    DECK SLAB POURING SEQUENCE

    Sequence of deck slab concreting shall follow as per drawing no: CS/S-12. Rev 2. and the

    purpose is to minimize upward deflections in previously placed spans.

    For continuous steel bridges with span lengths greater than 200 feet. The deck placementsequence guidelines are below:

    1. Positive moment spans shall be poured prior to pouring negative moment area;2. Construction joints at each point of dead load contraflexure point shall be shown in the

    deck placement plan;

    3. Longer span between points of contraflexure shall be placed before shorter adjacent span.4. Positive moment pours in adjacent spans shall be separated by 72 hours;

    In order to minimize the shrinkage of the deck, the selective of low shrinkage concrete mix and

    concreting time had been limited; only allow the concreting work at evening time with the lower

    temperature. It is to prevent the aggressive loss of water through evaporation process during thehot day.

    The following figure illustrates the deck placement sequence for the Batukawa Bridge .

    It consist 8 spans with total length of 292m. The total of 15 pouring required for the whole

    bridge.

    PREPARATION BEFORE CONCRETING

    M+ M+M+M+M+M+M+M+ M-M-M-M-M-M- M-

    Abutment

    A

    Abutment

    B

    1324 5768 9111012 1314 15

    Sealing gap using between formwork and

    girders

    Cleaning the formwork before concreting

  • 8/4/2019 Deck Slab Concreting- Aug 2011

    2/11

    CHECKING BEFORE CONCRETING WORK

    Inspection for formwork-

    Formwork support and tie rodFormwork dimension

    Gap for formwork checked and sealed

    Cleanliness of formworkDepth of concreting

    Inspection for Reinforcement bar-Size and spacing of rebar checkLapping

    Concrete cover/ spacers block checkFinal concrete level marked

    Deflection

    monitoring rod

    Finish level marking

    (bottom red tape)

    650mm

    Sufficient lapping >

    600mm

  • 8/4/2019 Deck Slab Concreting- Aug 2011

    3/11

    Sufficient bottom cover and side cover

    Expansion joint checked

    - Left construction joint at deck slab for future expansion joint installation

    Construction joint location checked (As per drawing)

    Constructionjoints

  • 8/4/2019 Deck Slab Concreting- Aug 2011

    4/11

    M&E conduit / Pipe / opening installation and checked.

    Installation of anchor bolt for hand rail

    Drainage outlet for runoff water

    Deflection monitoring rod, reserved recess for 30mm cover. The re-bar shall cut off after

    monitoring and patch back with cement mortar as cover of deck slab.

    Protection of bolt

    tread during

    concreting

    Proper

    sealed

  • 8/4/2019 Deck Slab Concreting- Aug 2011

    5/11

    CONCRETING WORKS FOR DECK SLAB

    Slump test for pump mix 125 25mm sufficient workability to flow.

    Cube prepared 6 nos per set (3 nos for 7days and 3 nos for 28 days), total of 3 set for 65m

    during the 1st pouring. Minimum required 20m per set.

    120mm

  • 8/4/2019 Deck Slab Concreting- Aug 2011

    6/11

    CURING FOR DECK SLAB

    Cover with plastic sheet after toweling the concrete surface.

    Spraying water to prevent aggressive evaporation during day time.

    Apply curing

    compound sika

    Antisol-A

    Apply curingcompoundCover withplastic sheet

  • 8/4/2019 Deck Slab Concreting- Aug 2011

    7/11

    CONSTRUCTION JOINTS PREPARATION

    Apply retarder at the formwork of the construction joint.

    Roughened the surface next day using wire brush to expose aggregates before 2nd

    casting.

  • 8/4/2019 Deck Slab Concreting- Aug 2011

    8/11

  • 8/4/2019 Deck Slab Concreting- Aug 2011

    9/11

    Concreting works for parapet handrail and concrete kerb

    Concreting works for 3rd

    pour deck slab at 19th

    Aug 2011.

    Checking depth of concrete deck , cover and spacer block Sealed the gap between formwork and steel girders with sponge

    Road Kerb .

    Parapet

    handrail

    Tie Rod

    Formwork

    support

  • 8/4/2019 Deck Slab Concreting- Aug 2011

    10/11

    Sufficient vibrate at the edge and construction joint area.

    Checked and marked finish level

    of deck before concreting

  • 8/4/2019 Deck Slab Concreting- Aug 2011

    11/11

    FOOTPATH CONCRETE COVER

    Steel frame for footpath 1 Layer of BMC A5 laid Concreting of footpath concrete cover