department of civil engineering, · pdf fileintegrated master in civil engineering sanitary...
TRANSCRIPT
2015/2016 1
José Saldanha Matos (responsible)
António Jorge Monteiro
Filipa Ferreira
Ana Galvão
INTEGRATED MASTER IN CIVIL ENGINEERING
SANITARY ENGINEERING
DEPARTMENT OF CIVIL ENGINEERING,
ARCHITECTURE AND GEORESOURCES
2015/2016 2
SANITARY ENGINEERING Lesson 1 / SUMMARY
Objectives and course program.
Evaluation methodology. Classes plan.
Urban Water Cycle.
System components.
2015/2016 3
SANITARY ENGINEERING MAIN OBJECTIVES
Develop skills to design infrastructures for water supply and
wastewater disposal in urban areas, namely:
Water transmission and storage systems
Water distribution systems
Wastewater sewage systems
Attain knowledge in concepts such as:
storm water drainage in urban areas
Treatment schemes (for water supply and wastewater)
Basic parameters for water quality characterization
Water distribution and wastewater simplified systems for
developing countries
2015/2016 4
SANITARY ENGINEERING COURSE PROGRAM
1- Scope and objectives of environmental sanitation. Fundamental concepts. Urban
water cycle. Basic data.
2 - Water supply systems: historical perspective and fundamental concepts
2.1 - Intake and water supply works;
2.2 - Pumping Facilities;
2.3 - Reservoirs / tanks;
2.4 - Water distribution network;
2.5 - Simplified water distribution systems for developing countries.
3 - Wastewater systems: historical and current perspective
3.1 - Source, quantification and nature of wastewater;
3.2 – Design and sizing of wastewater drainage network;
3.3 – Drainage system components;
3.3 – Appurtenances for drainage systems;
3.5 – Storm water drainage in urban areas.
3.6 - Special works (inverted syphon, overflow and purging installations)
4 - Introduction to water quality and pollution control
4.1 – Water quality, water and wastewater treatment basic concepts;
4.2 – Simplified sanitation systems (drainage and treatment) for developing countries.
2015/2016 5
SANITARY ENGINEERING Method of evaluation
Final written exam at the end of the semester (40%)
(Minimum grade 9,50).
Evaluation of 2 projects developed during practical classes, with
“power point” presentation and discussion
(60%) Project 1: Study of a water supply;
Project 2: Project of a water distribution network and a wastewater
sewage network.
2015/2016 6
14 weeks of classes;
1 Theoretical lesson per week, (2h each);
1 Practical lesson per week (3h each);
3 or 4 students per group;
Each practical lesson has a maximum of 7 groups-
The practical lesson do not have a general presentation.
Doubts about the projects will be clarified, usually for
each group individually.
SANITARY ENGINEERING Lesson planning
2015/2016 7
WATER AND SEWAGE SYSTEMS URBAN WATER CYCLE – IMPACT ON AQUIFERS
2015/2016 8
WATER AND SEWAGE SYSTEMS URBAN WATER CYCLE – IMPACT ON AQUIFERS
2015/2016 9
WATER AND SEWAGE SYSTEMS HISTORICAL REFERENCES OF SANYTARY SYSTEMS
Historical References
3000 BC – Mohengo-Doro (Hindu civilization, nowadays Pakistan)
1000 a 3000 BC–Cnossos Palace, Island of Crete
500 BC – Roman Cloaca Máxima (cloacarium tax and clocarium curators )
200 AC – Caracala Therms – Rome public water supply
1650 AC – 1st underground sewer main (London)
1800 AC – Paris sewers/tunnels
1870 AC – 1st separative systems (Lenox and Memphis, USA)
Ruins of a 1st century public latrine.
Ephessos, Turkey
Boat tour to the Paris
sewers, 1896
2015/2016 10
PORTUGUESE HISTORICAL REFERENCES
1400 – Limpeza dos canos (D. João II)
1748 – Aqueduto da Águas Livres (Water supply to Lisbon)
1755 – Methodical canalization (unitary system mesh )
Lisbon: mains made of cascões, or “rateiros”
1950 – Setúbal “canecos” on the doorway for the of excreta retrieval
Saimel (Pombalino) Cascões
WATER AND SEWAGE SYSTEMS HISTORICAL REFERENCES OF SANYTARY SYSTEMS
2015/2016 11
BY THE END OF THE XIX CENTURY AND BEGGINING OF XX CENTURY
THERE WAS THE TRUE TECNOLOGICAL REVOLUCION
1 – Utilization of cast iron on pressured pipes.
2 – Sewer networks (clay and stoneware).
3 – Concrete mains, circular shape.
HYGIENIST MOVEMENT
Concern with public health
Analogy between cities’ systems (water and sewer) and the human
body and blood circulatiiom
Circular (ceramic stoneware) Cast iron
WATER AND SEWAGE SYSTEMS HISTORICAL REFERENCES OF SANYTARY SYSTEMS
2015/2016 12
WATER AND SEWAGE SYSTEMS URBAN WATER CYCLE – SYSTEM’S COMPONENTS
1. Water catchment
2. WTP
3. Reservoir
4. Distribution system
5. Water use
6. Sewer system
7. WWTP
8. Discharge
3
1
2
4 5 6
7
8
2015/2016 13
Components Structures Objective / function
Intake
Water catchment
Catch raw water (superficial or subterraneous) as
described on the Portguese legislation (DL 236/98,
de 1 de Agosto), in agreement with the needs and
availability.
Treatment
Water treatment plant
WTP
Produces, from raw water, drinkable water. In
accordance with the quality regulations (DL
306/2007, de 27 de Agosto - Anexo I).
Pumping stations
Booster pumping
stations
Pump the water (raw or treated) between a lower
elevation point and one or more higher locations.
Transmission
Transmission pipes,
aqueducts, and
channels
Set of works designed to transport water from its
origin to its distribution. This transport can be done
under pressure (pumped or gravitationally) or with
free surface (aqueducts or channels).
WATER AND SEWAGE SYSTEMS URBAN WATER CYCLE – SYSTEM’S COMPONENTS
2015/2016 14
The production and transport
system is know for its 3 sub-
systems that have over 700 km
of water mains, with a nominal
capacity that can go up to 1 000
000 m³/day and a storage
capacity of about 337 230 m³.
These sub-systems have 2
WTP (Asseisseira e Vale da
Pedra), 32 pumping stations, 36
reservoirs and 19 chlorination
posts.
WATER DISTRIBUTION AND SUPPLY SYSTEMS EPAL, S.A. PRODUCTION AND TRANSPORT SYSTEM
2015/2016 15
The water produces by the 3 sub-
systems is transported by its
respective mains (Castelo do
Bode, do Tejo e do Alviela ) and
one additional main at Vila Franca
de Xira-Telheiras, having transport
capacity of 240 000 m³/day and
the Circunvalação main that has a
capacity of 410 000 m³/day.
WATER DISTRIBUTION AND SUPPLY SYSTEMS EPAL, S.A. PRODUCTION AND TRANSPORT SYSTEM
2015/2016 16
Water intake tower
Reservoir
walkway
WATER DISTRIBUTION AND SUPPLY SYSTEMS SYSTEM’S COMPONENTS WATER CATCHMENT AT CASTELO DO BODE / EPAL, S.A.
2015/2016 17
Hydropneumatic (Pressure) Tanks
Elevation main
WATER DISTRIBUTION AND SUPPLY SYSTEMS PUMPING STATION AND ELEVATION MAIN AT CASTELO DO BODE /
EPAL, S.A. [1st AND 2nd PHASES- 500 000 m3/day]
Pumping station at Castelo do Bode
2015/2016 18
Main Building
P de transformação
Reagent’s storage
Sludge dehidration
Thickeners
Treated water storage
CO2 and chlorine storage
Mistura rápida Floculation
Filtraton
Cleaning filter’s water
storage
Workshops
WATER DISTRIBUTION AND SUPPLY SYSTEMS SYSTEM COMPONENTS / TREATMENT
WTP ASSEISSEIRA / EPAL, S.A. [1st AND 2nd PHASES- 500 000 m3/day]
2015/2016 19
WATER DISTRIBUTION AND SUPPLY SYSTEMS SYSTEM COMPONENTS / TREATMENT
WTP ASSEISSEIRA / EPAL, S.A. [CURRENTLY - 625 000 m3/day]
2015/2016 20
WATER DISTRIBUTION AND SUPPLY SYSTEMS SYSTEM COMPONENTS / PUMPING STATIONS
Pumping stations
2015/2016 21
Components Structures Objective / Function
Storage
Tanks
Regulates and compensates the fluctuations of
the consumption when compared to the intake.
It’s also the storage for emergencies (firefighting
or other cases of acidental or involuntary
interruption of the system upstream).
It also balances the pressures on the distribution
network.
It regulates the operation of the pumps.
Distribution
Water distribution
networks
Set of pipes and appurtenances, as joints, gate or
flushing valves, blow-offs, air release valves,
hydrants and metering instruments that aims to
convey water for distribution.
Household
connection Water connections
Ensure the household supply of water, since the
public network until the boundaries of the
property, with good conditions of flow and
pressure.
Interior Distribution Building water piping
Systems
Set of pipe and other elements that ensures the
water distribution inside the buildings.
WATER DISTRIBUTION AND SUPPLY SYSTEMS URBAN WATER CYCLE – SYSTEM COMPONENTS
2015/2016 22
WATER DISTRIBUTION AND SUPPLY SYSTEMS SYSTEM COMPONENTS – STORAGE TANKS
RESERVOIR’S MANEUVRE CHAMBER WITH TWO CELLS
2015/2016 23
WATER DISTRIBUTION AND SUPPLY SYSTEMS SYSTEM COMPONENTS / PUBLIC WATER DISTRIBUTION
WATER DISTRIBUTION NETWORK
2015/2016 24
WATER DISTRIBUTION AND SUPPLY SYSTEMS SYSTEM COMPONENTS / INTERIOR DISTRIBUTION
BUILDING WATER PIPING SYSTEMS
2015/2016 25
WASTEWATER DRAINAGE SYSTEMS AND FINAL DESTINATION SYSTEM COMPONENTS
2015/2016 26
Components Structures Objective / Function
Interior drainage
network
Wastewater building
drainage pipes
Set of pipes and accessory items to collect indoor
wastewater.
