design

Upload: rupack-halder

Post on 10-Jan-2016

13 views

Category:

Documents


0 download

DESCRIPTION

Design

TRANSCRIPT

  • DESIGN OF A GAS PROCESSING PLANT

    Submitted By

    Suman Sarkar (0802019)

    Abdullah Al Mamun (0802021)

    Nilay Kumar Sarker (0802031)

    Sabbir Alam (0802034)

    A Design submitted in partial satisfaction of the requirements for the degree of

    B.Sc. in Chemical Engineering

    Under the supervision of

    Dr. Dil Afroza Begum

    Professor

    Department of Chemical Engineering

    Bangladesh University of Engineering & Technology (BUET)

    Dhaka-1000, Bangladeh

    June 2014

  • Acknowledgements

    We would like to express our most sincere gratitude to our supervisor, Professor Dr. Dil

    Afroza Begum for her inspiration, guidance, support and drive for progress has been a great

    motivation during our work. We are deeply indebted to her for her sincere effort to teach us

    the art of doing design works as a group. His patience, enthusiasm, immense knowledge and

    encouragements have carried us through to the end of the design. Thank you for being the

    greatest mentors. This dissertation would not have been possible without her.

    We also wish to thank our parents and family members. Their concern, encouragement, and

    advice will always be remembered and welcome.

    Sincerely,

    Suman Sarkar (0802019)

    Abdullah Al Mamun (0802021)

    Nilay Kumar Sarker (0802031)

    Sabbir Alam (0802034)

  • Table of Contents Definition of the Project ....................................................................................................... v

    1.1 Definition of the Project ............................................................................................................... vi

    1.2 Raw Material ................................................................................................................................ vi

    1.3 Product Specification ................................................................................................................... vi

    1.4 Utility .......................................................................................................................................... vii

    Selection of Process ............................................................................................................. viii

    2.1 Selection of the Process .......................................................................................... ix

    2.1.1 Different method of Gas sweetening Process ....................................................................... ix

    2.1.2 Different method of Gas Dehydration Process ...................................................................... x

    2.2 Selection Criteria ......................................................................................................................... xi

    2.3 Conclusion ................................................................................................................................... xi

    Process Description ................................................................................................................ xii

    3.1 Process Description .................................................................................................................... xiii

    3.2 Sweetening Plant ........................................................................................................................ xiii

    3.3 Dehydration Plant .......................................................................................................................xiv

    3.4 Stabilizing the Condensates ........................................................................................................xiv

    Design Basis .................................................................................................................................. xv

    4.1 Design Basis................................................................................................................................xvi

    4.2 Product Specification ..................................................................................................................xvi

    4.3 Raw Material Specification ........................................................................................................ xvii

    4.4 Specification of Utilities ........................................................................................................... xviii

    4.5 Meteorological Condition and Soil Properties of the Plant Site ..................................................xx

    Process Block Diagram ....................................................................................................... xxiii

    Process Flow Diagram .......................................................................................................... xxv

    Engineering Calculation: Material and Energy Balance ........................... xxvii

    7.1Equipment List ......................................................................................................................... xxviii

    Major Equipment Design ..................................................................................................... xxix

    8.1 Glycol Absorber design (1/4 of Total Flow) .............................................................................. xxx

    8.2 Sizing of Pumps .......................................................................................................................... xli

    8.3 Sizing of Gas Liquid Separator ...................................................................................................xlv

    8.3 Heat Exchanger ......................................................................................................................... xlvii

    8.4 DEA Contractor Design Calculation ............................................................................................ lvii

    Mechanical Design .................................................................................................................. lxix

  • P & ID .............................................................................................................................................. lxxvii

    Plot Plan ................................................................................................................................... lxxxiii

    14.1 Estimation of Total Capital .................................................................................................. lxxxvi

    Appendix ....................................................................................................................................... xcvii

    Reference ........................................................................................................................................ c

  • Definition of the Project

  • 1.1 Definition of the Project

    A Natural Gas processing plant with a capacity of 550 MMSCFDPipeline quality Natural gasis to

    be produced using raw Natural Gas from the newly invented gas wellis to be set up at Kailashtilla,

    Sylhetin Bangladesh including all off sites, auxiliaries and utilities and supporting facilities.

    1.2 Raw Material

    Raw Natural Gas from 3 producing gas wells (550 MMSCFD)

    DEAmine Solution (32.5 USGPM)

    TEG (866 USGPM)

    1.3 Product Specification

    Composition:

    COMPONENTS MOLE FRACTION

    Methane

    Ethane

    Propane

    i-Butane

    n-Butane

    n-Pentane

    n-Hexane

    H2O

    Nitrogen

    CO2

    0.930973

    0.040237

    0.000658

    0.000022

    0.000014

    0.000007

    0.000002

    0.000101

    0.002029

    0.012562

  • Properties of product:

    Vapour/Phase Fraction

    Molar Density (kgmole/m3)

    Mass Density (kg/m3)

    Molar Heat Capacity (KJ/kgmole-C)

    Mass Heat Capacity (KJ/kg-C)

    Thermal Conductivity (W/m-k)

    Viscosity (cP)

    Molecular Weight

    Z Factor

    1.0000

    3.319

    57.53

    36.98

    2.133

    4.095e-002

    1.357e-002

    17.34

    1.000

    1.4 Utility

    Power

    Own power generation of total Capacity of 2 MW

    Where one is gas generator (1350KW) & a diesel generator (650KW).

    Natural Gas

    Raw Natural Gas from 3 gas wells.

  • Selection of Process

  • 2.1 Selection of the Process

    2.1.1 Different method of Gas sweetening Process

    a) Solid bed Sweetening Process

    b) Aquasorption Process (Wash water process)

    c) Selexol Process

    d) Chemical Absorption process

    e) The Holmes-Stretford Process

    2.1.1.a Solid bed Sweetening Process

    The processes are based upon physical or chemical of adsorption of acid gases on

    solid. Simplicity, high selectivity (only H2S is removed) and process efficiency is

    independent of pressure are the main advantages of the process. Solid bed Sweetening

    Process are of two type- (i) The Iron Sponge Process, (ii) Molecular sieves Process.

    2.1.1.bAquasorption Process (Wash water process)

    This is an effective process for application of high pressure gas with high acid gas

    content and high H2S to CO2 ratio. For high H2S to CO2 ratio gases, operating and

    investment can be reduced by applying this process.

    2.1.1.c Selexol Process

    In selexol process Dimethyl ether of polyethylene glycol (DMPEG) is used as solvent.

    Solubility of the acid gas in DMPEG is directly proportional to the partial pressure of

    the acid gas component. H2S gas is more soluble than CO2.. Higher hydrocarbons

    have the greater solubility.

  • 2.1.1.d Chemical Absorption process

    The alkanol-amin process-

    The alkanol-amine process are the most prominent and widely used process for H2S

    and CO2 removal. They give offer good relatively low cost and good flexibility in

    design and operation. Monoethanolamine (MEA), Diethanolamine (DMA),

    Teriethanolamine (TEA) etc are most common alkanol-amin.

    The hot carbonate process-

    An aqueous potassium carbonate solution is the main reagent of hot carbonate

    process. High concentration & temperature of potassium carbonate and high partial

    pressure of CO2 gas are required for better performance. It is not applicable for gas

    stream which contains only H2S.

    2.1.1.e The Holmes-Stretford Process

    By this process H2S can be removed as elementary carbon but CO2 content remains

    unaltered. This process can be designed for large temperature & pressure range.

    Lower operating cost and flexibility is the main advantage of this process.

    2.1.2 Different method of Gas Dehydration Process

    a) Absorption dehydration Process

    b) Adsorption Process

    Among these, Glycol process for Dehydration and DEAmine Process for Sweetening are

    used in this process design.

  • 2.1.2.a Absorption Process

    Absorption dehydrationis a process where a liquid dessicant is used for the removal of

    water vapor from a gas. Glycol, Ethylene glycol (EG), diethylene glycol (DEG),

    triethylene glycol (TEG), etc are the most common absorbent used in absorption

    dehydration process

    2.1.2.b Adsorption Process

    Adsorption dehydrationis a process where a solid desicant is used for the removal of

    water vapor from a gas stream. Alumina, silica gel, alumina silica gel, Molecular

    sieves are the most common adsorbent used in adsorption dehydration process.

    2.2 Selection Criteria

    As there are many variable in Natural Gas treating process, it is difficult to choose an

    appropriate application area of the process. However among the several factors the most

    significant which are to be considered are

    The types and concentrations of impurities present in the gas and degree of removal

    desired.

