© OGA 2018This presentation is for illustrative purposes only. The OGA makes no representations or warranties, express or implied, regarding the quality, completeness or accuracy of the information contained herein. All and any such responsibility and liability is expressly disclaimed. The OGA does not provide endorsements or investment recommendations. Oil and Gas Authority is a limited company registered in England and Wales with registered number 09666504 and VAT registered number 249433979. Our registered office is at 21 Bloomsbury Street, London, United Kingdom, WC1B 3HF
Decommissioning - The Cost Challenge
Nils Cohrs
23 May 2018
Ensure MER UK
behaviour implemented
Supportsupply chain
to develop capacity and
efficiency
Promote collaboration across industry
Identify cost reduction
opportunities/ challenges for
decommissioning
Publicise benchmarks using OGA
Stewardship Survey data
Engage early on decommissioning
plans with operators
To steer the UKCS overall decommissioning cost to £39bn* or less * 2016 money
OGA Decommissioning
Identify and share lessons
learned
How?
Our team’s mission
Asset Stewardship Expectations
Cost certainty and reduction
Delivery capability
Scope, guidance and stakeholder engagement
Driving targeted cost efficiency programmes including innovative and regional approaches with extensive and effective knowledge sharing and best practice adoption
Developing an efficient and exportable low cost and profitable delivery capability supported by a competent and efficient supply chain, a selection of business execution models all designed to
allocate risk, align industry participants and drive down costs
Working with BEIS and other relevant parties to identify and evaluate opportunities to further optimise and define parameters for decommissioning scope and improve industry engagement
Builds on the Strategy
Focus over the next year
Reviewed on an annual basis
Clear action plan and timetable for delivery
Sets out a number of key deliverables
Strategy and Programme
Costs
59.7bn 59.7bn
Source: OGA 2017 Decom Cost Report using 2016 UKCS Stewardship Survey Data
5
Late life operation RemovalWarm stack/suspension Cold stack/suspension
Decommissioning Workflow
Dismantling Monitoring
OGA
OPRED
HSE
MER UKDecommissioning Cost
DP approvalDP execution and progress monitoring
Review
Offshore Safety Case adherence with regular amendmentsOnshore H&S regs
Need for Change
P90
P50
P10
Transformational approach
P90
P50
P10
Business as usual
Cost
Cost
Prob
abili
ty
Prob
abili
ty
• Industry and government have shared desire to minimise cost
• Awareness that business as usual will not be sufficient to transform cost
• Typical improvements of 35% seen in other industries e.g. automotive and aviation
How to deliver the £39bn target
Diagram for illustration only
By realising opportunities By minimising risks
8
DecommissioningProduction Installations 0 Northern North Sea Pipeline(s) Wells Execution Plan
Name DescriptionInstallation
CategoryPOB Mass (Te) Premise Ref.: Description OD (") Dist.(km) Product Premise Well Base OGUK Type Well-Count Late-Life Management
Alfalfa A Integrated platform Combination 110 12,000 Remove PL678 Kittiwake A Platform to Fulmar Receiver Tree 0 0 Gas Remove Type 0 0Alfalfa B NUI - Normally Unmanned Installation Combination 0 7,000 Remove PL123 Well-211/19- 2 to Murchison Platform 3 0 Light Oil Part Remove Type 1 0
0 PL517 Rob Roy Production Manifold to PL Seabed Location 5 0 Well Fluids Leave Type 2 00 0 0 Type 3 200 0 0 Type 4 0
Subsea structures Number Mass (Te) Premise 0 0 Type 0 2Mass: 0-25 Te Subsea 5 Remove 0 0 Type 1 0Mass: 25-150 Te Subsea 2 Remove 0 0 Type 2 0Mass: 150-500 Te Subsea 2 Remove 0 0 Type 3 7 P&AMass: 500+ Te Subsea 1 1,100 Remove 0 0 Type 4 0