Household
connection Wastewater connections
Ensure the collection of wastewater from the
property boundary to the public network.
Drainage System Wastewater collection
system
Set of pipes and accessories, such as manholes, in
order to collect the wastewater to interceptors and
outfalls.
Transporte para
ETAR e destino Final
Wastewater interception
sewer
Set of pipes and accessories such as manholes,
intended to carry wastewater to the treatment plant
or to final destination.
Wastewater
treatment
Wastewater treatment
plant
TTreat the wastewater in order to produce an
effluent compatible with its reuse or to be
discharged in to the receiving environment.
WASTEWATER DRAINAGE SYSTEMS AND FINAL DESTINATION URBAN WATER CYCLE – SYSTEM COMPONENTS
2015/2016 27
Lesson 2
Quantitative basis for projects of water supply and sanitation;
Design flows;
Groundwater and surface water abstractions.
Water supply pipeline in plant
SANITARY ENGINEERING LESSON 2 / SUMMARY
2015/2016 28
Goal:
Assess, as accurate as possible, the quantities of water for which
the system components must be designed.
Main Elements:
A) Design horizon;
B) Design population;
C) Design flows;
D) Served area;
E) Design Hydrology;
WATER SUPPLY AND DISTRIBUTION SYSTEMS QUANTITATIVE BASIS FOR PROJECTS (WATER AND SEWER)
2015/2016 29
WATER SUPPLY AND DISTRIBUTION SYSTEMS QUANTITATIVE BASIS FOR PROJECTS / PROJECT HORIZON
Definition:
Number of years for which the system or structures and equipment
have to work in good conditions
Factores:
Useful life of civil works and equipment
Easiness or difficulties to expand the system);
Preditcion of demographic trends;
Interest rate during the amortization period of the investment
Operating conditions during the first years of operation;
Financial capacity of the managing body;
Water resources availability;
2015/2016 30
Type of structure Likely
Duration (years)
Design Horizon (years)
Drilled wells
50 to 60
20 to 30
Water intake
40 to 50
20 to 40
WATER SUPPLY AND DISTRIBUTION SYSTEMS QUANTITATIVE BASIS FOR PROJECTS / USEFUL LIFE AND PROJECT HORIZON
2015/2016 31
Type of structure Likely
Duration (years)
Design Horizon (years)
Large trunk pipes 60 to 80 40 to 50
Storage and elevated tanks
80 to 100 20 to 40
WATER SUPPLY AND DISTRIBUTION SYSTEMS QUANTITATIVE BASIS FOR PROJECTS / USEFUL LIFE AND PROJECT HORIZON
2015/2016 32
Type of structure Likely
Duration (years)
Design Horizon (years)
Pumping stations
(civil works) 40 to 60 20 to 40
Pumps and electromechanical
equipment 25 to 35 20 to 25
WATER SUPPLY AND DISTRIBUTION SYSTEMS QUANTITATIVE BASIS FOR PROJECTS / USEFUL LIFE AND PROJECT HORIZON
2015/2016 33
Type of structure Likely
Duration (years)
Design Horizon (years)
Water treatment plants
(civil works)
40 to 60
20 to 40
Water treatment plants
(equipment)
20 to 30
20 to 25
WATER SUPPLY AND DISTRIBUTION SYSTEMS QUANTITATIVE BASIS FOR PROJECTS / USEFUL LIFE AND PROJECT HORIZON
2015/2016 34
Type of structure Likely
Duration (years)
Design Horizon (years)
Water supply pipe networks
30 to 40
Maximum
urban
expansion
Sewer networks
30 to 40
Maximum
urban
expansion
WATER SUPPLY AND DISTRIBUTION SYSTEMS QUANTITATIVE BASIS FOR PROJECTS / USEFUL LIFE AND PROJECT HORIZON
2015/2016 35
Definition:
Population to be served on the design horizon
Design Population:
Methods:
Extrapolation or regression methods;
a. Linear P20= P0 + Ka ( t20 - t0 )
b. Geometric P20= P0 (1+Kg )(t20
- t0)
Comparison;
Visual extrapolation;
Decreasing growth rate;
Curve logistic;
Piecemeal analysis;
Employment prediction;
Information of Master
Plans
Base elements:
Census and voter registration.
Problems: Migrations.
WATER SUPPLY AND DISTRIBUTION SYSTEMS QUANTITATIVE BASIS FOR PROJECTS / PROJECT POPULATION
2015/2016 36
Demand components:
Permanent or resident population;
Temporary population;
Public Entities;
Commercial Activities;
Industry;
Agricultural and livestock activities;
Firefighting;
Emergencies;
Losses.
Per capita consumption:
Relation between the total annual demand and the number of
inhabitants per day of the year [L/(hab.day)].
Per capita consumption is an average characteristic of the
demand;
Difficulties on the assignment of a value for design horizon.
WATER SUPPLY AND DISTRIBUTION SYSTEMS QUANTITATIVE BASIS FOR PROJECTS / PROJECT FLOWS
2015/2016 37
Factors afecting per capita flow:
1. Population
Minimum demand dicated by the portuguese legislation (Regulamento Geral dos
Sistemas Públicos e Prediais de Distribuição de Água e de Drenagem de Águas Residuais
(RGAAR)) (Dec. Reg 23/95, 23 August):
80 L/(hab.day) until 1000 hab.
100 L/(hab.day) from 1000 hab. to 10 000 hab.
125 L/(hab.day) from 10 000 hab. to 20 000 hab.
150 L/(hab.day) from 20 000 hab. to 50 000 hab.
175 L/(hab.day) aborve 50 000 hab.
2. Climatic conditions
3. Personal hygiene habits
4. The existence, or not, of outdoor
networks
5. Type of wastewater disposal
6. Conservation condition of the system
7. Tariff structure
8. Inclusion of small commercial
activities, public (5 a 20 L/(hab.
day)) or industrial.
9. Water losses (minimum to be
consxidered (RGAAR) 10% of total
flow)
WATER SUPPLY AND DISTRIBUTION SYSTEMS QUANTITATIVE BASIS FOR PROJECTS / PROJECT FLOWS
2015/2016 38
Type of establishment Demand
Wineries
Schools
Offices
Rest stations
Garages
Dairy
Laundries
Slaughterhouse (large animals)
Abattoir (midsize)
Bakeries
Pensions (no kitchen or laundry)
Restaurants
5 L /litro de produto
50 L /(student.day)
50 L /(worker.day)
150 L /(vehicle.day)
50 L /(vehicle.day)
4-12 L/(kg of product)
30 L/(kg of laundry)
300 L/(head)
150 L/(head)
0,6 L/(kg of flour)
120 L/(guest.day)
25 L/meal
Type of animal Per capita consumption
Cattle
Goats
Sheep
Equines
Chickens
Turkeys
Pigs
Cattle (dairy cows)
40 (L/animal/day)
8 (L/animal/day)
8 (L/animal/day)
40 (L/animal/day)
0,4 (L/animal/day)
0,75 (L/animal/day)
10 (L/animal/day)
75 (L/animal/day)
WATER SUPPLY AND DISTRIBUTION SYSTEMS QUANTITATIVE BASIS FOR PROJECTS / PROJECT FLOWS
2015/2016 39
Annual average flow – Qm:
Product between population and per capita demand:
Qm = Per capita demand x Population [L3T-1]
Peak flow – Qp:
Defines the characteristics of extreme demand;
Determined by multiplying the average flow by the appropriate peak
factor :
Qp = fp x Qm [L3T-1]
Usually defined by:
Monthly peak flow (average flow for the month of highest
consumption);
Daily peak flow (average flow of the day higher consumption);
Hourly peak flow (average flow of the hour of greatest
consumption).
WATER SUPPLY AND DISTRIBUTION SYSTEMS QUANTITATIVE BASIS FOR PROJECTS / PROJECT FLOWS
2015/2016 40
Spring Radial well
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER INTAKE / GROUDWATER ABSTRACTIONS
2015/2016 41
Problems in coastal areas : saline intrusion
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER INTAKE / GROUDWATER ABSTRACTIONS
2015/2016 42
Water intake in river or bayou (longitudinal view)
Water intake and pumping
station (top view)
SISTEMAS DE ABASTECIMENTO E DISTRIBUIÇÃO DE ÁGUA CAPTAÇÕES DE ÁGUA / CAPTAÇÃO DE ÁGUAS SUPERFICIAIS WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER INTAKE / SURFACE WATER ABSTRACTIONS
2015/2016 43
Centrifugal Pumps with vertical axis
for direct water intake Mobile water intakes
Floating water intake
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER INTAKE / SURFACE WATER ABSTRACTIONS
2015/2016 44
Uptake in bayou
Direct uptake in the upstream of an earth dam
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER INTAKE / SURFACE WATER ABSTRACTIONS
2015/2016 45
Water intake in a reservoir
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER INTAKE / SURFACE WATER ABSTRACTIONS
2015/2016 46
Design constraints
Topographic problems
Adaptation of channel’s layout /aqueduct
to the topography of the terrain.
Special obstacles
Steep valleys crossings
Inverted siphons. Aqueducts)
Crossing hills or mountains
Tunnels
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER INTAKE / WATER CHANNELS WITH FREE SURFACE FLOW
2015/2016 47
Transposition of topographic obstacles (streams, valleys and ridge lines);
Minimum depth for laying the pipes (1 m);
Minimum slopes in ascending (3 ‰) and descending (5 ‰) reactors;
0,5 % 0,5 % 0,5 % 0,3 % 0,3 %
air air air air
Water supply pipeline in plant:
The study of a pipeline requires the analysis of the
layout conditions outlined, on plant and on
longitudinal profile.
Constraints:
Extension (as short as possible with large diameters and
large radius of curvature);
Pipe pressure;
Easiness of construction, repair and surveillance
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER INTAKE / PRESSURIZED FLOW
2015/2016 48
Source: Water Supply and Waste-Water Disposal – Fair et al.
