delay in government construction project , types & factors
TRANSCRIPT
DELAY DELAY IN GOVERNMENT CONSTRUCTION IN GOVERNMENT CONSTRUCTION PROJECTS,PROJECTS,
Types Types & & CausesCauses
Prepared by: :
Twana Ahmed Xeyat.Civil Engineer (1996-2000)Master of Business Administration(2013-2015) , [email protected] , 07701528521
1
INTRODUCTION
� Definition� Types� Factors & Causes � Impacts� Conclusion
2
• To make something happen later than expected,or to be performed later than planned.
Delay Definition
later than planned.
• A situation where the contractor and the project owner jointly or severally contribute to the non-completion of the project within the agreed contract period.
3
Types Of Delay :
4
1. Critical & non Critical Delay:
• Critical delays: Prevent the contractor from finishing the work on the scheduled completion date
• Non critical delays:affect the progress of the work.
5
2. Excusable Or Non Excusable Delay:
Excusable Delays: Unpredicted
1. General labor strikes,Fires,Floods , Owner-directed changes.
2. Errors & omissions in the plans and specifications.2. Errors & omissions in the plans and specifications.
3. Differing site conditions or concealed conditions.
4. Usually sever weathers.
5. Intervention by outside agencies.
6
2. Excusable Or Non Excusable Delay:
Non excusable :
1. Late performance of subcontractors.2. Untimely performance by suppliers.3. Faulty workmanship by the contractor and subcontractors.4. A project specific labor strike.
7
3. Compensable or Noncompensable Delay:
A compensable delay:
• Time extension • Additional compensation. • Only excusable delays can be compensable.
A noncompensable delay:
• Neither additional compensation nor a time extension.
8
Note:
Compensable depends primarily on the terms of the contract.
But in most cases:Does not receive any additional money but time extension.
9
4.Concurrent or Non Concurrent Delay:
• Two or more delays that occur or overlap within the same period,
• One an employer risk event, the other a contractor risk event
• The effects of which are felt at the same time.
10
Factors and Causes of Delay :
1. Internal Factors
2. External Factors
11
Delay Factors
Internal Factors
Consultant Related
Contractor Related
Design Related
External Factors
Natural Disasters, Government Laws,
Economic Conditions, etc.
Design Related
Client Related
Labor Related
Material Related
Equipment Related
12
Internal Related Factors of Delay Internal Related Factors of Delay
13
14
15
16
17
18
19
20
21
22
23
External Related Factors of Delay External Related Factors of Delay
24
25
Methodology
Likert five-point scale ranging from 1 (Very Low) to 5 (Very High).
five point scale starting from (1 =Very Low), (2= Low). (3= High), (4= Medium) and (5 =Very High). The Relative Importance Indices (RII) is computed as follows;follows;
Where,
W is the weighting given to each factor by the respondents starting from 1 to 5
A is the highest weight in the scale which is 5,
N is the total number of respondents (which is 47 people).
26
Impacts of Delay
1. Cost overrun.2. Overtime .3. Disputes.3. Disputes.4. Lawsuits.5. Abandonement.
27
Conclusion
Delays are inevitable( unavoidable);
But can be minimized by:But can be minimized by:● Detailed Site Investigations.● Careful monitoring and regular meetings.● Effective site management.● Collaborative working and effective coordination.● Careful scheduling.● Full commitment to the project by all parties.
28
1] Construction Delay: Understanding them clearly, analyzing them correctly. Second edition by Theodore J. Trauner Jr.Ar25,2009 ,PP( 25-31) [2] Construction Project Delays: Assessing the Effectiveness of Supervisor Paperback – May 2, 2013by Najat Krima (Author)[3] Analysis of Construction Project Delays and Cost overruns: Construction Projects in Universities and Higher Education Institutes of Pakistan as Case Study Paperback – April 9, 2014by Attaullah Shah (Author)[4] Factors Causing Delay in Construction Projects: Delay and Speed Factors of Construction Projects in Malaysia Paperback – January
Refrences
3, 2012 by Wa'el Alaghbari (Author)[5] Enshassi, A., Hallaq, K. and Mohamed, S. (2006). Causes of contractor’s business failure in developing countries: the case of Palestine. Journal of Construction in Developing Countries, Vol. 11, No. 2. [6] Chitkara, K. (2004). Construction Project Management, Planning, Scheduling, and Controlling. Tata McGraw Hill, 4th edition, India.
[7] Gündüz, M., Nielsen, Y., and Özdemir, M., 2013, Quantification of delay factors using the relative importance index method for construction projects in Turkey, Journal of Management in Engineering, 29(2), pp. 133–139. [8] Hemanta, D., Anil, S., Iyer, K. C., and Sameer, R. 2012, Analysing factors affecting delays in Indian construction projects, International journal of Project Management, 30(4), pp. 479 – 489. [9] Aibinu, A. A., and Odeyinka, H. A., 2006, Construction delays and their causative factors in Nigeria, Journal of Construction Engineering and Management, 132, pp. 667–677.