dendy st beach pavilion...• jcb architects • site office landscape architects the water...
TRANSCRIPT
Melbourne Sydney
Dendy Street Beach
Pavilion
Water Management
Strategy
Report Prepared for:
Bayside City Council
Project No. 1680
Prepared by:
Storm Consulting Pty Ltd
SUSTAINABLE WATER
STORMWATER & RUNOFF
STREAMS & WATERWAYS
CIVIL & INFRASTRUCTURE
Melbourne Office:
Unit 7, 84 Church Street
Richmond VIC 3121
T: (03) 9208 0111
www.stormconsulting.com.au
i
Document Verification Project title Dendy Street Beach Pavilion
ACN 080 852 231
ABN 73 080 852 231
Document title Water management strategy Project number
1680
Description Draft
Client Contact Graham Burrows, JCB Architects
Name Signature Issue: Date
Prepared by RW / MA
C 1/8/17 Checked by Rod Wiese
Issued by Rod Wiese
Filename 1680 Dendy Stormwater Managment VB.docx
Document History
Issue A Issue B Issue C
Issue to: Date No. Copies Date No. Copies Date No. Copies
Stephanie Burton 17/3/17 pdf
Chris Sawyer 17/3/17 pdf 28/7/17 pdf
Simon Beeton 28/7/17 pdf 1/8/17 pdf
Kathleen Kopietz 28/7/17 pdf 1/8/17 pdf
Denise Whitehead 28/7/17 pdf 1/8/17 pdf
Copyright and Confidentiality
All intellectual property rights, including copyright, in designs developed and documents created by Storm Consulting Pty Ltd
remain the property of that company. Other than as permitted by the Copyright Act and as outlined in the Terms of Engagement,
no part of this report and associated drawings may be reproduced or used in any form, copied or transmitted in any current or
future unknown form without the prior written permission of Storm Consulting Pty Ltd. To do so will constitute an infringement
of the rights of that company which reserves all legal rights and remedies in respect of any such infringement.
The information, including the intellectual property, contained in this document is confidential and proprietary to Storm Consulting
Pty Ltd. It may only be used by the person to whom it is provided for the stated purpose for which it is provided, and must not
be imparted to any third person without the prior written approval of Storm Consulting Pty Ltd. Storm Consulting Pty Ltd reserves
all legal rights and remedies in relation to any infringement of its rights in respect of its confidential information.
© 2017 Storm Consulting Pty Ltd
Limitations
This report is prepared by Storm Consulting Pty Ltd for exclusive use by its client only. No responsibility is accepted for the use
of or reliance upon this report in whole or in part by any third party.
The sole purpose of this report and the associated services performed by Storm Consulting Pty Ltd is to display information in
accordance with the scope of services set out in the contract/quotation between Storm Consulting Pty Ltd and its client. The
scope of works and services were defined by the requests of the Client, by the time and budgetary constraints imposed by the
client, and by the availability of access to site/s and information.
This report is prepared with information supplied by the client and possibly others which is presumed to be accurate and
complete. No responsibility is accepted for information that is withheld, incorrect or that is inaccurate, nor for changes to the
conditions over the passage of time or from latent circumstances or conditions. No warranty or guarantee is made in relation to
the data, findings and conclusions expressed in this report.
This report has been compiled at the level of detail specified in the report and no responsibility is accepted for interpretations
made at more detailed levels than so indicated.
ii
TABLE OF CONTENTS 1.0 INTRODUCTION .............................................................................1
1.1. Preamble .........................................................................................1
1.2. Background and Context ..............................................................1
1.3. Objectives .......................................................................................1
1.4. Scope ...............................................................................................1
2.0 DESCRIPTION .................................................................................2
2.1. Overview of Proposed Works .......................................................2
2.2. Water Management Strategy .......................................................3
2.3. Site soils ..........................................................................................4
3.0 WATER SENSITIVE URBAN DESIGN .............................................5
3.1. Stormwater Quality Treatment.....................................................5
3.2. Reuse ...............................................................................................5
3.3. MUSIC Modelling ...........................................................................5
3.4. Summary .........................................................................................9
4.0 PEAK FLOW ASSESSMENT.......................................................... 10
4.1. Strategy ....................................................................................... 10
4.2. Methodology ............................................................................... 10
4.3. Key Hydraulic Features ............................................................... 12
4.4. Results .......................................................................................... 12
4.5. Summary ...................................................................................... 13
5.0 CONCLUSIONS ............................................................................ 14
5.1. Water Sensitive Urban Design ................................................... 14
5.2. Peak Flow Assessment ................................................................ 14
iii
APPENDICES
APPENDIX A
Functional Design Drawings
1
1.0 INTRODUCTION
1.1. Preamble STORM_CONSULTING (Storm) has been engaged to design and assess the development of the Dendy
Street Beach Pavilion project for the drainage and water quality infrastructure as well as supporting
civil works. The primary objective is to reduce the impact of the large stormwater pipe draining
directly onto the beach which detracts from the aesthetics. Water Sensitive Urban Design (WSUD) is to
be utilised as an alternative treatment to mitigate against this ‘eye-sore’.