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEM / PRESSURIZED FLOW LONGITUDINAL PROFILE OF A SUPLLY MAIN PRESSURIZED TROUGH GRAVITY
2015/2016 49
LESSON 3
Design flows
Velocity criteria: hydraulic design of water supply pipelines
Design of pipelines to pressure
Materials
SANITARY ENGINEERING LESSON 3 / SUMMARY
2015/2016 50
Flow speed limitations:
Reasons for limiting the maximum speed :
Overpressure caused by variable flow rate;
Excessive and uneconomic load losses.
Reasons for limiting the minimum speed :
Water quality inside the mains;
Self-cleaning and settling of solids.
Flow speed :
Pumped pressurized stretches
0,6 m/s ≤ V ≤ 1,5 m/s
Gravity pressurized stretches
0,3 m/s ≤ V ≤ 1,5 m/s
Custo de Energia (€)
0
1000
2000
3000
4000
5000
6000
7000
8000
0 200 400 600 800
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPLLY SYSTEM / HYDRAULIC DESIGN OF MAIN WATER PIPES
2015/2016 51
daily work period:
Transport by boost pumping:
Except in special cases, 16h/day
(NP 837);
The reliability of mechanical
systems may allows 20 h/day,
with reasonable safety.
Gravitatic transport:
Maximum daily transport 24 h/day.
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEMS / HYDRAULIC SIZING OF INTAKE PIPES
2015/2016 52
Pipe design flow:
Sizing for the highest demand day :
Qdim = Kt x Kp x fD x Qm
Sizing for the highest demand month:
Qdim = Kt x Kp x fM.Qm
Where;
Kt – factor of the duration of the transport = (24 h/nº of transport hours);
Kp – factor of losses (1,05 to 1,10);
fM ; fD – monthly peak factor ou daily peak factor;
Qm – average flow.
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEMS / HYDRAULIC SIZING OF INTAKE PIPES
2015/2016 53
Choice of technical viable diameters:
Qdim (m3/s) => Q = V.S => Diameter range
Vmax, Vmin (m/s) => S = pi.D2/4 => D (m) = (4 Q / pi.V)0.5
Dmin Dmax
D1 D2 D3
Gravítico (Qdim 40)
Dmin Dmax
D1 D2
Pumped
(Qdim 20)
(Qdim 40)
Di = commercial diameters that exist on the diameter range
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEM / HYDRAULIC DESIGN OF MAIN WATER PIPES
2015/2016 54
In a gravitic system (without booster pump):
When choosing the technically feasible diameter the available energy must be
analysed.
DetermineJmáx = Dz / L
Use the head loss formula (Colebrook-White ou Manning Strickler),
to determine Dmin’
Dmin Dmax
D1 D2 D3
Gravitaional (Qdim 40)
Dmin’
Dz L
Jmax
1
Dmin’
D<Dmin’
Dynamic energy line (LED)
D>Dmin’
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEM / HYDRAULIC DESIGN OF MAIN WATER PIPES CHOOSING THE RIGHT DIAMETER
The most economical diameter is the minimum diameter (or the
combination of) which is within the range of Dmax and Dmin (checks the two
criteria) and allows the transportation of water to the desired level.
2015/2016 55
In order to determine the most economic diameter it is necessary to account,
besides the costs of installing the piping, the energy cost.
This way, all the possible diameters are analyzed (D1 and D2) and the
energetic burden of the different viable energy solutions assessed.
DN
€ Total Cost
Pipes Cost
Running Costs
(energy)
Dec
Qdim 40
Dmin Dmax
D1 D2
Qdim 20
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEMS / HYDRAULIC DESIGN OF MAIN WATER PIPES CHOOSING THE RIGHT DIAMETER
In pumping or mixed system (case of a valley)
Economical diameter concept
2015/2016 56
Colebrook- White Formula
More accuracy +/- 15% error
More suitable for water supply systems usually for long pipeline
systems with big continuous head losses
Manning Strickler Formula
Suitable for water supply network and surface flow (like drainage
systems or channels/rivers)
2/13/2 JRSKQ S
JD2gD
2,51
3,7D
k
2gJπ
Q2D
nnn
2/510
2/5
1n log
n
210
2
1nJD2gD
2,51
3,7D
k
D8g
UJ log
Ks PE,PVC = 100-120 m1/3s-1
(water20ºC) = 10-6 m2s-1
kPE,PVC = 0,003-0,02 mm
kFFD,aço = 0,01-0,1 mm
Ks FFD, Steel = 75 - 90 m1/3s-1
Quintela (1981), p.140
Quintela (1981), p.153
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEMS / HYDRAULIC DESIGN OF MAIN WATER PIPES DETERMINING THE WATER ENERGY LINE
2015/2016 57
Gravitic main water supply pipes:
Static head
E-2
E-3
PN 6
PN 10
PN 16
PN 20
E-1E-2
E-3
P-3
PN 6
PN 10
PN 16
PN 20
Pumped main transmission pipes:
Dynamic head
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEMS / HYDRAULIC DESIGN OF MAIN WATER PIPES DETERMINING PIPELINE PRESSURE
2015/2016 58
Characteristics:
PVC (polyvinyl chloride) pipes are rigid with a
compact wall manufactured by extrusion.
The Duronil pipes are presented in the following pressure classes:
PN6 kgf/cm2 (0,6 MPa);
PN10 kgf/cm2 (1,0 MPa);
PN16 kgf/cm2 (1,6 MPa).
External diameters (mm):
63; 75; 90;110; 125; 140; 160; 200;
250; 315; 400; 500; 630
Duronil \ Pipes
WATER SUPPLY AND DISTRIBUTION SYSTEMS PIPES / POLYVINYL CHLORIDE (PVC)
2015/2016 59
Characteristics:
HDPE pipes are rigid with a compact wall
manufactured by extrusion.
HDPE pipes are presented in the following
pressure classes:
PN4 kgf/cm2 (0,4 MPa) a PN16 kgf/cm2 (1,6 MPa)
External diameters (mm):
63; 75; 90;110; 125; 140; 160; 200;
250; 315; 400; 500; 630
PEAD \ Pipes
WATER SUPPLY AND DISTRIBUTION SYSTEMS PIPES / HIGH DENSITY POLYETHYLENE (HDPE)
2015/2016 60
Characteristics:
These pipes are manufactured by an automatic
centrifugation process.
The pipe is formed by a set of layers, varying the materials
used in each one of them.
For the manufacture of this pipe four components are use:
Polyester resin: Acts as a binder and its made of an unsaturated
and non-solvent polyester resin;
Filler (sodium carbonate): This component is mixed with the resin to improve
his structural characteristics;
Silica sand: This sand is used as a structural load reinforcement to improve their
mechanical properties;
Glass fibres: As a reinforcement to the polyester resin, the glass fibres is also
used to produce FRP pipes
This pipes are presented in the following pressures classes:
0,2 MPa a 2,5 Mpa
Commercial interior diameters (mm):
150; 200; 250; 300; 350; 400; 450; 500; 600; 700; 800; 900; 1000; 1100;…; 2400
FRP \ PIPES
WATER SUPPLY AND DISTRIBUTION SYSTEMS PIPES/ FIBERGLASS REINFORCED POLYESTER (FRP)
2015/2016 61
FFD \ Tubagens Characteristics:
The cast iron pipes are known to have a significant
longevity. This type of pipes can have various
internal coatings.
The cast iron pipes are presented in a pressure
classes of:
3,2 MPa a 4,0 Mpa
Commercial interior diameters (mm):
150; 200; 250; 300; 350; 400; 450; 500; 600; 700; 800; 900; 1000; …
WATER SUPPLY AND DISTRIBUTION SYSTEMS PIPES / DUCTILE CAST IRON
2015/2016 62
Steel \ Pipes
WATER SUPPLY AND DISTRIBUTION SYSTEMS PIPES/ STEEL
Características:
Iron pipes can be design with multiple thicknesses
and are usually used in sections with high
pressures and when the pipes are visible. They can
have various internal coatings.
Steel pipes are presented in a pressure classes of:
3,2 MPa a 4,0 Mpa
Commercial interior diameters (mm):
150; 200; 250; 300; 350; 400; 450; 500; 600; 700; 800; 900; 1000; …
2015/2016 63
Other types \ PIPES
Asbestos Cement
Although this material has fallen into disuse, in older
networks there is still significant extensions with this
type of pipe.
Pressure classes: CL6, CL12; CL18; CL24; CL30
Reinforced concrete (prestressed or steel core)
It’s a competitive material in large diameters with cast
iron.
Other plastic pipes:
Polypropylene
These pipes resist to high pressures (20 kgf/cm2) and
allow high temperature fluid.
WATER SUPPLY AND DISTRIBUTION SYSTEMS PIPES / OTHER TYPES
2015/2016 64
Instantaneous velocity reduction (water hammer)
with,
a – celerity (m/s)
Vi – flow velocity (m/s)
k – constant, depends on the pipe material
(steel= 0,50; cast iron= 1,0;
concrete= 5,0; plastic= 18)
e – pipe thickness(m)
D – pipe diameter (m)
g
VVaH
)( 10 D
) (
3,48
9900 1
sm
e
Dk
a
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEMS / HYDRAULIC DESIGN OF MAIN WATER PIPES WATER HAMMER
2015/2016 65
Time to cancel the flow:
Rosich Formula(1970)
Where,
C – parameter that depends on the main water pipe gradient
Ht/L ≤ 20% => C = 1s
Ht/L > 40% => C = 0s
K –adimensional coeficient, lenght dependent:
L – Main water pipe length
U0 – Flow velocity
Ht – Elevation height
tHg
ULKCT
.
.. 0
L(m) <500 ~500 500<L<1500 ~1500 >1500
K(-) 2 1,75 1,5 1,25 1,0
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEMS / HYDRAULIC DESIGN OF MAIN WATER PIPES
OVERPRESSURE AND NEGATIVE PRESSURE (BOOSTER PUMP STOPPING)
2015/2016 66
Maximum negative pressure (Michaud):
Instantaneous velocity reduction.
Usually it is necessary to protect the water main through
proteccion appurtenances against the water hammer effect
g
UaH
a
LT 0.2
DTg
ULH
a
LT
.
