg) Calcium Sodium

MATERIALS

Minimum of 30ppm Bray-P1 200ppm, and have a 2.0% or greater base saturation 10.0% to 20.0% base saturation Ratio Range of 0.2 to 0.35 Less than 85.0% base saturation Less than 0.5% base saturation

Topsoil

Subsection 570.05.01, first paragraph is deleted in its entirety and replaced by the following:

Topsoil for Eeneral park / open space areas shall be loose, fiiable, fertile loamy material that is 6-ee from subsoil, weeds, roots, vegetation and other deleterious material greater than 25mm diameter in the greatest dimension. The topsoil shall also be certified to meet the fertility requirements of table 1.

Topsoil for sport fields areas shall be loose, friable, fertile loamy material that is free fiom subsoil, weeds, roots, vegetation and other deleterious material greater than 151nm in diameter in the greatest dimension. The topsoil shall also be certified to meet the fertility requirements of table 1.

Table 1 Topsoil Fertility Requirements

I Organic Matter I Minimum of 4.0% content I

I PH I 6.2-6.8 I I Micronutrients I High 1

Page 129: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SPO-8

570.07 CONSTRUCTION

570.07.01 Stockpiling of Topsoil

Subsection 570.07.01 is deleted in entirety and replaced by the following:

Topsoil shall be removed from construction surfaces as specified and stock-piled within City Park land. Stockpile shall be constructed neatly with uniform surfaces.

The topsoil stockpiles shall be located as per Contract Documents

570.07.03 Placement of Topsoil

Subsection 570.07.03 is deleted in its entirety and replace with the following:

Topsoil shall be placed, spread and leveled as required to match existing grades and to allow for positive drainage away from pathways, structures and sport field areas or as specified by the Contract Administrator. Minimum consistent depth for topsoil aRer settlement shall be as follows; For general parks / open space areas - 1OOmm deep, For sport field areas - 15Omm deep.

Page 130: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SPO-9

571.07

571.07.04

571.10

571.10.01

0.P.S.S 571 CONSTRUCTION SPECIFICATION

FOR SODDING

CONSTRUCTION

Placement of Sod

Subsection 571.07.04 is amended by the addition of the following:

Butt joints will be used where new sod blends with existing grass; lap joints will not be permitted.

BASIS FOR PAYMENT

Sod - Item

Subsection 571.10.01 is amended by the addition of the following:

All cost associated with maintaining the sod throughout the 30 day period shall be factored into the Contract Price. This includes and required watering to ensure satisfactory sod performance as specified in clause 571.08.01 Performance Measure.

Page 131: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SPO-10

572.03

0.P.S.S 572 CONSTRUCTION SPECIFICATION FOR SEEDING AND COVER

DEFINITIONS

Clause 572.03 is amended by the deletion of paragraph 5 and replacement with the following:

Seeding: means the application of seed and cover material onto the specified areas in the Contract Document by the specified means in the Contract Document.

572.06 EQUIPMENT

572.06.04 Brillion Seeder

Clause 572.06 shall be amended by the addition of clause 572.06.04 Brillion Seeder.

The Brillion Seeder shall be capable of distributing seed and fertilizer uniformly in a dry state.

572.06.05 Slit-Disc Over Seeder

Clause 572.06 shall be amended by the addition of clause 572.06.05 Slit-Disc Over Seeder .

The Slit-Disc Over Seeder shall be capable of distributing seed and fertilizer uniformly in a dry state. The cutting knives shall be mechanically driven with a maximum spacing of 50mm.

572.07 CONSTRUCTION

572.07.02 Surface Preparation for Seeding

Clause 572.07.02 shall be amended by the deletion of the last sentence of the first paragraph and replace with the following:

The surface shall be free of foreign material and weeds or other unwanted vegetation.

Page 132: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SPO-11

572.07.02.01

572.07,02.01

572.07.04.02

Standard Park Seed or Naturalization Seed

Clause 572.07.02 shall be amended by the addition of clause 572.07.02.01 Standard Park Seed or Naturalization Seed.

The surface shall be uniformly cultivated to a minimum depth of 1OOmm and shall not have surface stones greater than 25mm in diameter.

Sport Field Seed

Clause 572.07.02 shall be amended by the addition of clause 572.07.02.02 Sport Field Seed.