    Selectivity of acid gas removal required, if any

    Temperature and pressure at which the sour gas is available and at which the sweet

    gas is to be delivered.

    Volume of the gas to be processed and its hydrocarbon composition.

    CO2 and H2S ratio in the gas.

    The desirability of sulfur recovery due to environmental problems or economics

    2.3 Conclusion

    Economic analysis over decades with respect to Bangladesh has proved that among all

    processes Glycol Dehydration and Amine sweetening process are the most proven ones. So

    nowadays this process is highly adopted throughout the world and involves so many possible

    variations in approach. Most of the processing plants in Bangladesh are built on these

    processes and have been performing at good condition. So, in this design project Glycol

    Dehydration and Amine sweetening process was adopted.

  • Process Description

  • 3.1 Process Description

    The process of producing Pipeline quality Natural Gas is divided into two parts.

    1) Sweetening

    2) Dehydration

    3) Stabilizing the Condensates.

    3.2 Sweetening Plant

    This process flow scheme varies little, regardless of the aqueous amine solution used as the

    sweetening agent. Slight modifications can appear linked to the type of amine which is

    selected and to the optimization of the scheme for specific purposes.

    The general process flow for an amine sweetening plant is shown in PBD. The feed gas (sour

    gas) containing H2S and/or CO2 always must enter the plant through an Inlet Separator to

    remove free liquids and/or entrained solids. The gas from this separator enters the bottom of

    the Absorber and flows upward trough the column in intimate counter-current contact with

    the aqueous amine solution (lean solution). In the column the chemical reaction between the

    amine and the feed gas acid gas occurs and the amine solution absorbs the acid gas. The

    chemical reaction (due to the heat of reaction between the amine and the acid gas) is

    exothermic. It will raise the temperature of the gas. Treated gas (sweet gas) leaves the top of

    the column and the amine solution loaded with acid gas (rich solution) leaves the bottom of

    the column.

    The absorber column operates at the feed gas pressure. A minimum pressure of 4/5 b.a is

    required to make the process feasible and operable. There is no limitation on high pressure as

    far as the process is concerned. If the feed gas be at high temperature, a gas/gas exchanger

    (using the hot treated gas as heating medium) will be provided. This equipment will be

    installed upstream of the inlet separator.

    The rich solution from the Amine Flash Drum then passes through an Amine/Amine Heat

    Exchanger. This heat exchanger serves as a heat conservation device and lowers the total heat

    requirements for the process. The rich solution is heated by the regenerated solution (lean

    solution) coming from the regenerator. Then the rich solution is let down to the operating

  • pressure of the Regenerator (generally between 1.2 and 2 b.a) also called stripper is a

    fractionation column (with trays or packing) with a condenser (using water or air as cooling

    medium) and a reboiler.

    3.3 Dehydration Plant

    Lean, water-free glycol (purity >99%) is fed to the top of an absorber (also known as a

    "glycol contactor") where it is contacted with the wet natural gas stream. The glycol removes

    water from the natural gas by physical absorption and is carried out the bottom of the column.

    Upon exiting the absorber the glycol stream is often referred to as "rich glycol". The dry

    natural gas leaves the top of the absorption column and is fed either to a pipeline system or to

    a gas plant. Glycol absorbers can be either tray columns or packed columns.

    After leaving the absorber, the rich glycol is fed to a flash vessel where hydrocarbon vapors

    are removed and any liquid hydrocarbons are skimmed from the glycol. This step is

    necessary as the absorber is typically operated at high pressure and the pressure must be

    reduced before the regeneration step. Due to the composition of the rich glycol, a vapor phase

    having high hydrocarbon content will form when the pressure is lowered.

    After leaving the flash vessel, the rich glycol fed to the stripper (also known as a regenerator).

    The glycol is thermally regenerated to remove excess water and regain the high glycol purity.

    3.4 Stabilizing the Condensates

    The liquid outlets from the 2 phase separators are sent to Stabilizer. Here hydrocarbon

    condensates are recovered as NGL Gases from the liquid phase. The NGL gas is the

    compressed by a compressor and stored into a storage tank. This NGLs are sent to the LPG

    plant for further processing.

  • Design Basis

  • 4.1 Design Basis

    The following is the design basis that has been assumed for the Natural Gas Processing plant

    producing 550 MMSCFD pipeline quality gas by using DEAmineProcess for Sweetening and

    Try Ethyle Glycol process for dehydration. The process will operate 365 days /yr.

    Design basis includes site conditions, utilities and climate conditions etc. which influence the

    design of individual unit, equipment or facility of the overall project. Selection of the site

    conditions is extremely important in determining the ultimate success of the project.

    4.2 Product Specification

    Composition:

    COMPONENTS MOLE FRACTION

    Methane

    Ethane

    Propane

    i-Butane

    n-Butane

    n-Pentane

    n-Hexane

    H2O

    Nitrogen

    CO2

    H2S

    0.930973

    0.040237

    0.000658

    0.000022

    0.000014

    0.000007

    0.000002

    0.000101

    0.002029

    0.012562

    0.0012

  • Properties of product:

    Vapour/Phase Fraction

    Molar Density (kgmole/m3)

    Mass Density (kg/m3)

    Molar Heat Capacity (KJ/kgmole-C)

    Mass Heat Capacity (KJ/kg-C)

    Thermal Conductivity (W/m-k)

    Viscosity (cP)

    Molecular Weight

    Z Factor

    1.0000

    3.319

    57.53

    36.98

    2.133

    4.095e-002

    1.357e-002

    17.34

    1.000

    4.3 Raw Material Specification

    Raw Natural Gas

    Composition:

    COMPONENTS MOLE FRACTION

    Methane

    Ethane

    Propane

    i-Butane

    n-Butane

    n-Pentane

    n-Hexane

    H2O

    Nitrogen

    CO2

    0.8634

    0.0392

    0.0088

    0.0007

    0.0005

    0.0005

    0.0003

    0.0467

    0.0018

    0.0204

    Pressure 1400 psi

    Temperature 77oF

  • DEAmine

    Composition:

    Components Mole fraction

    DEAmine

    H2O

    CO2

    0.2795

    0.7187

    0.0018

    Try Ethylene Glycol (TEG)

    Composition:

    Components Mole fraction

    Glycol

    H2O

    0.995

    0.005

    4.4 Specification of Utilities

    Electric Power Voltage 380/220 V

    Frequency 50 Hz

    Phase 3 phases

    Process Water

    Temperature 25 oC

    Pressure 0.5 MPa (G)

    OH

    NH

    OH

    OH

    O

    O

    OH

  • Quality:

    PH 6.5 - 8.5

    Total hardness 5 mg

    Total basically 5 mg

    Total Fe3+ 0.1 mg/l

    Turbidity 5 mg/l

    Circulating Cooling Water

    Inlet Outlet

    Temperature < 30 oC 38 oC

    Pressure 0.5 MPa 0.2 MPa

    Fouling factor 6x10-4 M2.hr. oC/kcal

    Turbidity 50 mg/l

    Chlorine < 5 ppm

    PH 6.5 8

    Steam

    State Saturated

    Pressure 7 kg/cm2

    Soft Water

    Conductivity < 1x10-6 Ohm-1.cm-1

  • 4.5 Meteorological Condition and Soil Properties of the

    Plant Site

    Ambient Temperature

    Absolute max. Temperature: 35 oC

    Absolute min. temperature: 12oC

    Designed max. Temperature: 40oC

    Designed min. temperature: 5oC

    Atmospheric Pressure

    Annual average atm. Pressure: 0.11 MPa

    Max. average atm. Pressure: 0.15 MPa

    Min. average atm. Pressure: 0.09 MPa

    Designed average atm. Pressure: 0.2 MPa

    Humidity

    Annual average relative humidity: 80 %

    Max. monthly average relative humidity: 87 %

    Min. monthly average relative humidity: 65 %

    Designed relative humidity: 90 %

    Wind

    Wind direction: Generally wind flows from the north to the south in the winter

    season and from the south to north in the summer in our country.

    Wind Velocity: 45 knot (45 nautical miles per hour or 52 miles/hr)

  • Rain

    Annual avg. rainfall: 2850 mm

    Max. Avg. rainfall: 690 mm

    Max. Monthly rainfall: 235 mm

    Earth bearing capacity

    Load bearing capacity: The soil has a bearing capacity of 0.38 ton/ft2

    required piling is used.

