design considerations and lessons learned - energypa.orgenergypa.org/assets/files/2017/sept...

33
PPL Gas Insulated Substations: Design Considerations and Lessons Learned Nicholas Matone – Support Engineer, T&S Standards

Upload: dangnhi

Post on 26-Mar-2018

213 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

PPL Gas Insulated Substations: Design Considerations and Lessons Learned

Nicholas Matone – Support Engineer, T&S Standards

Page 2: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Agenda

• PPL Overview • Previous GIS Experience • Present GIS Installations • Mobile GIS Investigation • Design Considerations and Lessons Learned • Latest Developments

Page 3: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

PPL Overview

Page 4: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

PPL Overview

• Northeast/Central Pennsylvania • 1.4 million customers • 10,000 sq. mi. • Predominantly rural • 500kV, 230kV, 138kV, 69kV transmission

voltages

Presenter
Presentation Notes
Rural may confuse people. Clarify why we’ve used GIS.
Page 5: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

GIS History

• Early generations of GIS: • Vintage ~1978 GIS (Sunbury Substation)

– Many problems throughout its service life – Catastrophic bushing failure in 2013

• Vintage ~1987 GIS (Wescosville Substation) – Similar problems to Sunbury – Taken out of service in 2012

Page 6: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Project Overview: Sunbury 500kV • Ultimate Build:

Eleven breakers, six lines, two transformers

• Arrangement: Breaker-and-a-Half

• Status: Brownfield • Original scope in

2013: Six breakers, two lines, one transformer (replaced old ASEA gear)

Page 7: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Project Overview: Sunbury 500kV (cont.)

• 2016: Two breakers, one line with ~1700’ of GIL to IPP. • 2017: Add second transformer connection, split

transformer bay

Page 8: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Project Overview: Lock Haven 69kV • Ultimate Build:

Fourteen breakers, eight lines, two transformers, two capacitor banks

• Arrangement: Breaker-and-a-Half

• Status: Greenfield • Original scope in

2016: Twelve breakers, eight lines, two capacitor banks

Page 9: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Project Overview: Lauschtown 500kV

• Ultimate Build: Eleven breakers, six lines, two transformers

• Arrangement: Breaker-and-a-Half

• Status: Greenfield • Original scope in

2017: Two lines, one transformer (near completion)

Page 10: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Project Overview: Sunbury 230kV

• Ultimate Build: Eighteen breakers, eight lines, five transformers

• Arrangement: Breaker-and-a-Half • Status: Brownfield • Original scope for 2018: Thirteen breakers,

four lines, five transformers

Page 11: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Project Overview: Wescosville 500kV

• Ultimate Build: Eight breakers, three lines, two transformers

• Arrangement: Double-Bus-Double-Breaker • Status: Brownfield • Original scope for 2019: Six breakers, two

lines, one transformer

Page 12: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Project Overview: Palooka 230/69kV

• Ultimate Build: 230kV – Twelve breakers, six lines, three transformers 69kV – Fourteen breakers, eight lines

• Arrangement: Breaker-and-a-Half • Status: Greenfield • Original scope for 2019: Nine breakers 230kV,

eight breakers 69kV, Four lines each voltage, two transformers

Page 13: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Mobile Substation Concept

Page 14: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Mobile Substation Intent

• Typically used for planned work, but can also be rapidly deployed for emergencies

• Bypass an entire 230/69kV yard • Programming and most testing complete

before deployment • Easily transportable (no permits)

Page 15: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Key Features

• Relaying+SCADA+RTU built-in to LCC Panels – Allows for an existing control cubicle to be taken

out of service

• AC and DC power supplied from external sources – Keeps weight down

Page 16: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

230kV Mobile GIS

Page 17: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

230kV Layout

• Two trailers, each with two breakers and three Pfisterer cable terminations – Each trailer would be capable of connecting

up to two transmission lines, and one centrally tapped transformer (refer to one-line)

– Combining the trailers will allow for up to four lines, and two transformers at one site

Page 18: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

69kV Mobile GIS

Page 19: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

69kV Layout • Two trailers, each with four breakers and four

Pfisterer cable terminations – Each trailer will be capable of connecting up to three

transmission lines, and one transformer (refer to one-line)

