deliverable 3.1 report about the requirements for masonry...
TRANSCRIPT
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 1 of 35
Deliverable 3.1
Report about the requirements for masonry units, reinforcement, mortar
and concrete
Due date: July 2006 Submission date: July 2006
Issued by: RWTH
WORKPACKAGE 3: Product development (Leader: RWTH)
PROJECT N°: COOP-CT-2005-018120
ACRONYM: DISWall
TYTLE: Developing Innovative Systems for Reinforced Masonry Walls
COORDINATOR: Università di Padova (Italy)
START DATE: 16 January 2006 DURATION: 24 months
INSTRUMENT: Co-operative Research Project
THEMATIC PRIORITY: Horizontal Research activities involving SMEs
a) unit material b) concrete infill
Hollow clay unit filled with concrete subjected to vertical load (RWTH)
Dissemination level: PU Rev: FINAL
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 2 of 35
INDEX
INDEX................................................................................................................................................................ 2 1 INTRODUCTION........................................................................................................................................ 3
1.1 OVERVIEW......................................................................................................................................... 3 1.2 DESCRIPTION OF THE WORKPACKAGE........................................................................................ 3
2 STATE OF THE ART.................................................................................................................................. 4 2.1 INTRODUCTION................................................................................................................................. 4 2.2 REQUIREMENTS ON THE MASONRY UNITS ................................................................................. 4 2.3 REQUIREMENTS ON THE MORTAR.............................................................................................. 10 2.4 PROPERTIES OF COMMONLY USED CONCRETE ...................................................................... 14 2.5 REQUIREMENTS ON THE REINFORCEMENT AND THE FASTENINGS..................................... 16
3 PERFORATED CLAY UNITS................................................................................................................... 17 3.1 REASONS FOR AND AIMS OF THE INVESTIGATIONS................................................................ 17 3.2 INVOLVED PARTNERS AND PLANNED TASKS............................................................................ 18 3.3 SELECTED APPROACH.................................................................................................................. 20 3.4 CONSTRAINTS AND REQUIREMENTS FOR THE REINFORCEMENT ........................................ 21 3.5 DESIGN OF PERFORATED CLAY MASONRY UNITS ................................................................... 21 3.6 BEDDING/FILLING MORTAR........................................................................................................... 21
4 LARGE HOLLOW CLAY UNITS .............................................................................................................. 23 4.1 REASONS FOR AND AIMS OF THE INVESTIGATIONS................................................................ 23 4.2 INVOLVED PARTNERS AND PLANNED TASKS............................................................................ 24 4.3 SELECTED APPROACH.................................................................................................................. 26 4.4 CONSTRAINTS AND REQUIREMENTS FOR REINFORCEMENT, FASTENINGS, MASONRY
UNITS AND CONCRETE INFILL................................................................................................................. 27 5 CONCRETE UNITS.................................................................................................................................. 29
5.1 REASONS FOR AND AIMS OF THE INVESTIGATIONS................................................................ 29 5.2 INVOLVED PARTNERS AND PLANNED TASKS............................................................................ 31 5.3 SELECTED APPROACH.................................................................................................................. 32 5.4 CONSTRAINTS AND REQUIREMENTS FOR THE REINFORCEMENT AND THE FASTENINGS32 5.5 DESIGN OF HOLLOW CONCRETE MASONRY UNITS ................................................................. 32 5.6 BEDDING/FILLING MORTAR AND GROUT.................................................................................... 34
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 3 of 35
1 INTRODUCTION
1.1 OVERVIEW
Within this document, a state of the art on the requirements on the aimed masonry components - masonry
units, mortar, reinforcement and fastenings, concrete - is compiled in section 2. In section 2.2 concerning the
state of the art on the masonry units a distinction between clay units and concrete units is made, which is
pursued in the following sections 3, 4 and 5. These sections contain the reasons for and aim of the
investigations, the planned tasks of the involved partners and the descriptions of the different approaches.
1.2 DESCRIPTION OF THE WORKPACKAGE
The goals of this Workpackage are:
- the development or the further development respectively of masonry units and their production,
- the development of suitable reinforcement and fastenings and their production,
- the development of a special purpose mortar,
- the development of a self-compacting concrete,
- the determination of material properties.
In general, in the sections 3, 4 and 5, it is distinguished between three different approaches for the
development of reinforced masonry systems, namely masonry made of:
- perforated clay units,
- large hollow clay units,
- concrete units.
The concepts, which were developed to reach the declared aims, are mentioned in the sections 3, 4 and 5.
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 4 of 35
2 STATE OF THE ART
2.1 INTRODUCTION
Within the following sections the state of the art on the requirements or the range of values of the properties
of the masonry components, i.e. masonry units, mortar, concrete and reinforcement, are compiled.
Furthermore the respective testing standards or regulations are given.
2.2 REQUIREMENTS ON THE MASONRY UNITS
The tables 1 to 4 contain the requirements on different properties of clay and concrete units. When specified,
instead of code given requirements, the property ranges given by producers and used up to now are given. It
is distinguished between geometrical properties (cf. table 1), physical properties (cf. table 2), durability
properties (cf. table 3) and mechanical properties (cf. table 4). Furthermore, the tables contain the testing
standards or regulations respectively used to determine the mentioned properties.
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 5 of 35
Table 1: Requirements on the geometrical properties of the masonry units
CLAY UNIT CONCRETE UNIT REQUIREMENT TEST METHOD
CODE REQUIRED PERFORMANCE
NOTES CODE REQUIRED PERFORMANCE
NOTES
1 2 3 4 5 6
Percentage of voids EN 772-2:2001 Methods of test for masonry units - Determination of percentage area of voids in aggregate concrete masonry units (by paper indentation) EN 772-3:2000 Methods of test for masonry units - Determination of net volume and percentage of voids of clay masonry units by hydrostatic weighing EN 772-9, methods of test for masonry units – Determination of volume and percentage of voids and net volume of clay and calcium silicate masonry units by sand filling
