design of a composite bridge deck
TRANSCRIPT
-
7/30/2019 Design of a Composite Bridge Deck
1/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulai
Declaration
I declare that this project entitled Re-design of Nariamabune Bridge in Kaabong District of
Karamoja is my own original Project work, except as cited in the references. The project has
not been accepted for any degree and is not concurrently submitted in candidature or award of
any other degree.
Signature Date ..
OKUCU ANTHONY TWENY
(STUDENT)
-
7/30/2019 Design of a Composite Bridge Deck
2/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulaii
Supervisor Approval
Having supervised the student and read through the work herein presented, I do hereby consent
that the project is worth the award of the Degree of Bachelor of Engineering in Civil and
Building Engineering of Kyambogo University
Signed Date
DR. MICHAEL KYAKULA
SUPERVISOR.
-
7/30/2019 Design of a Composite Bridge Deck
3/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulaiii
Project Title:
The title to this project is:
RE-DESIGN OF NARIAMABUNE BRIDGE IN KAABONG DISTRICT
OF KARAMOJA, UGANDA
-
7/30/2019 Design of a Composite Bridge Deck
4/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulaiv
Dedication
To Jehovah God Almighty from whom all wisdom and blessings flow. Take all the praise,
glory and honour!
-
7/30/2019 Design of a Composite Bridge Deck
5/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulav
Acknowledgements
I must in all sincerity, thank my wife, Margaret, children: Shalom, Emmanuel, Rebecca and
Ezra who have had to endure my absence from home during the times I had to be away in order
to pursue this course of studies. From your patience and endurance I derived courage and
feeling of support.
Special thanks to my parents: Joshua J. Tweny and his dear wife Mummy Alice Tweny who
forfeited enjoyment of their meager income in order that I may be schooled.
To Charles Ayo, my very concerneduncle who rekindled my interest in studies when I was
almost giving up on academics. You picked me up and helped me reach here. And to my sister,
Dr. Atim C. Oyet, you were a challenge, an inspiration and a helping hand at the time of need.
To my former school teacher, Mr. Ahimbisiibwe Wilson, who helped me to realize my
engineering aptitude, and encouraged me to tow that line. Little did you know you were
shaping this work but youve done it.
Great appreciation to my Project Supervisor, Dr. Michael Kyakula for the guidance advice and
positive criticisms that have shaped this project and made it such a successful and
comprehensive design report. All my lecturers in the department of Civil and BuildingEngineering of Kyambogo University. The knowledge and skills you imparted was quite
helpful in this project.
To all the staff of Uganda National Roads Authority, Kotido Station for the support and
information they provided and to my course mates for criticizing positively the works
especially during the processes of analysis and design of the structures.
To all the authors and authorities whose works have been cited herein
Thank you all sincerely.
Okucu Anthony Tweny.
-
7/30/2019 Design of a Composite Bridge Deck
6/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulavi
Abstract
Nariamabune Bridge is found in Kaabong District, Karamoja Sub-region, located at
N03Po
P38 57 and E34 Po
P0209 along the Kaabong Kapedo Road link. The road link offers
trade opportunities to the local people with other communities and neighbouring towns,
promotes tourism industry (Kidepo Valley National Game Park) and links the Region to Kenya
and Southern Sudan. It also facilitates humanitarian assistance and security interventions, in
case of insurgencies.
The existing bridge structure comprises of a Bailey bridge (steel decking) supported on stone
masonry abutments that in turn sit on foundations observed to be sinking (a sign of settlement).
Scouring / erosion have also been observed at the abutments and embankments pointing to an
imminent failure.
The problems associated with the imminent failure of the bridge are quite adverse. There is
urgent need to prevent this imminent failure by re-designing the bridge. This project has had to
be carried out, therefore, by using the geo-soil properties of the existing bridge site,
determining the flood levels at the water crossings, carrying out the hydraulic design that will
minimize scouring, determining the significant loads for analysis of the substructure and the
superstructure and designing the decking of the bridge, the abutments (and piers) as technicallynecessary. Finally detailed drawings and appropriate recommendations will be made.
-
7/30/2019 Design of a Composite Bridge Deck
7/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulavii
Table of Contents
Pictures ....................................................................................................................................- 1 -
Chapter 1 .................................................................................................................................- 2 -
1. Introduction.........................................................................................................................- 2 -
1.1. Project Title:.....................................................................................................................- 2 -
1.2. Background:.....................................................................................................................- 2 -
1.2.1. Bridge: ...........................................................................................................................- 4 -
1.2.2. Bridge design:................................................................................................................- 4 -
1.4. Project Aim: .....................................................................................................................- 5 -
1.5. Project Objectives:...........................................................................................................- 5 -
1.6. Scope of the Project:........................................................................................................- 6 -
1.7. Justification:.....................................................................................................................- 6 -
Chapter 2 .................................................................................................................................- 8 -
2.1 Definition of a bridge; ......................................................................................................- 8 -
2.2.1 Bridge Materials: ...........................................................................................................- 9 -
2.2.2 Classification:...............................................................................................................- 10 -
Steel Bridges..........................................................................................................................- 10 -Classification according to structural action:....................................................................- 13 -
Simply supported span bridge.............................................................................................- 13 -
Continuous span bridge .......................................................................................................- 14 -
Cantilever bridge ..................................................................................................................- 14 -
Rigid frame bridges..............................................................................................................- 15 -
Classification according to Floor location..........................................................................- 15 -
Classification based on type of connections: ......................................................................- 17 -
Reinforced- concrete Bridges...............................................................................................- 18 -
Types of Bridges....................................................................................................................- 18 -
2.2.3 Requirements:..............................................................................................................- 20 -
2.3 Site Investigation.............................................................................................................- 21 -
2.4 Substructure and Foundations ......................................................................................- 22 -
2.4.1 Abutments ....................................................................................................................- 24 -
-
7/30/2019 Design of a Composite Bridge Deck
8/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulaviii
2.4.3. Design of Gravity and Cantilever Retaining Walls. ................................................- 24 -
2.4.3.1. Gravity retaining walls............................................................................................- 25 -