    Corrosive tendency: Non Corrosive

    Climate Condition

    Summer:

    Wet bulb Temperature (max) 29C

    Dry bulb Temperature (max) 32C

    Relative humidity 84%

    Wet bulb temperature (min) 22C

    Dry bulb Temperature (min) 25C

    Dew point 21C

    Relative humidity 80%

  • Winter:

    Wet bulb Temperature (max) 22C

    Dry bulb Temperature (max) 26C

    Dew point 20C

    Relative humidity 72%

    Wet bulb temperature (min) 11OC

    Dry bulb Temperature (min) 9C

    Dew point 9C

    Relative humidity 65%

    Other Information

    Natural catastrophe: A possibility of storm in the months of April-May.

    Value of by-products: No economically feasible by-products are

    obtained.

  • Process Block Diagram

  • Process Flow Diagram

  • Engineering Calculation:

    Material and Energy Balance

  • 7.1Equipment List

    Table 7.1: Table of Equipment List

    Equipment Name Quantity Designation in the HYSYS

    silulation

    Compressor 1 K-100

    Heat Exchanger 2 E-100, E-102

    Adsorber 2 T-100, T-102

    Separator 3 V-100, V-101, V-104

    Pump 2 P-100, P-101

    Storage Tank 1 V-106

    Stripper Column 2 V-102, V-103

    Stabilizer Column 1 V-105

  • Major Equipment Design

  • 8.1 Glycol Absorber design (1/4 of Total Flow) TOP Bottom

    Vapor rate, ft3/sec

    Liquid rate, ft3/sec

    Vapor Density, lb/ft3

    Liquid Density, lb/ft3

    Surface tension, dynes/cm

    4.1

    0.49

    3.6

    70.31

    45.87

    3.7

    0.84

    3.92

    52.12

    22.1

    Assumptions:

    Clean service, no fouling or suspended material

    Tray spacing is to be close as possible, because vertical installation space is a

    premium.

    All equations and data used here refer to the book A P P L I E D PROCESS D E S I G N

    FOR CHEMlCAlAND PETROCHEMICA1 PlANTS, Volume 2, Third Edition by Ernest E.

    Ludwig.

    Calculation of Tower Diameter Souders-Brown method

    W = C(v)[(l) (v)]

    At the Surface Tension 22.1,

    From Figure 8-82, C = 280 for 12-inch tray spacing.

    In this case Vapor rates are close and vdoes not change much from bottom to top of tower.

    W = 280 [3.92(52.12 3.92)]= 3848.796 lbs/hr (ft2)

    = 3848.796

    3600 2.872= 0.3722 ft3/sec (ft2)

    Tower cross-section area, A =

    =

    4.1

    0.3722 ft2 = 11.02 ft2

    Diameter, D = 4 3.1416 = 3.75 ft

    Using Hunt equation:

    Assuming Height clear liquid in bubbling zone on tray, hc = hw + how = 3.5 in.

    S' = St 2.5 hc = 12 2.5 3.5 = 3.25 in.

    At surface tension = 22.1 dynes/cm,

    For Liquid entrained, ew = 5% = 0.05

  • From Figure 8-121, allowable tower velocity = 1.5 ft/sec

    Required tower area = 3.7

    1.5= 2.47 ft2 (bottom, largest)

    Diameter = 4 1.23 3.1416 = 1.78 ft

    Selecting tower diameter = 4.0 ft

    Tray Layout Based on 4.0 ftDiameter Tower

    Using a segmental downcomer on a cross-flow tray.

    From the residence time in downcomers for bubble cap trays and at the tray spacing of 12

    inches, selecting an allowable liquid velocity of .4 ft/sec.

    Downcomer area = . 84 .4= 2.8 ft2

    Total tower area =3.1416 4.02 4= 12.57 ft2

    Percent of tower area = 2.8

    12.57 100 % = 22.3%

    Using Figure 8-100 for segmental downcomers, at 22.3% downcomer area, the weir length is

    89% of tower diameter.

    Weir length, lw= 0.89 4.0 = 3.56 ft

    Since standard details for fabrication are already available for a tray with a 19.5-in. weir in a

    30-in. tower (65% of dia.), try this asfirst tray examined. This is 6.8% of tower cross

    sectional area.

    Downcomer area = 0.068 12.57 = 0.86 ft2.

    Hole Size

    Assuming 3/16-in. dia. 3/5-in. pitch

    This is spacing of 2.66do, and is asclose as good design would suggest. Using 1/2-in. tray

    thickness.

    Ratio,=do

    =

    3/16

    3/5 = 0.3125

    Percent hole area = 13% (of perforation area only) as shown in Figure 8-143.

  • Minimum Hole Velocity: Weeping

    Assuming vo (v)1/2= 13

    Assuming Submergence = 4 in. = hsl= hdl (neglecting /2)

    Dry Tray Pressure drop, hdt = 0.003(vo2 v)

    water

    L (1 2)/Co2

    The hole dia

    tray thickness ratio=

    3/16

    1/2 = 1.5

    From Figure 8-126, = 0.2

    From Figure 8-128, orifice coefficient, Co= 0.78

    hdt = 0.00313264.2(1.22)

    52.12.782= 1 in. liquid

    Effective head

    For hsl= 4, Fs

  • For hsl= ,Fs14 and hsl= 1.25 inch

    Total wet tray pressure drop, ht= 5.4 + 1.35= 6.75 inches liquid

    Liquid Back-up or Height in Downcomer Hd= ht+ (hw+ how) + + hd

    Hd= 6.75 + 1.25 + 0 + 0 (assuming and hd to be confirmed) Hd= 8.0 in. liquid

    The limit on Hd for flooding is St/2= 12/2= 6 in.

    Therefore Fs= 30 appears to be a good assumption.

    Design Hole Velocity

    A velocity represented by Fs factor between minimum and maximum limits is to be selected.

    30 >Design >25

    A median value of Fs= 27.5 is selected, because freedom to operate above and below the

    design value is preferred in this case.

    Design Basis

    Fs= 27.5

    1. Weir Height selection: hw= 3.0 inch

    2. Weir Length selection:For good design, ratio of weir length to tower diameter is 0.5

    to 1.0

  • Selected weir length lw = 4.0 ft.

    Weir length to tower diameter ratio is 1.0

    ()

    2.5 =

    .84448.8

    4.02.5 = 11.78

    From figure-8-105, correction factor: Fw: 1.0

    Francis Formula , how = .092 ()

    2/3 = .092

    .84 448.8

    4.0

    2/3

    in = 1.9 in

    3. Submergence: hsl= (Fw) (hw) + how= (1) (3.0) + 1.9 = 4.9 in. liquid

    4. Downcomer pressure loss:

    Clearance between bottom of downcomer and plate = 3-in. max. Underflow area = (9.5 in.) (3

    in.)/144 = 0.2 ft2. Because this is less than the downflow area, it must be used for pressure

    drop determination. No inlet weir used on this design.

    hdu= 0.56

    Lg

    449AD

    2 = 0.56[

    .84449

    449 0.2]

    2 = 9.88 in liquid

    5. Dry tray pressure drop:

    hdt = 0.00327.5264.2(1.12)

    52.12.782= 4.55 in. liquid

    6. Effective head:hsl= 4.9 in.

    he= 2.55 in. liquid for Fs>14, Figure 8-130

    7. Total wet tray pressure drop:

    8.

    ht= 4.55 + 2.55 = 7.10 in. liquid

    9. Total tower pressure drop for 19 trays:

    (tower)= 7.119(70.31+52.12)

    17282 = 4.78 psi

    which is not greater than 5 psi. So, it is satisfactory.

    10. Number of holes required:

    Assumed Hole size = 3/16 in.

    Hole spacing or pitch = 3/5 in.

  • From Figure 8-144, Holes/(in.2 plate area) = 3.25

    Area of a 3/16 -in. hole = 0.0276 in.2

    At Design condition: Fs = 27.5

    Top Vapor Velocity, vo,Top =

    () =

    27.5

    3.6 = 14.5 ft/sec

    Bottom Vapor Velocity, vo,Bottom = =

    () =

    27.5

    3.92= 13.9 ft/sec

    Number of holes required = Vapor Flow rate 144

    vo hole area

    at Top = 4.1144

    14.5.0276= 1476

    at Bottom = 3.7144

    13.9.0276= 1389

    At Flooding condition: Fs = 30

    Top Vapor Velocity, vo,Top =

    () =

    30

    3.6 = 15.82 ft/sec

    Bottom Vapor Velocity, vo,Bottom = =

    () =

    30

    3.92= 15.16 ft/sec

    Number of holes required = Vapor Flow rate 144

    vo hole area

    at Top = 4.1144

    15.82.0276= 1353

    at Bottom = 3.7144

    15.16.0276= 1274

    At Weeping condition: Fs = 25

    Top Vapor Velocity, vo,Top =

    () =

    25

    3.6 = 13.18 ft/sec

    Bottom Vapor Velocity, vo,Bottom = =

    () =

    25

    3.92= 12.63 ft/sec

    Number of holes required = Vapor Flow rate 144

    vo hole area

    at Top = 4.1144

    13.18.0276= 1624

    at Bottom = 3.7144

    12.63.0276= 1529

    11. Tower Height:

    Height of the column

    H = (N-1) + Ht + Hb + Htr

    Total tray thickness ,Htr=

    12 ft =

    190.5

    12 ft = 0.8 ft

  • Space at the top typically an additional 5 to 10 ft is needed to allow for disengaging space.