1.2. Background and Context Dendy Street Beach Pavilion project is located on the southwestern corner of the intersection of
Esplanade and Keith Court, in Brighton, Victoria. The project encompasses a new beach pavilion, major
stormwater drainage modification, water quality treatment, access path, car park and landscape
improvements. Storm is part of a broader team working together to deliver this project. The team
includes:
• JCB Architects
• Site Office Landscape Architects
The water management strategy relies heavily on infiltration and reuse. Detention in the form of both
surface and subsurface is utilised to enhance infiltration.
A summary of our assessment on the water management strategy is detailed in this report.
1.3. Objectives The water management objectives are:
• Reduce the impact of unsightly stormwater outlet from the front of the current pavilion
• Infiltrate stormwater from the upstream catchments into surrounding soil
• Manage pollutant runoff
• Harvest stormwater for toilet flushing
1.4. Scope STORM has been engaged to:
• Prepare a MUSIC model to confirm reduction in pollutant loads
• Undertake a peak flow analysis
• Size the infiltration detention system
• Size rainwater tanks for toilet flushing
• Prepare brief report on proposed treatment system and treatment results.
1680 Dendy Stormwater Managment VC.docx 2
2.0 DESCRIPTION
2.1. Overview of Proposed Works The proposed development site is located at the end of Dendy Street where it connects to the
esplanade. The site development includes:
• Removal and re-construction of the existing carpark and its use
• Removal and replacement of the existing Pavilion with Environmentally Sustainable Design
features (including a rainwater harvesting system).
• Introduction of a new beach access ramp
• Reduction of the existing outfall drain to the beach via a drainage upgrade to incorporate
infiltration and water quality improvement
Table 1 notes the catchment areas.
Table 1: Catchment areas
Location Catchment area (m2)
Upstream Urban Area 410,000
Carpark 1,521
Footpaths 1,623
Forecourt 1,014
Roof 582
TOTAL 414,740
The following sketch highlights the catchment areas graphically:
1680 Dendy Stormwater Managment VC.docx 3
Figure 1: Site Catchment Plan
2.2. Water Management Strategy Through collaboration amongst the project team including lead consultants and architects Jackson
Clements Burrows and landscape architects from Site Office we developed a treatment train which
included the following assets:
• Diversion
• GPT
• Subsurface leaky retarding basin
• Raingarden
• Subsurface infiltration pipe network
• Rainwater re-use tank
The following schematic highlights the chosen water quality assets and associated catchments:
410,000 sqm
1680 Dendy Stormwater Managment VC.docx 4
Figure 2: Water Management Strategy Overview
2.3. Site soils Investigations were undertaken on site by HardRock Geotechnical. A total of 4 test holes were drilled
noting that the subsurface soils were primarily sands to the limit of excavation. This is consistent with
the regional geology by the Geological Survey of Victoria as being Quaternary sand ridges and
Quaternary alluvial flats with silt, sandy silt, minor sand and gravel.
Percolation test were attempted to define the saturated hydraulic conductivity rates for design
purposes. The outflow rates of the wells were too great to be reliably calculated with the outflow
being higher than what could be poured into the wells. It was concluded that the saturated hydraulic
conductivity rates were very high which is consistent with sands.
HardRock has noted in other studies that the rates in this region have been 500-1500mm per hour.
They advised to be conservative and suggested a nominal design rate of 200mm per hour. This has
been utilised in the assessment however the rate of 1000mm per hour is also reported on as
potentially a more realistic figure.
1680 Dendy Stormwater Managment VC.docx 5
3.0 WATER SENSITIVE URBAN
DESIGN
3.1. Stormwater Quality Treatment The main contributing catchment for this site is the external urban catchment that currently connects
410,000m2 of area directly to the beach. The stormwater is delivered via the drainage system and
conveys up to the 1 in 5 year ARI event (typically) to the project site. The following treatment assets
will improve the water quality and disconnect as much of the flow as possible.
Gross Pollutant Trap (GPT)
A GPT is proposed to be located within the carpark for easy maintenance access. The preferred
product is a CDS unit supplied by Rocla. This type of product is already in use by Council and easily
inserted into the maintenance regime and schedule. The product has advanced filtering capability to
capture a lot of sediment as well as gross-pollutants which enables it to stand out amongst its
competitors. Any comparable product would need to confirm it has similar capabilities to ensure it
also reflects the same water quality results.
Raingarden
The minor flows (post GPT treatment) will be directed through an orifice to the raingarden for
treatment and infiltration. Flows in excess of the orifice capacity will flow into the leaky retarding basin
also referred to as detention basin. The overflow from the leaky retarding basin in larger events will
then be directed into the raingarden for some treatment but primarily for further detention. The
raingarden is treating the new path hardstand areas, access ramps and any overflows form the roof of
the new Pavilion. The raingarden is approximately 400m2 and will not contain an under drain to
encourage infiltration rather than filtration. Overflows are directed to the existing outlet.
Leaky Retarding basin
Flows exceeding the capacity of the orifice draining to the raingarden are directed into a leaky
retarding basin located beneath the surface to encourage infiltration into the natural soils. The
storage required for this system has a footprint of around 450m2 and volume of almost 500m3. The
preferred storage to facilitate the infiltration is the StormTech arches by ADS pipe. The natural site
soils facilitate an exfiltration rate of around 200mm/hr which makes it an ideal solution in the bid to
disconnect the upstream catchment from the beach. This is also tested at 1000mm/hr which is
arguably more realistic. The newly upgraded carpark will also report into the treatment train at this
stage adding to the external catchment.