Scope & Cost Phasing (£MM) Prior Years Future Cost L/Cycle Cost Est.Quality % Lifecycle 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 +Operator Proj.Mgmt 0 MM£ 61 MM£ 61 MM£ AACE Class 4 12% £10 £10 £10 £10 £5 £5 £5 £5 £1 -£ -£ -£ -£ -£ -£ Running/Owners Costs 0 MM£ 125 MM£ 125 MM£ AACE Class 4 25% -£ £50 £50 £20 £5 -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ Well P&A 0 MM£ 90 MM£ 90 MM£ AACE Class 4 18% £10 £20 £20 £10 £30 -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ Fac./Pipelines Make Safe 0 MM£ 10 MM£ 10 MM£ AACE Class 4 2% -£ £10 -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ Topsides Preparation 0 MM£ 50 MM£ 50 MM£ AACE Class 4 £20 £20 £10 -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ Topsides Removal 0 MM£ 90 MM£ 90 MM£ AACE Class 4 -£ -£ -£ -£ -£ £90 -£ -£ -£ -£ -£ -£ -£ -£ -£ Fac./Pipeline Make SafeSub-structure removal 0 MM£ 50 MM£ 50 MM£ AACE Class 3 -£ -£ -£ -£ -£ -£ £50 -£ -£ -£ -£ -£ -£ -£ -£ Super-/Sub-structure recycling 0 MM£ 6 MM£ 6 MM£ AACE Class 3 -£ -£ -£ -£ -£ -£ £2 £4 -£ -£ -£ -£ -£ -£ -£ Subsea infrastructure 0 MM£ 10 MM£ 10 MM£ AACE Class 4 -£ -£ -£ -£ -£ -£ -£ £10 -£ -£ -£ -£ -£ -£ -£ Site remediation 0 MM£ 1 MM£ 1 MM£ AACE Class 4 -£ -£ -£ -£ -£ -£ -£ £1 -£ -£ -£ -£ -£ -£ -£ Monitoring 0 MM£ 2 MM£ 2 MM£ AACE Class 4 0% -£ -£ -£ -£ -£ -£ -£ -£ £1 -£ -£ -£ £1 -£ £1Cessation of Production (Year) 2019 495 MM£ 495 MM£ Warm StackCold Stack Removals & Recycling
Scope & Cost Phasin Prior Years Future CostOperator Proj.Mgmt -£ 61£ Running/Owners Co -£ 125£ Well P&A -£ 90£ Fac./Pipelines Make -£ 10£ Topsides Preparatio -£ 50£ ContractingTopsides Removal -£ 90£ Sub-structure remov -£ 50£ Super-/Sub-structur -£ 6£ Subsea infrastructur -£ 10£ Site remediation -£ 1£ Monitoring -£ 2£
Business Environment
Operating Model
Industry Collaboration
Facilities re-use / Carbon Capture & Storage
Saving Opportunities vs P10s vs P50sProject Management £36 £12 MMPost-CoP Running Costs £58 £0 MMWell P&A £42 £0 MMFacilities/Pipelines Make Safe £7 £0 MMTopsides & Substructure Prep. + Removal £148 £10 MMTopsides & Substructure recycling & disposal £4 £4 MMSubsea infrastructure £4 £0 MMSite remediation £1 £0 MMMonitoring £1 £0 MM
£301 £26 MM
Summary / Conclusion
42%
Conclusion Added on Cost Category review tab
Total
19 February 2018 I.Fozdar
Conclusion Added on Cost Category review tab
Conclusion Added on Cost Category review tab
Conclusion Added on Cost Category review tab
Conclusion Added on Cost Category review tab
Platform
Subsea
Conclusion Added on Cost Category review tab
Conclusion Added on Cost Category review tab
Conclusion Added on Cost Category review tab
Conclusion Added on Cost Category review tab
Conclusion Added on Cost Category review tab
£-
£20
£40
£60
£80
£100
£120
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 +
MM
Decommissioning Cost Phasing
Operator Proj.Mgmt Running/Owners Costs Well P&A Fac./Pipelines Make Safe Topsides Preparation Topsides Removal Sub-structure removal Super-/Sub-structure recycling Subsea infrastructure Site remediation Monitoring
Decommissioning Cost Breakdown (WBS)
Operator Proj.Mgmt Running/Owners Costs Well P&A Fac./Pipelines Make Safe Topsides Preparation Topsides Removal
Sub-structure removal Super-/Sub-structure recycling Subsea infrastructure Site remediation Monitoring£0
£50
£100
£150
£200
£0
£50
£100
£150
£200
Project Management Post-CoP Running Costs Well P&A Facilities/Pipelines MakeSafe
Topsides & SubstructurePrep. + Removal
Topsides & Substructurerecycling & disposal
Subsea infrastructure Site remediation Monitoring
Decommissioning Project Cost Uncertainty and UKCS Benchmarks
Project P10 - P90 Range
Project Lifecycle Total Spend
UKCS Benchmark P10 - P50 Range
Decommissioning Dashboard
How to measure success to deliver the target?
1.Change in total cost forecast vs previous year from Asset Stewardship Survey
2.Change in key cost area benchmark (P50) after each Stewardship Survey with new actual data
3.Improved cost definition for first 5 and 10 year forecast
4.Actual industry success stories indicating realised savings
OGA’s key deliverables in 2018
1.Publish 2018 Decommissioning Cost Report
2.Publish Decommissioning Lessons learnt report
3.Complete Tier reviews with top 10 operators (based on total spent forecast over next 5 years)
4.Issue update for Decommissioning Delivery Plan
Minimise the cost of decommissioning in an appropriate manner, with a focus on delivering what would otherwise not be delivered by industry
Objective:
Team:
Terri King (ConocoPhillips) Nils Cohrs (OGA)Nigel Lees (Wood/Decom NS) Win Thornton (BP)Roy Aspden (CNRI) Mike Tholen (O&GUK) Pauline Innes (BEIS)