The surface shall be uniformly cultivated to a minimum depth of 1 O O m r n and shall not have stones greater than 15m.m in diameter.

Seed and Fertilizer Application

Clause 572.07.04.02 shall be amended by the addition of the following paragraphs:

Sport Field Seed and Fertilizer shall only be applied using a slit-disc over seeder. No other methods of applications are acceptable. The fertilizer shall be applied to the soil prior to application of seed. The application of the seed shall take place in three separate installations. The first application shall install the perennial rye grass in the shortest direction. The second application shall install Kentucky blue grass perpendicular to the first application. The third application shall install Kentucky blue grass at an angle of 1 Odegrees in relation to the second installation. All seed and fertilizer applications shall be in conformance with table 2.

Seed and fertilizer can also be applied separately by a brillion seeder.

Page 133: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 SPO-12

Permanent Seed Mix Seed Mix Y O Grade Minimum % Minimum

YO Composition Name Germination YO Purity Park Standard Seed 70 N/A Turf Type Perennial Rye Grass ~~ ~ (entophyte ~- enhanced) 30% 25% - 30% Hard Fescue ~ ~ 20% -15%-25% Turf Type Tall Fescue 35% 30%-40% Creeping Red Fescue 15% 12%-18% Sport Field Seed 75 N/A Kentucky Blue Grass: Dwarf Variety (“Award” or 60% 58% - 62% “Liberator” or “Ramb 0’’)

Turf Type Perennial Rye

Turf Type Perennial Rye

Naturalization Seed 70 N/A

Grass: “Top Gun” 20% 18%-22%

Grass: “Player” 20% 18%-22%

Orchard Grass 12% 7%-17% Creeping Red fescue 13% a%-i8% Perennial Rye Grass 13% a % - m Double Cut Red Clover 17% 12%-22%

Table 1 - Permanent Seed Mixes and Seed Certificate Analysis Values

Table 1 shall be deleted in its entirety and replaced by the following table:

Maximum YO of Weed Seed

3.0

0.2

3 .O

Dutch White Clover O.S.C. Native Prairie Meadow Mixture

Kentuckv Blue Grass I 17% I12%-22% I I I I 13% a%-is%

15% 13%-17%

Permanent Seed Mix 1 Rate kg/10,000m2 Permanent Seed Mixers

Table 2 - Application Rates for Seed and Fertilizer

Table 2 shall be deleted in its entirety and replaced by the following table:

per kg/10,000m2 Nurse Crop Species 1-2-2 (with 50% Sulfur Rate kg/10,000m2

I I I Fertilizer Rate Minimum(

Park Standard Seed 100 200 N/A Perennial Rye Grass

I I I Coated Urea) I

Naturalization Seed 100 N/A

Sport Field Seed ~ Kentucky Blue Grass 350 NIA

Page 134: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003

I.

11.

111.

rv.

tl

PAYMENT CERTIFICATE CONTRACT ADMINISTRATOR'S CHECKLIST

ALL PAYNIENT CERTIFICATES

1. Two original Payment Certificates are prepared (including measured Tendered quantities and change orders (blue)), reviewed, checked and signed by the Contract Administrator.

2. Payment Certificates are signed by the Contractor.

3. Payment Certificates, along with the required documentation and checklist, are submitted to the Environmental and Engineering Services Department - Administrative Sewices Division, City Hall, Roam 1006.

4. Certificate of Clearance from the Workplace Safety and Insurance Board (Reference City of London Standard Contract Documents, Sample Tender Document, Page IT-2, Clause 8 Information for Tenderers

PAYMENT CERTIFICATE NUMBER 1

Required Documentation

b) Copy of Certificate of Clearance

SUBSTANTIAL COMPLETION

Required Do cumen t ation

a) Statutory Declaration re: Liens and Payment of Accounts (Reference City of London Standard Contract Documents, Section Statutory Declaration)

b) Copy of Certificate of Clearance

c) Workers' Compensation Declaration - Corporation Tax Act WD-1 (Reference City of London Standard Contract Document, Section Sample Tender Document

RELEASE OF HOLDBACK

Required Documentation

a) A copy of the Notice of Substantial Performance from the Daily Commercial News

Memo to City Clerk, City Hall, shall be submitted to have confirmed in writing any claims or liens against the 10% Holdback. The memo shall cc. Administrative Services

FINAL (may coincide with Release of Holdback)

Required Documentation

a)

b)

c)

Statutory Declaration re: Liens and Payment of Accounts

Copy of Certificate of Clearance

Workers' Compensation Declaration - Corporation Tax Act WD-1

Date Contract Administrator

Page 135: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

TENDER AND PROPOSALS Website Address:

TENDER: 04- cal time,

refundable Administrative Fee by cheque payable to the City Treasurer, City of London.