3.2. Reuse Rainwater from the building's roof area will be harvested into a 20KL tank adjacent to the proposed
pavilion. The harvested water will be used for toilet flushing in both the building and public toilets.
The tank was sized using historic rainfall information and estimated toilet usage data that was
calculated from projected visitor numbers provided by the architects. The roof area draining to the
tanks was estimated to be 582m².
3.3. MUSIC Modelling MUSIC was used to size the various water quality treatment components and provide evidence of the
impact the assets would make to the outflows.
1680 Dendy Stormwater Managment VC.docx 6
Model Layout
The overall model was developed around the main treatment train as described above that focused on
the much larger external urban catchment. The local catchment components including carpark, roof,
paths and forecourt were connected into the treatment train at various points based on their
convenience and practicality. Figure 3 below illustrates the MUSIC model layout.
Figure 3: MUSIC Model Layout
An infiltration rate of 200mm/hr was used as a conservative design figure by HardRock. We also
assessed a rate of 1,000mm/hr to gauge a more realistic result. These are also reported below.
Modelling Results
The MUSIC model was run using the Melbourne City 1966 rainfall data as recommended in the
Melbourne Water MUSIC guidelines for this area. However we also ran the 10 years of data from 1952
to 1961 to remove some of the potential inaccuracies relating to interpreting a single year of data. The
results are based on a time-step of 6 minutes over the 10 year period for infiltration rates of 200 and
1000mm/hr.
It is expected that the rainwater harvesting system off the pavilion roof will meet the consistent toilet
demand nominated for the pavilion and café users. The summer period is expected to draw a higher
demand and therefore the 20KL volume nominated should be the minimum and additional storage
recommended to increase the volumes supplied to the public toilets.
The proposed treatment train uses a series of infiltration based assets to treat and infiltrate the
maximum volume of stormwater into the landscape to minimise drainage and pollution volumes at the
beach. Most of the flows will be infiltrated and never reach the beachfront. This clearly translates to
removal of pollutants from the system which is beyond the Best Management Practice of 80% removal
of Total Suspended Solids, 45% removal of Total Phosphorous and Total Nitrogen. The water quality
results are presented below noting that the data includes the site as well as the upstream catchment.
1680 Dendy Stormwater Managment VC.docx 7
Table 2: MUSIC modelling results
Parameter Source
Infiltration rate 200mm/hr Infiltration rate 1000mm/hr
Residual Load % reduction Residual Load % reduction
Flow (ML/yr) 130 38 71% 16 88%
Total
Suspended
Solids (kg/yr)
18100 2980 84% 1630 91%
Total
Phosphorus
(kg/yr)
42.6 9.1 79% 4.4 90%
Total
Nitrogen
(kg/yr)
332 95 72% 41 88%
Gross
Pollutants
(kg/yr)
5110 129 98% 129 98%
It may be difficult to appreciate the impact that the system has on improving the condition of the
beach outfall. A series of graphs have been produced to aid the interpretation of these results. Figure
4 shows the peak outflows predicted for the period of record as a daily average. Figure 5 shows the
cumulative impact on beach outflows and Figure 6 shows the cumulative impact on TSS.
Figure 4: Impact on beach outflows (average daily)
0
0.05
0.1
0.15
0.2
0.25
0.3
25/0
8/19
50
7/0
1/19
52
21/0
5/19
53
3/1
0/19
54
15/0
2/19
56
29/0
6/19
57
11/1
1/19
58
25/0
3/19
60
7/0
8/19
61
20/1
2/19
62
m3 /
s
Beach Outflow Existing Outflow
Outflow (200 mm/hr Exfiltration)
Outflow (1000 mm/hr Exfiltration)
1680 Dendy Stormwater Managment VC.docx 8
Figure 5: Impact on beach outflows cumulative over 10 years
Figure 6: Impact on beach outflows cumulative over 10 years
1680 Dendy Stormwater Managment VC.docx 9
3.4. Summary Using the proposed system, the modelling results indicate that in an average year the proposed
development of the site will reduce the total flows draining to the beach by 71-88%. The pollution
reduction to the beach is drastically reduced and superior to best practice in an effort to minimise the
unsightly impact that the current stormwater drainage has on the beach. The reduction in TSS is a
good indicator where it is expected that 84-91% will be retained in the treatment system.
The 20kL tank harvesting from the roof will supply most of the nominated toilet demand for the
pavilion and contribute to the supply of toilet flushing to the public toilets. A larger tank will supply
additional water to the public toilets.
1680 Dendy Stormwater Managment VC.docx 10
4.0 PEAK FLOW ASSESSMENT A peak flow assessment is required to ensure that the system can cope with the larger flow events and
maximise the opportunity for infiltration to occur. This analysis will inform the design of weir
structures, size of pits and pipes as well as the assessment of hazards risks relating to overland flows
down the path.
4.1. Strategy Figure 2 shows the layout of the elements proposed. Diverting the majority of flows to the treatment
system will improve public amenity through water quality improvement and infiltration. Detention is
the key management to maximising the available infiltration of the site. Detention is achieved in the
underground storage referred to as detention or leaky retarding basin as well as the volume above the
raingarden surface.