.22 0D
Flywheel
Vacuum
relief valves
Compressed air
reservoir(RAC)
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEMS / HYDRAULIC DESIGN OF MAIN WATER PIPES
OVERPRESSURE AND NEGATIVE PRESSURE (BOOSTER PUMP STOPPING)
2015/2016 67
Example
Instantaneous stop:
Power cut in pump group :
mx
g
UaH 85
8,9
4,1600. 0 D
E-1E-2
E-3
P-3
PN 6
Ht = 50 m
L = 1000 m
V = 1,4 m/s
HDPE
Time to
cancel the
flow:
sx
xx
Hg
ULKCT
t
3,5508,9
4,110005,11
.
.. 0
Maximum
overpressure
Therefore, s
x
a
LT 3,3
600
100022
mgT
ULH 54
..2 0 D
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEMS / HYDRAULIC DESIGN OF MAIN WATER PIPES
OVERPRESSURE AND NEGATIVE PRESSURE (BOOSTER PUMP STOPPING)
2015/2016 68
Head Loss Chambers (HLC) Pressure Reduction Valve (PRV)
HLC
Static Head Line (SHL)
Dynamic Head Line (DHL)
PRV
DHL
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEMS / HYDRAULIC DESIGN OF MAIN WATER PIPES DEVICES AND APPURTENANCES TO REDUCE HYDRAULIC HEAD
SHL
2015/2016 69
High pressures due to a big difference of heights between the start and
the final destination of the main
Excessive pressure on the water main pipe
HLC
SHL
DHL
RPV
SHL
DHL
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEMS / HYDRAULIC DESIGN OF MAIN WATER PIPES DEVICES AND APPURTENANCES TO REDUCE HYDRAULIC HEAD
FACTORS WHICH INFLUENCE ITS INSTALATION
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEMS / HYDRAULIC DESIGN OF MAIN WATER PIPES DEVICES AND APPURTENANCES TO REDUCE HYDRAULIC HEAD
2015/2016 70
:
An intermediate reservoir, where part of
the hydraulic head is dissipated on
entering (localized head loss)
The new energy level coincides with the
ground level
HLC
SHL
DHL
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEMS / HYDRAULIC DESIGN OF MAIN WATER PIPES DEVICES AND APPURTENANCES TO REDUCE HYDRAULIC HEAD (HEAD LOSS CHAMBERS )
OPERATION MODE
2015/2016 71
It aims to keep a certain pressure,
downstream, that is inferior to the
one upstream, whenever the latter
excedes a given value.
Advantage (comparing to the HLC)
that it doesn’t loose all the energy
downstream.
Valve types
• de spring, piston and
diaphragm
RPV
SHL
DHL
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEMS / HYDRAULIC DESIGN OF MAIN WATER PIPES DEVICES AND APPURTENANCES TO REDUCE HYDRAULIC HEAD (PRESSURE REDUCTION VALVE )
OPERATION MODE
2015/2016 72
SHL
DHL Dmenor
D1
D2
SHL
DHL
HLC
HLC
HLC
HLC
HLC HLC
Minimun Diameter
Combination of diameters
1, 2, 3, 4 HLC
Base Scenario Alternative Scenario
WATER SUPPLY AND DISTRIBUTION SYSTEMS PROJECT 1: STUDY OF A TRANSMISSION SYSTEM
ALTERNATIVE SCENARIOS
GRAVITATIONAL SYSTEM
2015/2016 73
SHL
D1 D2
PS Pump Station
Change diameter or 1 ou 2 PS (2 ou 3PS)
SHL
D1
D1
D1
PS
PS
WATER SUPPLY AND DISTRIBUTION SYSTEMS PROJECT 1: STUDY OF A TRANSMISSION SYSTEM
ALTERNATIVE SCENARIOS
PUMPED SYSTEM
Base Scenario Alternative Scenario
2015/2016 74
Smaller diameter (D1)
diameter larger (D2) than the one on the default scenario
WATER SUPPLY AND DISTRIBUTION SYSTEMS PROJECT 1: STUDY OF A TRANSMISSION SYSTEM
ALTERNATIVE SCENARIOS
MIXED SYSTEM
Base Scenario Alternative Scenario
2015/2016 75
LESSON 4
Water supply sytems economical analsys.
Net Present Value (NPV).
Pumped systems economical diameter.
Function of water storage tanks
Different types of storage tanks
Location of tanks in the water supply system
SANITARY ENGINEERING LESSON 5 / SUMMARY
2015/2016 76
INSTALATION COSTS
Piping
Removal and replacement of pavements;;
Earthworks;
Supply, installation and assembly
(incl. appurtenances).
Pumping stations
Construction;
Electromechanic equipment.
Appurtenances
Hydraulic head reduction devices ( HLC or PRV);
Vacuum relief valves;
Bottom discharge valve;
Isolation valves.
Reservoirs
Operation costs and maintenance
Energy;
Labour costs
Maintenance.
WATER SUPPLY AND DISTRIBUTION SYSTEMS ECONOMIC STUDY OF SUPPLY SYSTEMS AND WATER STORAGE
2015/2016 77
:
11211
1121212111111 ..
LLL
HDJLDJL
totalLLL
HDJLDJL
21
222111..
22221
2222222212121 ..
LLL
HDJLDJL
WATER SUPPLY AND DISTRIBUTION SYSTEMS ECONOMIC STUDY OF SUPPLY SYSTEMS
GRAVITATIC SUPPLY SYSTEMS
2015/2016 78
Determining economical diameter
WATER SUPPLY AND DISTRIBUTION SYSTEMS ECONOMIC STUDY OF SUPPLY SYSTEMS
PUMPED SUPPLY SYSTEMS
DN
€
Total Cost
Pipes Cost
Running Costs (energy)
Dec
2015/2016 79
Present net value tell us the value, at the moment, of a revenue or expense
that takes place in the future
1€ today is worth more than 1€ in a year.
Yearly costs can only be added when are updated to a reference year
(usually, year 0) through the discount rate (ta)
0 1 2 3 .... n .... HP
C1 C2 C3 … Ci .... Cn .... CHP
1 / (1+ta)n 1 / (1+ta)3 1 / (1+ta)HP
Ci updated_year0 = Ci / (1+ta)i
WATER SUPPLY AND DISTRIBUTION SYSTEMS ECONOMIC EVALUATION OF AN INVESTMENT PROJECT
PRESENT NET VALUE CONCEPT
2015/2016 80
Discount rate a.k.a. capital oportunity cost or project’s minimum return rate
It’s the profitability that the investor requires to implemente a project
ta = (1+treal) x (1+trisk) x (1+tinflation) - 1
0 1 2 3 .... n .... HP
C1 C2 C3 … Ci .... Cn .... CHP
1 / (1+ta) n 1 / (1+ta) 3 1 / (1+ta) HP
Ci updated_year 0 = Ci / (1+ta)i
WATER SUPPLY AND DISTRIBUTION SYSTEMS ECONOMIC EVALUATION OF AN INVESTMENT PROJECT
DISCOUNT RATE
2015/2016 81
Current prices analysis
Unit prices increase with inflation rate (ti);
The revenues and the estimated costs are more realistic, in nominal
terms, but the sensitivity towards the resources that represente that
value gets lost
0 1 2 3 .... n .... HP
C0 C1 C2 C3 .... Cn .... CHP
1 / (1+tj) n
1 / (1+tj) 3
1 / (1+tj) HP
(1+ti) n (1+ti)
HP
WATER SUPPLY AND DISTRIBUTION SYSTEMS ECONOMIC EVALUATION OF AN INVESTMENT PROJECT
NPV AT CURRENT PRICES
2015/2016 82
It is considered that unit prices are constant throughout a the project’s life
(there is no inflation, ti=0)
It allows to compare (with advantage) alternative solutions where the used
costs and the revenues have unit prices with similar expected inflation rate;
The revenue value, and estimated costs for each year are more perceptible
in terms of real equivalence to the resources that correspond to that value
(man-hour; kWh; materials;….)
0 1 2 3 .... n .... HP
C0 C0 C0 C0 .... C0 .... C0
1 / (1+ta) n 1 / (1+ta) 3 1 / (1+ta) HP
Ci updated_year 0= C0 / (1+ta) n
WATER SUPPLY AND DISTRIBUTION SYSTEMS ECONOMIC EVALUATION OF AN INVESTMENT PROJECT
NPV AT CURRENT PRICES
2015/2016 83
Energy demand on year i:
Energy cost on year i:
Pumped volume on year i:
Different water volumes are pumped throughout the project’s life;
To calculate the total yearly energetic needs it’s not necessary to know
the average pumping time for each year
tii
HVE
.. Energy unitary price
iti
i VKpHV
CE ...
p
HK t
.
daysCapPopV iii 365..
WATER SUPPLY AND DISTRIBUTION SYSTEMS ECONOMIC EVALUATION OF AN INVESTMENT PROJECT
ENERGY COSTS
2015/2016 84
Total energy present cost
Year Year value Present value
1
2
3
: :
N
N
i
i
ai tVK1
)1/ (.
N
i iVK1
.
1.VK
2.VK
3.VK
NVK.
)1/(. 1 atVK
22 )1/(. atVK
33 )1/(. atVK
NaN tVK )1/(.
WATER SUPPLY AND DISTRIBUTION SYSTEMS ECONOMIC EVALUATION OF AN INVESTMENT PROJECT
UPDATING ENERGY COSTS
2015/2016 85
Hypothesis:
Pumped volumes increase anually according to a geometric law.
Total energy present cost
Year Yearly pumped volume Present energy cost
1
2
3
: :
N
)1(01 gtVV
202 )1( gtVV
303 )1( gtVV
NgN tVV )1(0 N
aN
g ttVK )1/()1(. 0
330 )1/()1(. ag ttVK
220 )1/()1(. ag ttVK
)1/()1(. 0 ag ttVK
N
i
ia
igo ttVK
1)1/ ()1(.
N
a
g
ga
g
ot
t
tt
tVK
1
11
)(
)1(.