2.4.3.2. Cantilever Walls of reinforced cement concrete (RCC) ......................................- 25 -
Abutment design...................................................................................................................- 25 -
Reinforced concrete abutments...........................................................................................- 26 -
2.4.4 Reinforced concrete retaining walls...........................................................................- 26 -
2.4.5 Bearing Shelves............................................................................................................- 26 -
2.4.6 Piers...............................................................................................................................- 27 -
Reinforced Concrete Piers ...................................................................................................- 27 -
2.4.7 Determination of allowable bearing pressure, ..........................................................- 27 -
Non cohesive soils..................................................................................................................- 27 -
Cohesive soils.........................................................................................................................- 28 -Presumed values....................................................................................................................- 30 -
Table 2................................................................................................................................- 31 -
2.4.8. Foundations on Rock..................................................................................................- 33 -
2.4.9. Run-on Slabs ...............................................................................................................- 33 -
2.5 Superstructure ................................................................................................................- 34 -
2.6 Design Detailing..............................................................................................................- 35 -
2.6.1 Vertical Profile over the Bridge..................................................................................- 35 -
2.6.2 Shear Connectors.........................................................................................................- 35 -
2.6.3 Protective Treatment to Steelwork ............................................................................- 36 -
2.6.4 Bolts and nuts...............................................................................................................- 36 -
2.6.5 Bearings ........................................................................................................................- 36 -
2.6.6 Expansion joints...........................................................................................................- 37 -
2.6.7 Construction joints ......................................................................................................- 37 -
2.6.8 Slab Reinforcement .....................................................................................................- 37 -
2.6.9 Drainage........................................................................................................................- 38 -
2.6.10 Parapets, Surfacing and Services.............................................................................- 38 -
2.6.11 Provision for Pedestrians and Cyclists ....................................................................- 38 -
2.7 River Hydraulics and Hydraulic Design.......................................................................- 38 -
-
7/30/2019 Design of a Composite Bridge Deck
9/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulaix
Chapter 3 ...............................................................................................................................- 44 -
METHODOLOGY...............................................................................................................- 44 -
3.3.1 Trial pit excavation......................................................................................................- 45 -
3.3.2 Sampling.......................................................................................................................- 46 -
3.3.3 Soil Testing ...................................................................................................................- 46 -
Chapter 4 .................................................................................................................................-49-
Analysis and Design................................................................................................................-49-
Chapter 5 .................................................................................................................................-99-
Recommendations...................................................................................................................-99-
Appendices.............................................................................................................................-101-
-
7/30/2019 Design of a Composite Bridge Deck
10/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulax
L ist of F igures
TFigure 1.1. Single span Simply supported BridgeT ..........................................................................- 13 -
TFigure 1.2. Simply Supported Multi- span Bridge.T .........................................................................- 13 -T
Figure 1.3 Continuous Span Bridge .................................................................................................- 14 -
Figure 1.4 Cantilever Bridge with a Suspended Span ....................................................................- 15 -
Figure 1.5 Solid Ribbed Arch............................................................................................................- 16 -
Figure1.6. Braced Ribbed Arch. .......................................................................................................- 16 -
Figure1.7. Spandrel Braced Arch Bridge.........................................................................................- 17 -
Figure 1.8. Tied Arch Bridge ............................................................................................................- 17 -
Figure 2.1 Slab Bridge .......................................................................................................................- 18 -
Figure 2.2. Deck Girder Bridge ........................................................................................................- 18 -
Figure 2.3. Composite Steel-Concrete Bridge..................................................................................- 19 -
Figure 2.4. Composite Pre-stressed Concrete Bridge ................................................................- 19 -
-
7/30/2019 Design of a Composite Bridge Deck
11/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 1 -
Pictures
-
7/30/2019 Design of a Composite Bridge Deck
12/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 2 -
Chapter 1
1 Introduction
1.1 Project Title:
Re-Design of Nariamabune Bridge in Kaabong District of Karamoja.
1.2 Background:
Nariamabune Bridge is found in Kaabong District, Karamoja Sub-region, located at N03Po
P38
57 and E34Po
P0209 along the Kaabong Kapedo Road. (see Plate 1 Appendix 1)
The history of this road link was not readily available but Kaabong Kapedo Road plays an
important role of linking parts of Kaabong district to Pader, Kitgum and Lira districts fromwhere most of the merchandise is brought into Kaabong.
This road link is significant not only for linking economic activities of the local people, but
in the promotion of tourism industry. According to a UWA brochure, Kidepo Valley
National Game Park receives tourists from various countries annually. Some of the tourists
reach the National Park by way of Kampala Mbale Soroti Kotido Kaabong route,
while others use the Kampala Karuma Lira Kotido Kaabong - Kidepo Route yet
others use the Kampala Karuma Lira Pader Orom Karenga Kapedo Route. The
former two therefore needs the bridge at Nariamabune to be safe and sound for easy
passage.
Most tourists from Europe, the Americas, Australia and other parts of the world land in
Kenya and from Nairobi, they travel by road to Western Uganda to Mgahinga Gorrila
National Park, Bwindi Impenetrable National Park, Kibale National Park, Queen Elizabeth
National Park, Murchison Falls National Park, and others before embarking on moving to
Kidepo National Park and finally passing along Kapedo Kaabong Kotido Soroti
Mbale to Mt Elgon National Park from where they get back to Kenya.
Besides the trade and commercial activities, this road link is significant in fostering
humanitarian assistances to Karamoja region most of which lies in the arid climatic zone of
North-eastern Uganda, often characterized by famine.
