Page 1: Delivering our transport future now

Presentation to AITPM Technical Forum

Lachlan RobertsSenior Project Manager/Interface Manager

9 September 2015

Page 2: Delivering our transport future now
Page 3: Delivering our transport future now

78 km running between Old Noarlunga and Gawler

Page 4: Delivering our transport future now
Page 5: Delivering our transport future now
Page 6: Delivering our transport future now

NORTH-SOUTH CORRIDORAdelaide’s North-South Corridor:• 78 km running between Gawler and Old

Noarlunga

Funding agreement has been reached between Australian and South Australian governments to fund two projects in parallel:• Torrens Road to River Torrens $896m• Darlington $620m

Total investment of $1.516b between 2013- 2014 and 2018-2019.

DPTI is currently developing a 10 year strategy to deliver the North-South Corridor.

Page 7: Delivering our transport future now

Southern Expressway duplication[completed 2014] $407.5m

Page 8: Delivering our transport future now

Darlington Upgrade project[due for completion 2018] $620m

Page 9: Delivering our transport future now

Gallipoli Underpass & Tram Overpass[completed 2009] $114.1m

Page 10: Delivering our transport future now

Potential Future Projects between Darlington – River Torrens excludes

Gallipoli Underpass [est. $4.77b]

Page 11: Delivering our transport future now

Torrens Road to River Torrens[due for completion 2018] $896m

Page 12: Delivering our transport future now

Regency Road to Torrens Road – future project [est. $760m]

Page 13: Delivering our transport future now

South Road Superway[completed 2014] $842m

Page 14: Delivering our transport future now

Northern Connector –future project [est. $860m]

Page 15: Delivering our transport future now

Northern Expressway[completed 2010] $564m

Page 16: Delivering our transport future now

Ashwin Parade and South Road Intersection Upgrade

James Congdon Drive and South Road Intersection Upgrade

Richmond Road and South Road Intersection Upgrade

Fitzroy Terrace, Park Terrace, Torrens Road Upgrade

South Road

Sir Donald Bradman Drive

Torrens Road

Page 17: Delivering our transport future now

The North-South Corridor early and associated works for the Torrens Road to River Torrens Project includes:• Demolition of buildings and structures and relocation of services.

• South Road / Ashwin Parade / West Thebarton Road intersection upgrade –completed April 2015 - $10m.

• The duplication of James Congdon Drive (JCD) between South Road and Sir Donald Bradman Drive and construction of a second right turn lane into JCD from South Road. Anticipated completion December 2015 - $8.8m.

• Upgrade of South Road and Richmond Road intersection, including an additional south bound lane on South Road and the provision of an additional city bound lane on Richmond Road between South Road and Railway Terrace. Anticipated completion December 2015 - $11m.

• Upgrade of Park Terrace, Fitzroy Terrace and Torrens Road will result in three lanes in each direction between Port Road and Prospect Road, with an extra city-bound lane also included on Torrens Road. Anticipated completion November 2015 - $11.3m.

Page 18: Delivering our transport future now

3.7 km upgrade of South Road from just north of Torrens Road to just south of the River Torrens

River Torrens

Torr

ens

Road

Page 19: Delivering our transport future now

SAPN Sub-Station

Aerial View South Road looking South

Page 20: Delivering our transport future now

3 km of non-stop section of roadway (incorporating 2 km of lowered motorway),

approx 8 m below the existing surface under Port and Grange Roads, and

Hawker Street

Improved cycling & pedestrian facilities

Landscaping & noise barriers

(where required)

SAPN Sub-Station

Page 21: Delivering our transport future now
Page 22: Delivering our transport future now

Pedestrian bridge across lowered motorway

Page 23: Delivering our transport future now

Pedestrian Crossing (artist impression)

Page 24: Delivering our transport future now

Aerial view of South Road/Port Road Intersection

South Road

Port Road

Page 25: Delivering our transport future now

Exit ramp to Port Road

Entry ramp from

Port Road

Page 26: Delivering our transport future now

Port Road/South Road Intersection

Outer Harbor Rail line crossing South Road

Page 27: Delivering our transport future now

Outer Harbor rail line overpass

Page 28: Delivering our transport future now

An overpass of the Outer Harbor rail line

Page 29: Delivering our transport future now
Page 30: Delivering our transport future now

Port Road/South Road Intersection (artist impression)

Page 31: Delivering our transport future now

Grange Road over the lowered motorway (artist impression showing advanced landscaping)

Page 32: Delivering our transport future now

Grange Road over the lowered motorway (artist impression showing advanced landscaping)