Group 2, 25% < φ ≤ 55%; Group 3, 25% < φ ≤ 70%; Group 4, 25% < φ ≤ 70%, horizontal holes (EN 1996-1-1, 2005) 15% < φ ≤ 45% 45% < φ ≤ 55%; (D.M. 20/11/87, D.M 14/9/2005) φ ≤ 45% (load-bearing walls in seismic area) (OPCM 3431) (EN 771-1:2005)
The percentage is related to the gross area
Group 2 25% < φ ≤ 55%; Group 3 25% < φ ≤ 70%; Group 4 (horizontal holes) 25% < φ ≤ 70% (EN 1996-1-1, 2005)
The percentage is related to the gross area
Transversal surface of any hole, (both deep and through holes)
- Multiple holes: Group 2 & 3, ≤ 2%; Group 4, ≤ 30%, Gripholes holes: Group 2 & 3, ≤ 12.5%; Group 4, ≤ 30%, (EN 1996-1-1, 2005) Multiple holes: for 15%< φ ≤ 45%,≤ 12 cm2 for 45%< φ ≤ 55%, ≤ 15 cm2 Gripholes holes: for A = 300 cm2, 1 hole ≤ 35cm2, for A = 580 cm2, 2 holes ≤ 35cm2
(D.M. 20/11/87) In seismic area: 1 hole ≤ 70cm2, (OPCM 3431)
- Multiple holes: Group 2 and 3, ≤ 30%; Group 4, ≤ 25%; Gripholes: Group 2 and 3, ≤ 30%; Group 4, ≤25%
-
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 6 of 35
Table 1: (continued) Requirements on the geometrical properties of the masonry units
CLAY UNIT CONCRETE UNIT REQUIREMENT TEST METHOD
CODE REQUIRED PERFORMANCE
NOTES CODE REQUIRED PERFORMANCE
NOTES
1 2 3 4 5 6
Dimensions EN 772-16:2002 Methods of test for masonry units - Determination of dimensions
(EN 771-1:2005) h = 5 – 20 cm, l = 25 – 30 cm, b = 12 – 35 cm
(EN 771-3:2003) -
Thickness of webs and shells
EN 772-16:2005 Methods of test for masonry units - Determination of dimensions
Web: Group 2, ≥ 5mm; Group 3, ≥ 3mm. Shell: Group 2, ≥ 8mm; Group 3, ≥ 6mm. (EN 1996-1-1, 2005) Web: ≥8mm; Shell: ≥ 10mm; (D.M. 20/11/87, D.M 14/9/2005) Webs ║ to plane of wall must be in a straight line (OPCM 3431)
Web: ≥ 14 mm Shell: ≥ 20 mm (EN 771-1:2005)
Web: Group 2 and 3 ≥ 15mm; Group 4, ≥ 20mm. Shell: Group 2, ≥ 18mm; Group 3, ≥ 15mm; Group 4, ≥ 20mm. (EN 1996-1-1, 2005)
-
Combined thickness of webs and shells
EN 772-16:2005 Methods of test for masonry units - Determination of dimensions prEN 1996-1-1:2004 (Table 3.1)
Group 2, ≥ 16mm; Group 3, ≥ 12mm. (EN 1996-1-1, 2005)
- Group 2, ≥ 18mm; Group 3, ≥ 15mm; Group 4, ≥ 45mm. (EN 1996-1-1, 2005)
-
Flatness of faces EN 772-20:2005 Methods of test for masonry units - Determination of flatness of faces of masonry units
- - (EN 771-3:2003) -
Straightness and squareness of the arris
UNI 8942-3:1986 (retired) Clay bricks and blocks. Test methods – Determination of shape, holes and profile (in Italian) ASTM C 67:2005 Standard Test Methods for Sampling and Testing Brick and Structural Clay Tile – Measurement of Warpage
- - - -
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 7 of 35
Table 2: Requirements on the physical properties of the masonry units
CLAY UNIT CONCRETE UNIT REQUIRE-MENT
TEST METHOD
CODE REQUIRED PERFORMANCE
NOTES CODE REQUIRED PERFORMANCE
NOTES
1 2 3 4 5 6
Aspect (cracks, lumps, flaking and other defects)
UNI 8942-3:1986 (retired) Clay bricks and blocks. Test methods – Exam of the aspect (in Italian) R.D.16/09/1939, N.2233 Sound Inspection
(EN 771-1:2005) - - -
Density EN 772-13:2002 Methods of test for masonry units – Determination of net and gross dry density of masonry units (except for natural stone)
LD ≤ 1000 kg/m3 HD > 1000 kg/m3 (EN 771-1:2005)
- - -
Porosity UNI 8942-3:1986 (retired) Clay bricks and blocks. Test methods. Determination of porosity (in Italian)
- The porosity is intended as the distribution of pores volume in respect to their diameter. The porosity can affect on the freeze-thaw resistance
- -
Shrinkage - - - - -
Moisture content
EN 772-10:2001 Methods of test for masonry units – Determination of moisture content of calcium silicate and autoclaved aerated concrete units.
- - - -
Water absorption
EN 772-11:2001 Methods of test for masonry units – Determination of water absorption of aggregate concrete, manufactured stone and natural stone masonry units due to capillary action and the initial rate of water absorption of clay masonry units
For only HD units (EN 771-1:2005) (R.D. 2233/1939)
- - -
Damp absorption
- - - - -
Capillarity ASTM C 67:2005 Standard Test Methods for Sampling and Testing Brick and Structural Clay Tile – Initial Rate of Absorption (Suction)
- - - -
Water vapour Permeability
EN 772-15:2001 Methods of test for masonry units – Determination of water vapour permeability of autoclaved aerated concrete masonry units
Diffusion coefficient of water vapour µ = 5 ÷ 10 (EN 1745:2002)
- - -
Hydric expansion
- - - - -
Thermal expansion
- - - - -
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 8 of 35
Table 2: (continued) Requirements on the physical properties of the masonry units
CLAY UNIT CONCRETE UNIT REQUIRE-MENT
TEST METHOD
CODE REQUIRED PERFORMANCE
NOTES CODE REQUIRED PERFORMANCE
NOTES
1 2 3 4 5 6
Efflorescence UNI 8942-3:1986 (retired) Clay bricks and blocks. Test methods - Determination of attitude to efflorescence (in Italian) ASTM C 67 – 2005 Standard Test Methods for Sampling and Testing Brick and Structural Clay Tile – Efflorescence
(EN 771-1:2005) - - -
Thermal conductivity
- For normal clay λ ≤ 0,55 W/(m . K) For lightened clay λ= 0,20 ÷ 0,30 W/(m . K) (D.M. 02/04/1998, EN 1745:2002)
- - -
Moisture movement
EN 772-19:2000 Methods of test for masonry units. Determination of moisture expansion of large horizontally perforated clay masonry units
(EN 771-1:2005) - (EN 772-14:2003) -
Table 3: Requirements on the durability properties of the masonry units
CLAY UNIT CONCRETE UNIT REQUIREMENT
TEST METHOD
CODE REQUIRED
PERFORMANCE
NOTES CODE REQUIRED
PERFORMANCE
NOTES
1 2 3 4 5 6
Freeze-thaw resistance
EN 772-18:2001 Methods of test for masonry units - Determination of freeze-thaw resistance of calcium silicate masonry units
Only for HD: F0 passive exposure F1 moderate F2 severe (EN 771-1:2005, R.D. 2233/1939)
- - -
Soluble salts content
EN 772-5:2003 Methods of test for masonry units - Determination of the active soluble salts content of clay masonry units.
For HD units not protected (EN 771-1:2005, R.D. 2233/1939)
- - -
Reaction to fire
EN 13823:2002 Reaction to fire tests for building products - Building products excluding floorings exposed to the thermal attack by a single burning itemEN ISO 1182:2002 Reaction to fire tests for building products - Non combustibility test prEN ISO 1716:2002 Reaction to fire tests for building products - Determination of the heat of combustion ISO 11925-2:2002 Reaction to fire tests - Ignitability of building products subjected to direct impingement of flame - Single-flame source test
Euroclass A1 (EN 771-1:2005, D.10/03/2005, L.818)
EN 13501-1:2002 Classification using test data from reaction to fire tests
Euroclass A1 (EN 771-3:2003)
EN 13501-1:2002 Classification using test data from reaction to fire tests
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 9 of 35
Table 4: Requirements on the mechanical properties of the masonry units
CLAY UNIT CONCRETE UNIT REQUIRE- MENT
TEST METHOD
CODE REQUIRED PERFORMANCE
NOTES CODE REQUIRED PERFORMANCE
NOTES
1 2 3 4 5 6
Normal to the bed face: 5 N/mm2 (EN 1998-1, 2004) 5 N/mm2 (OPCM 3431)
Compressive strength
EN 772-1:2002 Methods of test for masonry units – Determina-tion of compressive strength
Parallel to the bed face in the plane of the wall: 2 N/mm2 (EN 1998-1, 2004) 1,5 N/mm2 (OPCM 3431)
Code requirements are according to the direction of bedding of the unit; the expected values are with respect to the direction of holes EC6: Normalized compressive strength OPCM: Characteristic compressive strength
- -
Elastic modulus
UNI 9730-3:1990 Clay blocks for flooring. Test methods.