-
7/30/2019 Design of a Composite Bridge Deck
13/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 3 -
Of great importance is the fact that a road link is being planned to join Kapedo to New Site
in Southern Sudan
Kaabong District of Karamoja is located within Latitudes 2 P0P 30 and 4 P0P 15 South and
Longitudes 33 P0
P 30 and 35 P0
P 00 East in the north eastern part of Uganda.The Total area is13,208 kmP
2P (5.47% of Ugandas total area) of which arable land coverage is 7,268 kmP
2P and
water coverage is 0 km P2
P. Since arable land coverage is only 7,268 square km the cropproductivity rating is limited.
Forestry:
There are 12 natural forests and five plantation forests. Artificial forest coverage is 0.2 KmP
2P
with acassia, same and eucalyptus.
Wild life:
The largest Game Park in Uganda (Kideepo Valley National Game Park) has an area of
1,442 square Km.
Animals:
water bucks, Jacksons hartebeest, zebras, buffalos, elands, ribi, warthogs, bush bucks,
jackals, elephants, giraffes, lions, cheetahs, leopards, ran antelopes and ostriches. Bird life is
in abundance.
Minerals:
Gold, silver, copper, iron, and mica and crude petroleum at Kathile basin.
Sunshine and wind:
Between December and April the Northeasterly wind usually exceed 200Km per day.
Characterized by dust storms, desiccating and pulverizing the sparse vegetating cover.
Average rainfall is 519mm per annum. Rainy season falls in April August with a marked
minimum in June and marked maximum peaks in May and July. The rain is erratic in nature.
-
7/30/2019 Design of a Composite Bridge Deck
14/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 4 -
Distinct wet and dry seasons are a prominent feature. The rainfall is unevenly distributed
and unreliable and has a significant influence on the economy and life of the district.
1.2.1. Bridge:
Bridge, in this context, shall mean a structure that permits traffic to pass over the water
crossing safely and conveniently.
1.2.2. Bridge design:
Bridge design in this context shall mean the application of scientific theories in combination
with field data and technological knowledge to come up with a safer and an economical
bridge structure that will permit traffic to pass safely, conveniently and comfortably above
the river crossing.
Almost all human activities involve problem solutions. Production of goods and services has
always resulted from almost all the human activities. Unless the goods and services
produced are distributed, exchanged and consumed the economic chain is not complete. In
order, therefore, to complete the economic chain, transportation becomes a vital factor in the
economy as the outcomes of the production process must find their ways into some market
where exchange and consumption take place.
Transportation involves the movement of factors of production like machinery, labour, raw
materials, fuels, and of finished goods or services to places of utility. Traffic of various
forms and kinds are involved in the said movement, depending on certain factors outlined
herein as: accessibility of the places of production and markets relative to the terrain,
existing infrastructure, drainage pattern and land use.
Traffic form is also dependent on the economic activities, magnitude of haulage and nature
and value of goods and services produced. In this case road transport has been considered as
it is the most feasible and is already an existing infrastructural investment in the area of the
project.
-
7/30/2019 Design of a Composite Bridge Deck
15/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 5 -
1.3 Problem Statement:
The existing bridge structure comprises of a Bailey bridge (steel decking) supported on
stone masonry abutments that in turn sit on an earth foundation. It is observed that since its
constructions in 2004, the bridge deck level is sinking. Information available from UNRA
Kotido Station estimates the level to have sunk by about 400mm yet there are indications
that the embankments are prone to be cut by the waters due scouring and erosion noticed at
the site.
The local scour at abutments are an indication that the width of the channel is not sufficient,
hence a hydraulic design needs to be done, taking into account the scour and a preventive
measures taken to minimize the same.
Qualitative site survey has shown no protective measures taken to minimize the effects of
scour at the abutments upstream of the water crossing, and the side drains of the
embankments are extremely gullied, progressively leading to the embankments failure.
1.4 Project Aim:
The aim of this project is to design a strong and economical bridge to meet the structural and
hydraulic requirements and improve on the level of service for a design life of 40 years.
1.5 Project Objectives:
The objectives are to:
o Carry out the hydrologic and hydraulic analysis of the catchments area and the river,o Determine the flood levels at the water crossings,o Carry out the hydraulic design that will maximize flow with minimal width of
channel and scouring effects
o Determine the significant loads for analysis,o Design the decking of the bridgeo Use the existing soils parameter to Design the abutments, piers and the foundations.o Come up with the working and structural drawingso Make recommendations
-
7/30/2019 Design of a Composite Bridge Deck
16/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 6 -
1.6 Scope of the Project:
o Obtaining Geotechnical data / soil parameter.o Hydrologic (Flow) analysis and Hydraulic Design,o Analysis and design of Superstructure,o Analysis and design of Substructure.o Detailed drawings
1.7 Justification:
Kaabong Kapedo - Karenga trunk road links Pader, Kitgum, Lira and Soroti to Kaabong
Town in the North - eastern part of Uganda. Failure of Nariamabune Bridge and therefore
has a very significant connotation in the economic life of the four towns.
Most of the goods and essential commodities consumed in Kaabong are sourced from
wholesale markets as far as Kampala, Soroti, Mbale and Lira by way of Lira Abim or
Soroti Abim routes. The same routes are used by humanitarian organizations to transport
relief food to the district
The same road is a link to Kidepo Valley National Game Park, therefore, very significant in
tourism industry. The road also links this part of Uganda to Southern Sudan and North-
western Kenya and therefore an important link for international trade. The two facts meanthe road is a foreign exchange earner in Ugandas economy.
There is a plan by the government of the republic of Uganda to connect this road link to
New Site in Southern Sudan through Kapedo, an investment that is anticipated to boost
traffic on Kaabong Kapedo road.