    The bottom of the tower must be tall enough to serve as a liquid reservoir. At bottom portion,

    top of both inlet and outlet pipes should be at least 400 to 450 mm below the bottom tray.

    Additional top height, Ht= 5ft

    Additional bottom height, Hb= 2.2ft

    Number of tray, N= 19

    H = [{(19-1) 12}/12 + 5 + 2.2 + 0.8]ft

    = 26 ft

    12. Mechanical tray layout details:

    A total of 4-in. on diameter for extension of tray ring-type support into the tower. This

    reduces available tray area.

    Assuming 6.5-in. clearance (no holes) between inlet downcomer and first row of holes. The

    6.5 in. could be reduced to 4 in. minimum if an inlet weir were used.

    Assuming 4-in. clearance (no holes) between outlet weir and adjacent row of holes.

    Downcomer width = .12 4 = 0.56 ft = 5.76 in (From Figures 8-100 at standard 65% weir

    length downcomer width is 12% of Tower diameter).

    Area determinations:

    Area of segment of circle (2) with chord AD:

    Diameter circle (2) = 48 - 4 = 44 in.

    Height of chord = 44

    2 (

    48

    2 5.76 6.5)= 10.26 in.

    Chord height/circle dia. H/D =10.26

    44 = 0.23

    Referring to Perrys Handbook, (pg. 32, 3rd Ed.)

    Area = 0.133 442= 258 in2

    Area of segment of circle (2) width chord BC:

    Height of chord = 44

    2 (

    48

    2 5.76 4)== 7.76 in

    H/D = 7.76

    44= 0.176

    Area = 0.08 442= 155in2

    Area of circle (2) = 442= 6028 in.2

    Area available for holes = 6028 (258 + 155) = 5615 in.2

  • Area required for holes = 1624

    3.25holes/in2= 500 in2.

    Number of holes = 1624

    Area = 5615 in.2

    Other Mechanical Designs:

    Maximum Operating Temperature = 38oC = 311k

    Maximum Operating Pressure = 1250 psi = 88 kg/cm2

    a) Shell Thickness:

    Material = SA-516-70 Carbon Steel

    Specific Gravity, s = 7.7

    Maximum allowable stress, fs = 1300 kg/cm2

    Welding efficiency, j = 0.9

    Design Pressure, PD = 1.5 Operating Pressure = 1.5 88 = 132 kg/cm2

    Internal Shell or column Dia, D = 4 ft = 1.2192 m = 1219.2 mm

    Here, C = corrosion Allowance = 3 mm

    Thickness, ts= PDD

    2 fs j PD + C =

    1321219.2

    2 1300 .9 132 + 3 = 73mm

    b) Tray:

    Thickness = 1/2 inch = 0.5 inch

    Material = SA-516-70 Carbon Steel

    Sieve Tray, hole size = 3/16 inch, pich = 3/5 inch, Triangular.

    Tray Spacing = 12 inch

    c) Support for trays:

    A total of 4-in. on diameter for extension of tray ring-type support into the tower.

    Material: Carbon steel.

  • d) Downcomer and Weir:

    Material = Carbon steel.

    e) Support for Column:

    Skirt type, Height = 6.6 ft, Material = Carbon steel.

    f) Heads:

    Material = SA-516-70 Carbon steel.

    Permissible tensile stress = 1300 kg/cm2

    Thickness of Head,

    th = PDRcW

    2 fs j

    =1321219.21.54

    2 1300 .9

    = 106 mm

    = 4.042 inch

    Rc = Crown Radius =1219.2

    W = Stress intensification factor = 1

    4

    3 + RcRl

    = 1.54 mm

    Where, Rl = Knuckle radius = 0.1 Rc

    g) Insulation and Coating:

    Insulating material: Polyurethane

    Insulating width: 4 inch

    Coating material: Zinc Sulfate

    Coating width: 0.06 inch

  • 8.2 Sizing of Pumps

    Pump (P-100) of Dehydration plant

    Given Density, = 972kg/m3 = 60.68 lb/ft3

    Viscosity, = 17.48 cP = 11.746 10-3lb/sec.ft

    Temperature = 62.370 F

    Mass flow rate =14.6487kg/hr = 7110.2 kg/hr = 1.975 kg/sec = 4.35 lb/sec

    Volumetric flow rate q = 072.068.60

    35.4

    m ft3/sec

    Di opt = 3.9 q0.45 0.13 [Peters and Timmerhaus]

    = 3.9 0.0720.45 60.680.13

    = 2.035 inch

    Let us assume, Nominal diameter = 2 inch and Schedule number = 40

    Outer Diameter, OD = 2.38 inch = 0.198 ft

    InnerDia, ID = 2.067 inch = 0.172 ft[From table D-13 (Peters and Timmerhaus)]

    Area, A = ID2/4 = (0.172)2/4 = 0.0233 ft2

    v = q/A = 0.072

    0.0233=3.092ft/sec

    Re = Dv

    =

    0.1723.0960.68

    11.746 103 = 2814.15

  • For commercial steel /D = 0.000885 for 2.067 inch dia [from Ernest E. Ludwig (vol-1)

    page- 68]

    From Moody diagram (Franzini, page -226)

    Friction factor f = 0.0195

    Loss calculation

    1. For 90 elbow(2 pcs)

    F1= 2k (v2/2g)

    = 20.233.09^2

    232.2

    =0.0682ft

    2. For Tee (1pcs)

    F2=k (v2/2g)

    = 1.83.09^2

    232.2

    =0.267ft

    3. For Gate valve (2 pcs)

    F3 = 2k (v2/2g)

    =20.193.09^2

    232.2

    = 0.0563 ft

    4. Entrance loss

    F4 = k (v2/2g)

  • = 0.53.09^2

    232.2

    = 0.0741ft

    5. Exit loss

    F5 = k (v2/2g)

    = 13.09^2

    232.2

    = 0.1482ft

    6. Friction loss

    F6 = f(L/D)(v2/2g)

    = 0.0195 110

    0.172

    3.09^2

    232.2

    =1.83ft

    Total Loss, hL= F = (0.0682+ 0.267+ 0.0563 + 0.0741+ 0.1482+ 1.83)ft

    = 2.4438 ft

    Energy Calculation:

    Using Bernoullis equation

    P1/ + Z1 +V12/2g +hA -hL=P2/ +Z2 +V22/2g

    Given that

    P1= 20 KPa = 2.9 psi

    P2= 9020KPa = 1308.6 psi

    Z2-Z1= 40ft

  • V1=V2=3.09ft/sec

    = 60% (assume)

    hA=P2 P1

    + (Z2-Z1)+ (V2

    2 - V12)/2g + hL

    = 1308.6 2.9

    60.68 32.2 + 40 + 0 + 2.4438

    =43.112ft

    P = hq/(500). = (60.6832.20.07243.112)/(5500.6)

    = 17.1hp

    Assuming over design, shaft power = 17.11.1= 18.8hp

    We can select 20 HP centrifugal pump.

    So straight centrifugal pump, model DUGL12A-20 was selected.

