decommissioning of offshore installations in the .... ramboll. decom in operational... ·...
TRANSCRIPT
Decommissioning of
offshore installations in
the operational phase
Kristian Lund Jepsen
Ramboll Oil & Gas
3SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Reasons for decom at fixed installations
Equipment redundant from day one
Equipment/system process wise outdated
Demolition
Equipment/system technological outdated
Equipment failed / worn-out
Replace with equipment / systems that fits changedprocess conditions
Replace with modernequipment / systems withnew technology
Refurbish / Repair
Replace (1 : 1)
4SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Redundant from day one - example
Gas fired heater – back-upfor turbine WHRU’s
Other examples:
•Mud tanks
•Well kill system
•Runway beams
•Trolleys/chain hoists
5SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Process wise outdated equipment
Increased amount of produced water
Change from HP separation to LP Mode
Change in gas composition / mole weight
Change in gas composition – increase of H2S + CO2
Increased amount of oil/gas
Debottlenecking of complete process train
Debottlenecking of produced water system
Larger pipe dia, larger volume in separators
Re-bundling of centrifugal compressors and larger driver
Change piping matr. class from CS to duplex
6SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Technological outdated equipment - examples
� Pneumatic analog instruments
� F&G Detectors / systems
� Control / ESD Systems
� Control panels for gas compressors
9SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Decommissioned – stay in place
Runway beams aredecommissioned to avoid periodicinspections / tests.
10SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Experiences from ”operational decom”
� Dangerous lifting operations (unknown weight+COG)
� Handling of NORM (NaturalOccuring Radioactive Matr)
� Handling of chemical/oil waste
� No asbestos in insulation(however: Flange Insulationkits, Carbon-Asbestos filledgaskets)
Scale may be barium orstrontium sulphate which is NORM material.
11SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Estimates – tons metal scrap per year
� Detailed data from one platform – backload to shore during one year.
� Assumed a model partly based on above data from one platform for calculating the amount of equipment “operational decommissioned” yearly.
� Assessed the Customs Authorities to obtain information about “import from offshore installations”.
� Assessed the oil Companies (DUC/Mærsk Oil, Hess, DONG E&P)
12SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Backload – Logistics and Handling
Return Goods
/ Supply Boat
Well Service
Company
Equipment
Waste skips
Chemical Tote
Tanks
Backload
Containers /
Baskets
Large scrap
items
To Service company
Not dangerous
waste
Chemicals/oil
waste
Empty - send
to Kommune
Kemi
Empty -
normal
renovation
Waste to Kommune Kemi
Tank Cleaning
Waste to Kommune Kemi
Refill Tote
Tank
Sorting /
Evaluation
To Service /
Repair
company
To be Stocked for
later use
(OIL COMPANY'S
STORE)
To be sold for
re-use
Repair /
scrap
Repaired/
To stock
Supply Goods
/ Supply Boat
Scrap Yard
Scrap
Repaird - directly return to offshore
Costums area
13SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Estimate Model. All Danish offshore fields – installedpiping / decomissioned piping and totally decommissioned
Estimated piping (incl. valves) from Danish offshore platforms decommissioned yearly
Installation
year 1987 and before 1987 - 1997 1997 - 2007 Totally
Age 20 years and more 10 - 20 years 0 - 10 years
Piping (tons) 6923 4825 3400 15148Scrap/change-
out % yearly 10 5 2,5Scrapped piping
- tons yearly 692 241 85 1018
Totally decommissioned from Danish offshore platforms yearly - estimated tons:
Piping 1000
Mech. Equipm. 500
Structures 250
Elect/Instrum 200
Other 50
Totally 2000
The model is based on a life time of 20 -25 years of an installation.
14SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Estimates from the 3 operators in Danish sector
� DUC/Mærsk Oil
� Hess Denmark Aps
� DONG E&P
Totally: 3100 tons – 3400 tons yearly
Variations: 2500 – 4000 tons yearly
15SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Jack-up rig conversion / decom
Maersk Giant:
•Converted to oil/gas production 1996.
•Production package owned by Schlumberger.
•Produced on Yme Field 1996 – 2001, operated by Maersk Contractors.
•Decommissioned production packagedemolished in Esbjerg Port 2001. Packagetaken over by Hannover Company
•The rig converted back to drilling.
16SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Statoil preparations to decom. HSE / NORM
� Study of consequences (“Konsekvensutredning – Ymeavslutningsplan”).
� Included evaluations regarding HSE impacts.
� Included evaluations regarding NORM – it was concluded there was no NORM as seawater had only been injected for a short period in the initial stage of the project.
� Samples of scale in the production equipment was taken.
� Concluded that scale was not radioactive and that it was calciumcarbonate.
21SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Maersk Giant – 2001 Decom/Conversion
� Noise / Fire Walls around package removed
� Flare tower removed
� Production package removed from deck
� All interconnecting piping and cabling removed
� Totally: 1200 tons removed
� Production package, 800 tons, sold from Schlumberger to Hannover Company – for possible re-use
23SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Mobile offshore units. Decom status.
� Yearly 2 units in the harbour.
� Equipment decommissioned/scapped yearly: 500 tons – 2000 tons
24SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Total status. Decom. Tonnes handled yearly
From fixed installations 2500 - 4000
From mobile offshore units 500 - 2000
Total 3000 - 6000
25SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Conclusion
� The amount (tonnes) of equipment decomissioned/scraped and then handled in the harbour of Esbjerg yearly corresponds to the weight of one medium size topside.
� The experience exists and the companies to handle the waste and scrap are used to handle these items.
� Large heavy lift cranes (Thialf) cannot go into the harbour.
� Need for companies who can handle and clean scrapped piping and equipment for NORM.
� Need for long-term storage facilities for NORM.