A bypass is proposed up-stream of the GPT to divert peak flows in excess of about 1m3/s. The bypass
will use the existing drainage system although an upgrade of the existing 675mm diameter pipe and
box culvert is required to manage the hydraulic grade line and life span of the system.
Overflows from the raingarden are directed back to the existing culvert however the outlet is proposed
to be upgraded from the existing 1200mm wide and 600mm high to 3000mm wide and 300mm high.
This reduces the energy levels considerably compared to the existing scenario and allows the invert
level to be lifted by 300mm. This will provide a better amenity and reduce the maintenance burden.
Sizing weir lengths and heights is an iterative process to enable the optimum combination to maximise
the performance for a range of storm events. This assessment has been described below.
4.2. Methodology The hydraulic and hydrologic modelling software called DRAINS was used to model the stormwater
network. DRAINS model was used to simulate what might occur during various rain events. DRAINS
accounts for pipe capacities as well as detention basins and associated weir structures.
The inlet pipe is typically designed for the 5 year ARI however the pipe capacity is expected to be
approximately 3m3/s. Therefore the 1, 2 and 5 year ARI events were assessed for the durations of 0.5,
1, 2 and 3 hours.
We used ARR 1987 rainfall data for our modelling with the upstream catchment area of 41.15 ha with a
46% impervious cover.
The DRAINS model layout is shown in Figure 7 below.
1680 Dendy Stormwater Managment VC.docx 11
Figure 7: DRAINS model layout (shown for 20 year ARI 2 hour storm)
1680 Dendy Stormwater Managment VC.docx 12
4.3. Key Hydraulic Features The key hydraulic features are described below. This has been a result of iterative investigations to
minimise the nuisance flows down the pathway.
Highflow bypass
• 1.5m weir at RL 4.25m in junction pit with existing 1200mm line and proposed offtake
• Upgraded 675mm pipe and 1200x300mm box culvert sections to single 2100x300mm box
culvert
Splitter box
• Interior area shall be a minimum 2.7 square meters
• Orifice (150mm diameter) directs low flows to raingarden
• 3m long weir at RL 3.5 to direct overflows to raingarden via 2 x 375mm diameter pipes
Leaky Retarding basin
• A storage volume of 500m3.
• Inflow from the splitter box with 2 x 600mm diameter pipes
• One overflow pit located in leaky retarding with overflow weir of 2 meters at RL 3.5m
• Overflow pipes connecting detention to raingarden via one 450 mm diameter pipes
Raingarden
• Low flow inlet from splitter box via 150mm diameter orifice
• Highflow inlet from splitter box via 2 x 375mm diameter pipes
• Secondary highflow inlet from detention via one 450mm diameter pipes
• All highflow inlets enter raingarden via surcharge pits
• The extended detention storage is approximately 180m3
• One overflow pits in the raingarden with a weir length of 4m
• One overflow 2700mm x 300mm box culvert connecting the raingarden to outlet
• The retaining wall level adjacent the raingarden is RL 2.52m.
4.4. Results The above key hydraulic features were used in the modelling to obtain the output noted in Table 3.
Storms greater than the 5 year ARI were tested to identify the likely maximum flowrate down the
pathway. The 20 year 2 hour storm yield 3.18m3/s which is just above expected pipe capacity.
Table 3: Peak flow modelling results
ARI Duration
(min)
Max Catchment Q
(m3/s)
Max Diverted Q
(m3/s)
Max Bypass Q
(m3/s)
Percentage Detention Used (%)
Raingarden Freeboard
(mm)
Raingarden Max Q out
(m3/s)
1
30 0.830 0.729 0.139 99 180 0.652
60 1.020 0.760 0.289 100 170 0.694
120 0.944 0.764 0.229 99 170 0.678
5
30 1.690 1.030 0.861 100 150 0.800
60 2.120 0.921 1.240 100 140 0.851
120 1.900 0.853 1.040 100 140 0.840
10
30 2.300 1.090 1.410 100 130 0.891
60 2.760 0.940 1.820 100 120 0.924
120 2.430 0.909 1.520 100 130 0.898
20 120 3.200 0.986 2.210 100 10 1.160
1680 Dendy Stormwater Managment VC.docx 13
4.5. Summary The storages and hydraulic features have been optimised to minimise the outflows onto the beach.
This is achieved by holding as much water as possible in the leaky retarding basin and the raingarden
to allow infiltration. The high percentage detention reported in Table 3 shows that the system is
effective to maximise infiltration even in the smaller events which cumulatively has a significant impact.
The peak flows onto the beach do not change dramatically for the larger storm events. This is mainly
due to the volume of these larger storms fill the detention storages and then spill. It should be noted
that the peak flows reported in Table 3 do not necessarily occur at the same time so the different peak
flows for each stream cannot readily be added together.
The peak flow out of the raingarden is a little higher than the diverted peak flow. This is related to the
timings of the various peaks and the additional catchments draining directly to the system
downstream of the diversion.
1680 Dendy Stormwater Managment VC.docx 14
5.0 CONCLUSIONS
5.1. Water Sensitive Urban Design Industry adopted best practice water quality improvement targets is readily achieved. However,
Council desires to exceed this target to minimise the potential of an unsightly outfall. The TSS
reduction is expected to be 84-91% and the flow reduction is 71-88%. The stormwater that bypasses
the treatment system directly influences the water quality performance.