Each tender must be accompanied by a bid deposit in the amount of

Page 136: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

City of London Environmental and Engineering Services Department

Time and Material Change Order Summary

Classification

Project No. : Contractor : Date: Page ___ of __

No. Hrs. Ea. Total Hrs. Rate Amount

Section “A” : Labour

Type Hrs. Ea. 127 Rate Amount Hrs Standby 127 Rate Amount

I I , I I I -I

Payroll Burden

Sub-total I 1

Sub-total %I 1 1

Labour Markup <=$3000 (33935% > $3000 @ 120%

Section “B” : Owned Equipment

Sub- to tal I I

Sub-total I I <=$10,000, 100% of 127 Rate

$10,000 < >= $20,000,90% of 127 Rates

> $20,000,80% of 127 Rates

Sub-total

35% of 127 Rates 7 1

Sub-total

Total of Section “B”: Owner Equipment

Page 137: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

City of London Environmental and Engineering Services Department

Time and Material Change Order Summary

Type

Project No. : Contractor : Date: Page __ of __

Hrs. Wrk. Rate Amount Hrs Standby Rate Amount

Section “C” : Rented Equipment

110% of 127 Rates 35% of 127 Rates

Total of Section “C” : Rented Equipment [m Section “D”: Material (Do Not Include “All-pricer”)

supporting invoices must be included.

1 Type I Unit I Total I Rate I Amount I I I I

Sub- to tal

<=$3000 @120% I I I >$3000 @ 115% I

Total of Section “D” Material

Section “E”: General Contractor’s Markup Check here if work was completed by a sub- contractor

<=$3,000 0120%

$3,000 o= $10,000 0115%

>$10,000 @OS%

Total I

Note: This Section to be completed only when the contractor has arranged for work to be carried out by others, who are not corporately linked to the prime contractor.

Page 138: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

N A

CONTRACT DOCUMENTS

FOR

Project Number : Tender Number :

ENVIRONMENTAL AND ENGINEERING SERVICES DEPARTMENT 300 Dufferin Avenue

P. 0. Box 5035 London, Ontario N6A 4L9

Page 139: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

DATA SHEET FOR TENDERERS November 3.2003

Contract Name:

Tender Closing Date:

Owner:

Address:

Bid Deposit (amount):

Open for Acceptance:

Bonding:

Performance

12:OO noon -

Corporation of the City of London

300 Dufferin Avenue, P. 0. Box 5035 LONDON ON N6A4L9

60 days from Tender Closing

50% of contract price, excluding G.S.T.

Labour and Material 50% of contract price, excluding G.S.T.

Maintenance Term: 12 months fiom Substantial Performance

Tentative Commencement Date:

Working Days:

Liquidated Damages:

Date of Pre-tender Meeting:

Date of Test Holes:

Office Supervision and Field Inspection Costs incurred By Corporation, in addition to $1 OOIworking day

NIA

NIA

Page 140: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

FORM OF TENDER November 3,2003

FT-1

TENDER FOR

Project No.

Tender No.

FOR

THE CITY OF LONDON

Tenderer's business name

Type of business: Proprietorship 17 Corporation Partnership (place checkmark in appropriate box)

Business address

G. S .T. Number .

TO THE MAYOR AND MEMBERS OF THE COUNCIL OF THE CORPORATION OF THE CITY OF LONDON

Clause No.

1. The Tenderer has carefully examined the locality and site of the proposed works, as well as the Contract Documents related to the works, including the Tender, City of London General Specifications (GS), Special Provisions, City of London Supplemental Standards for Roads (SR), City of London Supplemental Standards for Sewer and Water (SW), City of London Supplemental Standards for Traffic Signals and Street Lighting (STS), City of London Supplemental Standards General Conditions of Contract (SGC), City of London Standards for Tree Planting and Preservation (TPP), City of London Supplemental Standards for Parks and Open Spaces, Ontario Provincial Standards for Roads and Municipal Services, Volumes 1 - 4 inclusive, Contract Drawings, and Addenda No. to inclusive*, relating to the said Contract(s).