    Specification of pump:

    Material: cast iron

    RPM: 1750

    Flow capacity: 770GPM (max)

    Impeller size:

    Weight: 255 lbs

    Price: $ 4662.00

  • 8.3 Sizing of Gas Liquid Separator

    Given,

    Vapor density, v= 4.854 lbm/ft3

    Liquid density, L = 55.703 lbm/ft3

    Molecular weight of vapor, MWvap = 17.766 lbm/ lbmole

    Vapor flow rate, V = 18.37 lbmole/sec

    k = 0.40for up-flow [Ludwig, vol. 1, Page-256]

    Design velocity

    VD = kvl vv

    = 0.40 ( 55.703 4.854

    4.854)^0.5

    = 1.3 ft/sec

    & Actual flow rate

    ACFS = V MWvap

    v

    = 67.23 ft3/sec

    Flow area (cross sectional),

    Ac=ACFS

    VD ft2

    = 67.23

    1.3= 51.72 ft2

    Inner Diameter, ID = (4 Ac /) 0.5 = (4 51.72 /3.14)0.5= 8.12 ft

  • For vertical separator, (h/D) min = 5

    Minimum height, h = 5 8.12 = 40.6 ft

    Thickness calculation

    Here, operating pressure, P = 800 psi

    Design pressure, PD= 1.5 P = 1.5 800 = 1200 psi

    Thickness, ts = PD D

    2 j0.2PD + Cs

    Where

    PD = Design pressure

    fs= Allowable working stress =1600 psi [ Low-alloy steel for resistance to H2 & He ]

    E= Joint efficiency (dimensionless) = 80%

    Cs=corrosion allowance= 0.12 inch

    ts = 1200 8.12 12

    2 1600 0.8 0.2 1200 + 0.12 = 39.6 inch = 3.3 ft

    (Ref: Peter and Timmerhaus, Chap 14, table 3 and 4, page: 537, 538 and 721)

  • 8.3 Heat Exchanger

    Thermal Design of Heat Exchanger (E-100)

    Tube side (Cold fluid)

    Inlet fluid: Glycol to be preheated

    Outlet fluid: Preheated glycol to absorber

    Inlet temperature: 67.59o F

    Outlet temperature: 770F

    Tavg = 72.2950F

    Density (by interpolation) =70.58 lb/ ft3

    Viscosity = 22.52 cP=54.5 lb/ft-hr

    Thermal conductivity K= 0.192 Btu/hrft0F

    Heat capacity Cp =0.5891 Btu/lb0F

    Flow rate, Wg = 4.88 x 105 lb/hr

    q = WgCpt = (4.88 x 105 x 0.5891 x 9.41) Btu/hr

    = 2.7x 106 Btu/hr

    Shell side (Hot fluid)

    Inlet fluid: Dry gas

    Outlet fluid: Sales gas

    Inlet temperature: 99.880 F

    Outlet temperature: 94.860F

    Tavg = 97.370F

  • Density (by interpolation) = 3.601 b/ft3

    Viscosity = 0.01362 cP=0.0333 lb/ft-hr

    Thermal conductivity K = 0.023875 Btu/hrft0F

    Heat capacity Cp = 0.5105 Btu/lb0F

    Flow rate,Wi = 1.05 x 106 lb/hr

    q = WiCpt = (1.05 x 106 x 0.5105 x 5.02) Btu/hr

    = 2.7x 106 Btu/hr

    Tube side calculation

    LMTD calculation:

    (First pass counter-current flow)

    Hot Cold Difference

    Higher 99.88 (T2) 67.59 (t1) 32.29

    Lower 94.86 (T1) 77 (t2) 17.86

    Difference 5.02 9.41 14.43

    LMTD =(22)(11)

    ln ((22)

    11)

    R =21

    21 S=

    21

    T2t1

    (LMTD)' = 4.39

    ln (22.88/27.27)R =

    5.02

    9.41 S =

    9.41

    99.8867.59

    = 25.01oF = 0.53 = 0.2914

  • From Fig 18 (kern) Page-828 for 1-Shell pass & 2 or more Tube pass heat exchanger

    FT = 0.95 which is satisfactory..

    Corrected LMTD = FT x (LMTD)'

    = 0.95 25.01

    = 24.510F

    Calculation of heat transfer area and tube numbers

    Q = Uassume Arequired LMTD

    For light - heavy organics

    Overall U = 10-40 Btu/hr ft20F

    Assume, Uassume = 35 Btu/hr ft20F

    A = 2

    6

    4.314751.2435

    107.2ft

    LMTDU

    Q

    assumee

    Iteration- 1

    The first iteration is started assuming 1 shell pass & 2 tube pass(np).

    Fixed tube plate

    1in. OD(d0), 14 BWG, 11

    4 in. square pitch, ID (di) 0.834 in.

    Assuming tube length (Lt) is 20 ft.

    So, no of tubes, nt =

    d0Lt= 562

    Nearest count from table 9(kern) Page-841 is 574

  • Now, Reynolds no, Re =4wgnp

    dint= 892 < 104

    Iteration- 2

    2nd iteration is started assuming 1 shell pass & 4 tube pass(np).

    Fixed tube plate

    1in. OD(d0), 14 BWG, 11

    4 in. square pitch, ID (di) 0.834 in.

    Assuming tube length (Lt) is 30 ft.

    So, no of tubes, nt =

    d0Lt= 561

    Nearest count from table 9(kern) Page-841 is 562

    Now, Reynolds no, Re =4wgnp

    dint= 1100 < 104

    Iteration- 3

    3rd iteration is started assuming 1 shell pass & 4 tube pass(np).

    Fixed tube plate

    1.25 in. OD(d0), 16 BWG, 19

    16 in. square pitch, ID (di) 1.12 in.

    Assuming tube length (Lt) is 26 ft.

    So, no of tubes, nt =

    d0Lt= 259

    Nearest count from table 9(kern) Page-841 is 268

    Now, Reynolds no, Re =4wgnp

    dint= 5647 < 104

  • Iteration- 4

    4th iteration is started assuming 1 shell pass & 6 tube pass(np).

    Fixed tube plate

    1.5 in. OD(d0), 16 BWG, 17

    8 in. square pitch, ID (di) 1.37 in.

    Assuming tube length (Lt) is 45 ft.

    So, no of tubes, nt =

    d0Lt= 178

    Nearest count from table 9(kern) Page-841 is 182

    Now, Reynolds no, Re =4wgnp

    dint= 16560 > 104

    Therefore, our final tube no 182 & Reynolds no (Re) is 16560 selected shell ID (Ds) is 35 in.

    Now,

    Nu =

    k

    hidi= 0.027 Re0.8

    3

    1

    K

    Cp(

    )0.14

    So, hi = 175.74 Btu/hrft2 0F

    hio = hi x

    =151.92 Btu/hrft2 0F

    Shell side calculation

    Assumption:

    25 % cut segmental baffles

    Baffles spacing, B = 0.5 Ds = 17.5 in = 1.46 ft (half of the shell ID is selected)

    Pitch, Pt = 17

    8 in. square pitch = 0.15625 ft

    Clearance, C = Pt do = 0.03125 ft

  • Shell ID, Ds = 35 in = 2.92 ft

    So, flows area, as =T

    shell

    P

    BCID

    = 0.8526 ft2

    Mass velocity, Gs = Wi / as = 1.23 x 106 lb/hrft2

    Equivalent dia, De =

    o

    T

    d

    dP

    4/4 20

    = 0.124 ft

    Reynolds no, Re = .

    = 465000

    So,

    Nu =

    k

    hoDe= 0.36 Re0.55

    3

    1

    K

    Cp(

    )0.14

    So, ho = 184 Btu/hrft2 0F

    Clean overall heat transfer coefficient (Uc) calculation

    Uc =(1

    + +

    2+

    1

    +

    Rd)-1 = 42.3 Btu/hrft20F

    Over design calculation:

    % of over design =

    = 20.86 % < 30 %

    So, design is accepted.

    Dirt factor calculation

    Clean overall heat transfer coefficient, Uc = 42.3 Btu/hrft20F

  • Assumed overall Coefficient, Ud = 35 Btu/hrft20F

    Dirt factor, Rd = Dc

    Dc

    UU

    UU

    = 0.00098

    Because for natural gas Rd, allowable=0.001 (Ref: Mechanical Design of Process System (vol-

    2))

    Therefore, Rd is acceptable.

    Pressure drop calculation

    Tube side calculation

    Flow area, at= passesofNo

    tubeperareaflowtubesofNo

    = 6

    01021.0182

    = 0.309 ft2

    Mass velocity,Gt = Wg/at = 1.6 104lb/hrft2

    For Ret = 16560

    From figure 26, tube side friction factors correlation (Kern) Page-836

    Friction factor, f = f = 0.288 ft2/ft2

    Assume, t =1

    So, frictional pressure drop, PsitSGdi

    nLtGfP

    ptf 22.2

    ...1022.5

    ..10

    .2

    Return loss rP = 1.334 10-13 (2np 1.5)tG2.

    = 0.34 Psi

  • So, total pressure drop in tube side, TP = fP + rP = 2.56 Psi < 8.7 psi which is acceptable.

