design-build:
DESCRIPTION
Design-Build:. RISKS. OR REWARDS. for the Consulting Engineer?. Presented at the FIDIC Annual Conference September 7, 2005 Gregs G. Thomopulos, P.E., FACEC. “ Many of the old rules for project delivery that held sway in the industry no longer have the same potency as they once did…. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/1.jpg)
![Page 2: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/2.jpg)
Design-Build:
RISKS OR REWARDSfor the
Consulting Engineer?
![Page 3: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/3.jpg)
Presented at the FIDIC Annual ConferenceSeptember 7, 2005
Gregs G. Thomopulos, P.E., FACEC
![Page 4: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/4.jpg)
“Many of the old rules for project delivery that held sway in the industry no longer have the same potency as they once did…
![Page 5: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/5.jpg)
“Design-bid-build still has its many followers among owners who believe that they can obtain the very best design and the most cost-effective construction by holding both sides separate…
![Page 6: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/6.jpg)
“Advocates of design-build believe that the sole-source method of procurement forces the team to iron out many of the project wrinkles on their own because the entire team will be held accountable…
![Page 7: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/7.jpg)
“Still others believe that construction management for fee is the best way of ensuring that the owner gets the best of all worlds because there is an agent inspecting, measuring, observing and protecting the owner’s interest…
![Page 8: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/8.jpg)
“Fans of CM At-Risk believe that the words ‘at‑risk’ say it all and force the CM firm to deliver what it promised on time and on budget or face the consequences. ”
Engineering News-Record, July 19, 2000
![Page 9: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/9.jpg)
Design-Build is not a new concept.
Most of the world’s great structureswere built under a Design-Build arrangement by master builders.
![Page 10: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/10.jpg)
Project Delivery Systems
Design-Bid-Build Construction Management (CM)
• CM At-Risk• CM – Owner’s Representative
Design-Build Other Variations
• Build-Operate-Transfer (BOT)• Build-Own-Operate-Transfer (BOOT)• Program Management
![Page 11: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/11.jpg)
OWNER
Design-Bid-Build
Contractual Relationship
CE CONTRACTORS
![Page 12: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/12.jpg)
PROJECTSTART
SELECT CE
Design-Bid-Build
Project Time Line
Contractual Relationship
CONSTRUCTION
DESIGN
PROJECTCOMPLETION
BIDDING/AWARD
![Page 13: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/13.jpg)
OWNER
Construction Management At-Risk
Contractual Relationship
CM / GCCE
![Page 14: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/14.jpg)
SELECT CE
PROJECTSTART
SELECT CM/GC
Construction Management At-Risk
Project Time Line
Contractual Relationship
CONSTRUCTION
DESIGN
PROJECTCOMPLETION
PRE-CONSTRUCTION
![Page 15: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/15.jpg)
OWNER
Design-Build
Contractual Relationship
DESIGN-BUILDER
OWNER’S CEOR IN-HOUSE CE
![Page 16: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/16.jpg)
Design-Build
Project Time Line
Contractual Relationship
OWNER’S CE
PROJECTSTART
OR IN-HOUSE
CONSTRUCTION
SELECT DESIGN
BUILDER
PROJECTCOMPLETION
DESIGN
PRE-CONSTRUCTION
![Page 17: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/17.jpg)
Why Owners Prefer Design-Build
Shorter Project Schedule Better Cost/Budget Management Efficiency and Innovation
(Contractors’ Means & Methods) Single Source Responsibility
(Avoids Pointing of Fingers) Risk Sharing
(More Risks Passed Down to Design-Builder) Fewer Claims and Litigations Fewer Contract Modifications Opportunity to Package Larger Contracts
![Page 18: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/18.jpg)
How Owners Procure Design-Build Services In the U.S. Negotiated Procurement
• Sole Source Selection (Strategic Alliance)• Qualifications Based Selection (QBS)• Best Value (Price and Technical)
Competitive Procurement• Low Bid (Lowest Price Technically Acceptable)• Adjusted Low Bid (Mix of Price, Schedule, etc.)• Fixed Budget/Best Technical Proposal• Best and Final Offer• Weighted Matrix
![Page 19: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/19.jpg)
Organization of the Design-Build Team In the U.S.
Integrated Firm (Design and Construction Capability in Same Firm)
Contractor As Prime CE As Prime Joint Venture Between the Contractor and CE
![Page 20: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/20.jpg)
“ Owners are willing to use alternate project delivery methods but firms worry that clients don’t always understand what they need.”
Engineering News-Record, June 19, 2000
Design-Build Risks and Rewards
![Page 21: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/21.jpg)
Risks for the Consulting Engineer Pre-Proposal Design Cost Reduced Fee for Share of Profit Errors and Omissions Liquidated Damages or
Consequential Damages Performance Guarantee Participation in Loss Joint and Several Liability Client Relationships
![Page 22: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/22.jpg)
Rewards for the Consulting Engineer
Success Fee Mark-Up on Procurement Higher Margins on Design Services Share in Overall Profit
![Page 23: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/23.jpg)
Design-Build “Best Practices”
for the CE in the Unites States
![Page 24: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/24.jpg)
For The CE, Subcontracting Tier Preferred (Some Are Sometimes the Prime)
No Free Pre-Bid Engineering Service Success Fee on Successful Bids Design Fees Should Include Additional Margins Design Fees May Be Reduced
for Share in Profits No “Sharing in Loss” Arrangements Procurement Services for Additional Fees Possible Joint Venture With Contractor
Best Practices For The Consulting Engineer in Design-Build
![Page 25: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/25.jpg)
Future Market Trends
Transportation - More DOTs Are Following Utah DOT’s Lead
Sports/Recreation Projects Power Generation and Transmission Communications Hotels/Resorts Medical/Health Care Commercial Buildings
?
![Page 26: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/26.jpg)
Design-Build:
RISKS OR REWARDSfor the
Consulting Engineer?
![Page 27: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/27.jpg)
Risky Business Has Its Rewards
![Page 28: Design-Build:](https://reader035.vdocument.in/reader035/viewer/2022062410/5681526b550346895dc09f0f/html5/thumbnails/28.jpg)
Thank You