2. The Tenderer hereby accepts and agrees that the items referred to in (1 .) above form part of the Contract(s)

3. The Tenderer hereby submits his Tender and offers to enter into a Contract(s) to construct all that is set out in the Contract Documents on the Terms and Conditions and under the provisions set out or called for in the Contract Documents for the Total Contract Price of

Dollars ($ ) , being made up as shown in the Schedule of Items and Prices - Form of Tender.

* The Tenderer will insert here the number of the Addenda received by him during the tenderingperiod and taken into account by him in preparing his Tender.

Page 141: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

FORM OF TENDER November 3,2003

FT-2

4. Enclosed with the Tender is a bid deposit in the amount of

5. The Tenderer proposes (name of Bonding Company)

which is willing to become bound with the Tenderer in accordance with Clause 18 - Information for Tenderers.

6.

7.

8.

The Tenderer shall comply with and post the appropriate Fair Wage Policy and Schedule in accordance to Supplemental Standards General Conditions (SGC).

If awarded the Contract, the Tenderer agrees to substantially complete the work within working days.

The Tenderer declares that:

No person, firm or corporation other than the Tenderer has any interest in this Tender or in the proposed Contract for which this Tender is made.

This Tender is made without any connection, knowledge, coinparison of figures or arrangements with any other person or persons making a Tender for the same work and is in all respects fair and without collusion or fraud.

No appointed officer or employee of The Corporation of the City of Londbn is, will be, or has become interested, directly or indirectly, as a contracting party, partner, shareholder, surety or otherwise in the Tender or in the proposed contract or in any portion of the profits thereof, or of any supplies to be used therein, or in any of the moneys to be derived therefiom.

The several matters stated in the Form of Tender are in all respects true.

Dated at this day of

Tenderer's Business Name:

Person authorized to bind tenderer:

(print name) (signature)

Person's position with tenderer:

Witness :

(print name) (signature)

Page 142: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

INFORMATION FOR TENDERERS November 3,2003

IT-1

1. GENERAL

SEALED TENDERS will be received by the Finance-Purchasing and Supply Division, 267 Dundas Street 4rd Floor, London, Ontario, N6A-lH2 for the construction of:

Project:

Project Number:

Tenders shall be submitted an envelope provided by the Contractor not later than 12:OO noon (local t h e )

on

Envelopes containing Tenders should be sealed and plainly marked on the outside as to their contents. Tender envelopes shall be addressed to: Chair and Members, Board of Control, Corporation of the City of London, Finance-Purchasing & Supply Division, 267 Dundas Street 4rd Floor, London, Ontario, N6A- 1H2. Drawings and Tender Documents may be obtained at the office of the Contract Administrator, upon paying a $30.00 (Thirty Dollars) non-refundable Adminstrative Fee, payable to the City Treasurer, City of London.

Conditions relating to tendering as prescribed in the Tender Documents must be complied with. The lowest or any Tender shall not necessarily be accepted.

All index and reference numbers in the Tender Documents are given for the convenience of the Contractor and such must be taken only as a general guide to the items referred. It must not be assumed that such numbering is the only reference to each item, but the Tender Documents must be read in detail for each item.

Tenders received by the Finance- Purchasing and Supply Division later than the specified closing time will be returned unopened to the Tenderer.

2. CONTRACT ADMINISTRATOR

Name

Address

Contact Person

Telephone Number

Location of Tender Documents

3. TENDERERS MAY OBTAIN INTERPRETATION OF TENDER DOCUMENTS

Should any person Contemplating submitting a Tender for the proposed Contract require additional information concerning the scope of the work or the manner in which it must be carried out, or should he be in doubt as to the meaning of the Drawings and Specifications, he may submit a written request to the Contract Administrator for such additional information or for such interpretation. The person

Page 143: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 INFORMATION FOR TENDERERS IT-3

If the Contractor fails to pay the required assessment or compensation, the Corporation may pay such assessments or compensation to the Workplace Safety and Insurance Board and deduct such amounts from the Contractor.

9. REQUIREMENTS AT TIME OF TENDERING

Failure of the Tenderer to comply with any of the following shall result in the Tender being rejected

(a) The Tenderer shall submit an original signed and sealed bid deposit with his Tender.