    Shell side calculation

    Pitch, Pt = 17

    8 in. square pitch = 0.15625 ft

    Clearance, C = Pt do = 0.03125 ft

    Shell ID, Ds = 35 in = 2.92 ft

    Flows area, as = 0.8526 ft2

    Mass velocity, Gs= 1.23 x 106 lb/hrft2

    Reynolds no, Re = 465000

    No of baffles, nb=

    = 30.82 ~ 31

    From figure 26, tube side friction factors correlation (Kern) Page-836

    Friction factor, f = 0.1296 ft2/ft2

    s =1(assuming)

    So, pressure drop = sSGDe

    nDssGfPs

    b

    ...1022.5

    )1.(..10

    2

    = 9.38 Psi < 14.5 Psi, which is acceptable.

  • Mechanical design

    Tube side properties:

    Materials: Stainless Steel

    No. of pass: 6

    Shell side properties:

    Materials: Stainless Steel

    No. of shell: 1

    Shell dia, Ds = 35 in

    Working pressure, P = 1247 Psi

    Design pressure, Dp = Wp 1.1 = 1371.7 Psi

    Permissible working pressure, f = 11000 Psi

    Welding efficiency, j = 0.9

    Shell thickness, ts= Pjf

    DsP

    ..2

    .

    = 2.088 in.

    Corrosion allowance =1/8 inch= 3.175 mm

    Shell thickness including corrosion allowance = (2.088+1/8)

    = 2.205 in.

    Nozzles

    Take inlet and outlet nozzles as 100mm diameter.

    Vent nozzle = 25mm diameter

    Drain nozzle = 25mm diameter

  • Relief Valve = 50 mm diameter.

    Nozzle thickness = [ P x Di ] / { 2 f J - P }

    = 0.68 mm

    Minimum nozzle thickness is 6mm and 8mm is chosen which includes

    thecorrosionallowance.

    Transverse baffles

    Number of Baffles = 31

    Baffle cut = 25%

    Baffle thickness = 6mm (standard)

    Flange design

    Flange is ring type with plain face.

    Flange material: IS 2004-1962 Class 2 Carbon Steel

    Bolting steel: 5% Chromium, Molybdenum Steel

    Gasket Material: Asbestos

    Shell OD = 37.205 in

    Shell Thickness = 2.205 in

    Shell ID = 35 in

    Allowable stress for flange material = 100 N/mm2

    Allowable stress of bolting material = 138 N/mm2

    Using matche.com we have estimated cost for this heat exchanger is $158900.

  • 8.4 DEA Contractor Design Calculation

    TOP Bottom

    Vapor rate, ft3/sec

    Liquid rate, ft3/sec

    Vapor Density, lb/ft3

    Liquid Density, lb/ft3

    Surface tension, dynes/cm

    4.1

    0.49

    3.65

    70.20

    45.60

    3.73

    0.85

    3.96

    52.00

    22.00

    Assumptions:

    Clean service,

    No fouling or suspended material,

    Tray spacing is to be close as possible, because vertical installation space is a

    premium.

    All equations and data used here refer to the book A P P L I E D PROCESS D E S I G N

    FOR CHEMlCAlANDPETROCHEMICA1 PlANTS, Volume 2, Third Edition by Ernest E.

    Ludwig.

    Calculation of Tower Diameter Souders-Brown method

    W = C(v)[(l) (v)]

    At the Surface Tension 22,

    From Figure 8-82, C = 280 for 12-inch tray spacing.

    In this case Vapor rates are close and vdoes not change much from bottom to top of tower.

    W = 280[3.96(52.00 3.96)]= 3862 lbs/hr (ft2)

    = 3862

    3600 2.872= 0.3735 ft3/sec (ft2)

    Tower cross-section area, A =

    =

    4.1

    0.3735 ft2= 10.98 ft2

    Diameter, D = 4 3.1416 = 3.73 ft

    Using Hunt equation:

    Assuming Height clear liquid in bubbling zone on tray, hc = hw + how = 3 in.

    S' = St 2.5 hc = 12 2.5 3 = 4.5 in.

  • At surface tension = 22.0 dynes/cm,

    For Liquid entrained, ew = 5% = 0.05

    From Figure 8-121, allowable tower velocity = 1.5ft/sec

    Required tower area = 3.73

    1.5= 2.49 ft2 (bottom, largest)

    Diameter = 4 2.49 3.1416 = 1.78 ft

    Selecting tower diameter = 4.0 ft to meet the requirement of both bottom and top

    diameter of the absorber.

    Tray Layout Based on 4.0ft Diameter Tower

    Using a segmental downcomer on a cross-flow tray.

    From the residence time in downcomers for bubble cap trays and at the tray spacing of 12

    inches, selecting an allowable liquid velocity of 0.3ft/sec.

    Downcomer area = 0.85 0.3= 2.83 ft2

    Total tower area =3.1416 4.02 4= 12.57ft2

    Percent of tower area = 2.83

    12.57 100 % = 22.5%

    Using Figure 8-100 for segmental downcomers, at 22.5% downcomer area, the weir length is

    89% of tower diameter.

    Weir length, lw= 0.894 = 3.56 ft

    Since standard details for fabrication are already available for a tray with a 19.5-in. weir in a

    30-in. tower (65% of dia.), try this asfirst tray examined. This is 6.8% of tower cross

    sectional area.

    Downcomer area = 0.068 12.57= 0.86 ft2.

    Hole Size

    Assuming 3/16-in. dia. 1/2-in. pitch

    This is spacing of 2.66do, and is asclose as good design would suggest. Use 1/8 in. tray

    thickness.

    Ratio,=do

    =

    3/16

    1/2 = 0.375

    C= 2.66do

  • Percent hole area = 12.8% (of perforation area only) as shown in Figure 8-143.

    Minimum Hole Velocity: Weeping

    Assuming Fs= vo (v)1/2= 13

    Assuming Submergence = 3 in. = hsl= hdl (neglecting /2)

    Dry Tray Pressure drop, hdt = 0.003(vo2 v)

    water

    L (1 2)/Co2

    The hole dia

    tray thickness ratio=

    3/16

    1/8= 1.5

    From Figure 8-126, = 0.128

    From Figure 8-128, orifice coefficient, Co= 0.78

    hdt = 0.00313264.2(1.1282)

    52.782= 1.01 in. liquid

    Effective head

    For hsl= 3, Fs

  • From Figure 8-128, orifice coefficient, Co= 0.78

    hdt = 0.00320264.2(1.1282)

    52.782= 2.4 in. liquid

    New Effective head

    For hsl= 2.25, Fs>14

    Reading from Figure 8-130; effective head, he= 1.65 in. liquid

    New Total Wet Tray Pressure Drop

    ht= hdt + he = 2.4 +1.65 = 4.05 in. liquid

    Using Figure 8-131 Curve A, and ht= 4.05 in. liquid

    Reading Weep point velocity = 21.6= vom (v)1/2

    Because vom (v)1/2= 21.6 is greater than the assumed value of 20, the 20 cannot be used.

    Assuming new Fs = vo (v)1/2= 25

    Assuming Submergence = 1.25-in. = hsl= hdl (neglecting /2)

    Dry Tray Pressure drop, hdt = 0.003(vo2 v)

    water

    L (1 2)/Co2

    The hole dia

    tray thickness ratio=

    3/16

    1/2= 1.5

    From Figure 8-126, = 0.128

    From Figure 8-128, orifice coefficient, Co= 0.78

    hdt = 0.00325264.2(1.1282)

    52.782= 3.74 in. liquid

    New Effective head

    For hsl=1.25,Fs>14

    Reading from Figure 8-130; effective head, he= 1.35 in. liquid

    New Total Wet Tray Pressure Drop

    ht= hdt + he = 3.74 +1.35 = 5.09 in. liquid

    Using Figure 8-131 Curve A, and ht= 5.09 in. liquid

    Reading Weep point velocity = 24.4= vom (v)1/2

  • Because vom (v)1/2= 24.4 is smaller than the assumed value of 25, the 25.0 is accepted value.

    Maximum Hole Velocity at Flood Conditions

    Assume F, = vo (v)1/2= 28 max.

    Submergence = 1.25-in. = hsl= hdl (neglecting /2)

    Dry Tray Pressure drop, hdt = 0.00328264.2(1.1282)

    52.782= 4.65 in. liquid

    Effective head, he= 1.35 in. liquid, for Fs>14 and hsl= 1.25 inch

    Total wet tray pressure drop, ht= 4.65 + 1.35= 6 inches liquid

    Liquid Back-up or Height in Downcomer Hd= ht+ (hw+ how) + + hd

    Hd= 6 + 1.25+ 0 + 0 (assuming and hd to be confirmed) Hd= 7.25 in. liquid

    The limit on Hd for flooding is St/2= 12/2= 6 in.