The outfall being raised by approximately 300mm will allow beach sand back onto the bedrock which
should improve the amenity. The reduction in TSS and flow volumes (best shown in Figures 5 and 6
above) is expected to significantly reduce to maintenance burden at the outlet and is.
5.2. Peak Flow Assessment Management of the peak flows is optimised to maximise infiltration. The hydraulic structures are also
configured to pass the expected maximum flowrate of approximately 3.2m3/s without overtopping. If
the upstream drainage network did allow more than the maximum adopted then stormwater may
surcharge at the splitter pit and spill over the wall at the raingarden. The overland flows in this case
would not exceed the velocity to depth ratio of 0.4 and would be considered low hazard.
Although the peak flows are not significantly reduced through the system for larger events, the
frequency of outflows is reduced significantly as described above.
APPENDIX A
Functional Design Drawings
DENDY STREET BEACH IMPROVEMENTSDESIGN DEVELOPMENT
BRIGHTON, VICTORIA
REVISIONDESCRIPTION
SHEET INDEX & REVISION DETAIL
D06
D05
EXISTING CONDITION PLAN
D04
D03
C01
P02
SHEET
OVERALL LAYOUT
COVER SHEET
DETAILED LAYOUT A
D09
D08
D07
COVER SHEET, LOCATION MAP, SHEET INDEX
COVER 01
C
OV
ER
STORM_CONSULTING authorise the use of this drawing only for the purpose described by the status stamp shown above.This drawing should be read in conjunction with all relevant contracts, specifications, reports & drawings.
Advanced Copy - Not for ConstructionDrawing No. Sheet
Designed:
Checked:
Authorised:
Approved:
ofDate
CLIENT:
CAD FILE:
DENDY STREET BEACH IMPROVEMENTSDESIGN DEVELOPMENT
BRIGHTON BEACH VIC 3186
1680-DD-
16
80
-DD
-
1528.07.17
JACKSON CLEMENT BURROWS
ARCHITECTS
1 HARDWOOD PLACE
MELBOURNE VIC 3000 PHONE:(03) 9654 6227
1680-DD-OP.dwg
O.T / V.Z / K.L
R.W
R.W
www.stormconsulting.com.au
SYDNEY SUITE 12, 130 PACIFIC HWY, GREENWICH, NSW 2065 P 02 9499 4333MELBOURNE UNIT 7, 84 CHURCH ST, RICHMOND VIC 3121 P 03 9208 0111
A AMENDED PLAN IN ACCORDANCE WITH COUNCIL COMMENTS V.Z 28.07.2017
SPECIFICATION & TYPICAL DETAILS
DETAILED LAYOUT C
DETAILED LAYOUT D
DETAILED LAYOUT E
DETAILED LAYOUT B
D14
D13
RAMP LONG SECTION
D12
D11
D10
CATCHMENTS PLAN
D16
STORM DRAIN LONG SECTIONS A
STORM DRAIN LONG SECTIONS B
DETAILED LAYOUT F
RAINGARDEN AND SPLITTER BOX DETAILS
A
A
A
A
A
A
A
A
A
A
A
A
A
A
A
STORM_CONSULTING authorise the use of this drawing only for the purpose described by the status stamp shown above.This drawing should be read in conjunction with all relevant contracts, specifications, reports & drawings.
Advanced Copy - Not for ConstructionDrawing No. Sheet
Designed:
Checked:
Authorised:
Approved:
ofDate
CLIENT:
CAD FILE:
DENDY STREET BEACH IMPROVEMENTSDESIGN DEVELOPMENT
BRIGHTON BEACH VIC 3186
1680-DD-
16
80
-DD
-
1528.07.17
JACKSON CLEMENT BURROWS
ARCHITECTS
1 HARDWOOD PLACE
MELBOURNE VIC 3000 PHONE:(03) 9654 6227
1680-DD-OP.dwg
O.T / V.Z / K.L
R.W
R.W
www.stormconsulting.com.au
SYDNEY SUITE 12, 130 PACIFIC HWY, GREENWICH, NSW 2065 P 02 9499 4333MELBOURNE UNIT 7, 84 CHURCH ST, RICHMOND VIC 3121 P 03 9208 0111
A AMENDED PLAN IN ACCORDANCE WITH COUNCIL COMMENTS V.Z 28.07.2017
SPECIFICATIONS & TYPICAL DETAILS
S02 02
S0
2
•
•
•
£
£
•
•
•
•
“ ”
•
•
•
•
•
•
•
··
·
·
·
·
EXISTING CONDITION
P03 03
P0
3
STORM_CONSULTING authorise the use of this drawing only for the purpose described by the status stamp shown above.This drawing should be read in conjunction with all relevant contracts, specifications, reports & drawings.