Kaabong District, as already noted elsewhere, is endowed with mineral resources likegold,silver, copper, iron, mica and crude petroleum at Kathile Basin. The exploitation of such
mineral resources require explicit transportation scheme that motivate deliberate investment
in the sector.
Besides the economic considerations, Karamoja region, in general, is an arid area and often
affected by famine. Food aid and humanitarian assistance will always require excellent
-
7/30/2019 Design of a Composite Bridge Deck
17/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 7 -
mobility. Any slight break in mobility will lead to massive death due to famine. Other social
services also need transportation networks that are consistent to facilitate emergency
deliveries.
Worth mentioning is the fact that a section of the Karamojong have firearms and are
aggressive to passers-by. In case of failure of Nariamabune Bridge, such people will not
hesitate to attack, loot, kill or harm the unfortunate road users that may find themselves
trapped in the ignominy.
The problems associated with the imminent failure of the bridge are quite adverse as has
been seen. This project therefore is intended to offer solutions by preventing the failure
through redesigning the bridge.
-
7/30/2019 Design of a Composite Bridge Deck
18/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 8 -
Chapter 2
2.0 LITERATURE REVIEW
The basic concept involved in this chapter is to examine the recent and historical significantstudies that form the basis of design of a bridge.
2.1 Definition of a bridge;
Abridge is a structure for carrying road traffic and other moving loads over a depression orgap or obstruction such as river, canal, channel, canyon, valley, road or railways (Punmia, et
al 1998). In other words, it's the structural system carrying the communication route and
includes beams, girders, stringers, arches, cables and all other components above bearing
level.
If a bridge is constructed to carry highway traffic, it is known as a highway bridge. If,
however, it is constructed to carry railway traffic, then it is known as a railway bridge. There
may be a combined highway and railway bridge to carry both the highway as well as railway
traffic. Some bridges, constructed exclusively to carry pedestrians, cycles and animals, are
known asfoot bridges while those constructed to carry canals and for pipe lines are known as
aqueduct bridges.
A bridge may be a culvert, high level bridge or submersible bridge. A culvert is a bridge
having a gross length of six metres or less between the faces of abutments or extreme
ventway boundaries, and measured at right angles there to the direction of water flow.
A high level bridge is a bridge which a carries the roadway above the highest floodlevel of the channel.
Asubmersible bridge is a bridge designed to be over topped in floods. A bridge may befixedormovable type. Afixed bridge is the one which always remains in one position.
-
7/30/2019 Design of a Composite Bridge Deck
19/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 9 -
A movable bridge is the one which can be opened either horizontally or vertically soas to allow river or channel traffic to pass. Such bridges are constructed over a
navigable stream where the normal headway is not sufficient for the vehicles to pass
through.
A bridge may be either of deck type or through type.
A deck type bridge is the one in which the roadway/railway floor rests on the top of the
supporting structure.
A through bridge is the one where the roadway/railway floor rests on the bottom of the main
load supporting structure.
However when the floor lies between the top and bottom of the main load supporting
structure, it is known as half through type bridge,semi-through bridge orpony bridge.
2.2.1 Bridge Materials:
Bridges are made of different material such as timber, stone masonry, brick masonry,
concrete and steel. Timber bridges are constructed only over small spans and for temporary
purpose, to carry light loads. Masonry bridges are also constructed for shorter spans.
Concrete bridge, both of reinforced cement concrete (RCC) as well as of prestressed cement
concrete (PCC) are constructed over moderate to high spans, to carry all types of loads.
Concrete arch bridges have been constructed of spans up to 200 m. Similarly, steel bridges,
are constructed both over moderate to high spans as well as for heavy trafficular loads. In
India, steal bridges are commonly used for railways for all types of spans. [Pumnia, et al
(1995)]
Abridge just like any other civil engineering structures has two component parts, namely
Substructure Super structure
-
7/30/2019 Design of a Composite Bridge Deck
20/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 10 -
2.2.2 Classification:
(i). According to end fixity a bridge can be classified as simple or continuous bridge.(ii). According to ability to slide/move a bridge can be fixed or movable bridge.
(iii).
According to purpose it may be foot railway or highway Bridge.(iv). According to location of bridge floor it may be deck, through or semi-through
bridge.
(v). According to highest flood levels it may be submersible or non-submersible.(vi). According to construction materials it may be stone and brick (Masonry), steel,
timber or concrete bridge
Steel Bridges
Classification
Steel bridges may be classified according to the following criteria:
1. Type of structural arrangement2. Structural action3. Floor location4. Type of connection5. Movement of structural parts
Classification according to structural arrangement:
Under this classification a steel bridge may be of the following types:
(i). I-girder bridge(ii). Plate girder bridge
(iii). Truss girder, or(iv). Suspension bridge.
-
7/30/2019 Design of a Composite Bridge Deck
21/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 11 -
I-girdersmay be used for small as the main load carrying members. For this purpose, wide
flanged I-sections are used. Such structures are suitable for spanning over crossings of
moderate widths. There are however limitations in the maximum size of available I-sections,
hence for longer span bridges built up plate girders are to meet the requirements of section
modulus corresponding to the applied loads.
Plate girder bri dges:This type of are quite popular with railway bridges, the advantage
being in transportation since it can be transported in one piece. the limiting depth of plate
girders is only 3 -4m hence when the structural requirement for depth is more than this, steel
truss girder bridges are preferred.
Truss girder bridges: in this arrangement, trusses are used as the main load carrying
members. They are commonly used over spans of 20 200m
For still longer spans, steel arch bridges or suspension bridges using high strength steelcables may be used.
-
7/30/2019 Design of a Composite Bridge Deck
22/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 12 -
-
7/30/2019 Design of a Composite Bridge Deck
23/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 13 -
Classification according to structural action:
According to the criteria of structural action, steel bridges may be of the following types:
(i).