WATER SUPPLY AND DISTRIBUTION SYSTEMS ECONOMIC EVALUATION OF AN INVESTMENT PROJECT
UPDATING ENERGY COSTS
2015/2016 86
Total Cost = Investment in fixed assets + Operating costs
Investment in fixed assets
Main Pipes . . . . . . . . . . . . . year 0
Reservoirs . . . . . . . . . . . . . . . . . . . year 0
PS construction works. . . . . . . . . . . . . year 0
Electromechanic Equip. PS . . . .. . . . . years 0 e 20
HLC. . . . . . . . . . . . . . . . . . . . . . . . . . year 0
Operating costs
Operation and Maintenance . . . . . . . .. 1 - 40 years
Main pipes
Reservoirs
PS construction works
Electromechanic Equip. PS
Energy (from pumps) . . . . . . . . . . 1 - 40 years
SANITARY ENGINEERING PROJECT 1: STUDY OF A TRANSMISSION SYSTEM
SYSTEM TOTAL COST / CONSTANT VALUE ANALYSIS
2015/2016 87
Main pipes
Defined per pipe running
meter (Table A.1 on the work
assingment )
Reservoir
Defined per m3
C = 1 400 .Vol 0,75
( in alternative em alternativa, Table A.4 on the work assingment )
Nominal
Diameter
(mm)
DCI Coated
Steel
PVC HDPE
PN6 PN10 PN16 PN6 PN10 PN16
60 53.97
63 27.64 27.98 28.99 28.89 30.24 32.02
75 30.42 31.43 34.51 29.54 31.03 33.06
80 57.97 71.32
…
100 64.45 77.66
800 536.33 513.44 490.70 740.88 425.33 572.35
SANITARY ENGINEERING PROJECT 1: STUDY OF A TRANSMISSION SYSTEM
SYSTEM TOTAL COST / CONSTANT VALUE ANALYSIS
2015/2016 88
Pumping stations
Defined as a function of the design flow and elevation height
Construction Ccc(€) = 39904 + 374 x Q +0.15 x Q x H
Equipement Ceq (€) = 1317 x Q0.769 x H0.184 + 2092 x (QxH)0.466
Being Q – water flow (l/s) e H – elevation height(m)
Construction costs
Adquired at year 0 and calculated with Qdim40 and Hdim40
Equipment Costs
Adquired at year 0 and calculated with Qdim20 and Hdim20
Adquired at year 20 and calculated with Qdim40 and Hdim40 and should
be updated to the year 0 multipying its value by 1 / (1+ ta)20
Head Loss Chamber
Unit Cost= 15 000 €
SANITARY ENGINEERING PROJECT 1: STUDY OF A TRANSMISSION SYSTEM
SYSTEM TOTAL COST / INVESTMENT IN FIXED ASSETS CONSTANT VALUE ANALYSIS
2015/2016 89
Operation and Maintenance
Defined as yearly investment percentage
Main pipes with joint connections. . . .. . . . . . . . . . . . . 1 % investiment/year
Welded main pipes . . . . . . . . . . . . . . . . . . . . . . . . . 0,75 % investiment/year
Reservoirs and HLC. . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 % investiment/year
PStation Construction. . . . . . . . . . . . . . . . . . . . . . . . . . . 1 % investiment/year
Electromechanic Equip. EE . . . . . . . . . . . . . . . . . . . . . . 2,5 % investiment/year
They have to be calculater year by yea throughout 40 years (year 1 to 40) and
updated to year 0:
Cost updated_year_0 = Cost year_n x 1 / (1+ ta) n
where,
ta = discount rate (e.g. 6%)
SANITARY ENGINEERING PROJECT 1: STUDY OF A TRANSMISSION SYSTEM
SYSTEM TOTAL COST / INVESTMENT IN FIXED ASSETS CONSTANT VALUE ANALYSIS
2015/2016 90
Energy (1st calculation process)
They have to be calculated year by yea throughout 40 years (year 1 to 40) and
updated to year 0
Yearly energy demand for year i - Sousa (2001) – Adução, p.32
Eyear_i = Power * Func_Time_year_i
= ( * Qdim * Hdim / m ) * Func_Time_year_i
= ( * Hdim / m ) * (Func_Time_year_i)
= ( * Hdim / m ) * Vmda_year_i
Variável do ano i = Popano i * Capano i
Cost of energy demand for year i
CEyear_i (€) = Eyear_i (kWh) * unit_price (€/kWh)
Cost of energy demand for year i at year 0 present value
CEupdated_year_0 (€) = CEano_i (€) * 1/(1+ta)I
Note: Attention to the conversion: 1 joule = W.s
Constante: do ano 1 ao 20 20 (Hdim20)
do ano 21 ao 40 (Hdim40)
SANITARY ENGINEERING PROJECT 1: STUDY OF A TRANSMISSION SYSTEM
SYSTEM TOTAL COST / INVESTMENT IN FIXED ASSETS CONSTANT VALUE ANALYSIS
2015/2016 91
Energy (2nd calculation process)
Can be calculated as the sum of n parcels of a geometric progression
Sn = U1 * ( 1-Rn) / (1-R)
• U1 corresponds to the 1st parcel
• R corresponds to the reason of the geometric progression
It will correspond to two sums
1-20 years and 21-40 years
Example of 1-20 years
Where tg1 = geometric growth rate of the demanded volume between 1-
20 years, given by:
tg1 = (V20/V0)(1/20) -1
The homologus expression for the years 21 to 40 this rate will be given as:
tg2 = (V40/V20)(1/20) -1
20
1
1
120dim0_)201(
1
11
)(
)1(..
.
a
g
ga
g
oanoac tat
t
tt
tVp
HC E
SANEAMENTO PROJETO 1: ESTUDO PRÉVIO DE UM SISTEMA ADUTORCUSTO TOTAL DO SISTEMA /
ENCARGOS DE EXPLORAÇÃO (CONTINUAÇÃO)
(ANÁLISE A PREÇOS CONSTANTES)
SANITARY ENGINEERING PROJECT 1: STUDY OF A TRANSMISSION SYSTEM
SYSTEM TOTAL COST / INVESTMENT IN FIXED ASSETS CONSTANT VALUE ANALYSIS
2015/2016 92
Total net present value of a pumping system for a given diameter D1::
Where;
The same calcuations should be done for D2 (if it exists).
The most economical diameter is the one that presents a lower
C_Sist.Elev.act_ano0
2 0
2 0_)4 02 1(
0_)2 01(2 0
4 0_
2 0_4 0_0_)1()1(
1.._a
a n oa c ta
a n oa c ta
a
a n oe q
a n oe qa n oc ct u b a g e ma n oa c tt
C EC E
t
E EE EE ECDE le vS is tC
20
1
1
120dim0_)201(
1
11
)(
)1(..
.
a
g
ga
g
oanoac tat
t
tt
tVp
HC E
20
2
2
2
2040dim
20_)4021(1
11
)(
)1(..
.
a
g
ga
g
anoac tat
t
tt
tVp
HC E
20 parcels (year 1 to 20). The present
value refers to the year immediatly
before the series start (year 0)
20 parcels (year 21 to 40). The present
value refers to the year immediatly before
the series start (year 20)
SANITARY ENGINEERING PROJECT 1: STUDY OF A TRANSMISSION SYSTEM
SYSTEM TOTAL COST / INVESTMENT IN FIXED ASSETS CONSTANT VALUE ANALYSIS
2015/2016 93
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER STORAGE TANKS - REFERENCES
LESSON 6
LESSON 7
Legislation (DL 23/95 – Secção III)
Art. 67º - Function
Art. 68º - Classification
Art. 69º - Location
Art. 70º - Design
Art. 71º - Constructive issues
Folhas da cadeira
Sousa, E. R. (2001)- Water Storage Tanks , IST (electronic version)
Manual de Saneamento Básico II.4 (Sanitation Manual II.4)
For everything that is not mentioned on the regulation
2015/2016 94
a) Serve as regulation device, compensating demand
fluctuations in regards to the supply
daily flow regulation
(between hours of the day)
monthly flow regulation)
(between days of the year)
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER STORAGE TANKS - PURPOSE (DL 23/95 – Art. 67.º)
Q1 = Accomulated flow supply
Q2 = Accomulated flow distribuition
A+B = Capacity
2015/2016 95
b) Serve as backup for firefighting or
to ensure distribution when there’s
involutary or accidental interruption
on the upstream system:
Backup for:
Fire fighting;
Water quality changes at the source;
Accidents related to water abstraction;
Interventions and repairing main trunk pipes
Power failure (pump shutdown).
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER STORAGE TANKS - PURPOSE (DL 23/95 – Art. 67.º)
2015/2016 96
c) equilibrium of water pressure in the
water supply system;
WATER SUPPLY AND DISTRIBUTION SYSTEMS
WATER STORAGE TANKS - PURPOSE (DL 23/95 – Art. 67.º)
Origin storage
tank
Energy line when there’s no
demand
Energy line while
on peak demand
Destination
storage tank
2015/2016 97
d) pump flow regulation
Transport Regulation Tanks
(TRT)
SISTEMAS DE ABASTECIMENTO E DISTRIBUIÇÃO DE ÁGUA RESERVATÓRIOS – FINALIDADE (DL 23/95 – Art. 67.º)
TRT 3 Gravitational - Pumped
RD1
RD2
RD3 TRT 1
Gravitational - Pumped
TRT 2
Gravitational - Pumped
Origin
WATER SUPPLY AND DISTRIBUTION SYSTEMS
WATER STORAGE TANKS - PURPOSE (DL 23/95 – Art. 67.º)
2015/2016 98
a) According to function
Pressure level equilibrium
Pump regulation
Fire fighting
b) According to ground level)
Underground
Partially underground)
Elevated (pressure towers)
c) According to its capacity
Small (V < 500 m3)
Medium (entre 500 m3 e 5000 m3)
Large (V > 5000 m3)
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER STORAGE TANKS - CLASSIFICATION (DL 23/95 – Art. 68.º)
2015/2016 99
1) As close as possible to the center of garvity
of the locations where there is demand, with
a height that ensures minimun pressure to
the entire network.