- - - This standard is for hollow tiles but it is generally used for units
Flexural strength
ASTM C 67: 2005 Standard Test Methods for Sampling and Testing Brick and Structural Clay Tile – Modulus of Rupture (Flexure test)
- - - -
Tensile strength
EN 772-6:2002 Methods of test for masonry units – Determina-tion of bending tensile strength of aggregate concrete masonry units
- - - -
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 10 of 35
2.3 REQUIREMENTS ON THE MORTAR
In the following tables the requirements for masonry mortars are compiled. Thereby it is distinguished
between requirements on the physical properties of fresh and hardened mortar, the durability and the
mechanical properties of the hardened mortar. The test standards used to determine the respective
properties are mentioned. According to the definition given by the Eurocode 6 (EN 1996-1-1, 2005), the
mortar types are distinguished as general purpose, thin layer or lightweight mortar according to their
constituents. The new Standards about mortar have been written using the performance based concept.
Instead of having prescribed proportions of the materials, the performance concept allows the producer to
select freely the mix proportions in order to achieve a stated performance required by the Standards
themselves. Thus the Standards move away from the “recipe approach”. The requirements of the mortars
are accordingly described following the performance concept.
Table 5: Requirements on the physical properties of fresh and hardened mortar
REQUIREMENT TEST METHOD GENERAL PURPOSE MORTAR
LIGHT-WEIGHT MORTAR
THIN LAYER MORTAR
NOTE
1 2 3 4 5 6
Composition UNI 11189:2006 Cultural heritage - Historical and repair mortars - Test methods for chemical characterization of a mortar - Chemical analysis
Classification of mortars in respect to the compositionM4 0:0:1:3:0 M4 0:1:0:0:3 M4 1:0:2:9:0 M3 1:0:1:5:0 M2 1:0:0.5:4:0 M1 1:0:0:3:0 (D.M.20/11/1987)
- Aggregates (DIN V 20000-412:2004)
EN 1996-1-1:2005 (section 3.2.2) Constituents by volume defined as cement:lime:sand D.M. 20/11/1987 (section 1.2.1) Constituents by volume defined as cement:common lime:hydraulic lime: sand:pozzolana There is no specific test-standard for new mortars
Workability EN 1015-9:2001 Methods of test for mortar for masonry - Determination of workable life and correction time of fresh mortar.
- - Workable life at least 4 h, correction time at least 7 min (DIN V 20000-412:2004)
-
Particle size distribution
EN 1015-1:2000 Methods of test for mortar for masonry - Determination of particle size distribution (by sieve analysis)
Generally a 4 mm max diameter is used
- Max aggregate diameter: 2 mm (EN 998-2:2003) respectively 1 mm
(DIN V 20000-412:2004)
-
Bulk Density EN 1015-6:2000 Methods of test for mortar for masonry - Determination of bulk density of fresh mortar EN 1015-10:2001 Methods of test for mortar for masonry - Determination of dry bulk density of hardened mortar.
- For hardened mortar ≤ 1300 kg/m3
(EN 998-2:2003)
≥ 1500 kg/m³ (DIN V 20000-412:2004)
-
Air content EN 1015-7:2000 Methods of test for mortar for masonry - Determination of air content of fresh mortar
(EN 998-2:2003) - - -
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 11 of 35
Table 5: (continued) Requirements on the physical properties of fresh and hardened mortar
REQUIREMENT TEST METHOD GENERAL PURPOSE MORTAR
LIGHT-WEIGHT MORTAR
THIN LAYER MORTAR
NOTE
1 2 3 4 5 6
Consistence EN 1015-3:2000 Determination of consistence of fresh mortar (by flow table) EN 1015-4:2000 Methods of test for mortar for masonry - Determination of consistence of fresh mortar (by plunger penetration)
- - - -
Chloride content UNI EN 1015-17:2002 Methods of test for mortar for masonry - Determination of water-soluble chloride content of fresh mortars
Should be ≤ 0.1% in mass of mortar by dry mass (EN 998-2:2003)
Should be ≤ 0.1% in mass of mortar by dry mass (EN 998-2:2003) respectively me be ≤ 0.1% in mass of mortar by dry mass (DIN V 20000-412:2004)
-
Shrinkage* UNI 6687:1973 Cement mortar. Hydraulic shrinkage determination. Laboratory test
- - - -
Water absorption EN 1015-18:2004 Methods of test for mortar for masonry - Determination of water absorption coefficient due to capillary action of hardened mortar
- - - -
Water vapour Permeability*
EN 1015-19:2000 Methods of test for mortar for masonry - Determination of water vapour permeability of hardened rendering and plastering mortars
- - - -
Specific heat* EN 1745:2005 Masonry and masonry products - Methods for determining design thermal values
- - - -
Thermal conductivity
EN 1745:2005 Masonry and masonry products - Methods for determining design thermal values
- - - -
Thermal expansion*
EN 1745:2005 Masonry and masonry products - Methods for determining design thermal values
- - - -
Fire Reaction EN 13501-1:2002 Classification using test data from reaction to fire tests EN 13823:2002 Reaction to fire tests for building products - Building products excluding floorings exposed to the thermal attack by a single burning item EN ISO 1182:2002 Reaction to fire tests for building products - Non combustibility test prEN ISO 1716:2002 Reaction to fire tests for building products - Determination of the heat of combustion ISO 11925-2:2002 Reaction to fire tests - Ignitability of building products subjected to direct impingement of flame - Part 2: Single-flame source test
- Class A1 (DIN V 20000-412:2004)
Mortars containing a fraction of organic materials ≤1% are Class A1 of fire reaction, mortars containing a fraction of organic materials > 1% have to be classified in respect of EN 13501-1:2002 and it has to declared the suitable fire reaction Class (EN 998-2:2003)
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 12 of 35
*It seems that shrinkage and water vapour permeability are more important for plasters than for mortars.
Shrinkage is generally hindered by the geometry of units and their assemblage and the water vapour
permeability is not very relevant on the overall permeability of the masonry wall. Furthermore, as far as
mortars for masonry are concerned, probably mechanisms of shrinkage control or expansive mechanisms to
hinder the shrinkage do not yet exist. Conversely, specific heat and thermal expansion are of basic
importance to evaluate the tendency to create thermal gradients between units and mortar when masonry is
subjected to heating and subsequent cooling. The thermal gradient is directly related to the risk that cracks
open in plaster in correspondence of the mortar joint in the backside masonry.
Table 6: Requirements on the durability properties of hardened mortar
REQUIRE-MENT
TEST METHOD GENERAL PURPOSE MORTAR
LIGHT-WEIGHT MORTAR
THIN LAYER MORTAR
NOTE
1 2 3 4 5 6
Freeze-thaw resistance
UNI 7087:2002 Concrete - Determination of the resistance to the degrade due to freeze- thaw cycles
- - - This standard is for concretes but it is usually used also for mortars.