Advanced Copy - Not for ConstructionDrawing No. Sheet
Designed:
Checked:
Authorised:
Approved:
ofDate
CLIENT:
CAD FILE:
DENDY STREET BEACH IMPROVEMENTSDESIGN DEVELOPMENT
BRIGHTON BEACH VIC 3186
1680-DD-
16
80
-DD
-
1528.07.17
JACKSON CLEMENT BURROWS
ARCHITECTS
1 HARDWOOD PLACE
MELBOURNE VIC 3000 PHONE:(03) 9654 6227
1680-DD-OP.dwg
O.T / V.Z / K.L
R.W
R.W
www.stormconsulting.com.au
SYDNEY SUITE 12, 130 PACIFIC HWY, GREENWICH, NSW 2065 P 02 9499 4333MELBOURNE UNIT 7, 84 CHURCH ST, RICHMOND VIC 3121 P 03 9208 0111
A AMENDED PLAN IN ACCORDANCE WITH COUNCIL COMMENTS V.Z 28.07.2017
STORM_CONSULTING authorise the use of this drawing only for the purpose described by the status stamp shown above.This drawing should be read in conjunction with all relevant contracts, specifications, reports & drawings.
Advanced Copy - Not for ConstructionDrawing No. Sheet
Designed:
Checked:
Authorised:
Approved:
ofDate
CLIENT:
CAD FILE:
DENDY STREET BEACH IMPROVEMENTSDESIGN DEVELOPMENT
BRIGHTON BEACH VIC 3186
1680-DD-
16
80
-DD
-
1528.07.17
JACKSON CLEMENT BURROWS
ARCHITECTS
1 HARDWOOD PLACE
MELBOURNE VIC 3000 PHONE:(03) 9654 6227
1680-DD-OP.dwg
O.T / V.Z / K.L
R.W
R.W
www.stormconsulting.com.au
SYDNEY SUITE 12, 130 PACIFIC HWY, GREENWICH, NSW 2065 P 02 9499 4333MELBOURNE UNIT 7, 84 CHURCH ST, RICHMOND VIC 3121 P 03 9208 0111
A AMENDED PLAN IN ACCORDANCE WITH COUNCIL COMMENTS V.Z 28.07.2017
OVERALL LAYOUT
P04 04
P0
4
1.1
STORM_CONSULTING authorise the use of this drawing only for the purpose described by the status stamp shown above.This drawing should be read in conjunction with all relevant contracts, specifications, reports & drawings.
Advanced Copy - Not for ConstructionDrawing No. Sheet
Designed:
Checked:
Authorised:
Approved:
ofDate
CLIENT:
CAD FILE:
DENDY STREET BEACH IMPROVEMENTSDESIGN DEVELOPMENT
BRIGHTON BEACH VIC 3186
1680-DD-
16
80
-DD
-
1528.07.17
JACKSON CLEMENT BURROWS
ARCHITECTS
1 HARDWOOD PLACE
MELBOURNE VIC 3000 PHONE:(03) 9654 6227
1680-DD-OP.dwg
O.T / V.Z / K.L
R.W
R.W
www.stormconsulting.com.au
SYDNEY SUITE 12, 130 PACIFIC HWY, GREENWICH, NSW 2065 P 02 9499 4333MELBOURNE UNIT 7, 84 CHURCH ST, RICHMOND VIC 3121 P 03 9208 0111
A AMENDED PLAN IN ACCORDANCE WITH COUNCIL COMMENTS V.Z 28.07.2017
DETAILED LAYOUT A
P05 05
P0
5
1.1
STORM_CONSULTING authorise the use of this drawing only for the purpose described by the status stamp shown above.This drawing should be read in conjunction with all relevant contracts, specifications, reports & drawings.
Advanced Copy - Not for ConstructionDrawing No. Sheet
Designed:
Checked:
Authorised:
Approved:
ofDate
CLIENT:
CAD FILE:
DENDY STREET BEACH IMPROVEMENTSDESIGN DEVELOPMENT
BRIGHTON BEACH VIC 3186
1680-DD-
16
80
-DD
-
1528.07.17
JACKSON CLEMENT BURROWS
ARCHITECTS
1 HARDWOOD PLACE
MELBOURNE VIC 3000 PHONE:(03) 9654 6227
1680-DD-OP.dwg
O.T / V.Z / K.L
R.W
R.W
www.stormconsulting.com.au
SYDNEY SUITE 12, 130 PACIFIC HWY, GREENWICH, NSW 2065 P 02 9499 4333MELBOURNE UNIT 7, 84 CHURCH ST, RICHMOND VIC 3121 P 03 9208 0111
A AMENDED PLAN IN ACCORDANCE WITH COUNCIL COMMENTS V.Z 28.07.2017
DETAILED LAYOUT B
P06 06
P0
6
1.1
STORM_CONSULTING authorise the use of this drawing only for the purpose described by the status stamp shown above.This drawing should be read in conjunction with all relevant contracts, specifications, reports & drawings.
Advanced Copy - Not for ConstructionDrawing No. Sheet
Designed:
Checked:
Authorised:
Approved:
ofDate
CLIENT:
CAD FILE:
DENDY STREET BEACH IMPROVEMENTSDESIGN DEVELOPMENT
BRIGHTON BEACH VIC 3186
1680-DD-
16
80
-DD
-
1528.07.17
JACKSON CLEMENT BURROWS
ARCHITECTS
1 HARDWOOD PLACE
MELBOURNE VIC 3000 PHONE:(03) 9654 6227
1680-DD-OP.dwg
O.T / V.Z / K.L
R.W
R.W
www.stormconsulting.com.au
SYDNEY SUITE 12, 130 PACIFIC HWY, GREENWICH, NSW 2065 P 02 9499 4333MELBOURNE UNIT 7, 84 CHURCH ST, RICHMOND VIC 3121 P 03 9208 0111
A AMENDED PLAN IN ACCORDANCE WITH COUNCIL COMMENTS V.Z 28.07.2017
DETAILED LAYOUT C
P07 07
P0
7
1.1
Δ
Δ
STORM_CONSULTING authorise the use of this drawing only for the purpose described by the status stamp shown above.This drawing should be read in conjunction with all relevant contracts, specifications, reports & drawings.