Simply-supported-span bridges(ii). Continuous span bridges
(iii). Cantilever bridge(iv). Arch bridges(v). Rigid Frame Bridge.
Figure 1.1. Single span Simply supported Bridge
(i) Simply supported span bridge
Such types are commonly used when the width of gap is small, necessitating the use of
single span. However, even if the width of the gap to be bridged is large, the whole widthcan be subdivided into a number of individual spans, each span being simply supported
Figure 1.2. Simply Supported Multi- span Bridge.
Such an arrangement is preferred specially .is those locations where there is likelyhood of
uneven settlement of intermediate piers. The analysis of simply supported span bridge is
very simple.
-
7/30/2019 Design of a Composite Bridge Deck
24/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 14 -
(ii)Continuous span bridgeWhen the width of gap is quite large, and where there are no chances of uneven settlements,
bridge may be continuous over two or more spans (Figure 1 (c)). Because of continuity,
moments are developed at pier supports resulting in the reduction of stresses at the inner
spans. This results in an economical design. Also, continuous span bridges require few
supports, since larger spans can be used; they can also support higher loads in comparison to
simply supported spans.
Figure 1.3 Continuous Span Bridge
(iii) Cantilever bridge
In the case of a three span continuous bridge, loaded with uniformly distributed load over all
the three spans, it is observed that these are two points of contraflexure in the central span.
Hence if the continuous beam/girder of the middle span is cut at these two points of
contraflexure, and shear resisting joints are made at these two points, the resulting
configuration will be a cantileverbridge with a central suspended span between these two
formed joints, as shown in Figure 1.4. Thus, a cantilever bridge consists of two simple
spans, one at each end, each having an overhanging or cantilever portion along with a
simple span (or suspended span) in between the two cantilever portions. The main
advantage of such an arrangement is that the B.M. diagram will now not be affected by the
settlement of supports. The suspended span is supported by the cantilever span, at each endby means of mechanical hinge. This gives rise to a statically determinate structure which can
be analyzed very easily. Because of development of moments at the pier supports, the
stresses in each end span is very much reduced. Another advantage of such bridge is that the
cantilever portion and the suspended span can be erected without the use of false work or
-
7/30/2019 Design of a Composite Bridge Deck
25/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 15 -
staging. Such bridges are usually provided for longer span, ranging between 200 m to 500
m.
Figure 1.4 Cantilever Bridge with a Suspended Span
(i v) Arch Bridge.
For deep gorges, arch bridges are generally used, since they offer economical and aesthetic
solution. However, they require strong abutments to resist the thrust from the arches. The
arches may consist of girder sections or trusses, and may be:
Fixed arches Two hinged arches, or Three hinged arches,
The two hinged arches are more common.
The arch bridge may further be classified as:
solid ribbed arches braced rib arch spandrel braced arches or Tied arches (Figure 1.8).
Solid ribbed arch bridges are more commonly used for highways, while braced rib arch
bridges and spandrel braced bridges are commonly used for railways.
( v) Rigid frame bridges
Rigid frame bridges, comprising of single span or two to three continuous spans, are usedfor dry-over or under-crossing, for gaps between 10 to 20 m. These consist of steel columns
and steel girders with continuity at the knee. Such bridges are quite suitable for rigid
foundations.
Classification according to Floor location
-
7/30/2019 Design of a Composite Bridge Deck
26/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 16 -
According to the location of the floor, bridges can be classified as under:
Deck-type bridge Through type bridge Half through-type bridge.
In deck type bridge the floor is placed on the top flange in the case of plate girder bridge and
on the top chord in the case of a truss bridge. No top bracing is therefore required.
In the case ofthrough type bridge, the floor" is placed at the level of lower chord of truss
type bridge, and the top chord is braced laterally.
However, in the case of plate-girder bridge, the floor of the through bridge is supported on the bottom flange. In half through bridge, also known as ponny truss bridge, the floor lies
between the top and the bottom. There are also double deck bridges constructed to carry the
traffic of both roadways and railways. Both the decks can have through floors. Alternatively,one deck may have through floor while another deck may be kept open. The requirements of
grade line and clearance of highways or railway track decide whether it should be through-
type bridge or a deck type bridge. Deck type bridges are more economical than through type
bridges, and hence they are more popular.
Figure 1.5 Solid Ribbed Arch.
Figure1.6. Braced Ribbed Arch.
-
7/30/2019 Design of a Composite Bridge Deck
27/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 17 -
Figure1.7. Spandrel Braced Arch Bridge
Figure 1.8. Tied Arch Bridge
Classification based on type of connections:
Depending upon the type of connections of the joints, bridges can be of the following types:
(i). Riveted bridges(ii).
Welded bridges
(iii). Bolted (pin connected) bridges
-
7/30/2019 Design of a Composite Bridge Deck
28/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 18 -
Reinforced- concrete Bridges
Types of Bridges
According to WinterandNilson (1972), reinforced concrete is particularly adaptable
for use in highway bridges because of its durability, rigidity, and economy, as well
as the comparative ease with which a pleasing architectural appearance can be
secured. For very short spans, from about 10 to 25 ft, one-way-slab bridges (Fig. 2.1)
are economical. For somewhat longer spans, concrete girder spans (Fig. 2.2) may be
used.
Probably most highway spans of medium length, from 40 to 90 ft, presently use
composite steel-concrete construction (Fig. 2.3) or composite pre-stressed-concrete
construction (Fig. 2.4).
Figure 2.1 Slab Bridge
Figure 2.2. Deck Girder Bridge
-
7/30/2019 Design of a Composite Bridge Deck
29/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 19 -
Figure 2.3. Composite Steel-Concrete Bridge
Figure 2.4. Composite Pre-stressed Concrete Bridge
In composite construction with structural steel, the concrete deck is made to act
integrally with supporting steel stringers by means of devices called shear connectors,
welded to the top flange of the steel section and embedded in the slab. Although such a
bridge is not strictly a reinforced-concrete structure, the design of this type of bridge
will be discussed in some detail in this section because of its widespread use. Pre-
stressed-concrete bridges frequently make use of composite section characteristics also.