Soluble salts content
UNI 11087:2003 Natural and artificial stones - Water soluble salts determination
- - - The soluble salts content is directly related with the tendency to create salt efflorescence on mortar joints subject to wet/dry cycles, such as mortar in facing walls but also in ordinary masonry
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 13 of 35
Table 7: Requirements on the mechanical properties of hardened mortar
REQUIRE-MENT
TEST METHOD GENERAL PURPOSE MORTAR
LIGHT-WEIGHT MORTAR
THIN LAYER
MORTAR
NOTE
1 2 3 4 5 6
Compressive strength
EN 1015-11:1999 Methods of test for mortar for masonry - Determination of flexural and compressive strength of hardened mortar
fm,min ≥ 4N/mm2 for reinforced masonry fm,min ≥ 2N/mm2 for bed joint reinforced masonry (EN1996-1-1:2005) In seismic zone fm,min ≥ 5 N/mm2 for unreinforced & confined masonry and ≥ 10N/mm2 for reinforced masonry (prEN1998-1:2003) fm,min ≥ 5N/mm2
(OPCM 3431, 2005)
- at least mortar class M15 (DIN V 20000-412:2004)
If the composition is prescribed, the compressive strength has to be declared on the basis of public reference, which establish the relation between the mixture proportions and the compressive strength (EN 998-2:2003)
Flexural EN 1015-11:1999 Methods of test for mortar for masonry - Determination of flexural and compressive strength of hardened mortar
- - - -
Initial shear strength
EN 1052-3: 2002 Determination of initial shear strength
0.10 ÷ 0.30 N/mm² for clay block 0.10 ÷ 0.20 N/mm² for concrete block
0.15 N/mm²
0.3 N/mm² 0.2 N/mm² (DIN V 20000-412:20041))
These values are not a limit, but they are an indication (EN 998-2:2003, EN 1996-1-1, 2005, D.M. 20/11/1987) 1) requirement
Adhesive tensile strength
EN 1052-5: 2005 Determination of bond strength by the bond wrench method; ASTM C952-91 Bond strength of mortar to masonry units
- - - -
Elastic modulus
UNI 6556:1976 Tests of concretes. Determination of static modulus of elasticity in compression.
- - - This standard is for concretes but it is usually used also for mortars.
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 14 of 35
2.4 PROPERTIES OF COMMONLY USED CONCRETE
The following table contains properties of concretes commonly used to fill masonry made of large hollow clay
units. Requirements on the respective concrete classes are defined in EN 206-1:2006 Concrete -
Specification, performance, production and conformity.
Table 8: Physical and mechanical properties of fresh concrete
REQUIREMENT TEST METHOD CODE REQUIRED PERFOR-MANCE
NOTE
1 2 3 4
Consistency EN 12350-3: 1999 Testing fresh concrete - Vebe test EN 12350-4: 1999 Testing fresh concrete - Degree of compactability EN 12350-5: 1999 Testing fresh concrete - Flow table test. UNI 11041:2003 Testing fresh self compacting concrete - Determination of free flow and time flow
- Consistency class F5 according to EN 206-1:2001 is usually used for hollow clay block masonry
Flowability EN 12350-2: 1999 Testing fresh concrete - Slump test. UNI 11043:2003 Testing fresh self compacting concrete - Determination of confined flowability in L-shape box UNI 11044:2003 Testing fresh self compacting concrete - Determination of confined flowability in U-shape box UNI 11045:2003 Testing fresh self compacting concrete - Determination of confined flowability in J-ring
- -
Composition UNI 6393:1988 Checking fresh concrete composition.
- -
Density EN 12350-6: 1999 Testing fresh concrete - Density.
- -
Air content EN 12350-7: 2000 Testing fresh concrete - Air content - Pressure methods.
- -
Viscosity UNI 11042:2003 Testing fresh self compacting concrete - Determination of flow time in V- funnel
- -
Bleeding UNI 7122:1989 Fresh concrete. Determination of bleeding.
- -
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 15 of 35
Table 9: Physical and mechanical properties of hardened concrete
REQUIREMENT TEST METHOD CODE REQUIRED PERFORMANCE
NOTE
1 2 3 4
Density EN 12390-7:2000 Testing hardened concrete - Density of hardened concrete
- -
Depth of penetration of water under pressure
EN 12390-8:2000 Testing hardened concrete - Depth of penetration of water under pressure
- -
Compressive strength EN 12390-3: 2001 Testing hardened concrete - Compressive strength of test specimens
D.M. 14/9/2005:
Rck≥15 N/mm2
Compressive strength class C20/25 according to EN 206-1:2001 is usually used for hollow clay block masonry
Tensile strength EN 12390-6: 2000 Testing hardened concrete - Tensile splitting strength of test specimens
- -
Flexural strength EN 12390-5: 2000 Testing hardened concrete - Flexural strength of test specimens
- -
Elastic modulus UNI 6556:1976 Tests of concretes. Determination of static modulus of elasticity in compression.
- -
Creep EN 1355:1996 Determination of creep strains under compression of autoclaved aerated concrete of lightweight aggregate concrete with open structure
- -
Shrinkage UNI 6555:1973 Concrete made with aggregate maximum size 30 mm. Hydraulic shrinkage determination. UNI 7086:1972 Concrete made with over 30 mm size aggregates. Hydraulic shrinkage determination. EN 680:2005 Determination of the drying shrinkage of autoclaved aerated concrete
- -
Pull-out EN 12504-3: 2005 Testing concrete in structures - Determination of pull-out force
- -
Carbonation UNI 9944:1992 Corrosion and protection of reinforcing steel in concrete. Determination of the carbonation depth and of the chlorides penetration profile in concrete.
- -
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 16 of 35
2.5 REQUIREMENTS ON THE REINFORCEMENT AND THE FASTENINGS
To define the requirements and the test standards for the reinforcement it is respectively distinguished
between special reinforcement for masonry as e. g. steel meshwork or trusses and simple rebars used to
reinforce the concrete infill of large hollow clay unit masonry. The test standards for these types of
reinforcement are compiled within the table 10. Table 11 contains the test standards used for fastening.
Table 10: Requirements on the mechanical properties of the reinforcement
REQUIREMENT TEST METHOD CODE REQUIRED PERFORMANCE
NOTE
1 2 3 4
Tensile strength EN ISO 15630-1:2002 Steel for the reinforcement and prestressing of concrete - Test methods - Reinforcing bar, wire rod and wire
- -*
Bond strength CNR UNI 10020:1971 Beam - test on steel bars. EN 12269-1:2000 Determination of the bond behaviour between reinforcing steel and autoclaved aerated concrete by the "beam test" - Short term test EN 12269-2: 2003 Determination of the bond behaviour between reinforcing steel and autoclaved aerated concrete by the "beam test" - Long term test EN 846-2:2000 Methods of test for ancillary components for masonry –Determination of bond strength of prefabricated bed joint reinforcement in mortar joints
D.M. 14/9/2005 Ribbed (improved bond) reinforcing steel
-
Shear strength EN 846-3:2000 Methods of test for ancillary components for masonry – Determination of shear load capacity of welds of prefabricated bed joint reinforcement
- -
* In Germany the requirements on reinforcement for concrete are determined in DIN 488-1:1984, DIN 488-
2:1986 and DIN 488-4:1986
Table 11: Requirements on the mechanical properties of the fastenings
REQUIREMENT TEST METHOD CODE REQUIRED PERFORMANCE
NOTE
1 2 3 4
Tensile strength EN 846-5:2000 Methods of test for ancillary components for masonry - Determination of tensile and compressive load capacity and load displacement characteristics of wall ties (couple test) EN 846-6:2000 Methods of test for ancillary components for masonry - Determination of tensile and compressive load capacity and load displacement characteristics of wall ties (single end test)
- -
Compressive strength
EN 846-5:2000 Methods of test for ancillary components for masonry - Determination of tensile and compressive load capacity and load displacement characteristics of wall ties (couple test) EN 846-6:2000 Methods of test for ancillary components for masonry - Determination of tensile and compressive load capacity and load displacement characteristics of wall ties (single end test)
- -
Shear load capacity
EN 846-7:2000 Methods of tests for ancillary components for masonry - Determination of shear load capacity and load displacement characteristics of shear ties and slip ties (couple test for mortar joint connections)
- -
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 17 of 35
3 PERFORATED CLAY UNITS
3.1 REASONS FOR AND AIMS OF THE INVESTIGATIONS
In many countries facing the Mediterranean basin (Italy, Spain, Portugal, Greece, etc.) and also northern
European countries, such as Slovenia, Germany, etc., load bearing masonry walls made of perforated clay
units are largely used for the construction of residential buildings as well as larger buildings with industrial or
services destination. However, the designers are facing many problems in the calculation of these kinds of
buildings, due to the introduction of more severe seismic codes, both at European (Eurocode 8) and National
(OPCM 3431 in Italy) level. For this reason, it is necessary to explore all the possibilities of existing masonry
systems for load bearing masonry buildings, and to develop new construction systems still based on the use
of perforated clay units, in order to save traditional construction techniques and materials by innovating
them, and at the same time to avoid the shrinkage of the clay unit industrial sector which is a leading sector
in many countries, and in Italy in particular.