(b) The Tenderer shall submit the Form of Tender issued by the Contract Administrator.

(c) The Tenderer's business name shall be inserted in at least one of the two spaces provided in the Form of Tender.

(d) The signature of the person authorized to bind the Tenderer shall be inserted in the space provided in the Form of Tender.

(e) The name of the bonding company shall be inserted in the space provided in the Form of Tender.

(0 The Tenderer shall not apply any conditions whatsoever to the Total Contract Price.

10. TENDER OPEN FOR ACCEPTANCE

The Tenderer shall keep his Tender open for acceptance and irrevocable until 60 days have elapsed om the closing date of the Tender or a formal contract is executed, based on a Tender other than this one.

11. NOTIFICATION OF CONTRACT AWARD

The awarding of the Contract, based on this Tender, shall constitute and be an acceptance of this Tender, and the Corporation shall notify the successful tenderer of the contract award.

12. INFORMAL OR UNBALANCED TENDERS

In addition to those errors in the Tender that shall result in the Tender being rejected, as indicated in Clause 9 "REQUIREMENTS AT TIME OF TENDERING", Tenders which are incomplete, illegible or obscure, or that contain additions not called for, erasures, alterations, errors or irregularities of any kind, or contain prices which appear to be unbalanced as to be likely to adversely affect the Corporation, may be rejected as informal.

All blanks must be legibly and properly filled in. Should any uncertainty arise as to the proper manner of doing so, the required information will, upon request, be given by the Contract Administrator.

Tenderers who have submitted Tenders which have been rejected by the Corporation because of informalities will be notified of the reasons for rejection. When checking Tenders, the following procedures shall be used:

(a) If the amount tendered for a unit price item does not agree with the extension of the estimated quantity and the tendered unit price, or if the extension has not been made, the unit price shall govern and the total price shall be corrected accordingly.

Page 144: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 INFORMATION FOR TENDERERS IT-4

(b) If both the unit price and the total price are left blank, then both shall be considered as zero.

(c) If the unit price is left blank but a total price is shown for the item, the unit price shall be established by dividing the total price by the estimated quantity.

(d) If the total price is left blank for a lump sum item, it shall be considered as zero.

(e) If the Tender contains an error in addition and/or subtraction and/or transcription, the error shall be corrected and the corrected total contract price shall govern.

13.

14.

REOUlREMENTS AT TIME OF EXECUTION

Subject to an award of the Contract by the Corporation, the Tenderer is required to submit the following documentation in a form satisfactory to the Corporation for execution within seven (7) days after being notified in writing to do so by the City.

(a) Executed Bonds

i)

ii)

Corporation of the City of London, Performance Bond

Corporation of the City of London, Labour and Material

(b) Executed Agreement

i) Corporation of the City of London, Form of Agreement

(c) Insurance

i) corporation of the City of London, Certificate of Insurance

(d) Declaration

i) Workers' Compensation

ii) Corporation Tax Act

( 4 Workplace Safety and Insurance Board - Certificate of Clearance

(f) Ontario RSO 1990 C.10 ,Occupational Health and Safety Act & Regulations

i) Corporation of the City of London, Acknowledgement of Receiving ANotification of Designated Substances on Project@

ii) Verification of Registration as Contractor (with Ministry Of Labour) Note: only required once for the Owner's files

WITHDRAWAL OF TENDERS

A Tenderer who has submitted a Tender may submit a further Tender at any time up to the official closing time. The last Tender received shall supersede and invalidate all Tenders previously submitted by that Tenderer for this Contract.

Page 145: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

INFORMATION FOR TENDERERS November 3,2003

IT-5

A Tenderer may withdraw his Tender at any time up to the official closing time by letter bearing the signature of any person authorized by the Tenderer.

All withdrawn or superseded Tenders will be returned unopened.

15. ABILITY AND EXPERIENCE OF TENDERERS

No Tender will be considered from any Tenderer unless known to be skilled and regularly engaged in work of a character similar to that covered by the Drawings and Specifications. In order to aid the Corporation in determining the ability of any Tenderer, the Tenderer shall, within 48 hours after being requested in writing by the Contract Administrator, furnish evidence satisfactory to the Corporation of the Tenderer's experience and familiarity with work of the character specified and his fmancial ability to prosecute the proposed work properly to completion within the specified time. The evidence requested may, without being limited thereto, include the following:

(a) The Tenderer's performance record with listing of work of a similar character and proportions which he has constructed, giving the name of the owner, date built and construction cost.