Page 33: Delivering our transport future now
Page 34: Delivering our transport future now
Page 35: Delivering our transport future now
Page 36: Delivering our transport future now
Page 37: Delivering our transport future now

Parallel surface (at-grade) roads along the length of the lowered

motorway to connect most local roads and arterial roads to South Road

Page 38: Delivering our transport future now

Request for Proposal

Closed March 2015

AwardedApril 2015

Completion of works

by end of 2018

Commence with T2T Alliance

Major Construction Works began

on siteAugust 2015

Project Timeline

Short listed to two

proponents

October2014

Expression of Interest released

August 2014

Closed Mid September

2014

Page 39: Delivering our transport future now

The award of the major works contract for the $896 million project was announced on 29 April 2015.

The successful tenderer was T2T Alliance, a consortium consisting of:

Leighton Contractors Pty Ltd Aurecon Australasia Pty Ltd and

York Civil Pty Ltd

Page 40: Delivering our transport future now

• An Alliance is a collaborative delivery method in which the Owner joins with one or more non-owner parties to share all the risks and responsibilities in delivering a Project.

• It is a proven infrastructure procurement method that is being used by governments across Australia to deliver infrastructure to the community.

Competitive Alliance – what is it?

Page 41: Delivering our transport future now

Choosing a Competitive Alliance Procurement Model

• Delivering projects with unclear scope of works.• Delivering projects with significant risk certainty.• Managing stakeholder issues.• Value-for-money.

Page 42: Delivering our transport future now

Alliance Contracting Key Benefits

• The parties are incentivised to work cooperatively to complete the project within time and budget forecasts.

• To find the best solutions for the project (rather than for their own interests).

• To work quickly and collaboratively to resolve issues as they arise.

• Promote a positive culture to achieve outstanding results for the project.

Page 43: Delivering our transport future now

T2T Alliance Key Result Areas (KRAs)

• Traffic Performance• Completion• Relationships with key stakeholders• Sustainability• Workforce and Industry Participation

Page 44: Delivering our transport future now

Why has the project been registered for an Infrastructure Sustainability (IS) Rating?

• To help drive sustainability initiatives within this major infrastructure project.

• To ensure that sustainability is a key consideration in the design and delivery of the project.

• To provide a sustainable performance baseline for future projects and enable DPTI to benchmark this project against other major infrastructure projects nationwide.

Page 45: Delivering our transport future now

Projects of this scale and nature create a range of opportunities for businesses along the supply chain in providing goods and services to the major works contractor. These typically include:

• Materials such as concrete, quarry products etc• Machinery hire• Landscaping• Fencing• Traffic control • Accommodation, food and drink• Fuel• Safety equipment, security etc

Page 46: Delivering our transport future now

The South Australian Industry Participation Policy

The Policy is in place to ensure that capable South Australian small and medium businesses are given full, fair and reasonable opportunity to tender and participate in significant public and private sector projects.

Page 47: Delivering our transport future now

A South Australian Industry Participation Plan is an important contractual requirement to:

• Promote economic contribution to the State including employment outcomes and economic growth.

• Ensure equitable access for local industry.• Monitor and record the outcomes of local industry involvement.

Page 48: Delivering our transport future now

SUPPLY INPUTSValue of goods and supplies

sourced from South Australian businesses

Directly linked to the delivery of contracts on behalf of the

South Australian Government

EMPLOYMENTNumber of South Australian

jobs or labour hoursINVESTMENT

Amount of new capital expenditure in South

Australia

Key drivers of economic contribution from procurement

Page 49: Delivering our transport future now

T2T Alliance South Australian Industry Participation Policy

The Office of the Industry Advocate has been involved throughout the procurement phases of this project, T2T Alliance has committed to:

• Use over 90% local labour with a value over $70 million.• Over $1 million in new capital purchases to be permanently located in

the State.• Over 90% of sub-contracts where most of the product or service will

be carried out in the State with a target spend of $290 million.

Page 50: Delivering our transport future now

Workforce Participation

In accordance with the State Government’s ‘Workforce Participation in Government Construction Procurement policy’ and the State’s ‘Our Jobs Plan’, T2T Alliance will be required to ensure that at least 20% of labour hours are undertaken by:

– Apprentices & trainees– Aboriginal people– Local people with barriers to employment– Displaced automotive industry workers– Up-skilling existing staff

Page 51: Delivering our transport future now

Sod Turning Event - 5 August 2015

Page 52: Delivering our transport future now
Page 53: Delivering our transport future now