2) When the topography becomes a challenge
diferente pressure levels may be created
(with or whithout storage tanks)
Example - Lisbon Water supply system
Approximate lenght of 1400 km
Diameters: 50 e 1500 mm
10 000 valves and 90 000 connections
5 altimetric zones
zones: lower, medium, high, superior, special
Pressure levels every 30 m
Supplied by different tanks and divided by PRV
WATER SUPPLY AND DISTRIBUTION SYSTEMS
WATER STORAGE TANKS - LOCATION (DL 23/95 – Art. 69.º)
2015/2016 100
3) Large areas in the same pressure level
may need more than one water tank
4) In expanding áreas there may be the
need for a secondary water tank for
pressure regulation
WATER SUPPLY AND DISTRIBUTION SYSTEMS
WATER STORAGE TANKS - LOCATION (DL 23/95 – Art. 69.º)
2015/2016 101
SANITARY ENGINEERING LESSON 6 / SUMMARY
Lesson 5
WATER STORAGE TANKS
Devices, instrumentation and constructions issues
Hydraulic design
2015/2016 102
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER STORAGE TANKS - HYDRAULIC LAYOUT
Incoming and outgoing water piping
Different types of entrance connection between a storage tank cell and the
main trunk pipe
Main trunk pipe exit from a storage tank cell.
2015/2016 103
Incoming and outgoing water piping
By-pass between supply and distribution pipes at a storage tank
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER STORAGE TANKS - HYDRAULIC LAYOUT
2015/2016 104
Incoming and outgoing water piping
Layout scheme in case the supply
and distribution pipes are
independent
Layout scheme in case the supply and
distribution pipes are the same
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER STORAGE TANKS - HYDRAULIC LAYOUT
2015/2016 105
Incoming and outgoing water piping
Piping layout for fire fighting volume management
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER STORAGE TANKS - HYDRAULIC LAYOUT
2015/2016 106
Surface discharge and bottom outlet
Layout scheme for
bottom outlets Surface and bottom discharge from a
storage tank cell
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER STORAGE TANKS - HYDRAULIC LAYOUT
2015/2016 107
Equipment household
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER STORAGE TANKS – EQUIPMENT HOUSEHOLD
2015/2016 108
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER STORAGE TANKS – EQUIPMENT HOUSEHOLD’S HYDRAULIC LAYOUT
2015/2016 109
Lazarim Alto
(430 m3)
Cassapo Alto
(500 m3)
Lazarim Baixo
(5 000 m3)
Cassapo Baixo
(6 000 m3)
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER STORAGE TANKS – EXAMPLES: ELEVATED WATER TANKS
2015/2016 110
Mãe de Água – Reservoir at Amoreiras
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER STORAGE TANKS – EXAMPLE
2015/2016 111
Câmara de carga de Visalto Storage tank at Feijó
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER STORAGE TANKS – EXAMPLE
2015/2016 112
Verify is the scale economy of planing less construction phasing compensates
the alternative solutions of postponing investments that aren’t capitalised
immediately
Example:
Reservoirs are construction works with a long lifetime, but as they are
easily expanded, it should be assessed if there’s na economic advantage
of it’s phasing
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER STORAGE TANKS – ECONOMIC IMPACT OF PHASING INVESTMENTS
2015/2016 113
Distribution tanks (DT)
Transport flow regulation tanks(TRT)
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER STORAGE TANKS – TYPES OF WATER TANKS
TRT 3 Gravitational - Pumped
RD1
RD2
RD3 TRT 1
Gravitational - Pumped
TRT 2
Gravitational - Pumped
Origin
2015/2016 114
“1 – Hydraulic design of regulation storage tanks consists on determining
its storage capacity, that should be the sum of regulatrization and
emergency storage needs”
[…] “6 – The storage capacity for emergency should be larger value
between the needed volumes for firefigthing or breakdown.
Capacity (m3)
V = Vregularization + Vemergency
Where,
Vregularization = Vreg_interdiaily + Vreg_interhourly
Vemergêncy = Maximum {Vbreakdown ; Vfriefighting}
Reservoirs are construction works with a long lifetime, but as
they are easily expanded, it should be assessed if there’s na
economic advantage of it’s phasing
(Ex: 3 cells with Phase 1: 2 cells Phase 2: 1 cell)
WATER SUPPLY AND DISTRIBUTION SYSTEMS DISTRIBUTION STORAGE TANKS – WATER VOLUME DESIGN
2015/2016 115
Regularization storage for normal demand
1) Regularization storage for daily regulation
Curves for type of demand
(Ex: Sanitation Manual)
2) Regularization storage for monthly regulation
Statistical curves for demand
(Ex: Sanitation Manual)
WATER SUPPLY AND DISTRIBUTION SYSTEMS DISTRIBUTION STORAGE TANKS – WATER VOLUME DESIGN
2015/2016 116
“2 - The regulation capacity depends on fluctuation on the demand that should be
regularised as to minimize the investments on the supply system and on the storage
tank.
3 – Generally, the supply system is designed for the flow of the day with higher
demand, while the tank’s storage capacity should be calculated as to cover hourly
fluctuations during the day.”
“4 – The supply system can also be designed for the average flow of the month with
higher demand, the tank’s storage capcity should then be calculated to cover the
daily fluctuations during that month
If the supply system is designed for Qdhd Vreg_iinterdiaily = 0
If the supply system is designed for Qmmc Vreg_interdiaily > 0
WATER SUPPLY AND DISTRIBUTION SYSTEMS DISTRIBUTION STORAGE TANKS – WATER VOLUME DESIGN: MONTHLY
REGULATION
2015/2016 117
Source:
Manual de Saneamento
Básico – Direcção Geral dos
Recursos Naturais, 1991
WATER SUPPLY AND DISTRIBUTION SYSTEMS
DISTRIBUTION STORAGE TANKS – WATER VOLUME DESIGN: MONTHLY
REGULATION
If the supply system is designed for Qdhd
fp=1.5 Vreg_interdiaily = 0 Vyda_40
Where,
Vyda_40 = yearly daily average volume
If the supply system is designed for Qmhd
fp=1.3 Vreg_interdiaily = 1 Vyda_40
If the supply system is designed for Qmda
fp=1.0 Vreg_interdiaily = 20 Vyda_40
In that case, it’s admited that Qmhd occurs during five
consecutive days 5 x (1.5-1.3) =1
If otherwise:“… should guarantee storage for one or
more days with demand higher than the supply”– MSB
II.4/1990, p.2
“…only for small settlements; water quality problems may
arise due to the slow water renovation” – MSBII.4, p.2
2015/2016 118
WATER SUPPLY AND DISTRIBUTION SYSTEMS
DISTRIBUTION STORAGE TANKS – WATER VOLUME DESIGN: DAILY
REGULATION
Supplied
flow
Pumped flow
Excessive
distribution
Excessive
supply
Storage
Storage for daily regulation
“5 – Once the demand fluctuations to
regularize are defined, the tank’s storage
capacity is determined, regarding flow’s
entry and exit fluctuation over time, using
numeric or graphical methods.”
41,7% of daily
demand
Pumped Flow
Distributed flow
Pumped Volume
Pumped Volume
Accumulated dist. volume
Storage
Capacity
Distributed Vol.
2015/2016 119
Storage for daily regulation
Pumping durint the periods with lower
energetic cost.
Caudal
distribuído
Armazenamento
Pumped Flow
Distributed flow
Pumped Volume
Pumped Volume
Accumulated dist. volume
Storage
Capacity
Distributed Vol.
Caudal
bombeado
Distribuição
excedentária
Adução
excedentária
91,7% do
consumo diário
WATER SUPPLY AND DISTRIBUTION SYSTEMS
DISTRIBUTION STORAGE TANKS – WATER VOLUME DESIGN: DAILY
REGULATION
2015/2016 120
WATER SUPPLY AND DISTRIBUTION SYSTEMS DISTRIBUTION STORAGE TANKS – WATER VOLUME DESIGN: VOLUME FOR
SUPPLY INTERRUPTIONS
“8 – The water storage for emergencies should me fixed admitting that:
a) The derangement happens during the least favourable period, but not in more than
one supply main turnk at the same time;
b) It’s location takes between one and two hours when the main trunk is accessible by
a passable road, or remote locations of no more than 1km and it takes na extra half
na hour for km of main pipe that is not reachable by motorized vehicles;
c) The repair takes between for to six hours, this period includes the necessary time for
the emptying of the pipe, the repair itself, re-filling and disinfection.”
Break location 1 a 2 h
Repair 4 a 6 h
Total 5 a 8 h
Vbreakdown = (5 to 8 h) x Qdim40 (m3/h)
2015/2016 121
WATER SUPPLY AND DISTRIBUTION SYSTEMS DISTRIBUTION STORAGE TANKS – WATER VOLUME DESIGN:
FIREFIGHT VOLUME
“1 – The volume of water for firefighting depends on the risk of its occurence, and
propagation on the said area to which should be attributed one of the following
degrees:
a) 1st Degree – urban area with minimum risk of fire, due to low building
implantation, and mainly family housing.;
b) 2nd Degree – urban low risk area, constituted predominantly by isolated
constructions with a maximum of 4 floor above the ground;
c) 3rd Degree – urban area with a moderate risk degree, predominantly constituted by
construções with a maximum of 10 floor above ground, destined to housing,
eventualy with some commerce or small industry;
d) 4th Degree – urban area with a considerable risk degree, constituted by
constructions of 10 or more floors, destined for housing and public services, namely
shopping centers;
e) 5th Degree – urban area of elevated risk, characterized by the existecnce of old
constructions or mainly commertcial buildings and industrial activity that stores,
utilizes or produces explosive or highly flammable materials.”
2015/2016 122
“7 – The storage of water for firefighting depends on risk degree of the area
and should not be lower than:
75 m3 - 1st degree;
125 m3 – 2nd degree;
200 m3 – 3rd degree;
300 m3 – 4th degree;
to define for each specific case – 5th degree.”
The previously mentioned risk degrees (from 1 to 5) are defined on the
same legal statement, first paragraph of the 18th article - Water volumes
for firefighting (ponto 1 do artigo 18.º - Volumes de água para combate a
incêndios)
[…]
9 – In storage tanks solely with the function of pressure equilibrium, the
capacity of the pressure tower should correspond to the minimum volume
demand of 15 minutes in peak demand”.