(b) A tabulation of other work now under contract, giving the location, type, size, required date of completion and the percent of completion to date of each job.

(c) An itemized list of the Tenderer's equipment available for use on the proposed Contract.

(d) A listing of the major parts of the work which are proposed to be sublet.

(e) The Tenderer's latest financial statement.

(f) Evidence that the Tenderer is licensed to do business in the Province of Ontario, in the case of a corporation organized under the laws of any other Province or Country.

16. SINGLE TENDER

A single tender may be opened and the Corporation reserves the right to accept or reject it.

17. BID DEPOSIT WITH TENDER

Tenders must be accompanied by an original bid deposit in the form of a sealed and signed Bid Bond, irrevocable Letter of Credit, Certified Cheque, or Canadian Currency ( PHOTOCOPIES OR FAXED COPIES OF BID BONDS WILL RESULT IN THE BID BEING REJECTED). Subject to the written approval of the City Treasurer, prior to Tender closing, other securities will be accepted as a bid deposit.

Bid bonds submitted as a security shall be in accordance with the standards of the Canadian Construction Association and shall be from the same guarantee surety company supplying the Performance and Labour and Material Bonds for this Contract. Should the Tenderer withdraw his tender before 60 days have elapsed from the closing date of the Tender, or a formal Contract is executed, based on a tender other than this one, or fail to comply with any or all the requirements at the

Page 146: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

INFORMATION FOR TENDERERS November 3,2003

IT-7

VI material suppliers

20.

21.

22.

23.

SUB-SURFACE SOIL INVESTIGATIONS

Tenderers will not be permitted to carry out independent sub-surface soil investigations by the excavation of "test pits".

The Contract Administrator will arrange to have a "test pit(s)" excavated at the project location commencing at (local time) on . Tenderers are invited to witness the excavation to make their own assessment of the subsurface conditions.

SOILS REPORT

The soils report was prepared by The soils report is for "information only" and shall not be part of the Contract Document.

, and accompanies the Tender Document.

ONTARIO PROVINCIAL SALES TAX

The prices tendered for the works shall be in accordance with the current legislation.

GOODS AND SERVICES TAX

Goods and Services Tax applies to all goods and services purchased by the City of London. G.S.T. is calculated at the rate of 7% on these purchases and is payable by the City at the time payment is made for the purchase.

Contractors will be required to register for purposes of the tax, collect the tax on their taxable supplies to the City of London and remit as required by legislation. Contractors must supply the City of London with their G.S.T. registration number.

The total contract price shall be inclusive of all government sales taxes, including G.S.T., custom duties and excise taxes applicable with respect to the contract, and shall be paid by the Contractor unless otherwise provided by statute. The estimated amount of Goods and Services Tax must be disclosed separately on the Form of Tender. The City will pay the Contractor all amounts of the G.S.T. in respect of the project.

G.S.T. is applicable at each trade level on virtually all goods and services consumed in Canada. Registrants are entitled to a refundable input tax credit for tax paid on goods and services to the extent the goods and services were acquired for use in a commercial activity.

All invoices and progress billings issued to the City must contain adequate information and supporting documentation as specified in the G.S.T. legislation and prescribed by regulations thereof, for the purpose of input tax credits and/or rebates in respect of the G.S.T. payable or paid by the City. Specifically, the Contractor must provide his G.S.T. registration number and must disclose the amount of G.S.T. payable on each billing. The Contractor shall make available any other reasonable information which the City may require in respect of supporting its claim for input tax credits or rebates.

Page 147: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

November 3,2003 IT-8 INFORMATION FOR TENDERERS

G. S.T. is not due on amounts held back until the period for retaining the holdback has expired. The Contractor will be required to exclude the amount of holdbacks from the consideration due for calculation of the G.S.T. payable.

24. CONTRACT DOCUMENTS

With the exception of Section 2 - Information for Tenderers, the following documents shall be part of this Contract, including revisions and amendments, up to and including the dates indicated.

