design and detailed plan for in vacuum diamond sensor for phil and atf2 s. liu, p. bambade, f....
TRANSCRIPT
Design and Detailed Plan for In Vacuum Diamond Sensor for PHIL and ATF2
S. Liu, P. Bambade, F. Bogard, P. Cornebise, I. Khvastnov, H. Monard, C. Sylvia
FJPPL-FKPPL Workshop on ATF2 Accelerator R&D, Annecy, 17-19 Mar., 2014
Contents
• Planned location of diamond detector at PHIL and ATF2
• Expected signal range @ATF2
• Design for electronics
• Design for mechanics
• Status of preparation for mechanics
• Summary and Future Plan
2
PHIL
Same "plug compatible" design for PHIL and ATF2: fabrication will be completed in April 2014 before testing in May-June at PHIL.
Diamond Detector
ATF2
Expected Signal Range @ ATF2
4
Total # Min. ~ Max. #/mm2 @ Sensor
Charge collected/mm2
Beam 1010 6.16*107 1.6887μCHalo
(δp/p0=0.01)107 1.14 *104 31.236pC
Halo (δp/p0=0.0008)
107 2.24*104 61.376pC
Compton 28340 3*10~ 5.2*102 82.2fC~ 1.4284pC
Tested signal ranged @ PHIL with 4.5X4.5mm2 diamond pad-> 11fC (with 40dB amplifier) to 1μC (with 12dB attenuator)
New design with 4 strips for diamond detector in vacuum
Top and Bottom View of PCB
PCB
Diamond
Top side of diamond Bottom side of diamond
Bottom side of PCBTop side of PCB
CH2 with R3=0.51Ω
6
Special channel for big signal
(beam core)
Design for Electronics
Filter for HV -> final choice of parameters being checked
k1k3
k2k4
k0
Bottom side of PCB
Cutoff frequency for HV: ω =1/ τ =1/ R1C1
Charging time constant: τ = R1 Ctotal
Ctotal=(C2 + C3 + C4+C5 +C6) ≈1uf
R1 =1kΩω = 1MHzτ = 1ms
SMA-MMCX
Prepared Mechanics
756mm
265mm
Laptop for control
Transformer and ethernet module
Moveable stageMin. step: 0.01mmMax. distance: 115mmVelocity can be adjusted
610mm cables for vacuum with SMA/MMCX connectors
11
Summary and Future Plan
• The design for diamond detector for vacuum is done and the order for 2 first units was sent in Feb. 2014, and two more units will be delivered in 2015;
• One set of mechanics for diamond detector in vacuum is ready and has been tested at LAL, it will be installed at PHIL for diamond tests in April;
• The components for the second set are delivered, except for the central vacuum chamber, which will be built by KEK;
• Holder for diamond detector will be ordered and fabricated soon;
• Fabrication of diamond detector for vacuum will be completed in April 2014 before testing in May-June at PHIL and installation at ATF2 in autumn.