– Combining the trailers will allow for up to six lines, and two transformers at one site

Page 20: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Design Considerations and Lessons Learned

Online Gas Density monitoring • Central system to track gas density of all zones • Can provide alerts to slow leaks before reaching

alarm or trip level, so repairs can be planned

Page 21: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Design Considerations and Lessons Learned

Camera System • Makes access to viewports much easier and

convenient • Analog system vs central computer system? Analog

provides direct connection, whereas a central computer could provide more convenience

Page 22: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Design Considerations and Lessons Learned

Additional Gas Zones • Typically on 3-in-1 equipment, CTs are in

the same gas zone as the breaker • This requires additional equipment to be

taken out of service in order to de-gas the breaker

• Solution: ensure there is a buffer zone between the MOD and the CB

Page 23: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Design Considerations and Lessons Learned

Switches for Future Expansion • We originally included isolation switches to ease

future expansion • Due to the need to soak test the last piece of

connection bus and tie into interlocking in existing LCCs, the switches proved unnecessary

ORIGINAL INSTALL NEW INSTALL

Page 24: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Design Considerations and Lessons Learned

Bushing Zones • PPL requires gas/air bushings to be in

their own gas zone • Limits the extent of SF6 leakage in the

case of bushing failure or vandalism

Page 25: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Design Considerations and Lessons Learned

Universal Bid Documents • Spec covers all voltages. Variances noted in tables

– Similar to IEEE C37.122

• Scope template that is project specific • Price and spec sheet template that vendors fill out • Dedicated GIL Spec

Page 26: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Recent GIS Developments

Initial Cost Estimator Tool • Spreadsheet to help with high-level GIS estimates • Filled in with budgetary values from vendors

69/138kV 230kV 500kV Breaker Quantity/ Line Exits Cost

Breaker Quantity/ Line Exits Cost

Breaker Quantity/ Line Exits Cost

6 / 3 6 / 3 6 / 3 8 / 5 8 / 5 8 / 5 10 / 7 10 / 7 10 / 7 12 / 9 12 / 9 12 / 9 14 / 10 14 / 10 16 / 12 Building Size (Breaker Quantity) Cost

Dimensions (incl. line exits)

Building Size (Breaker Quantity) Cost

Dimensions (incl. line exits)

Building Size (Breaker Quantity) Cost

Dimensions (incl. line exits)

6 6 6 8 8 8 10 10 10 12 12 12 14 14 16

Page 27: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Recent GIS Developments (Cont.)

Lifecycle Cost Estimator Tool • Spreadsheet to help estimate maintenance costs • Filled in using maintenance cycles from vendors, as

well as PPL’s maintenance experience

Page 28: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

GIS Maintenance Costs

Labor Rate/hr: $ 110.00

Discount Rate: 0.11

Number of breakers: 8

Number of disconnects per breaker 5

Category Item Frequency (yrs) Manhours Cost Notes Breaker Multiplier?

Disconnect Multiplier? Total Cost

Building and General Costs Crane Inspection 1 $ 900.00 OSHA requirement. Escorting third party inspector N N $ 900.00

Building and General Costs Air Handling System 1 16 $ 1,760.00

-Replace filters -Clean screens of dust and debris -Verify proper functionality of louvers -Verify functionality of fans/motors N N $ 1,760.00

Building and General Costs Camera System 1 1 $ 110.00

-Verify batteries charged and functional. -Verify camera is functional by spot checking several ports. N N $ 110.00

Building and General Costs Miscellaneous Indoor 1 8 $ 880.00

-Verify building heaters are functional -Check for sources of water intrusion, correct if possible. -Spot check trenways for signs of rodent infestation/damage. -Perform a test of fire detection system -Inspect GIS grounding conductors for signs of loose or damaged hardware. N N $ 880.00

Building and General Costs Miscellaneous Outdoor 5 1.5 $ 165.00

-Inspect grounding conductors for loose/damaged hardware -Review SF6 gauges for proper levels. Y N $ 1,320.00