Within the research project DISWall, two systems made with perforated clay units are thus going to be
studied. The first one is a system similar to confined masonry, made by using a special unit for the reinforced
masonry panel and an ordinary unit for reinforced confining columns. The units have to be placed in the
masonry panel with horizontal holes, and they have to present recesses for the placement of the horizontal
reinforcement. The main advantages are that all the problems related to cover of bars and mortar shrinkage
are overcome, due to the fact that there is a special recess to place the reinforcement, it is possible to have
the un-coupling of the reinforcement, it is possible to preserve a construction technique (masonry made with
horizontal holes) which is very traditional for all the countries facing the Mediterranean basin, which also
allows reaching very good thermal and acoustic insulation.
The second construction system that is going to be studied within the research project DISWall, is a system
of reinforced masonry, made by using the perforated clay units with vertical holes, developed and aimed at
building mainly tall, load bearing reinforced masonry walls for factories, sport centres, etc., which have to
resist out-of-plane actions in particular when they are in the presence of a deformable roof. For this system,
a ‘C’ shaped unit to be used very simply with the possibility of putting it in place after the vertical
reinforcement has been already placed, and with dimensions that allow to use it in two different direction (but
still with vertical holes) will be developed. No particular improvement is foreseen for the reinforcement
element, apart for exploring the possibility, through the hole in the ‘C’ shaped unit, of un-coupling the
reinforcement. Special reinforcement elements should only be developed if necessary, for simpler and exact
installation of the reinforcement in this system.
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 18 of 35
3.2 INVOLVED PARTNERS AND PLANNED TASKS
Table 12: Involved partners, proposed tasks and restraints
INVOLVED PARTNER
PROPOSED TASKS
1 2
ALAN Masonry units: - Formulation of the application field of the masonry units with horizontal holes. - Compilation of the dimensions, geometry, manufacturing constraints, mechanical properties
for perforated clay units with horizontal holes and of the limiting constraints concerning the workability (dimensions of the recesses).
- Design and production of new units Reinforcement: - Formulation of requirements on the layout of reinforcement and fastenings for the new
construction system. Mortar: - Formulation of requirements on the flow properties to allow for a proper recess filling - Formulation of requirements for mortar with additives to improve the bond properties
CISEDIL Masonry units: - Formulation of the application field of the masonry units with vertical holes. - Formulation of new geometry for unit in order to allow reinforcement un-coupling and better
out-of-plane behaviour for the wall and of the limiting constraints concerning the workability (dimensions of the cores).
- Design and production of units Mortar: - Formulation of requirements on the flow properties, the workability, the water retention, the
mechanical properties. - Formulation of requirements (both mortar and units) to improve bond
TASSULLO Mortar/concrete: - Formulation of new mortar/concrete composition or use of additives to meet the
requirements for reinforced masonry made with perforated hollow unit - Design and production of new mortar/concrete
ANDIL Masonry units: - Formulation of requirements for masonry units
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 19 of 35
Table 12: (continued) Involved partners and proposed tasks
INVOLVED PARTNER
PROPOSED TASKS
1 2
UNIPD Masonry units: - Formulation of desired improvements of the mechanical properties and of test methods for
testing the behaviour under in-plane loads - Testing of the mechanical and physical properties - Modelling to assess the behaviour of units with horizontal holes and to formulate
improvements of the unit geometry in general Reinforcement: - Formulation of desired requirements on the amount and mechanical properties of
reinforcement and fastenings Mortar: - Formulation of desired mechanical properties and bonding strength between masonry and
masonry unit. - Testing of the mechanical and physical properties - Testing of bond between mortar and masonry units.
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 20 of 35
3.3 SELECTED APPROACH
According to section 3.1, the main task of UNIPD is the development of two reinforced masonry construction
systems based on the use of perforated clay units.
For the system based on the use of horizontally perforated clay units, first of all the properties of the
perforated clay unit are to be designed and studied, in particular the shape (geometry of the unit) in order to
allow the creation of all the needed structural details and a proper filling for the mortar that surrounds the
reinforcement, and the mechanical properties of the unit (still related not only to the material properties but
also to the shape of the unit). For this construction system, physical properties and material laws for the
components perforated clay blocks and mortar will be determined at first, by tests on the masonry
components and on small components, and will be modelled in order to find improved unit shape and
configuration:
- FE modelling of masonry units;
- Compression tests, splitting tests and special tests on masonry units;
- Compression and tensile tests on mortar;
- Shrinkage and flow tests on mortar;
- Bond tests between mortar and masonry units.
The development of the masonry construction system as a whole will be done in WP4. Testing and modeling
of structural components will be carried out in WP5. Particularly significant will be the development of design
rules (WP6), as currently the Eurocodes or other National codes do not consider special rules for the
confined masonry, but they simply treat it as unreinforced masonry.
For the system based on the use of ‘C’ shaped vertically perforated clay units, again, the properties of the
perforated clay unit are to be designed and studied, in particular for what concern the shape (geometry of the
unit) in order to allow the creation of all the needed structural details and a proper filling for the mortar that
surrounds the reinforcement and to consider the use of specific blocks for concentrated nucleuses. For this
construction system, physical properties and material laws for the components perforated clay blocks and
mortar will be determined by tests on the masonry components and on small components:
- Compression tests on masonry units;
- Compression and tensile tests on mortar;
- Shrinkage and flow tests on mortar;
- Bond tests between mortar and masonry units.
Testing and modelling of structural components will be carried out in WP5 and the development of design
rules will be done in WP6, and this will be particularly aimed at studying the out-of-plane behaviour of the
masonry system, as currently the code requirements on slenderness ratios for walls seems to be too
conservative and the approach in the design and verification of walls subjected to wind and earthquake
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 21 of 35
actions has to be improved, as well as new construction systems conceived for better out-of-plane
performances can be proposed.
3.4 CONSTRAINTS AND REQUIREMENTS FOR THE REINFORCEMENT
Constraints for the properties of the reinforcement are:
- Reinforcement has to be made only of ribbed bars (when bars are used);
- The actual available masonry reinforcement complies with EN 846-2 and 846-3 (when trusses are used).
- The products can be produced from cold drawn steel wire in diameters ranging from 3 to 5 mm with
tensile strengths up to 600 N/mm².
- The horizontal reinforcement cannot be placed with distance greater than 600 mm. The percentage of
horizontal reinforcement has to be 0,04% ≤ ρh ≤ 0,5%.
- The vertical reinforcement (at least 200 mm2) has to be placed at any wall intersection/wall edge/opening
and cannot be placed with distance greater than 4 m. The percentage of vertical reinforcement has to be
0,05% ≤ ρv ≤ 1,0%.
