design and construction of a mining haul road · design and construction of a mining haul road ......
TRANSCRIPT
Design and Construction of a Mining Haul RoadDr Richard Yeo, Austroads & Max Wallis, Polymix Industries
135 km from
Mount Isa
Annual wet and
dry seasonsdry seasons
Environment has
a greater impact
than traffic
loading
Pavement design
focused on mitigating
the risk of saturation of
the pavement and
subgrade subgrade
Construction during dry
season
• unbound ‘track’
• running surface directly on the natural subgrade or worn well below this
• alignment varied by creek crossings and areas of black soils
• uneconomic to build up above natural ground
• existing compacted materials adopted
Existing conditions
• existing compacted materials adopted
Variable subgrade:
• laterite soils
• very reactive black soils
• weathered rock outcrops
• flooding anticipated during the design period
• possible inundation for up to 2 to 3 days
• road closed during flood events
Pavement inundation
• design involved use of rock won within the road reserve rather than importing material
• criteria included Particle Size Distribution, Plasticity Index (PI), Hardness, Linear Shrinkage
Fit for purpose pavement materials
In situ stabilisation adopted:
• correct mechanical deficiencies (particle size distribution and/or plasticity)
• increase strength or bearing capacity while maintaining a flexible pavement
• reduce permeability and/or moisture sensitivity
• cost-effective new pavement
Fit for purpose pavement materials
• cost-effective new pavement
• use of non-standard gravels
• minimal maintenance
• ease of maintenance
Dry powder polymer selected on the basis of:
• proven track record – TIPES approved
• enabled a more open grading curve
suited to the local materials
• reduced capillary rise
In situ stabilisation
reduced capillary rise
• increased soaked CBR
• increased wet strength
• reduced permeability
• lower water required for compaction
60
80
100
120
140CBR (%)
0
20
40
60
A B C D EPavementmaterial:
Unsoaked 4 day soaked 4 day soaked - stabilised
Sprayed seal
Binder Shoulders l/m2 Inbound l/m2 Outbound l/m2 Aggregate
S4.5S 1.7 1.4 1.0 10 mm
S4.5S 1.9 1.7 1.4 20 mm
Prime: AMC00: 0.8 l/m2Prime: AMC00: 0.8 l/m