Building and General Costs SF6 Quality checks 5 3 $ 330.00

-Dew Point -SF6 purity -SF6 monitor switching points Y N $ 2,640.00

ABB 500 Costs Breaker Mechanism Inspection/Service 5 24 $ 2,640.00

Check switching times, oil level, carbon brushes, possible leaks, electrical connections (standard breaker service) Y N $ 21,120.00

INPUT

Page 29: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

$-

$10,000.00

$20,000.00

$30,000.00

$40,000.00

$50,000.00

$60,000.00

$70,000.00

$80,000.00

$90,000.00

$100,000.00

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40Year of Service

VENDOR 1 vs VENDOR 2 500kV

Vendor 2 Costs

Vendor 1 Costs

Building and General Costs

OUTPUT

Page 30: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Recent GIS Developments (Cont.)

Conceptual Planning with GIS • GIS previously used as a “Plan B” • Now evaluating GIS as a viable “Plan A” amongst

AIS alternatives • Spreadsheet takes into account total lifecycle costs,

as well as qualitative criteria

Page 31: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

INPUT GLOBAL INPUTS: Discount Rate 0.11 Lifecycle (years) 40 OPTION 1 NAME OPTION 2 NAME

GIS AIS SPECIFIC INPUTS: Frequency (yrs) Cost Frequency (yrs) Cost Initial Cost $ 38,500,000.00 $ 37,500,000.00

Failure Cost Estimate 12 $ 200,000.00 4 $ 120,000.00

Maintenance Item 1 1 $ 10,000.00 1 $ 8,000.00 Maintenance Item 2 4 $ 12,000.00 4 $ 30,000.00 Maintenance Item 3 12 $ 30,000.00 8 $ 60,000.00 Maintenance Item 4 1 $ - 1 $ - Maintenance Item 5 1 $ - 1 $ -

Failure Net Present Cost $ 149,184.18 Failure Net Present Cost $ 268,531.52 Maintenance Net Present Cost $ 138,741.29

Maintenance Net Present Cost $ 205,874.17

Weight Value Rank Value Value Rank Value

Initial Cost 50.0% $ 38,500,000.00 0.487012987 $ 37,500,000.00 0.5

Net Present Lifecycle Cost 20.0% $ 287,925.47 0.20000000 $ 474,405.69 0.12138365 Security 5.0% Extremely Good 0.05 Very Good 0.041666667 Permitting 10.0% Good 0.066666667 Bad 0.033333333 Land Acquisition 0.0% Neutral 0 Neutral 0 Schedule 5.0% Good 0.033333333 Good 0.033333333 Safety 2.5% Extremely Good 0.025 Very Good 0.020833333 Ecological Impact 2.5% Good 0.016666667 Bad 0.008333333 Air Pollution Tolerance 0.5% Extremely Good 0.005 Good 0.003333333 Appearance/Aesthetics 1.0% Very Good 0.008333333 Good 0.006666667 Audible Noise 0.5% Very Good 0.004166667 Good 0.003333333 EMF 0.0% Extremely Good 0 Good 0 Disposal Concerns 3.0% Neutral 0.015 Very Good 0.025

100.0% RANK 0.911179654 RANK 0.797216981 Soft Considerations 0.224166667 0.175833333

Page 32: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

OUTPUT

$-

$5,000,000.00

$10,000,000.00

$15,000,000.00

$20,000,000.00

$25,000,000.00

$30,000,000.00

$35,000,000.00

$40,000,000.00

$45,000,000.00

GIS AIS

Option Net Present Costs

Failure Net Present Cost

Maintenance Net Present Cost

Initial Cost

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

GIS AIS

Option Rankings

Soft Considerations

Net Present Lifecycle Cost

Initial Cost

Page 33: Design Considerations and Lessons Learned - energypa.orgenergypa.org/assets/files/2017/Sept 11-13/Electric Event... · • Relaying+SCADA+RTU built-in to LCC Panels ... -Inspect GIS

Questions/Comments?

Nicholas Matone 2 North Ninth Street, GENN5 Allentown, PA 18101 Work: (610) 220-4403 Mobile: (570) 856-9922 E-mail: [email protected]