    Therefore Fs= 28 appears to be a good assumption.

    Design Hole Velocity

    A velocity represented by Fs factor between minimum and maximum limits is to be selected.

    28>Design >25

    A median value of Fs= 26.5 is selected, because freedom to operate above and below the

    design value is preferred in this case.

    Design Basis

    Fs= 26.5

    13. Weir Height selection: hw= 3 inch

    14. Weir Length selection:For good design, ratio of weir length to tower diameter is 0.5

    to 1.0

    Selected weir length lw = 4.0 ft.

    Weir length to tower diameter ratio is 1.0

    ()

    2.5 =

    .85448.8

    4.02.5 = 11.79

    From figure-8-105, correction factor: Fw: 1.0

    Francis Formula, how = .092 ()

    2/3

    = .092 .85 448.8

    4.0

    2/3

    in = .92 in

  • 15. Submergence: hsl= (Fw) (hw) + how= (1) (3) + 1.92= 4.92 in. liquid

    16. Downcomer pressure loss:

    Clearance between bottom of downcomer and plate = 3-in. max. Underflow area =

    (43.14161.52 in2.)/144 = 0.2ft2. Because this is less than the down flow area, it must be

    used for pressure drop determination. No inlet weir used on this design.

    hdu= 0.56

    Lg

    449AD

    2 = 0.56[

    .85448.8

    449 0.2]

    2 = 10.1 in liquid

    17. Dry tray pressure drop:

    hdt = 0.00326.5264.2(1.1282)

    52.782= 4.25in. liquid

    18. Effective head:

    hsl= 4.92 in.

    he= 2.55 in. liquid for Fs>14, Figure 8-130

    19. Total wet tray pressure drop:

    ht= 4.25+ 2.55= 6.8 in. liquid

    20. Total tower pressure drop for 20 trays:

    (Tower)=6.820(70.2+52)

    17282= 4.8 psi

    4.8 psi is not greater than 5 psi. So, it is satisfactory.

    21. Number of holes required:

    Assumed Hole size = 3/16 in.

    Hole spacing or pitch =1/2 in.

    From Figure 8-144, Holes/(in.2 plate area) = 5

    Area of a 3/16 -in. hole = 0.0276 in.2

    At Design condition: Fs = 26.5

    Top Vapor Velocity, vo,Top =

    () =

    26.5

    3.65 = 13.87 ft/sec

  • Bottom Vapor Velocity, vo,Bottom = =

    () =

    26.5

    3.96= 13.32 ft/sec

    Number of holes required = Vapor Flow rate 144

    vo hole area

    at Top = 4.1144

    13.87.0276= 1542

    at Bottom = 3.73144

    13.32.0276= 1461

    At Flooding condition: Fs = 28

    Top Vapor Velocity, vo,Top =

    () =

    28

    3.65 = 14.66 ft/sec

    Bottom Vapor Velocity, vo,Bottom = =

    () =

    28

    3.96= 14.07 ft/sec

    Number of holes required = Vapor Flow rate 144

    vo hole area

    at Top = 4.1144

    14.66.0276= 1460

    at Bottom = 3.73144

    14.07.0276= 1383

    At Weeping condition: Fs = 25

    Top Vapor Velocity, vo,Top =

    () =

    25

    3.65 = 13.09 ft/sec

    Bottom Vapor Velocity, vo,Bottom = =

    () =

    25

    3.96= 12.56ft/sec

    Number of holes required = Vapor Flow rate 144

    vo hole area

    at Top = 4.1144

    13.09.0276= 1634

    at Bottom = 3.73144

    12.56.0276= 1550

    22. Mechanical tray layout details:

    A total of 5-in. on diameter for extension of tray ring-type support into the tower. This

    reduces available tray area.

    Assuming 8-in. clearance (no holes) between inlet downcomer and first row of holes. The 8

    in. could be reduced to 5 in. minimum if an inlet weir were used.

    Assuming 5-in. clearance (no holes) between outlet weir and adjacent row of holes.

  • Downcomer width = .12 4= 0.56 ft = 5.76 in (From Figures 8-100 at standard 65% weir

    length downcomer width is 12% of Tower diameter).

    Area determinations:

    Area of segment of circle (2) with chord AD:

    Diameter circle (2) = 48 - 5 = 43 in.

    Height of chord = 43

    2 (

    48

    2 5.76 8)= 11.26 in.

    Chord height/circle dia. H/D =11.26

    43 = 0.26

    Referring to Perrys Handbook, (pg. 32, 3rd Ed.)

    Area = 0.121 432= 224 in2

    Area of segment of circle (2) width chord BC:

    Height of chord = 43

    2 (

    48

    2 5.76 5)== 8.26 in

    H/D= 8.26

    43= 0.19

    Referring to Perrys Handbook, (pg. 32, 3rd Ed.)

    Area = 0.071 432= 131.3 in2

    Area of circle (2) = 432= 1849 in.2

    Area available for holes = 1849 (244+ 131.3) = 1473 in.2

    Area required for holes = 1634

    5holes/in2= 326.8 in2.

    Number of holes = 1634

    Area = 1473 in.2

    23. Tower Height Height of column Hc = (Nact 1)HS +Ht+ Hb +Plate Thickness

    No. Of plates = 20

    Tray Spacing HS =12 inch

    Ht = 5 ft for vapor disengagement

    Hb = 2.5ft for liquid hold up

    Minimum height of column Htower= (20-1) 1+2.5+5+200.1042

  • Htower = 26.7 ft

    24. Other Mechanical Designs:

    Maximum Operating Temperature = 40oC = 313k

    Maximum Operating Pressure = 1290 psi = 90.75 kg/cm2

    a) Shell Thickness:

    Material = SA-516-70 Carbon Steel

    Specific Gravity, s = 7.7

    Maximum allowable stress, fs = 1300 kg/cm2

    Welding efficiency, j = 0.9

    Design Pressure, PD = 1.5 Operating Pressure = 1.5 90.75 = 136 kg/cm2

    Internal Shell or column Dia, D = 4 ft = 1.2192 m = 1219.2 mm

    Here, C = corrosion Allowance = 3 mm

    Thickness, ts= PDD

    2 fsj PD + C =

    1361219.2

    2 1300.9 136+ 3 = 78.23 mm

    ts= 78.23 mm

    b) Tray:

    Thickness = 1/8 inch = 0.125 inch

    Material = SA-516-70 Carbon Steel

    Sieve Tray, hole size = 3/16inch, pitch =1/2 inch, Triangular.

    Tray Spacing = 12 inch

    c) Support for trays:

    A total of 5 inch on diameter for extension of tray ring-type support into the tower.

    Material: Carbon steel.

    d) Downcomer and Weir:

    Material = Carbon steel.

    e) Support for Column:

  • Skirt type, Height = 10 ft , Material = Carbon steel.

    f) Heads:

    Material = SA-516-70 Carbon steel.

    Permissible tensile stress = 1300 kg/cm2

    Thickness of Head,

    th = PDRcW

    2 fsj

    =1361219.21.54

    2 1300.9

    = 109 mm

    th = 4.16 inch

    Rc = Crown Radius =1219.2 mm

    W = Stress intensification factor = 1

    4

    3 + RcRl

    = 1.54 mm

    Where, Rl = Knuckle radius = 0.1 Rc

    g) Insulation and Coating:

    Insulating material: Polyurethane

    Insulating width: 4 inch

    Coating material: Zinc Sulfate

    Coating width: 0.06 inch

  • Mechanical Design

  • Vertical section of gas liquid separator

    8.7 ft

    12.0 ft

    44.0 ft

  • Cross section view of gas liquid separator

    8.7 ft

    12.0 ft

  • Pump

  • Heat Exchanger

    Heat Exchanger

  • P & ID

  • Figure: P & I diagram for centrifugal pump

    E-1

    P-1

    P-2

    P-3

    feed

    Vapor

    phase

    Liquid phase

    AT

    AC

    0-100

    deg

    mV

    10-50

    I-3

    P-4 P-2

    S-1

    S-2

    S-3

    Xsp

    V-1

    P-5

    S-4

    P-6

    LIP-7

    P-8

    light

    Figure: P & I diagram for gas liquid separator

    V 5 V 4

    V 2

    V 3

    Y strainer

    V 1

    P

    PUMP

  • TT

    TI

    AC P/I

    Preheated glycol

    Heated glycolTo absorber

    Dry gas

    Sales gas

    Figure: P & I diagram for Heat exchanger

  • Plot Plan

  • Economic Analysis

  • 14.1 Estimation of Total Capital

    Investment and Production Cost

    Table 12.1: Equipment cost for Heat Exchanger

    Table 12.2: Equipment cost for Pumps

    Equipment Identification No. Quantity US $

    Centrifugal

    Pump P-101 2 9400

    Centrifugal

    Pump P-100 3 12900

    Total = 22300

    Table 12.3: Equipment cost for Compressor

    Equipment Identification

    No. Quantity US $

    Reciprocating Compressor K-100 2 35600

    Equipment Identification

    No. Quantity US $

    Floating head HE E-100 1 80,000

    Floating head HE E-102 1 158,000

    Total= 238,000

  • Table 12.4: Equipment cost for Storage Tanks

    Equipment Identification

    No. Quantity US $

    Storage Tank V-106 1 6300

    Table 12.5: Equipment cost for Adsorption Column

    Equipment Identification

    No. Quantity US $

    Glycol Absorber T-101 4 220,000

    DEA Contractor T-100 4 260,000

    Total = 480,000

    Table 12.6: Equipment cost for Regenerator Column

    Equipment Identification

    No. Quantity US $

    Glycol Stripper V-103 1 145000

    DEA Stripper V-102 1 19000

    Total = 164000

    Table 12.7: Equipment cost for Stabilizer

    Equipment Identification

    No. Quantity US $

    Stabilizer V-105 1 7600

  • Table 12.8: Equipment cost for 2 phase Separators

    Total Equipment cost in the year 2002 = $ 958300

    Total Equipment cost at present (2014) = $ 958300index value at present

    index value at 2002

    = $ 958300 443.26

    390.4

    = $ 1.088 million.

    Equipment Identification

    No. Quantity US $

    Separator V-100 1 2200

    Separator V-101 1 1900

    Separator V-104 1 400

    Total = 4500

  • Table 12.9: Estimation of Capital Investment

    Items Percentage of Purchased

    Equipment Cost

    Cost

    Million $

    Purchased equipment 100 1.088

    Purchased equipment installation 47 0.511

    Instrumentation and control 20 0.22

    Piping (installed) 68 0.74

    Electrical (installed) 11 0.12

    Building 18 0.196

    Yard improvement 10 0.1088

    Service facilities 70 0.762

    Land 6 0.0653

    Total direct plant cost 350 3.81

    Indirect Cost

    Engineering and supervision 33 0.36

    Construction & expenses 41 0.45

    Contractors fee 22 0.24

    Contingency 42 0.46

    Fixed capital investment

    (Indirect + Direct cost)

    488 5.32

  • Ref: Plant Design and Economics by Peter and Timmerhaus; page-251

    Working capital investment

    (15% of total capital investment)

    73.2

    0.8

    Total Capital Investment 561 6.12

  • Table 12.10: Manufacturing Expenses

    (Working day basis 330day/yr)

    Overhead (payroll &

    plant), Packing, storage

    (50% of opt. labor plus

    supervision &

    maintenance

    0.085

    Local taxes (9%of Fixed 0.4788

    Cost type Item Cost /yr

    $ Million

    Major Raw Material

    Raw Gas 3.75/1000 scf 7.2

    TEG 0.75 $/lb 0.82

    Direct

    DEAmine 0.6 $/lb 0.02

    Cost of Raw materials $ 8.04

    Operating labor (10% of RM) 0.804

    Supervisory & Clerical

    labor

    (10% of Opt.

    labor) 0.0804

    Utilities 0.55

    Maintenance & repair

    (20% of FC)

    1.064

    Opt. expenses (10% of

    resistance & repair) 0.1064

    Laboratory charges

    (10% of opt. labor) 0.01064

    Total direct manufacturing expenses $ 10.66

  • capital)

    Insurance (0.4% of fixed

    capital)

    0.0213

    Total annual indirect manufacturing expenses $ 0.5851

    Total manufacturing expenses $ 11.24

    Depreciation (10%

    of fixed capital for

    machinery &

    equipment)

    0.532

    General Expenses Administrative Cost (20% of Operating labor) 0.1608

    Distribution of selling cost ( 10% of total

    manufacturing expenses)

    1.124

    Research & development (5% of total expenses) 0.18

    Total annual expenses $ 13.24

    Economic Analysis

    Percent rate of return

    Gas production = 2.92 105 ft3/hr = 2.32 109 scf/year

    LPG production = 2356 ton/year

    Total sale = $31.34 million

    Total income =31.34 13.24 = $ 18.1 million

    Net profit after tax = $ 15.4 million (15% Tax)

    Total investment cost = $ 6.12 million

  • Depreciation of fixed capital investment (FCI)

    Project life = 20 yr

    Salvage value at the end of the project life = 0.15.32= $ 0.532 million

    Total depreciation = 0.95.32 = $ 4.788 million

    Now depreciation by sinking fund method with 15% interest rate,

    = Depreciable FCI (A/P, 15%, 20)

    = 4.7880.15 1.1520

    1.1520 1

    = $ 0.765 million/yr

  • Cash flow diagram

    Payback period calculation

    Formula uses

    F = P(1 + ),

    = (1 + ) 1

    (1 + )

    Assumed MARR is 15%

    1st yr

    P0= - $6.12million

    So, F1= -$7.04 million

    Cost = -$13.24 million

    Profit = $15.4 million

    So, net cash P1 = -$4.88 million

    2nd yr

    P1 = -$4.88 million

    So, F2= -$5.612 million

    Cost = -$13.24 million

    Profit = $15.4 million

    So, net cash P2 = -$3.452 million

  • 3rd yr

    P2 = -$3.452 million

    So, F3= -$3.97 million

    Cost = -$13.24 million

    Profit = $15.4 million

    So, net cash P3 = -$1.81 million

    4th yr

    P3= -$1.81 million

    So, F4= -$2.08 million

    Cost = -$13.24 million

    Profit = $15.4 million

    So, net cash P4 = $0.08million

    Here, net positive cash flow produced, which indicate the payback period.

    By linear interpolation, actual payback period is 3.96 yr (3 yr 11month 15 day)

    5th yr

    P4= -$0.08 million

    So, F5= $0.92 million

    Cost = -$13.24 million

    Profit = $15.4 million

    So, net cashP5 = $ 2.252 million

  • IRR calculation

    In annual worth (AW) method:

    Total annual revenue, R= $ (15.4 13.24) = $ 2.16 million

    AW= -$6.12 million (A/P, i%, 20) + $ 2.16 million + $ 0.532 million (A/F, i%, 20)

    i% (assumption) AW($,million)

    20 0.903

    40 -0.2897

    By linear interpolation, for AW is 0 i% = 35.17%> 15% (MARR)

    ERR calculation

    Ek( P/F, %,k)(F/P, i%, N) = Rk(F/P, %, N-k)

    Where,

    % = 15 %

    N = 20 yr

    Using the above equation, i% = 19.67 %> 15% (MARR)

  • Appendix

  • Reference

    Ludwig, E.E Applied Process Design for Chemical and Petrochemical Plants, 3

    volm,2ndedn, Gulf Pub.

    Peters and Timmerhaus, Plant Design and Economics from Chemical Engineers,

    4thedn, McGraw Hill (1991)

    Phillip C. Wankat, Equilibrium stage separations, prentice hall

    A.K.M. Abdul Quader, Design and Building of Process Plant, World University

    Service.

    Bassel, W.D, Preliminary Chemical Engineering Plant Design, Elsevier Pub, New

    York (1976)

    Rudd, D.F. and C.C Watson, Strategy of Process engineering, Wiley (1968)

    Vilbrandt, F.C and C.E Dryden, Chemical Engineering Plant Design, 4thedn,

    McGraw-Hill (1959)

    Modern cost Engineering: Methods and Data, compiled and edited by Chemical

    Engineering , McGraw-Hill(1979)

    Ludwig, E.E Applied Project Engineering and Management, 3rdedn,Gulf Pub.

    George T. Austin, Shreves Chemical Process Industries, 5thedn, McGraw-Hill (1954)

    RifatM.Dakhil, SataK.Ajjam; General Operating Problems and Their Solutions of

    Natural Gas Sweetening Process (Amine System).

    http://www.lessmytax.com/cost-inflation-index/

    http://allinfoindia.com/eLearning/Income%20tax/current%20index%20of%20capital

    %20gain.htm