Attached Or Not Attached

Revisiodhendment Date Section

Section 1

Section 2

Section 3

Section 4

Section 5

Section A

Section B

NIA

Section C

Section D

Section E

Issue Date

April 29, 1994

April 29,1994

October 15,2002 Form of Tender Attached

November 3,2003 Information for Tenderers (not part of Contract Document)

Attached

Special Provisions

Workers' Compensation Declaration Tax Act

Attached NIA

April29,1994

April 29, 1994

April 29,1994

NIA

February 29,2000

November 3,2003

November 3,2003

Attached

Form of Agreement Attached

City of London General Specifications (GS) Reference Document Not

Attached

City of London Supplemental Standards for Roads (SR), City of London Supplemental Standards for Sewer and Water (SW), City of London Supplemental Standards for Traffic Signals and Street Lighting (STS), City of London Supplemental Standards General Conditions of Contract (SGC),City of London Standards for Tree Planting and Preservation (TPP), City of London Supplemental Standards for Parks and Open Spaces (SPO)

Reference Document Not

Attached

April29, 1994 November 3,2003

Ontario Provincial Standards for Roads and Municipal Services, Volumes 1 to 4 inclusive

Reference Document Not

Attached

various dates Volume 1 April 2003 Volume 2 April 2003 Volume 3 Nov.2002 Volume 4 March 2002

City of London Statutory Declaration re: Liens and Payment of Accounts

April 29,1994

April29,1994

As Applicable

February 29,2000 Reference Document Not

Attached

Fonns (Bonds and Misc.) i) Performance Bond ii) Labour and Material Payment Bond

February 29,2000 Reference Document Not

Attached

Contract Drawings as listed below Part of Tender Document and

Contract Document

As Applicable

Page 148: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

FORM OF AGREEMENT November 3,2003

FA-1

CORPORATION OF THE CITY OF LONDON

F O R M O F A G R E E M E N T

THIS AGREEMENT made on the day of 20 -*

BETWEEN

THE CORPORATION OF THE CITY OF LONDON

(hereinafter called the “Corporation”)

OF THE FIRST PART

-and-

(hereinafter called the “Contractor”)

OF THE SECOND PART

WITNESSETH

That the Corporation and the Contractor in consideration of the fulfilment of their respective promises and obligations herein set forth, covenant and agree with each other as follows:

ARTICLE 1

(b) A general description of the work is:

The construction of

(b) The Contractor shall, except as otherwise specifically provided, at his own expense, provide all and every kind of labour, machinery, plant, structures, roads, ways, materials, appliances, articles and things necessary for the due execution of all the work set out in this Contract and shall forthwith according to the instruction of the Contract Administrator commence the works and diligently execute the respective portions thereof, and deliver the works complete in every particular to the Corporation within the time specified in Subsection GC3.07 EXTENSION OF CONTRACT TIME and Clause 6 FORM OF TENDER.

ARTICLE 2

In the event that the Tender provides for and contains a Contingency Allowance, it is understood and agreed that such Contingency Allowance is merely for the convenience of accounting by the Corporation, and the

Page 149: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

FORM OF AGREEMENT November 3,2003

FA-2

Contractor is not entitled to payment thereof except for extra or additional work carried out by him in accordance with the Contract and only to the extent of such extra or additional work.

ARTICLE 3

In case of any inconsistency or conflict between the provisions of this Agreement and the Plans or Specifications or General Conditions or Tender or any other document or writing, the provisions of such documents shall take precedence and govern in the following order, namely:

Agreement

Addenda

Special Provisions

Contract Drawings

City of London General Specifications (GS)

City of London Supplemental Standards for Roads (SR), City of London Supplemental Standards for Sewer and Water (SW), City of London Supplemental Standards for Traffic Signals and Street Lighting (STS), City of London Supplemental Standards General Conditions of Contract (SGC), City of London Standards for Tree Planting and Preservation(TPP) and City of London supplemental Standards for Parks and Open Spaces (SPO)

Ontario Provincial Standards for Roads and Municipal Services, Volumes 1 - 4 inclusive

Tender

Working Drawings

ARTICLE 4

The Contractor shall not assign the Contract, either in whole or in part, without the written consent of the Owner, as set out in Subsection GC3.09 - Ontario Provincial Standards - General Conditions of Contract.

