design considerations and lessons learned - energypa.orgenergypa.org/assets/files/2017/sept...
TRANSCRIPT
PPL Gas Insulated Substations: Design Considerations and Lessons Learned
Nicholas Matone – Support Engineer, T&S Standards
Agenda
• PPL Overview • Previous GIS Experience • Present GIS Installations • Mobile GIS Investigation • Design Considerations and Lessons Learned • Latest Developments
PPL Overview
PPL Overview
• Northeast/Central Pennsylvania • 1.4 million customers • 10,000 sq. mi. • Predominantly rural • 500kV, 230kV, 138kV, 69kV transmission
voltages
GIS History
• Early generations of GIS: • Vintage ~1978 GIS (Sunbury Substation)
– Many problems throughout its service life – Catastrophic bushing failure in 2013
• Vintage ~1987 GIS (Wescosville Substation) – Similar problems to Sunbury – Taken out of service in 2012
Project Overview: Sunbury 500kV • Ultimate Build:
Eleven breakers, six lines, two transformers
• Arrangement: Breaker-and-a-Half
• Status: Brownfield • Original scope in
2013: Six breakers, two lines, one transformer (replaced old ASEA gear)
Project Overview: Sunbury 500kV (cont.)
• 2016: Two breakers, one line with ~1700’ of GIL to IPP. • 2017: Add second transformer connection, split
transformer bay
Project Overview: Lock Haven 69kV • Ultimate Build:
Fourteen breakers, eight lines, two transformers, two capacitor banks
• Arrangement: Breaker-and-a-Half
• Status: Greenfield • Original scope in
2016: Twelve breakers, eight lines, two capacitor banks
Project Overview: Lauschtown 500kV
• Ultimate Build: Eleven breakers, six lines, two transformers
• Arrangement: Breaker-and-a-Half
• Status: Greenfield • Original scope in
2017: Two lines, one transformer (near completion)
Project Overview: Sunbury 230kV
• Ultimate Build: Eighteen breakers, eight lines, five transformers
• Arrangement: Breaker-and-a-Half • Status: Brownfield • Original scope for 2018: Thirteen breakers,
four lines, five transformers
Project Overview: Wescosville 500kV
• Ultimate Build: Eight breakers, three lines, two transformers
• Arrangement: Double-Bus-Double-Breaker • Status: Brownfield • Original scope for 2019: Six breakers, two
lines, one transformer
Project Overview: Palooka 230/69kV
• Ultimate Build: 230kV – Twelve breakers, six lines, three transformers 69kV – Fourteen breakers, eight lines
• Arrangement: Breaker-and-a-Half • Status: Greenfield • Original scope for 2019: Nine breakers 230kV,
eight breakers 69kV, Four lines each voltage, two transformers
Mobile Substation Concept
Mobile Substation Intent
• Typically used for planned work, but can also be rapidly deployed for emergencies
• Bypass an entire 230/69kV yard • Programming and most testing complete
before deployment • Easily transportable (no permits)
Key Features
• Relaying+SCADA+RTU built-in to LCC Panels – Allows for an existing control cubicle to be taken
out of service
• AC and DC power supplied from external sources – Keeps weight down
230kV Mobile GIS
230kV Layout
• Two trailers, each with two breakers and three Pfisterer cable terminations – Each trailer would be capable of connecting
up to two transmission lines, and one centrally tapped transformer (refer to one-line)
– Combining the trailers will allow for up to four lines, and two transformers at one site
69kV Mobile GIS
69kV Layout • Two trailers, each with four breakers and four
Pfisterer cable terminations – Each trailer will be capable of connecting up to three
transmission lines, and one transformer (refer to one-line)
– Combining the trailers will allow for up to six lines, and two transformers at one site
Design Considerations and Lessons Learned
Online Gas Density monitoring • Central system to track gas density of all zones • Can provide alerts to slow leaks before reaching
alarm or trip level, so repairs can be planned
Design Considerations and Lessons Learned
Camera System • Makes access to viewports much easier and
convenient • Analog system vs central computer system? Analog
provides direct connection, whereas a central computer could provide more convenience
Design Considerations and Lessons Learned
Additional Gas Zones • Typically on 3-in-1 equipment, CTs are in
the same gas zone as the breaker • This requires additional equipment to be
taken out of service in order to de-gas the breaker
• Solution: ensure there is a buffer zone between the MOD and the CB
Design Considerations and Lessons Learned
Switches for Future Expansion • We originally included isolation switches to ease
future expansion • Due to the need to soak test the last piece of
connection bus and tie into interlocking in existing LCCs, the switches proved unnecessary
ORIGINAL INSTALL NEW INSTALL
Design Considerations and Lessons Learned
Bushing Zones • PPL requires gas/air bushings to be in
their own gas zone • Limits the extent of SF6 leakage in the
case of bushing failure or vandalism
Design Considerations and Lessons Learned
Universal Bid Documents • Spec covers all voltages. Variances noted in tables
– Similar to IEEE C37.122
• Scope template that is project specific • Price and spec sheet template that vendors fill out • Dedicated GIL Spec
Recent GIS Developments
Initial Cost Estimator Tool • Spreadsheet to help with high-level GIS estimates • Filled in with budgetary values from vendors
69/138kV 230kV 500kV Breaker Quantity/ Line Exits Cost
Breaker Quantity/ Line Exits Cost
Breaker Quantity/ Line Exits Cost
6 / 3 6 / 3 6 / 3 8 / 5 8 / 5 8 / 5 10 / 7 10 / 7 10 / 7 12 / 9 12 / 9 12 / 9 14 / 10 14 / 10 16 / 12 Building Size (Breaker Quantity) Cost
Dimensions (incl. line exits)
Building Size (Breaker Quantity) Cost
Dimensions (incl. line exits)
Building Size (Breaker Quantity) Cost
Dimensions (incl. line exits)
6 6 6 8 8 8 10 10 10 12 12 12 14 14 16
Recent GIS Developments (Cont.)