Advanced Copy - Not for ConstructionDrawing No. Sheet
Designed:
Checked:
Authorised:
Approved:
ofDate
CLIENT:
CAD FILE:
DENDY STREET BEACH IMPROVEMENTSDESIGN DEVELOPMENT
BRIGHTON BEACH VIC 3186
1680-DD-
16
80
-DD
-
1528.07.17
JACKSON CLEMENT BURROWS
ARCHITECTS
1 HARDWOOD PLACE
MELBOURNE VIC 3000 PHONE:(03) 9654 6227
1680-DD-OP.dwg
O.T / V.Z / K.L
R.W
R.W
www.stormconsulting.com.au
SYDNEY SUITE 12, 130 PACIFIC HWY, GREENWICH, NSW 2065 P 02 9499 4333MELBOURNE UNIT 7, 84 CHURCH ST, RICHMOND VIC 3121 P 03 9208 0111
A AMENDED PLAN IN ACCORDANCE WITH COUNCIL COMMENTS V.Z 28.07.2017
DETAILED LAYOUT D
P08 08
P0
8
1.1
STORM_CONSULTING authorise the use of this drawing only for the purpose described by the status stamp shown above.This drawing should be read in conjunction with all relevant contracts, specifications, reports & drawings.
Advanced Copy - Not for ConstructionDrawing No. Sheet
Designed:
Checked:
Authorised:
Approved:
ofDate
CLIENT:
CAD FILE:
DENDY STREET BEACH IMPROVEMENTSDESIGN DEVELOPMENT
BRIGHTON BEACH VIC 3186
1680-DD-
16
80
-DD
-
1528.07.17
JACKSON CLEMENT BURROWS
ARCHITECTS
1 HARDWOOD PLACE
MELBOURNE VIC 3000 PHONE:(03) 9654 6227
1680-DD-OP.dwg
O.T / V.Z / K.L
R.W
R.W
www.stormconsulting.com.au
SYDNEY SUITE 12, 130 PACIFIC HWY, GREENWICH, NSW 2065 P 02 9499 4333MELBOURNE UNIT 7, 84 CHURCH ST, RICHMOND VIC 3121 P 03 9208 0111
A AMENDED PLAN IN ACCORDANCE WITH COUNCIL COMMENTS V.Z 28.07.2017
DETAILED LAYOUT E
P09 09
P0
9
1.1
Δ
Δ
Δ
STORM_CONSULTING authorise the use of this drawing only for the purpose described by the status stamp shown above.This drawing should be read in conjunction with all relevant contracts, specifications, reports & drawings.
Advanced Copy - Not for ConstructionDrawing No. Sheet
Designed:
Checked:
Authorised:
Approved:
ofDate
CLIENT:
CAD FILE:
DENDY STREET BEACH IMPROVEMENTSDESIGN DEVELOPMENT
BRIGHTON BEACH VIC 3186
1680-DD-
16
80
-DD
-
1528.07.17
JACKSON CLEMENT BURROWS
ARCHITECTS
1 HARDWOOD PLACE
MELBOURNE VIC 3000 PHONE:(03) 9654 6227
1680-DD-OP.dwg
O.T / V.Z / K.L
R.W
R.W
www.stormconsulting.com.au
SYDNEY SUITE 12, 130 PACIFIC HWY, GREENWICH, NSW 2065 P 02 9499 4333MELBOURNE UNIT 7, 84 CHURCH ST, RICHMOND VIC 3121 P 03 9208 0111
A AMENDED PLAN IN ACCORDANCE WITH COUNCIL COMMENTS V.Z 28.07.2017
DETAILED LAYOUT F
P10 10
P1
0
1.1
Le
ve
l
-2
-1
0
1
2
3
4
5
6
7
8
9
10
-2
-1
0
1
2
3
4
5
6
7
8
9
10
STORM_CONSULTING authorise the use of this drawing only for the purpose described by the status stamp shown above.This drawing should be read in conjunction with all relevant contracts, specifications, reports & drawings.
Advanced Copy - Not for ConstructionDrawing No. Sheet
Designed:
Checked:
Authorised:
Approved:
ofDate
CLIENT:
CAD FILE:
DENDY STREET BEACH IMPROVEMENTSDESIGN DEVELOPMENT
BRIGHTON BEACH VIC 3186
1680-DD-
16
80
-DD
-
1528.07.17
JACKSON CLEMENT BURROWS
ARCHITECTS
1 HARDWOOD PLACE
MELBOURNE VIC 3000 PHONE:(03) 9654 6227
1680-DD-OP.dwg
O.T / V.Z / K.L
R.W
R.W
www.stormconsulting.com.au
SYDNEY SUITE 12, 130 PACIFIC HWY, GREENWICH, NSW 2065 P 02 9499 4333MELBOURNE UNIT 7, 84 CHURCH ST, RICHMOND VIC 3121 P 03 9208 0111
A AMENDED PLAN IN ACCORDANCE WITH COUNCIL COMMENTS V.Z 28.07.2017
RAMP LONG SECTION
D11 11
D1
1
STORM_CONSULTING authorise the use of this drawing only for the purpose described by the status stamp shown above.This drawing should be read in conjunction with all relevant contracts, specifications, reports & drawings.