ARTICLE 5

The Corporation covenants with the Contractor that the Contractor having in all respects complied with the provisions of this Contract, will be paid for and in respect of all the work at the tendered unit prices after measurement approved by the Engineer, the total which is presently estimated at

), including G.S.T., together with such additional sum or sums up to a maximum of Dollars ($ ), including G.S.T., for such extra or additional work at the unit rates or the amounts, as the case may be, stipulated in the written orders of the Engineer authorizing the extra or additional work; such payment, however, shall be subject to Article 2 hereof and subject to such additions and deductions as may be properly made under the terms hereof, and further subject to the provisions that the Corporation may make payments on account monthly or otherwise as may be provided in the General Conditions attached hereto.

Dollars ($

Page 150: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

ARTICLE 6

FORM OF AGREEMENT November 3,2003

FA-3

Where any notice, direction or other communication required to be or may be given or made by one of the parties hereto to the other or to the Contract Administrator or to his agent, it shall be deemed sufficiently given or made if mailed or delivered in writing to such party or to the Engineer at the following address:

The Corporation The Engineer

The Corporation of the City of London P. 0. Box 5035 London, Ontario N6A 4L9

City Engineer or General Manager of Planning and Development The Corporation of the City of London P. 0 Box 5035 London, Ontario N6A 4L9

The Contractor Contract Administrator

Where any such notice, direction or other communication is given or made to the Engmeer, a copy thereof shall likewise be delivered to the Contract Administrator of the Engineer, if appointed, and where any such notice, direction or other comunication is given or made to such agent, a copy thereof shall likewise be delivered to the Engineer.

ARTICLE 7

A copy of each of the Tender, Special Provisions, Addenda inclusive is hereto annexed and together with the plans, detailed drawings, Ontario Provincial Standards for Roads and Municipal Services, Volumes 1 - 4 inclusive, City of London Supplemental Standards for Roads (SR), City of London Supplemental Standards for Sewer and Water (SW), City of London Supplemental Standards for Traffic Signals and Street Lighting (STS), City of London Supplemental Standards General Conditions of Contract (SGC), City of London General Specifications (GS), City of London Standards for Tree Planting and Preservation (TPP), City of London Standards for Parks and Open Spaces (SPO) relating thereto, all as listed in the Information for Tenderers are made part of this Contract, as fully to all intents and purposes as though recited in full herein.

to

ARTICLE 8

No implied Contract of any kmd whatsoever by or on behalf of the Corporation shall arise or be implied fkom anything in this Contract contained nor fi-om any position or situation of the parties at any time, it being clearly understood that the express covenants and agreements herein contained made by the Corporation shall be the only covenants and aBeements upon which any rights against the Corporation may be founded.

Page 151: December REVISION INFORMATION Re.vision #10 …December 9,2003 Page-1 Index Page October 15,2002 Index Page November 3,2003 Pages GS-3 October 15,2002 Page GS-3 November 3,2003 Page

FORM OF AGREEMENT November 3,2003

FA4

ARTICLE 9

Time shall be deemed the essence of this Contract.

ARTICLE 10

The Contractor declares that in tendering for the works and in entering into this Contract he has either investigated for himself the character of the work and all local conditions that might affect his tender or his acceptance of the work, or that hereby assume all risk of conditions arising or developing in the course of the work which might or could make the work, or any items thereof, more expensive in character, or more onerous to fulfil, than was contemplated or known when the tender was made or the Contract signed. The Contractor also declares that he did not rely upon information furnished by any methods whatsoever, by the Corporation or its officers or employees, being aware that any information fiom such sources was and is approximate and speculative only and was not in any manner warranted or guaranteed by the Corporation.

ARTICLE 11

In compliance with the current regulations made under the Retail Sales Tax, Ontario, for the purpose of the purchase of materials to be in the works which are the subject matter of this Contract, the Contractor is hereby appointed as a special purchasing agent for the Corporation which will be provided to the Contractor.

ARTICLE 12

This Contract shall apply to and be binding on the parties hereto and their successors, admirustrators, executors and assigns and each of them.

IN WITNESS WHEREOF the parties have hereunto set their hands and seals the day and year fxst above written or cause their corporate seals to be affixed, attested by the signature of their proper officers, as the case may be.

.................................................. ) Witness as to signature of contractor )

Address. ....................................... .) )

)

-> )

Occupation. )

...............................................

...................................

.................................................................. Contractor

..................................................................

CORPORATION OF THE CITY OF LONDON

.................................................................. Mayor

................................................................. City Clerk