WATER SUPPLY AND DISTRIBUTION SYSTEMS DISTRIBUTION STORAGE TANKS – WATER VOLUME DESIGN:
FIREFIGHT VOLUME
2015/2016 123
“10 – No matter what are the storage tank’s supply conditions, th system’s storage
capacity should be:
V ≥ K Qad
Qad is the annual average daily flow (cubic meters) for the
K is a coefficient that has the following minimum values:
K = 1,0 for populations that have more than 100 000 inhabitants;
K = 1,25 for populations that have between 10 000 and 100 000 inhabitants;
K = 1,5 for populations that have between 1000 and 10 000 inhabitants;
K = 2,0 for populations that have fewer than 1000 inhabitants and for areas with
bigger risk
Vmin = K x Vmda40 (m3)
= K x Qmda40 (m3/d) x 1 day
For small settlements, high Vmin can lead to low water renewal (may give problems
of water quality)
WATER SUPPLY AND DISTRIBUTION SYSTEMS DISTRIBUTION STORAGE TANKS – WATER VOLUME DESIGN: MINIMUN
VOLUME
2015/2016 124
18 Qm
“5 – Once the demand fluctuations to regularize are defined, the tank’s storage
capacity is determined, regarding flow’s entry and exit fluctuation over time, using
numeric or graphical methods.”
Storage tantk level
Accumulated demand curve Vacum
0 6 12 18 24 h
Graivitational supply
3 Qm
12 Qm
Distribution
24 Qm
|VA|
|VB|
Demand curbe
Q
0 6 18 24 h
0,5 Qm
1,5 Qm
0,5 Qm
Qm
Example – Gravitic supply
VA / VB = maximum difference
positive/negative between Vacum
supply and distribution
V inter-hourlyr egulation = |VA|+|VB|
Qm=Qdmc ou
Qmmc (m3/h)
24 h 0
6 h
18 h
12 h
WATER SUPPLY AND DISTRIBUTION SYSTEMS DISTRIBUTION STORAGE TANKS- WATER VOLUME DESIGN: DAILY FLOW
REGULATION
2015/2016 125
a = Qm = Qdmc_40 ou Qmmc_40 (m3/h)
Depends on whether the main
pipes have been designed for the
day or for the month of higher
demand
Gravitatic supply (MSBII.4, p.15)
WATER SUPPLY AND DISTRIBUTION SYSTEMS DISTRIBUTION STORAGE TANKS- WATER VOLUME DESIGN: DAILY FLOW
REGUTLATION
2015/2016 126
0
6
12
18
24
0 6 12 18 24h
Accumulated demand curve
Vacum (Qm)
Pumped supply
Distribution
|VA|
|VB|
0 9 11 18 20 24 h
Pumping curve
Q 1,2 Qm
Qm
Demand curve
Pumped supply
Q
0 6 18 24 h
0,5 Qm
1,5 Qm
0,5 Qm Qm
WATER SUPPLY AND DISTRIBUTION SYSTEMS DISTRIBUTION STORAGE TANKS- WATER VOLUME DESIGN: DAILY FLOW
REGUTLATION
VA / VB = maximum difference
positive/negative between Vacum
supply and distribution
V inter-hourlyr egulation = |VA|+|VB|
2015/2016 127
Pumped supply (MSBII.4, p.15)
WATER SUPPLY AND DISTRIBUTION SYSTEMS DISTRIBUTION STORAGE TANKS- WATER VOLUME DESIGN: DAILY FLOW
REGUTLATION
2015/2016 128
WATER SUPPLY AND DISTRIBUTION SYSTEMS REGULARIZATION PUMP STATIONS– CAPACITY
Regulation between gravitational and pumped sections
Regulation between pumped sections
TRT 3 Elevatório-Gravítico
RD1
RD2
RD3 TRT 1
Gravítico - Elevatório
TRT 2
Elevatório-Elevatório
Origin
2015/2016 129
Regularization between gravitational and pumped sections
The necessary volume depends on the
maximum number of the considered
daily stops.
The regularization volume is equal to
the maximum transported value over
24h minus the maximum number of
pumping hours (Vreg max = 4 h ou 8 h).
0
4
8
12
16
20
24
0 4 8 12 16 20 24
|VA|
0
4
8
12
16
20
24
0 4 8 12 16 20 24
1 stop/day 2 stops/day
0
4
8
12
16
20
24
0 4 8 12 16 20 24
4 stops/day
TRT 3 Pumped - Gravitational
RD1
RD 2
RD 3 TRT 1 Gravitational - Pumped
TRT 2 Pumped-Pumped Origin
WATER SUPPLY AND DISTRIBUTION SYSTEMS REGULARIZATION PUMP STATIONS – CAPACITY
2015/2016 130
WATER SUPPLY AND DISTRIBUTION SYSTEMS REGULARIZATION PUMP STATIONS – CAPACITY
Regularization between gravitational and pumped sections
In case the pumping period is the
same for the upstream and
downstream pumping stations, the
accumulated demand curves are
coincidente and, theoretically,
Vregularization will be zero
Usual solution
Consider the corresponding volume to 1/2h or 1h of the supply pumped flow as
to take into accounto possible un-sycrony between each pumping station’s start
and stop cycles.
TRT 3 Pumped - Gravitational
RD1
RD 2
RD 3 TRT 1 Gravitational - Pumped
TRT 2 Pumped-Pumped Origin
2015/2016 131
LESSON 6
APPURTENANCES
Appurtenances. Types, function and location.
Pumping stations.
Examples of location.
Retention Valves
Flow control valves.
Pumping stations.
Appurtenance location examples.
SANITARY ENGINEERING LESSON 8 / SUMMARY
2015/2016 132
WATER SUPPLY AND DISTRIBUTION SYSTEMS APPURTENANCES
APPURTENANCES
Types, function and location
2015/2016 133
Main types of appurtenances
Maneuvering and safety valves (manual or autonomous functioning)
Sectioning valves
Discharge Valves
Air relief valves
Retention valves
Typically have manual functioning but can
also be autonomous, controlled
telemanagement
Manual control
Flow controlled
Flow controlled
WATER SUPPLY AND DISTRIBUTION SYSTEMS WATER SUPPLY SYSTEMS’ APPURTENANCES
2015/2016 134
Main types of appurtenances
Regulation and control valves
Pressure reduction valves
Flow control valves
Level regulation valves
Two component valves: body of the valve and pilot circuit
Many times, the same valve (body) can be used for different functions (different pilot circuits)
WATER SUPPLY AND DISTRIBUTION SYSTEMS REGULATION AND CONTROL APPURTENANCES
2015/2016 135
Course textbook: Sousa, E.R. (2001) - “Sistemas de adução” (Water supply
sistems)
Manual de Saneamento Básico, Volume II.2 (1990), pp. 6-7 (Sanitation
Manual)
Implementig Decree n.º 23/95, de 23 de Agosto Capítulo IV - Elementos
acessórios da rede (Network’s Appurtenances) (for distribuition and supply
networks)
Art. 39.º - Juntas (Joints)
Art. 40.º - Válvulas de seccionamento (Sectioning Valves)
Art. 41.º - Válvulas de retenção (Check valves )
Art. 42.º - Redutores de pressão (Pressure regulators)
Art. 43.º - Válvulas redutoras de pressão (Pressure reduction valves)
Art. 44.º - Câmaras de perda de carga (Head loss tanks)
Art. 45.º, 46.º - Ventosas (Air relief valves)
Art. 47.º, 48.º e 49.º - Descargas de fundo (Bottom Discharge Valves)
Art. 50.º, 51.º e 52.º - Medidores de caudal (Flow meters)
Art. 53.º - Bocas de rega e de lavagem (Washing and watering hydrants)
Art. 54.º, 55.º e 56.º - Hidrantes (Fire Hydrants)
Art. 57.º - Câmaras de manobra (Maneuvre Chambres)
WATER SUPPLY AND DISTRIBUTION SYSTEMS REGULATION AND CONTROL APPURTENANCES
2015/2016 136
WATER SUPPLY AND DISTRIBUTION SYSTEMS SECTIONING VALVES
SECTIONING VALVES
Legislation, function, location, types and installation
2015/2016 137
WATER SUPPLY AND DISTRIBUTION SYSTEMS SECTIONING VALVES / LEGISLATION - DL 23/95, DE 23 DE AGOSTO
Article 40.º - Sectioning Valves
“1 - The sectioning valves should be installed to facilitate the operation of
the system and minimize the disadvantages of possible supply
interruptions.
2 - The sectioning valves should be properly protected, easily
manoeuvrable and their location should be such as:
[...]
b) close to appurtenances or other installations that may need to be put
out of service
c) [...]
f) Near main junctions, in a number of two.”
2015/2016 138
WATER SUPPLY AND DISTRIBUTION SYSTEMS SECTIONING VALVES / FUNCTION AND LOCATION ON MAIN TRUNKS
Function
Allow isolation of trunk sections in case of breakdown,
Avoiding the emptying of large piping sections in case of
Breakdown or cleaning.
Location in trunk mains
1.With a maximum spacing between 2 and 4 km (depending on the
profile and diameters)
If located on high ground, it is easier to manoeuver because the pipe is
subjected to lower pressures.
If located on lower grounds, the pipe becomes divided in lower sections
regarding the emptying of the same number of valves
2.The entrance and exit of storage tanks of pumping station and of
pressure reduction chambers
3.In branches of the main trunk, place one in each branch
2015/2016 139
WATER SUPPLY AND DISTRIBUTION SYSTEMS SECTIONING VALVES / MAIN TYPES OF VALVES
Wedge valves (with a T-head key or in a chamber)
T-head key
2015/2016 140
Butterfly valves (in a chamber)
WATER SUPPLY AND DISTRIBUTION SYSTEMS SECTIONING VALVES / MAIN TYPES OF VALVES
2015/2016 141
Installation with a t-head key Installation in a chamber
WATER SUPPLY AND DISTRIBUTION SYSTEMS SECTIONING VALVES / INSTALLATION EXAMPLE
2015/2016 142
Butterfly valves with a reduction cone
by-pass for the filling of the valve
WATER SUPPLY AND DISTRIBUTION SYSTEMS SECTIONING VALVES / INSTALLATION EXAMPLE
2015/2016 143
WATER SUPPLY AND DISTRIBUTION SYSTEMS AIR RELIEF VALVES
AIR RELIEF VALVES
Legislation, function, location, types and installation
2015/2016 144
Artigo 45.º - Air relief valves
The air relief valves […] aim to expel and admit air in the pipes
Artigo 46.º - Location and diameters in networks
1.The air relief valves should be located on high ground, namely on the extremes of
peripheral pipes and on pipes with a length superior to 1000m without distribution service.
