depm inc - anacond contracting inc. · depm inc. 429 queen street east, toronto, on m5a 1t5 t:...
TRANSCRIPT
DePM Inc. 429 Queen Street East, Toronto, ON M5A 1T5 T: 416•515•7245 F: 416•515•9492
Email: [email protected]
Community Living Toronto 65 The East Mall Project #19139 1 pages total + attachments
ADDENDUM AD04
Date of Issue: Thursday, January 9, 2020 2.0 ARCHITECTURAL ADDENDUM – AD.04
1.1 CLARIFICATION: Detail 5/A-2 (Architectural drawings): New exterior door & door frame N104 and
new door N100 to receive shop finished semi gloss black paint finish to match existing doors and windows. Detail 2/A-2: Canopy to be finished in semi-gloss black paint to match existing metal work.
1.2 CLARIFICATION: Drawing A-0 (Architectural drawings): Parking line work to be completed when weather is appropriate and may not be completed by April 24th substantial completion date.
1.3 CLARIFICATION: Engineering Addendums (Electrical, Mechanical and Communications) have been attached for review & pricing:
1.3.1 Electrical: ADD E01 1.3.2 Mechanical: ADD M01 1.3.3 Communications T01
END OF ADDENDUM – AD04 Issued by:
cc: L.Ruiz, C. Martin, Community Living Toronto
_________
Janice LeBlanc, DIRECTOR OF DESIGN
ADDENDUM
To: DePM Inc. No.: E-01
429 Queen Street East, Toronto, ON M5A 1T5
Date: January 9, 2020
Project: Community Living Toronto 65 East Mall, Toronto, ON M8Z 5W3 Fax/Email: [email protected]
Attention: Ms. Janice Leblanc
From: Jian Wang Project No.: 2019-0426
This Addendum shall be attached to the drawings and specifications and shall form an integral part of the Contract Documents. The contents of this Addendum shall be brought to the attention of all concerned. 1. Reference Drawing: E00.02 – Electrical Details 1 of 2 (Drawing issued
herewith)
1.1. Provide 1” conduit in lieu of 1¼” conduit for communication and A/V cabling in following details:
Detail 10 – Type ‘C’ Combination Wall Outlet
Detail 11 – Type ‘D’ Combination Wall Outlet
Detail 12 – Type ‘A’ Combination Floor Monument
Detail 13 – Communication and A/V Conduit Requirement
2. Reference Drawing: E01.00 – Demolition Layouts (Drawing issued herewith)
2.1. For information only.
3. Reference Drawing: E01.01 – Lighting Layouts (Drawing issued herewith)
3.1. Provide two (2) type ‘LD1’ luminaires in lieu of four (4) type ‘LD1’ luminaires in West Stairwell.
3.2. Revise location of one (1) type ‘D1’ dimmer switch in Recreation Room 118, 119 and 120 (3 in total).
3.3. Provide electrical separate price #3
No.: E-01
To: DePM Inc.
Attention: Ms. Janice Leblanc
Date: January 9, 2020
Project No.: 2019-0426
2
3.3.1. Electrical contractor to provide separate price in base bid to
Provide four (4) type 'LD1' luminaires in lieu of four (4) type 'S1' luminaires in ground floor interior floor lobby (101).
Provide three (3) type 'LD1' luminaires in lieu of three (3) type 'S1' luminaires in second floor interior floor lobby (202).
Refer to interior designer’s drawing for alternative layouts.
4. Reference Drawing: E01.02 – Power and Systems Layouts (Drawing issued herewith)
4.1. Delete electrical rough-ins for one (1) security camera outside the Reception Area 100.
4.2. Delete 120V/1ph power connection to one (1) exhaust fan in Kitchen 107.
4.3. Provide one (1) duplex USB receptacle and electrical rough-ins for one (1) communication outlet in Recreation Room 124.
4.4. One (1) duplex receptacle shall be existing in lieu of providing one (1) new duplex receptacle.
4.5. Provide electrical separate price #4
4.5.1. Electrical contractor to provide separate price in base bid to disconnected and reconnect automatic door opener.
4.6. For clarification:
Shown conduits size between type ‘B’ floor monument and type ‘C’ combination wall outlet and drawing keyed notes 23.