Advanced Copy - Not for ConstructionDrawing No. Sheet
Designed:
Checked:
Authorised:
Approved:
ofDate
CLIENT:
CAD FILE:
DENDY STREET BEACH IMPROVEMENTSDESIGN DEVELOPMENT
BRIGHTON BEACH VIC 3186
1680-DD-
16
80
-DD
-
1528.07.17
JACKSON CLEMENT BURROWS
ARCHITECTS
1 HARDWOOD PLACE
MELBOURNE VIC 3000 PHONE:(03) 9654 6227
1680-DD-OP.dwg
O.T / V.Z / K.L
R.W
R.W
www.stormconsulting.com.au
SYDNEY SUITE 12, 130 PACIFIC HWY, GREENWICH, NSW 2065 P 02 9499 4333MELBOURNE UNIT 7, 84 CHURCH ST, RICHMOND VIC 3121 P 03 9208 0111
A AMENDED PLAN IN ACCORDANCE WITH COUNCIL COMMENTS V.Z 28.07.2017
CATCHMENT PLAN
P12 12
P1
2
STORM_CONSULTING authorise the use of this drawing only for the purpose described by the status stamp shown above.This drawing should be read in conjunction with all relevant contracts, specifications, reports & drawings.
Advanced Copy - Not for ConstructionDrawing No. Sheet
Designed:
Checked:
Authorised:
Approved:
ofDate
CLIENT:
CAD FILE:
DENDY STREET BEACH IMPROVEMENTSDESIGN DEVELOPMENT
BRIGHTON BEACH VIC 3186
1680-DD-
16
80
-DD
-
1528.07.17
JACKSON CLEMENT BURROWS
ARCHITECTS
1 HARDWOOD PLACE
MELBOURNE VIC 3000 PHONE:(03) 9654 6227
1680-DD-OP.dwg
O.T / V.Z / K.L
R.W
R.W
www.stormconsulting.com.au
SYDNEY SUITE 12, 130 PACIFIC HWY, GREENWICH, NSW 2065 P 02 9499 4333MELBOURNE UNIT 7, 84 CHURCH ST, RICHMOND VIC 3121 P 03 9208 0111
A AMENDED PLAN IN ACCORDANCE WITH COUNCIL COMMENTS V.Z 28.07.2017
DRAINAGE LONG SECTION A
L13 13
L1
3
STORM_CONSULTING authorise the use of this drawing only for the purpose described by the status stamp shown above.This drawing should be read in conjunction with all relevant contracts, specifications, reports & drawings.
Advanced Copy - Not for ConstructionDrawing No. Sheet
Designed:
Checked:
Authorised:
Approved:
ofDate
CLIENT:
CAD FILE:
DENDY STREET BEACH IMPROVEMENTSDESIGN DEVELOPMENT
BRIGHTON BEACH VIC 3186
1680-DD-
16
80
-DD
-
1528.07.17
JACKSON CLEMENT BURROWS
ARCHITECTS
1 HARDWOOD PLACE
MELBOURNE VIC 3000 PHONE:(03) 9654 6227
1680-DD-OP.dwg
O.T / V.Z / K.L
R.W
R.W
www.stormconsulting.com.au
SYDNEY SUITE 12, 130 PACIFIC HWY, GREENWICH, NSW 2065 P 02 9499 4333MELBOURNE UNIT 7, 84 CHURCH ST, RICHMOND VIC 3121 P 03 9208 0111
A AMENDED PLAN IN ACCORDANCE WITH COUNCIL COMMENTS V.Z 28.07.2017
DRAINAGE LONG SECTION B
L14 14
L1
4
STORM_CONSULTING authorise the use of this drawing only for the purpose described by the status stamp shown above.This drawing should be read in conjunction with all relevant contracts, specifications, reports & drawings.
Advanced Copy - Not for ConstructionDrawing No. Sheet
Designed:
Checked:
Authorised:
Approved:
ofDate
CLIENT:
CAD FILE:
DENDY STREET BEACH IMPROVEMENTSDESIGN DEVELOPMENT
BRIGHTON BEACH VIC 3186
1680-DD-
16
80
-DD
-
1501.08.17
JACKSON CLEMENT BURROWS
ARCHITECTS
1 HARDWOOD PLACE
MELBOURNE VIC 3000 PHONE:(03) 9654 6227
1680-DD-OP.dwg
O.T / V.Z / K.L
R.W
R.W
www.stormconsulting.com.au
SYDNEY SUITE 12, 130 PACIFIC HWY, GREENWICH, NSW 2065 P 02 9499 4333MELBOURNE UNIT 7, 84 CHURCH ST, RICHMOND VIC 3121 P 03 9208 0111
A AMENDED PLAN IN ACCORDANCE WITH COUNCIL COMMENTS V.Z 28.07.2017
RAINGARDEN AND SPLITTER BOX DETAILS
D15 15
D1
5