Defence College of Technical Training:Defence College of Technical Training: A Planning Update
Royal Wootton Bassett and Cricklade Area Board MeetingRoyal Wootton Bassett and Cricklade Area Board Meeting 23rd January 2013
Outline of PresentationOutline of Presentation
• Feedback on web‐site consultation
• Update on Development Proposals and Master Plan
• Next Steps and Programme
Web Site Consultation FeedbackWeb Site Consultation Feedback
• Web‐site concept master plan
• Web‐site launched November 2012Sh t ti i i iti• Short questionnaire inviting comments
• Over 100 respondents• Over 100 respondents– 50% adjacent to site – Only 15% with employment O y 5% t e p oy e t
directly related to MoD presence
Web Site Consultation FeedbackWeb Site Consultation Feedback
• 95% support for on‐going military presence
• Impact of the proposed development
Web Site Consultation FeedbackWeb Site Consultation Feedback
• Issues to be addressed through consultation and the planning application:
Proposals for access and impact of traffic– Proposals for access and impact of traffic– employment and impact on local economy– Potential access to sport and community facilitiesp y– Nature of proposed development and activities close to
existing propertiesP i l i– Potential noise sources
– INSERT SOME IMAGESINSERT SOME IMAGES
Update on Development ProposalsUpdate on Development Proposals
Existing Site
A siteA site
h i lTechnical Area
Main entrance
B site
D site
C site
Existing Site
A siteA site
h i l iTechnical Area
Domestic Area
Main entrance
B site
D site
C site
Existing Site
Key Facts and FiguresKey Facts and Figures
Existing (RAF Lyneham)• Building Footprint
Proposed (Under DTTCP)• Building Footprint
– 170,000sqm
• Building Floorspace– 200,000sqm
• Building Floorspace– 200,000sqm – Tranche 1: 150,000sqm refurbish
(50%) new build (50%)– End State: Additional 150 000sqm
• Personnel (2000‐2010)
– End State: Additional 150,000sqm refurbish 20% new build (80%)
• PersonnelPersonnel (2000 2010)– 3,000 to 4,000 – 2,000 Tranche 1
– 5,500 End State
M i Main entrance
LEGEND
T1 – New buildings
T1 – Refurbished buildings
T1 – Training area and Sports
End State – New buildings
End State – Refurbished buildings
End State Training
Preliminary Masterplan
Sports End State – Training area and Sports
M i Main entrance
LEGEND
T1 – New buildings
T1 – Refurbished buildings
T1 – Training area and Sports
End State – New buildings
End State – Refurbished buildings
End State Training
Preliminary Masterplan: Domestic Area
Sports End State – Training area and Sports
Domestic Area
M i Main entrance
LEGEND
T1 – New buildings
T1 – Refurbished buildings
T1 – Training area and Sports
End State – New buildings
End State – Refurbished buildings
End State Training
Preliminary Masterplan: Technical Training Area
Sports End State – Training area and Sports
Technical Area
M i Main entrance
LEGEND
T1 – New buildings
T1 – Refurbished buildings
T1 – Training area and Sports
End State – New buildings
End State – Refurbished buildings
End State Training
Preliminary Masterplan: Other Support Buildings
Sports End State – Training area and Sports
Other Support Buildings
M i Main entrance
LEGEND
T1 – New buildings
T1 – Refurbished buildings
T1 – Training area and Sports
End State – New buildings
End State – Refurbished buildings
End State Training
Preliminary Masterplan: External Training and Sports Area
Sports End State – Training area and Sports
External Training and Sports Area
Next Steps and ProgrammeNext Steps and Programme
• Completing technical assessments
• Public Exhibition of proposals 12th and 13th March 2013
• Planning Application submission May 2013
• Construction– Tranche 1 2014/2015
d l– End State complete 2019