Commonly, the girders are pre-cast and placed into final location by crane, eliminating
-
7/30/2019 Design of a Composite Bridge Deck
30/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 20 -
the necessity for obstructing traffic by falsework. The deck slab is then cast in place,
bonded, and tied to the pre-cast sections by steel dowels.
Hollow box girders, usually pre-stressed, are often used for intermediate and long-
span concrete bridges. Spans up to about 80 ft are pre-cast in one piece and lifted into
position. Longer spans of similar cross section, carrying two lanes of highway traffic
as well as shoulders and walkways, have either been cast in place or pre-cast in short
segments, which are post tensioned after positioning.
Bridge spans as long as 320 ft have been attained using pre-stressed girders. Other
possibilities for long-span concrete bridges are the various forms of arches, including
the barrel arch and the three-hinged arch. [Winter and Nilson (1972)]
2.2.3 Requirements:
The bridge should be efficient, effective and equitable so that;
It is economical
It's aesthetically sound It should serve the intended function with utmost convenience, comfort and
safety.
It is durable
-
7/30/2019 Design of a Composite Bridge Deck
31/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 21 -
2.3 Site Investigation
The soils supporting the abutments and pier foundations always carry the weight of the
traffic, superstructure, abutments and piers. In order to design for the best suitable
foundations, the designer has to determine the nature and location of the different soil typesoccurring at the site of the bridge and its approaches, to depths containing strata sufficiently
strong to support the bridge and embankments without failure.
This information is obtained by analyzing samples taken from a grid of bore-holes or test pits
covering the whole of the proposed site, and by testing the samples for density, shear
strength, plasticity and penetration, in order to provide quantitative data for foundation
design.
2.3.1 Methods of site investigation
Test pits Hand auger boring Cable percussion boring Rotary drilling Geophysical surveying.
2.3.2 Sampling
The choice of sampling technique depends on the purpose for which the sample is required
and the character of the ground.
There are four main techniques for obtaining samples:
Taking disturbed samples from drill tools or from excavating equipment in the courseof boring or excavation
Drive sampling in which a tube or split tube sampler with a sharp cutting edge at itslower end is forced into the ground, either by static thrust or by dynamic impact
Rotary sampling, in which a tube with a cutter at its lower end is rotated into theground, so producing a core sample
-
7/30/2019 Design of a Composite Bridge Deck
32/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 22 -
Taking block samples cut by hand from a trial pit, shaft or heading.Samples obtained by the last three techniques will be sufficiently intact to enable the ground
structure within the sample to be examined. However, the quality of these samples can vary
considerably, depending on the sampling technique and ground conditions, and most sampleswill exhibit some degree of disturbance. Table 2.1 indicates the mass of sample required for
identification purposes, Atterburg tests, moisture content, sieve analysis and sulphate tests.
Care should be taken to ensure that samples are as pure and undisturbed as possible.
Table1. Required Sample Mass
2.3.3 Aggressive Chemicals
The ground or ground water may contain chemicals capable of causing damage to concrete
or steel. These chemicals may emanate from nearby industrial processing or may occur
naturally. Total sulphate content of more than 0.2% by weight in soil and 300 ppm in ground
water are potentially aggressive (BRF 1981). There are often difficulties in specifying
ground condition before the excavation for constructions are complete. For this reason the
engineer should be prepared to review his plan, both during construction, if evidence is
found of unexpected soil conditions.
2.4 Substructure and Foundations
This is a support for the super structure and comprises of; abutments, piers, wing walls and
any part below bearing level i.e. the foundation.
Soil typeMass required
(kg)
Cla , silt, sand 2Fine and medium gravel 5
Coarse gravel 30
-
7/30/2019 Design of a Composite Bridge Deck
33/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 23 -
The substructure can be made of materials such as mass concrete, reinforced concrete, steel,
timber and ifexperience is available in structural masonry it can be an economical substitute
for concrete. However, the engineer must be certain of the strength of materials used,
particularly when they are submerged in flowing water.
All concrete decks must have rigid substructures like those detailed in this booklet, because
uneven settlement of either abutment or pier can result in unacceptably high stresses in the
materials of the decks. The positioning of the abutment and pier foundations is critically
important.
Because the most likely cause of bridge failure is scour, a bridge designer should pay careful
attention to the estimation of general and local scour. Pier foundation depths are specified
according to foundation type and protection method. However when dealing with
substructures and foundation, there are two important issues to consider:-
The general scour area must not be obstructed or the flow will be impeded meaningmore scour damage.
Local scour is caused by turbulence and may be reduced by armouring the bed.Abutments also fail when the soil under the foundation is not strong enough to carry the
combined forces from the bridge structure and the embankment. It's recommended that
spread foundations be used wherever possible, but if adequate support is unavailable, a piled
foundation is required.
If a satisfactorily strong soil is found not too far below preferred foundation level, caisson
support may be considered. The technique is simple if the caissons are short, but the engineer
must take care that:-
The maximum soil reaction at the sides does not exceed the maximum passivepressure at any depth,
The soil pressure at the base remains compressive throughout and the maximumpressure does not exceed the allowable pressure.
-
7/30/2019 Design of a Composite Bridge Deck
34/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 24 -
2.4.1 Abutments
Besides carrying the dead load of the superstructure, it's imperative that the abutments of a
bridge must:
Resist the vertical and horizontal live loads exerted on them by vehicles and otherelements.
Retain the approach embankments and the live loads (or surcharge) applied to them. Provide a smooth transition from the road surface to the deck running surface.
The essentials features of abutments are:-
A foundation slab, which transmits the weight of the abutment and the superstructureand its loads directly to the supporting soil, or which forms a capping slab to a system
of load bearing piles.