3.5 DESIGN OF PERFORATED CLAY MASONRY UNITS
For the reinforced masonry system made with horizontally perforated units, the units width is 30 cm (but can
vary between 35 and 20 cm) and will be mainly with square shape, in order to be used in a second time in
both direction, also for the masonry columns, without any problem. The compressive strength in the direction
orthogonal to the holes has to be at least 5 N/mm2, but even more, in order to provide adequate robustness
of the unit, to allow for a suitable behaviour when the masonry element is subjected to combined vertical and
horizontal in-plane loading. This will be provided by change in the raw material mix and also by adequate
mould design (no straight angles between shells and webs). For the ‘C’ shaped vertically perforated units the
unit width is 38 cm. The mechanical properties of the unit are less important to be developed (but still
needed to be known), as the units with vertical holes already meet the main required structural performances
of having a compressive strength in the direction of loading equal to at least 5 N/mm2. The holes for the
vertical reinforcement should have a diameter of at least 6 cm.
3.6 BEDDING/FILLING MORTAR
The mortar will cover a topic of development, in particular for what concern the properties of consistence and
plasticity, to allow for a proper joint (recess) filling for the masonry system made with horizontally perforated
clay units, and to allow for a proper vertical filling where the reinforcement is placed for the masonry system
with ‘C’ shaped vertically perforated clay units. The vertical filling could be also done with concrete, but the
use of a fluid mortar would allow the use of a single material for the entire masonry element and so it would
be much more competitive as construction technique. In any case, the developed mortar should have
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 22 of 35
strength equal to at least 10 N/mm2. It has to be underlined that the requirements for bedding mortar is 5
N/mm2, as specified by the Italian seismic code OPCM 3431, other Italian codes ask for 15 N/mm2 for the
mortar to be used for the vertical reinforcement, the Eurocode 8 asks for 10 N/mm2 indistinctly for the
bedding/filling mortar. This seems a reasonable compromise in order to allow using a single product on site.
Secondary aspects to be studied could be the possible use of fibers or other additives, in order to improve
the bond of mortar with bars and with the clay unit, as all the reinforced joints will be created on the external
part of the shells, which allow for a generally less strong bond behaviour (in the case of the masonry system
with horizontally perforated holes); in the case of masonry made with vertically perforated units the bond
between mortar and unit is also developed by means of the use of staggered units. In this case, a secondary
aspect to be eventually covered is the possibility of using lightweight mortar to preserve good thermal
properties.
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 23 of 35
4 LARGE HOLLOW CLAY UNITS
4.1 REASONS FOR AND AIMS OF THE INVESTIGATIONS
Due to the increased design actions it is necessary to develop masonry with an increased load bearing
capacity or to utilize existing load bearing capacities. For German purposes an appropriate approach is
masonry of concrete filled hollow clay units presently used in Germany. These blocks are applicable in
Germany so far by general building inspection approvals only. The hollow clay units have got large holes,
which are filled so far with mortar or flowable concrete. Inside these holes a vertical reinforcement can be
installed. Furthermore it is possible to arrange a horizontal reinforcement by introducing recesses in the
cross web of the hollow clay units.
In dependence on the respective general building inspection approval it is allowed to apply either the load
bearing capacity of the unfilled hollow clay units or the load bearing capacity of the concrete. A structural
design considering the load bearing behaviour of the bonded materials is not possible so far.
Within the research project DISWall, in the German point of view, the focus should be directed to the
aforementioned building method. This building method should be optimized and existing load bearing
capacities should be utilized by taking the bond of units and concrete into account. For this, first of all the
properties of the masonry components “hollow clay units” and “concrete” are to be improved considering, for
example, the substantial properties in the point of view of the structural designer and the fabricator. With the
hollow clay units it suggests itself to adapt among other things the geometrical and mechanical properties.
As concrete a self-compacting concrete is to be developed. On the one hand filling the hollow clay units
should be made easier and the probability of voids in the concrete infill should be reduced. On the other
hand the concrete should be adapted in its properties very well to the formulated requirements. Furthermore
special reinforcement elements should be developed, which make a simple and exact installation of the
reinforcement possible.
For the optimized building materials a calculation approach is to be compiled which allows to consider the
load bearing behaviour of the bonded materials - hollow clay units and concrete -, to be able to utilize the
existing load bearing capacity reserves. It is planned to achieve this by tests on structural components,
which will be simulated by means of the Finite-Element-Method. Within the scope of parametric studies with
the developed Finite-Element-Models sensitive factors will be characterized influencing the load bearing
behaviour. By use of non destructive testing methods the quality of workmanship on site can be analyzed
and ensured. Within this Workpackage the self-compacting concrete will be developed and the masonry
units will be improved. The selected approach is described in section 4.3.
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 24 of 35
4.2 INVOLVED PARTNERS AND PLANNED TASKS
In the following, the tasks of the partners participating within this Workpackage are described.
Table 13: Involved partners and proposed tasks
INVOLVED PARTNER
PROPOSED TASKS
1 2
UNIPOR Masonry units: - Formulation of the application field of the masonry units (Which buildings are to be
constructed with hollow clay units?). - Compilation of the dimensions and the mechanical properties (Which dimensions of the
units are of interest?). - Formulation of manufacturing constraints (e.g. which material properties of the units
material are possible, which thicknesses of the webs and the shells are possible?). - Formulation of the limiting constraints concerning the workability (e.g. which dimensions of
the cores are necessary to ensure a good workability on site?). Concrete: - Are there requirements on the density of the concrete to ensure sufficient sound
insulation? Reinforcement: - Which reinforcement is used up to now? - Formulation of requirements on the layout of reinforcement and fastenings to ensure an
improved workability (Are there reinforcement-elements required to enhance the workability? Are fastenings to be developed? How should the elements and fastenings look like?).
TUM Masonry units: - Formulation of design actions in dependence on the application field e. g. row houses,
multi storey buildings (How is the masonry typically loaded or designed respectively?) - Formulation of desired improvements of the mechanical properties (Which properties are
necessary to ensure a sufficient load bearing capacity or are to be optimized to enhance the load bearing capacity respectively?)
- Concrete: - Formulation of desired mechanical properties (Which properties are necessary to ensure a
sufficient load bearing capacity? Which properties are required to further develop the load bearing capacity? Is a fibre-reinforcement of the concrete useful to enhance the load bearing capacity of the masonry?).
- Formulation of requirements on the bonding strength between concrete and masonry unit (Is a bonding strength required?).
- Reinforcement: - Compilation of design actions for the reinforcement and fastenings. - Which amount of reinforcement are required? - Formulation of desired requirements on the mechanical properties of reinforcement and
fastenings?
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 25 of 35
Table 14: (continued) Involved partners and proposed tasks
INVOLVED PARTNER
PROPOSED TASKS
1 2
RWTH Masonry units: - Formulation of possible improvements of the mechanical and physical properties Concrete: - Formulation of requirements on the flow properties and the workability. - Formulation of requirements on the water retention. - Compilation of possible mechanical properties.
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 26 of 35
4.3 SELECTED APPROACH
To derive possible approaches for the further development of masonry units and the concrete used for
constructions with large hollow clay units practical tests on small specimens and simulations using the Finite-
Element-Method are planned. Within the Finite-Element-Model, which will be developed, masonry unit,
concrete and the contact zone between them will be considered with different material properties. The model
will be calibrated and validated with tests on bonded specimens. The following material properties on
masonry units, specimens taken from them and on masonry units in combination with concrete will be
determined:
- Dimensions, flatness and parallelism of bed faces of whole units,
- Density and Compressive strength of whole units,
- Fracture mechanical properties of the unit material,
- Load bearing behavior under tensile stresses parallel and perpendicular to the bed joint of specimens
taken from the units,
- Load bearing behavior under compressive stresses perpendicular to the bed joint of specimens taken
from the units,
- Load bearing behavior of filled units under both, compressive and tensile stresses perpendicular and
parallel to the bed joint,
- Adhesive tensile strength between unit and concrete.