Lifecycle Cost Estimator Tool • Spreadsheet to help estimate maintenance costs • Filled in using maintenance cycles from vendors, as
well as PPL’s maintenance experience
GIS Maintenance Costs
Labor Rate/hr: $ 110.00
Discount Rate: 0.11
Number of breakers: 8
Number of disconnects per breaker 5
Category Item Frequency (yrs) Manhours Cost Notes Breaker Multiplier?
Disconnect Multiplier? Total Cost
Building and General Costs Crane Inspection 1 $ 900.00 OSHA requirement. Escorting third party inspector N N $ 900.00
Building and General Costs Air Handling System 1 16 $ 1,760.00
-Replace filters -Clean screens of dust and debris -Verify proper functionality of louvers -Verify functionality of fans/motors N N $ 1,760.00
Building and General Costs Camera System 1 1 $ 110.00
-Verify batteries charged and functional. -Verify camera is functional by spot checking several ports. N N $ 110.00
Building and General Costs Miscellaneous Indoor 1 8 $ 880.00
-Verify building heaters are functional -Check for sources of water intrusion, correct if possible. -Spot check trenways for signs of rodent infestation/damage. -Perform a test of fire detection system -Inspect GIS grounding conductors for signs of loose or damaged hardware. N N $ 880.00
Building and General Costs Miscellaneous Outdoor 5 1.5 $ 165.00
-Inspect grounding conductors for loose/damaged hardware -Review SF6 gauges for proper levels. Y N $ 1,320.00
Building and General Costs SF6 Quality checks 5 3 $ 330.00
-Dew Point -SF6 purity -SF6 monitor switching points Y N $ 2,640.00
ABB 500 Costs Breaker Mechanism Inspection/Service 5 24 $ 2,640.00
Check switching times, oil level, carbon brushes, possible leaks, electrical connections (standard breaker service) Y N $ 21,120.00
INPUT
$-
$10,000.00
$20,000.00
$30,000.00
$40,000.00
$50,000.00
$60,000.00
$70,000.00
$80,000.00
$90,000.00
$100,000.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40Year of Service
VENDOR 1 vs VENDOR 2 500kV
Vendor 2 Costs
Vendor 1 Costs
Building and General Costs
OUTPUT
Recent GIS Developments (Cont.)
Conceptual Planning with GIS • GIS previously used as a “Plan B” • Now evaluating GIS as a viable “Plan A” amongst
AIS alternatives • Spreadsheet takes into account total lifecycle costs,
as well as qualitative criteria
INPUT GLOBAL INPUTS: Discount Rate 0.11 Lifecycle (years) 40 OPTION 1 NAME OPTION 2 NAME
GIS AIS SPECIFIC INPUTS: Frequency (yrs) Cost Frequency (yrs) Cost Initial Cost $ 38,500,000.00 $ 37,500,000.00
Failure Cost Estimate 12 $ 200,000.00 4 $ 120,000.00
Maintenance Item 1 1 $ 10,000.00 1 $ 8,000.00 Maintenance Item 2 4 $ 12,000.00 4 $ 30,000.00 Maintenance Item 3 12 $ 30,000.00 8 $ 60,000.00 Maintenance Item 4 1 $ - 1 $ - Maintenance Item 5 1 $ - 1 $ -
Failure Net Present Cost $ 149,184.18 Failure Net Present Cost $ 268,531.52 Maintenance Net Present Cost $ 138,741.29
Maintenance Net Present Cost $ 205,874.17
Weight Value Rank Value Value Rank Value
Initial Cost 50.0% $ 38,500,000.00 0.487012987 $ 37,500,000.00 0.5
Net Present Lifecycle Cost 20.0% $ 287,925.47 0.20000000 $ 474,405.69 0.12138365 Security 5.0% Extremely Good 0.05 Very Good 0.041666667 Permitting 10.0% Good 0.066666667 Bad 0.033333333 Land Acquisition 0.0% Neutral 0 Neutral 0 Schedule 5.0% Good 0.033333333 Good 0.033333333 Safety 2.5% Extremely Good 0.025 Very Good 0.020833333 Ecological Impact 2.5% Good 0.016666667 Bad 0.008333333 Air Pollution Tolerance 0.5% Extremely Good 0.005 Good 0.003333333 Appearance/Aesthetics 1.0% Very Good 0.008333333 Good 0.006666667 Audible Noise 0.5% Very Good 0.004166667 Good 0.003333333 EMF 0.0% Extremely Good 0 Good 0 Disposal Concerns 3.0% Neutral 0.015 Very Good 0.025
100.0% RANK 0.911179654 RANK 0.797216981 Soft Considerations 0.224166667 0.175833333
OUTPUT
$-
$5,000,000.00
$10,000,000.00
$15,000,000.00
$20,000,000.00
$25,000,000.00
$30,000,000.00
$35,000,000.00
$40,000,000.00
$45,000,000.00
GIS AIS
Option Net Present Costs
Failure Net Present Cost
Maintenance Net Present Cost
Initial Cost
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
GIS AIS
Option Rankings
Soft Considerations
Net Present Lifecycle Cost
Initial Cost
Questions/Comments?
Nicholas Matone 2 North Ninth Street, GENN5 Allentown, PA 18101 Work: (610) 220-4403 Mobile: (570) 856-9922 E-mail: [email protected]