A front wall with bearing shelf that supports the superstructure and usually retains thesoil of the embankment.
Wing walls or retaining walls which may be separate from the abutments or, if theyare short, may be built integrally with them. These walls retain the road embankment
or river bank adjacent to the abutment and are usually built so as to bisect the angle
between the road and the river bank, though they can be set at any angle to the
abutments and may be built parallel to the road or perpendicular to it.
2.4.3. Design of Gravity and Cantilever Retaining Walls.
A gravity retaining wall is that which resists the lateral earth pressure by its own weight;
whereas, a cantilever retaining wall is that which resists the lateral earth pressure by bending
action. Garg (2005)
-
7/30/2019 Design of a Composite Bridge Deck
35/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 25 -
2.4.3.1. Gravity retaining walls
Gravity retaining walls are, therefore, thicker in section, and are made of stone or brick
masonry or sometimes plain cement concrete (PCC).
2.4.3.2. Cantilever Walls of reinforced cement concrete (RCC)
The cantilever walls of reinforced cement concrete (RCC) are more economical, because the
backfill itself is employed to provide most of the dead weight to counteract the lateral thrust.
Both types of walls are liable to rotational turning or translational sliding movements, and
the lateral pressure for the design is computed by Rankines or Coulomb,s theories.
The design of retaining wall should be such that the wall as a whole must satisfy the two
basic conditions: The base pressure at the toe of the wall must not exceed the allowable bearing
capacity of the soil.
The Factor of safety against sliding between the base and the underlying soil must beadequate; value of 1.5 being usually required.
Unyielding retaining walls, such as the bridge abutments, restrained by the deck structure,
do not deform. In such cases, therefore, active or passive pressures would not be developed;
rather, the lateral pressures should be computed as equal to rest value using the coefficient
KBRB (also represented byKBOB).
This value ofKBRB is also very high when the backfill is compacted artificially; say as high as
0.8 or so. It has, thus, been noticed that in such unyielding walls, compaction caused by the
flow of sewers, etc. may lead to residual lateral pressures, considerably higher than the
corresponding values for the uncompacted soil.
(i)Abutment design
While designing the abutment, there is need to carefully analyze and take into account all the
individual characteristics of the site and the superstructure, e.g. foundation conditions, deck
thickness, expansion joints etc. Specifications for the concrete and steel are also important.
-
7/30/2019 Design of a Composite Bridge Deck
36/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 26 -
(ii)Reinforced concrete abutments
For small span bridges of (span not exceeding 12m) abutments are provided with a standard
width of 1200mm at the top but the front and rear faces are vertical. This structure is
considerably lighter than its mass concrete counterpart. The bearing shelf is an integral partof the stem. The widths of the toe and heel, and the thickness of the foundation for various
heights, span and bearing pressures are suggested in ORN9.
2.4.4 Reinforced concrete retaining walls
Considerations here are just as in the abutments with reinforced concrete stems. If the
retaining wall is not long, weep holes can usually be ignored. These details apply to thetypical case of walls set at 45 to the abutments supporting road embankments with slopes of
1 in 2.
2.4.5Bearing Shelves
These designs are generally suitable for concrete, composite or timber decks, though the
bearing details will be specific to the deck type. The dowel and bearing pad details are
required for concrete and composite decks. Good drainage and the facility for removal ofdebris are important requirements on all bearing shelves. The road approaches should be
built to prevent water draining onto the bridge, but some water falling on the deck will
penetrate expansionjointseals and leak through to the bearing shelves. This is particularly
likely to occur when no seal at all is provided. A number of drainage configurations are
available, Hambly (1979), but the two main principles to be observed are:-
Slope horizontal surfaces to direct water away from the bearing pads. Provide good access for the removal of stones, vegetation, bird nests and other
debris.
-
7/30/2019 Design of a Composite Bridge Deck
37/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 27 -
2.4.6 Piers
Just like abutments, piers perform a support function by transmitting vertical and horizontal
loads from the superstructure via the bearing shelf, stem and foundation slab to the
supporting soil. In most cases, piers stand on saturated soils for most or all of the year: theydo not retain soil embankments but are designed to withstand hydraulic pressures and impact
loads. Piers are often more affected by scour damage than abutments and need to be
orientated carefully with respect to flow direction. Their foundations should be located well
below maximum scour depth.
Reinforced Concrete Piers
Though piers may be built using masonry or mass concrete, reinforced concrete has severaladvantages, notably a more slender stem presenting less interference to flow and hence
causing less induced scour. Superstructure spans are sometimes designed to be simply
supported at the abutments and at the piers. Each span should have one fixed and one free
end. It is usual practice, though not essential, to provide one fixed bearing and one free
bearing on the bearing shelf of each pier. Pier foundations are even more susceptible to
damage by erosion than abutment foundations. They must be constructed on soils of well
established allowable bearing pressure
2.4.7 Determination of allowable bearing pressure,
a) Non cohesive soils
The allowable bearing pressure under foundation in non cohesive soils is governed by the
permissible settlement of the structure due to consolidation of the soils under the appliedloading.
If standard penetration tests have been performed in bore holes, the values of N can be used
to obtain allowable bearing pressure for various foundation dimensions.