For the test a commonly used masonry unit with a width of 240 mm will be used. The concrete will be a
vibrated concrete of the strength class C20/25 and the consistency F5. The age of the concrete will mainly
be 28 days. For the concrete, the following properties will be determined:
- Stress-strain-curves under compressive stresses,
- Stress-strain-curves under tensile stresses.
Both the tests on masonry units, specimens taken from these, bonded specimens and on concrete are part
of the Workpackage 5. By conducting parametric studies using the Finite-Element-Method possible
approaches for the further development of the masonry unit will be determined. For example the mechanical
properties of the masonry unit, the bonding strength and the geometry may be varied.
To develop the self-compacting concrete, the following tests are planned:
- Slump flow test,
- Modified L-Box-test,
- V-Funnel-test,
- Blocking ring test,
- Sedimentation test,
- Viscometer-test,
- Water retention test.
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 27 of 35
4.4 CONSTRAINTS AND REQUIREMENTS FOR REINFORCEMENT, FASTENINGS, MASONRY UNITS AND CONCRETE INFILL
Constraints for the properties of reinforcement and fastenings are:
Reinforcement:
- The actual available masonry reinforcement complies with EN 846-2 and 846-3.
- The products can be produced from cold drawn steel wire in diameters ranging from 3 to 5 mm with
tensile strengths up to 600 N/mm².
- The availability ranges from 30 mm to 280 mm for horizontal bed joints reinforcement.
- Finishes: hot dip galvanized, duplex coated (Zn + epoxy) and stainless steel
- The amount of reinforcement can be determined by the demand of a sufficient load bearing capacity
under in-plane bending. A rough reference value can be taken from the minimum code requirements for
reinforced concrete walls given in Eurocode 2: up to 0.2% Ac. The maximum value results from the
geometric possibilities of the application of the reinforcement.
- The amount of reinforcement should be greater than the tension strength of the corresponding concrete
cross-section area to avoid an abrupt and brittle tension failure in the tension zone of the wall. This can
also be easily avoided by the application of fibre reinforcement, where a very ductile behavior under
tension is ensured.
Fastenings:
- orthogonal masonry reinforcement with the ancillary components is available and may be adapted to the
geometry of the masonry specimens;
- the fastenings should be able to couple the deformations of the walls with the concrete slabs to avoid
rocking effects caused by a tension failure in the bed joint between slab and masonry wall. The use of the
fastenings on site has to be easy and safely to avoid mistakes in practice.
Masonry units:
The masonry units have to withstand the loadings during the erection phase, e.g. hydraulic pressure from the
concrete infill (bending capacity of the shells) or the loadings of the structure before the final compression
strength of the concrete is reached. In the final system the units should have a sufficient diagonal tension
strength being relevant for the shear loading capacity. The compression strength of the units should be high
enough (> 12 N/mm²), ideally in a range near to the compression strength of the concrete infill.
The relevant loadings on the wall system can be generally characterized as in-plane shear loadings in
combination with an eccentric compression force, i.e. in-plane bending. Also loadings perpendicular to the
wall face like wind or earth-pressure should be included. For the loadings on the structure it is important to
distinguish between row houses, where the compression stress level is generally low, and multi storey
buildings where high compression strength has to be assumed.
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 28 of 35
Concrete infill:
The concrete infill has to ensure that the interaction of the clay bricks and the concrete leads to a ductile
behaviour of the component material under the acting stresses. A sufficient bonding strength between clay
bricks and the concrete infill is deciding under long time loading effects, e.g. shrinkage and creeping of the
concrete and also the quasi permanent compression stresses, and short time loadings e.g. under seismic
loadings. The compression strength of the concrete should be in a range near to the compression strength of
the masonry units and may be limited to a C20/25. In addition also the stress-strain relationship should
ensure a maximum strain value under the maximum compression strength.
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 29 of 35
5 CONCRETE UNITS
5.1 REASONS FOR AND AIMS OF THE INVESTIGATIONS
The major challenge that has to be faced in the Portuguese construction industry is the obtainment of an
effective and attractive load bearing and non-load masonry construction system that is able to convince
contractors to use it in the standard construction. In fact, masonry is only used as non-load bearing infill,
whose behaviour may be improved by placing horizontal reinforcement and only recently bed joint
reinforcement is known to be used. This means that new masonry concrete units can probably be developed
for the purpose of obtaining a more efficient non-load bearing system and particularly a novel load bearing
system. The solutions to be studied intend to cover both needs without introducing considerable changes in
the construction techniques.
Within the scope of the DISWall project, two types of concrete hollow blocks are to be designed. The
concrete block with two vertical hollow cells (B1), quite similar to the typical blocks used in the infill, and a
block with three hollow (B2) cells especially formulated to accommodate uniformly spaced vertical
reinforcement. The non-load bearing walls solution is intended to be obtained by the introduction of
prefabricated horizontal reinforcements in mortar bed joints. No special novel reinforcements are foreseen
for this application. However, an enhancement of the non-load bearing behaviour should be provided by the
study of the appropriate anchorages from the horizontal reinforcements to the structural concrete columns
are to be performed. The comparative analysis of the performance of load bearing walls under in-plane and
particularly under out-of-plane loading would be performed by using both types of units. This solution
foresees the use of vertical and horizontal reinforcements. Again, appropriate anchorages of vertical
reinforcements to the bound concrete structural elements are to be analyzed. The constructive construction
technique is intended to be studied in order to have minimal changes concerning the traditional technique
used for unreinforced masonry walls. The optimization of the shape, geometry and formulation of concrete
admixtures for the concrete blocks is intend to be carried out by UMINHO together with unit producer, C&A
company. By practical issues, 1:2 reduced concrete blocks will be adopted. Besides the control of the
mechanics of concrete units, an assessment of the physical properties should be performed. A central issue
to be solved concerning this structural system is the obtainment of a mortar for the bed joints that
simultaneously is able to properly fill the hollow cells and vertical joints. Moreover, it is needed that stiffness
properties of mortar and concrete units are compatible. With this respect, an additional investigation about
the economical possibilities of using self-compacted micro concrete is foreseen.
Besides the standard tests for mechanical characterization of masonry materials (units and mortar) and
interfaces, particular attention should be paid to the bond strength between reinforcements and mortar.
These tests enable the obtaining of the constitutive behaviour of masonry compounds. The experimental
program includes the flowing experimental tests:
- Compressive and tensile tests of the units
- Compressive and tensile tests of mortar
- Bond strength characterization of the unit mortar interface
- Determination of the bond strength of the prefabricated reinforcements in mortar joints
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 30 of 35
The particular aspects of the constructive system will be discussed on WP4 and the experimental and
numerical evaluation of the in-plane and out-of-plane behaviour of the reinforced masonry walls is the
subject of WP5.