2.For the long pipes previously referred, the air relief valves should be located at:
a)Downstream or upstream of the sectioning valves, depending on whether they are located
on ascending or descending sections;
b)Downstream of descending sections when the mains have small slope and are followed by
a stretch with a higher slope.
3.The minimum diameter of an air relief valve shouldn’t be inferior to an eighth of the pipe
where it is installed, with a minimum of 20mm.
WATER SUPPLY AND DISTRIBUTION SYSTEMS AIR RELIEF VALVES / LEGISLATION - DL 23/95, DE 23 DE AGOSTO
2015/2016 145
Function
i) Expelling the air accumulated sections with high elevation.
ii) Expelling the air and allowing it to enter when the pipes are being
emptied r filled
iii) Function ii) + the entrance of small amounts of air to enter, in case of
depression.
WATER SUPPLY AND DISTRIBUTION SYSTEMS AIR RELIEF VALVES / FUNCTION AND LOCATION
2015/2016 146
Location
a) In every high section of the elevation profile
b) Upstream or downstream sectioning valves, for descending or
ascending mains.
c) Downstream descending low slope mains when a high slope follows
(e.g., 0.5%->5%) or in ascending mains when a sudden slope
reduction occurs
d) Maximum distance between valves of 1 km in stretches with the
same slope – only for Execution Project)
WATER SUPPLY AND DISTRIBUTION SYSTEMS AIR RELIEF VALVES / FUNCTION AND LOCATION
2015/2016 147
Simple effect (small hole) Function i; Location d)
Double effect (large hole) Functions i e ii; Location e)
triple effect Functions i, ii e iii; Locations a) e c)
WATER SUPPLY AND DISTRIBUTION SYSTEMS AIR RELIEF VALVES / TYPES
2015/2016 148
WATER SUPPLY AND DISTRIBUTION SYSTEMS AIR RELIEF VALVES / INSTALLATION
2015/2016 149
WATER SUPPLY AND DISTRIBUTION SYSTEMS AIR RELIEF VALVES / INSTALLATION
2015/2016 150
DISCHARGE VALVES
Legislation, function, location, types and installation
WATER SUPPLY AND DISTRIBUTION SYSTEMS DISCHARGE VALVES
2015/2016 151
Article 47.º - Bottom Discharges
1. Bottom discharges aim to allow the emptying of mains or distribution
networks situated between sectioning valves, namely to proceed with
cleaning, disinfection or repair and they should be installed:
a) On lows in the mains;
b) On intermediate main sections, with the same slope and relatively high
lengths;
[…].
2. For the case referred on paragraph b) to the previous point, bottom
discharges should be located immediately upstream or downstream from,
respectively, the sectioning valves on ascending or descending pipes.
WATER SUPPLY AND DISTRIBUTION SYSTEMS DISCHARGE VALVES / LEGISLATION - DL 23/95, DE 23 DE AGOSTO
2015/2016 152
Article 48.º - Bottom discharges’ effluents release
1. The bottom discharges’ effluent should be released in water lines, natural,
pluvial collectors or transitory storage chambers, while safeguarding, in any
case, the risk of contamination of the water inside the main.
2. Whenever necessary, kinetic energy dissipation devices should be
predicted on the effluent release area
Artigo 49.º - Design of bottom discharges
The design of bottom discharges consists on determining its diameter as
to obtain a emptying time of the main’s stretch that is compatible with the
proper functioning of the system, it shouldn’t be inferior to a sixth of the
diameter of the main where it is installed, having a minimum of 50 mm.
WATER SUPPLY AND DISTRIBUTION SYSTEMS DISCHARGE VALVES / LEGISLATION - DL 23/95, DE 23 DE AGOSTO
2015/2016 153
Function
Allow the complete emptying of the main, or between sectioning
valves whenever necessary (e.g. repair, operation and
maintenance).
Location
a) On every low elevation point
b) upstream/downstream of sectioning valves on ascending/descending
valves, respectively
Types
Small diameter valve
Free or drowned discharge
WATER SUPPLY AND DISTRIBUTION SYSTEMS DISCHARGE VALVES / FUNCTION, LOCATION AND TYPES ON MAINS
2015/2016 154
Practical lesson of the week:
Previous Preparation
Alternative scenarios defined;
Main supply trunks design defined;
Economical study should be started (construction and energy costs).
This week’s objectives :
Storage tank’s capacity;
Calculation of the storage tanks costs.
Location of appurtenances
SANITARY ENGINEERING PROJECT 1: STUDY OF A TRANSMISSION SYSTEM (WEEK 5)
2015/2016 155
RETENTION VALVES
Function, location, instalation
WATER SUPPLY AND DISTRIBUTION SYSTEMS RETENTION VALVES
2015/2016 156
Function
Avoid return flow
Location
Immediately downstream each pump
Closed
Open
WATER SUPPLY AND DISTRIBUTION SYSTEMS RETENTION VALVES / FUNCTION AND LOCATION
2015/2016 157
Hidropneumatic tank
for protection against
water hammer
Retention
valve
Pumping station Pump with downstream protection
against water hammer
1 2 3 4
1 – Retention valve
2 – Mounting joint
3 – Sectioning valve
4 – Discharge valve
WATER SUPPLY AND DISTRIBUTION SYSTEMS RETENTION VALVES / INSTALLATION
2015/2016 158
The pumping station, the retention
valve and the flow and pressure
meters should be installed
between the sectioning valves
Discharge valve
Sectioning valve
Retention valve
Pressure meter
Flow meter
Pump station
P
Su
ctio
n c
ha
mb
er
or
tan
k
General compression pipe
P
P
WATER SUPPLY AND DISTRIBUTION SYSTEMS RETENTION VALVES / INSTALLATION
2015/2016 159
WATER SUPPLY AND DISTRIBUTION SYSTEMS REGULATION AND CONTROL VALVES / HEAD LOSS CHAMBERS
REGULATION AND CONTROL VALVES
PRESSURE LOSS TANKS
Types and function
constructional features
2015/2016 160
Regulation and control valves
Types
Pressure reduction valves (PRV)
Flow control valves
Level valves
Composition - 2 components
Body of the valve)
Pilot circuit(s)
Often, the same valve (mechanical body)
is used with different pilot circuits
depending on the intended purpose
WATER SUPPLY AND DISTRIBUTION SYSTEMS REGULATION AND CONTROL VALVES
2015/2016 161
Installation of a Pressure Reduction Valve with a by-pass circuit
2
1
1 - Discharge circuit
2 - Sectioning valve
3 –Filter
3 4
4 – Mounting junction
5 - Pressure reduction valve
6 –By-pass circuit
5 2
2
6
WATER SUPPLY AND DISTRIBUTION SYSTEMS REGULATION AND CONTROL VALVES / INSTALLATION EXAMPLE
2015/2016 162
WATER SUPPLY AND DISTRIBUTION SYSTEMS PRESSURE REDUCTION DEVICES
Pressure loss tank Pressure Reduction Valve (PRV)
Flow control valves
2015/2016 163
Static energy line, without PLT
Static energy line with PLT
Pressure loss tanks (location)
WATER SUPPLY AND DISTRIBUTION SYSTEMS PRESSURE REDUCTION DEVICES
2015/2016 164
WATER SUPPLY AND DISTRIBUTION SYSTEMS PUMPING STATIONS
PUMPING STATIONS
Components disposition. Examples
2015/2016 165
.
WATER SUPPLY AND DISTRIBUTION SYSTEMS PUMPING STATIONS / UPSTREAM AND DOWNSTREAM PROTECTION
2015/2016 166
WATER SUPPLY AND DISTRIBUTION SYSTEMS PUMPING STATIONS / UPSTREAM AND DOWNSTREAM PROTECTION
2015/2016 167
WATER SUPPLY AND DISTRIBUTION SYSTEMS PUMPING STATIONS
Suction of two
reservoir cells Direct suction of
the upstream
main pipe
2015/2016 168
EXAMPLES
Location of appurtenances
WATER SUPPLY AND DISTRIBUTION SYSTEMS LOCATION OF APPURTENANCES
2015/2016 169
WATER SUPPLY AND DISTRIBUTION SYSTEMS EXAMPLE LOCATION OF APPURTENANCES ON MAIN PIPES
Example 1: 12 km main)
3 km 6 km
or
3 km
Air relief
Discharge valve
Sectioning valve
Regulation valve
2015/2016 170
PLT
SEL
DEL
Example 2: Regulation valves (flow)
WATER SUPPLY AND DISTRIBUTION SYSTEMS EXAMPLE LOCATION OF APPURTENANCES ON MAIN PIPES
2015/2016 171
WATER SUPPLY AND DISTRIBUTION SYSTEMS EXAMPLE LOCATION OF APPURTENANCES ON MAIN PIPES
• Example 3: Mains with derivations
(Schematic and functional representation)
Air relief
Discharge valve
Sectioning valve
Regulation valve
Retention valve
Nota: A representação destes órgãos no perfil da adutora pretende ser
apenas funcional. Os órgãos são realmente instalados nas câmaras de
manobras dos reservatórios ou Estações Elevatórias.
2015/2016 172
WATER SUPPLY AND DISTRIBUTION SYSTEMS EXAMPLE LOCATION OF APPURTENANCES ON MAIN PIPES
Example 4: Stretch with various high and low points.
Static energy line, without PLT
Static energy line with PLT
2015/2016 173
Practical lesson of the week:
Previous preparation:
Storage tank’s capacity;
Calculation of the storage tanks costs.
This week’s objectives :
Location of appurtenances on the longitudinal profile;
Complete Project 1.
SANITARY ENGINEERING PROJECT 1: STUDY OF A TRANSMISSION SYSTEM (WEEK 6)