4.7. Provide 120V/1ph power connection to one (1) exhaust fan in Staff Lunchroom 207.
4.8. Provide one (1) duplex receptacle and connected to circuit as noted in 2nd floor corridor 211.
4.9. Revise location of the 120V/1ph power connection to hand dryer in Barrier Free Washroom 212.
4.10. Provide electrical rough-ins for one (1) communication outlet in Print/Copy 214.
No.: E-01
To: DePM Inc.
Attention: Ms. Janice Leblanc
Date: January 9, 2020
Project No.: 2019-0426
3
4.11. Revise requirements for communication and A/V conduits in Meeting Room 218 and 220. Refer to item 1.1 and drawing E00.02 for details.
4.12. Provide one (1) duplex receptacle for security panel and connected to circuit as noted in storage room 223.
End of Addendum
ADDENDUM
To: DePM Inc. No.: M-01
429 Queen St., E, Toronto, ON M5A 1T5
Date: January 9, 2020
Project: Community Living Toronto, 65 The East Mall, Ground & Second Floors, Toronto, ON M8Z 5W3
Fax/Email: [email protected]
Attention: Ms. Janice Leblanc
From: Lebelo Makhene Project No.:
2019-0426
This Addendum shall be attached to the drawings and specifications and shall form an integral part of the Contract Documents. The contents of this Addendum shall be brought to the attention of all concerned. 1. Drawing M-3 – Mechanical Equipment (Drawing not reissued)
1.1. Refer to Miscellaneous Plumbing Equipment Schedule and add specification for Trench Drain ‘TD-1’ as follows:
TD-1 TRENCH DRAIN - 6" WIDE TRENCH SYSTEM Watts #P Trench Drain, UV stabilized talc-filled polypropylene channels with integral 4" (102 mm) and 6" (152 mm) no hub bottom outlets, pre-sloped trench, 6" (152 mm) wide, 48" (1219 mm) long, including frame connectors, grate lockdowns and construction covers, UV stabilized glass-filled polypropylene frame, framed anchored grate.
2. Drawing M-4 – HVAC Plans (Drawing reissued)
2.1. Refer to Kitchen 107 and revise location of Exhaust Fan EF-2 to Staff Lunchroom 207 as shown.
3. Drawing M-5 – Plumbing & Drainage Plans (Drawing reissued)
3.1. Refer to Existing Universal WC 113, BF Shower 117 and Barrier Free WC 211 and delete new floor drain. Provide trench drain ‘TD-1’ at door as shown.
3.2. Refer to Drawing Notes and add Note # 26 as shown.
End of Addendum
SEAL:
JAN 09, 2020
PM Inc.De
THE HIDI GROUP
155 Gordon Baker Road, Suite 200
Toronto, ON M2H 3N5 Canada
t. 416 364 2100 | HIDI.comHIDI
·
·
·
·
·
PM Inc.De
THE HIDI GROUP
155 Gordon Baker Road, Suite 200
Toronto, ON M2H 3N5 Canada
t. 416 364 2100 | HIDI.comHIDI
·
·
·
·
·
·
·
·
ADDENDUM
To: DePM Inc. No.: T-01
Date: January 9, 2020429 Queen Street East, Toronto, ON M5A 1T5
Project:Fax/Email: [email protected]
Attention: Ms. Janice Leblanc
Community Living Toronto 65 East Mall, Toronto, ON M8Z 5W3
From: Simon Harker Project No.: 2019-0426
This Addendum shall be attached to the drawings and specifications and shall form an integral part of the Contract Documents. The contents of this Addendum shall be brought to the attention of all concerned.
1. Reference Drawing: T-03 – Ground & Second Floor Cabling Layouts (Drawing issued herewith)
1.1. Supply and install one (1) communications cable in Print/Copy area [214] as shown on drawing.
End of Addendum
PM Inc.De
THE HIDI GROUP
155 Gordon Baker Road, Suite 200
Toronto, ON M2H 3N5 Canada
t. 416 364 2100 | HIDI.comHIDI