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 31 of 35
5.2 INVOLVED PARTNERS AND PLANNED TASKS
Table 15: Involved partners and proposed tasks
INVOLVED PARTNER
PROPOSED TASKS
1 2
C&A Masonry units: - Evaluation of the application field of the masonry concrete units - Compilation of the dimensions and the mechanical properties - Formulation of manufacturing constraints (possible properties of the units’ material). - Formulation of the limiting constraints concerning the workability (dimensions of the cores
that ensure a good workability on site). - Production of the units Concrete: - Control of the physical properties (density) of the concrete to ensure sufficient sound and
thermal insulation Reinforcement: - Survey of the available prefabricated reinforcements - Formulation of requirements on the layout of reinforcement and fastenings to ensure an
improved workability (Are there reinforcement-elements required to enhance the workability? Are fastenings to be developed? How should the elements and fastenings look like?).
UMINHO Masonry units: - Formulation of desired mechanical properties for load and non-load bearing walls - Testing of the mechanical and physical properties of concrete units Mortar: - Formulation of desired mechanical properties and bonding strength between masonry and
masonry unit. - Formulation of the appropriate physical properties to obtain a workable infill mortar to the
reinforced hollow cells - Testing of the bond strength of the unit mortar interface - Testing of the mechanical and physical properties - Testing of the bond between reinforcement and mortar Reinforcement: - Compilation of design actions for the reinforcement and fastenings. - Design of the required reinforcement
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 32 of 35
5.3 SELECTED APPROACH
According to section 5, the main task of UMINHO is the development of a novel constructive system based
on reinforced masonry walls. The major issue related to reinforced masonry walls is the efficient placement
of vertical reinforcement, which leads that suitable masonry units and mortar have to be used. Another issue
under discussion concerns the usage of mortar embedding to fill the hollow concrete cells that avoids the
simultaneous use of grout and mortar in the construction of reinforced masonry.
This section addresses the description of the preliminary work carried out and the work that is running on the
domain of the development of masonry materials to be used in the construction of reinforced masonry walls.
5.4 CONSTRAINTS AND REQUIREMENTS FOR THE REINFORCEMENT AND THE FASTENINGS
Constraints for the properties of reinforcement and fastenings are:
Reinforcement:
- The actual available masonry reinforcement complies with EN 845 – 3 and EN 846-2 and 846-3.
- The products can be produced from cold drawn steel wire in diameters ranging from 3 to 5 mm with
tensile strengths up to 600 N/mm².
- The availability ranges from 30 mm to 280 mm for horizontal bed joints reinforcement.
- Finishes: hot dip galvanized, duplex coated (Zn+ epoxy) and stainless steel
Fastenings:
- An orthogonal masonry reinforcement with the ancillary components is available and may be adapted to
the geometry of the masonry specimens.
5.5 DESIGN OF HOLLOW CONCRETE MASONRY UNITS
The design of the masonry wall specimens to be tested in the scope of the WP5 led that 1:2 reduced scaled
concrete masonry units has to be used. Figure 1 shows the two types of concrete masonry units that were
adopted. A more classic shape is obtained through the two cell blocks, CB2C, which to certain extent is
representative of the Portuguese concrete masonry units used for non structural proposals, see Figure 1a.
They are basically used as infill of the reinforced concrete frames. A foreseen possibility of placing the
vertical reinforcement is the hollow cell. The other type of concrete masonry units is composed by three
vertical hollow cells, CB3C, see Figure 1b.
This type of block allows the placing of the vertical reinforcements in the central hole or in alternative cell
constituted by the external webs. The latter possibility can simplify the constructive process if mortar is used
in the filling of the cell. Further details about the constructive solutions will be discussed in WP4. According
to EC6, the units with this geometry are classified as belonging to Group 2.
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 33 of 35
The production of the concrete blocks has been carried out by C&A. The production is normalized according
the European Standard referring to the specification to aggregate concrete masonry units (EN 771-3),
namely with respect to dimensions of the blocks and corresponding tolerances (EN 772-16), flatness of the
faces of the aggregate concrete (EN772-20), water absorption (EN 772-8), water absorption by soaking (EN
772-11), net and gross dry density of masonry units (EN 772-13) and moisture movement of aggregate (EN
772-14).
The proportion of raw materials (cement, sand, gravel) is adjusted so that the compressive strength ranges
from 20.0 to 25.0 N/mm2. An additional concern refers the maximum aggregate size, which should be
selected to attend the 1:2 scale requirements. This issue is also important in order to achieve an appropriate
texture that enables to comply with other standard requirements (dry density, water absorption).
The mechanical characterization of the concrete masonry units is intended to be presented in WP5. This
includes uniaxial compressive strength, tensile strength and modulus of elasticity in the direction of vertical
hollow cells (perpendicular direction to the bed joints).
(a)
(b)
Figure 1: Geometry of the hollow concrete blocks; (a) three cell concrete blocks, CB3c; (b) two cell
concrete blocks, CB2c (dimensions in cm)
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 34 of 35
5.6 BEDDING/FILLING MORTAR AND GROUT
Reinforced masonry is usually composed of hollow concrete/clay masonry units, and bedding mortar and
different types of reinforcement. The filling of the vertical hollow cells is usually carried out by means of grout.
In spite of the mortar and grout can be composed of the same components, the relative proportion is quite
different. Bedding mortar, composed of a mix of cement, lime and sand, is required to have enough
plasticity/workability to be spread on the webs and shells of the masonry units, providing at same time
sufficient adhesion. On the other hand, grout is required to present enough flowability that allows the proper
filling of the hollow cells. It is stressed that the performance of the reinforced masonry, and particularly as
concerns the effectiveness of the contribution of vertical reinforcements, depends essentially on the bond
conditions between infill material and the reinforcements. This is directly related with the homogeneity of the
filling material in the sense that no voids weak the bond adherence between the infill and the reinforcements.
However, the usage of same material as embedding and as infill material has the economical advantages of
simplifies considerably the constructive process.
The major challenge is, thus, to find an embedding mortar that is suitable as an infill material to be used in
the vertical hollow cells. This constitutes the main proposal at the level of material development. An
experimental study of mortars with different mixes is to be performed to find an equilibrium point, i.e., an
intermediate mix with appropriate plasticity and sufficient workability. The mortar under study will be cement-
lime based. The reference mix will be composed by Portland cement and sand. The raw materials for the
subsequent mixtures will be Portland cement, lime and sand. The workability/flowability of the different
mixtures will increase by the addition of water, see Table 16. The Mix M2 intends to be a grout with the
addition of water. In order to evaluate the reliability of using a commercial ready mortar, an additional pre-
mixed mortar is to be used, M5.
Table 16: Set of admixtures to be studied
MIX PROPOSED TASKS
1 2 M1 1:3 (reference) M2 1:0.1:3.3 M3 1:0.5:4.5 M4 1:1:6 M5 Pre-mixed mortar
The evaluation of the performance of the mortar to work as bedding and infill material is composed of three
steps:
Step1
- Determination of the properties of fresh mortar (flow test, plunger penetration, workability, water
absorption, retention of water).
Step2
- Evaluation of the workability of the mortar by preliminary construction of small wall specimens.
DEVELOPING INNOVATIVE SYSTEMS FOR REINFORCED MASONRY WALLS
COOP-CT-2005 CONTRACT N. 018120
Product Development D3.1 Page 35 of 35
- Assessment of the proper filling by means of non-destructive testing – Ultrasonic tomography.
Step3
- Determination of the properties of hardened mortar (compressive and flexural strength, modulus of
elasticity, Poisson’s ratio).
- Obtainment of the bond characteristics of the unit masonry interface (tensile and shear).
- Uniaxial compressive tests on grouted and ungrouted masonry prisms.
- Preliminary assessment of the performance of the distinct types of mortar through flexural tests in
masonry beams (results will also be discussed in Workpackage 5).
- Bond tests between masonry and reinforcements (stainless steel truss reinforcement).