-
7/30/2019 Design of a Composite Bridge Deck
38/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 28 -
The allowable bearing pressure is that which causes 25mm of settlement under the given
breadth of foundation front to back, B BrB i.e. measured perpendicular to water flow direction on
the assumption that the water table always remains at the depth of at least B BrB below the
foundation level. If the water table can be higher than this, then the allowable pressure is
halved. At a shallow depth, the test seriously under-estimates the relative densities of
cohesionless soils thus the engineer may need to correct the standard penetration values
measured in boreholes before applying the relationships
To allow for this, a correction factor should be applied to the measured values
Where the N values of a fine or silty sand below the water table is greater than 15, the
density of the soil should be assumed to be equal to that of sand having the N value of
)15(2
115 + N
Very loose uniformly graded sands with N equal to 5 or less and subject to rapid changes of
water level are liable to suffer large settlements under load. In these circumstances, either the
sand should be dug out and thoroughly re-compacted or the foundation should be supported
on piles.
b)Cohesive soils
Most cohesive soils at the foundation level are saturated and have an angle of shearing
resistance equal to zero. Provided that no water is expelled from the soil as the load is
applied. This is accepted as the basis for calculating the ultimate bearing capacity of
foundations where the load is applied relatively quickly.
The ultimate bearing capacity of cohesive soils can be calculated from the following
formula.
Ultimate bearing capacity, qBfB = CBuBNBeB = P
Where
-
7/30/2019 Design of a Composite Bridge Deck
39/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 29 -
Cu = untrained shear strength (kN/m P2
P)
NBeB = bearing capacity factor
P = total overburden pressure at foundation level kN/mP2
P
= D
Where
= density of soil above foundation level kN/m P3
P
D = depth of foundation level below ground surface.
Values of the bearing capacity factor N BcB for square or circular foundations can be read from
the graph inFigure 8.6 ORN9
For rectangular foundations
NBc(rectangular) B=BB cr N
L
B
+ 16.084.0
Where
BBrB = breadth of the foundation front to back
L = length of the foundation
The undrained shear strength CBuB of soft clays can be measured by means of field vane tests
but the results need to be corrected because the soil is sheared in the horizontal direction.
The value of CBuB to be used in the bearing capacity formula is the vane shear strength
multiplied by the correction factor read from the graph in figure 8.7 ORN 9. This factor is
dependent on the plasticity index of the soil.
-
7/30/2019 Design of a Composite Bridge Deck
40/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 30 -
The allowable bearing pressure is one third of the calculated ultimate bearing capacity.
c)Presumed values
Sometimes at the preliminary stage of design there may be no measured values of soil
density or field strengths available. For purposes of estimation, Table 2.2 below lists
approximate values of allowable bearing pressures for different soil types.
-
7/30/2019 Design of a Composite Bridge Deck
41/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 31 -
Table 2. Presumed Bearing Capacities
(a) Foundations beadng on ROCK, width not exceeding
3m and the length not more than 10 times width.
Description of rockPresumed
bearing
valuekN/mPzPMassive strong igneous and
metamorphic rocks and limestones10,000
Unweathered medium to fine grained
sandstones4,000
Schists and slates 3,000Hard shales, mudstones and soft
sandstones1,500
Soft limestones 600
(b) Foundations in non cohesive soils at a minimum
depth of 1m below ground level
Presumed bearing
value,kN/mPz
P
Foundation widthDescription of soil
1m 2m 3m
Very dense sands and gravels 600 500 400
Dense sands and gravels 500 400 300
Medium dense sands and gravels 250 200 150
Loose sands and gravels 100 75 75
(c) Foundations in cohesive soils at a minimum depth of
1m below ground level
Presumed bearing
value,kN/mPz
P
Foundation widthDescription of soil
1m 2m 3m
Hard boulder clays, hard fissured
clays, weathered shales and
weathered mudstones800 600 400
Very stiff boulder clays, very stiff
marls600 400 200
stiff boulder clays, stiff fissured clays
and stiff marls300 200 100
Firm clays 150 100 75Soft alluvial clays 75 35 0
Source: Table 8.1 ORN 9
-
7/30/2019 Design of a Composite Bridge Deck
42/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 32 -
-
7/30/2019 Design of a Composite Bridge Deck
43/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 33 -
2.4.8. Foundations on Rock
The foundation designs presented in the preceding sections are for soils readily excavated by
hand or mechanical digger. Modifications may be required to suit individual site conditions,
particularly when bedrock is encountered. Where foundations are set on rock at ground levelor on the river bed, substantial keying will be necessary in the form of steel dowels and
notching.
2.4.9.Run-on Slabs
Almost all earth embankments are subject to settlement. The amount they settle will depend
on the height, the degree of compaction of the material and the strength of the sub-grade.
Relatively uniform settlement can be expected from most embankments until a cause of
uneven compaction is met, such as a bridge or a box culvert with little fill above it. It is
difficult to compact fully the embankment material close to the bridge abutments or the
culvert walls, and the result of poor compaction is more pronounced settlement. The
resulting longitudinal profile is uncomfortable for road users and causes impact loads on the
structure, owing to vehicle bounce. These local depressions in the carriageway close to
drainage structures may be bridged using run-on slabs. They are more easily constructed at
the same time as the structure, rather than afterwards as a remedial measure, and they span
the fill material susceptible to settlement. One end of the slab rests on a small shelf cast onto
the culvert wall or on the abutment ballast wall, while the other rests on well compacted
material several meters away.
Run-on slabs are usually between 3 and 6 meters long. The concrete and reinforcement
details may be abstracted from the culvert detailing, assuming that the slab is resting on good
support for one third of its length, i.e. a 6m slab will have similar details to a 4m wide
culvert lid. Run-on slabs are usually made wide enough to support the kerbs on the approach
roads.
Run-on slabs should not be required where efficient maintenance facilities are readily
available (Hambley 1979).
-
7/30/2019 Design of a Composite Bridge Deck
44/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 34 -
2.5 Superstructure
2.5.1Steel/concrete Composite Superstructures
Because they are easy to erect, more durable if well maintained and are light in weight, steel
beams with concrete decking are often a good solution for structures intended to have a long
service life. Through regular maintenance painting can prevent deterioration of the beam
webs and bottom flanges. Where structures are intended to be permanent, the durability of
the steel over a service life of 50 years or more can be achieved more readily by the use of a
cast in situ concrete deck slab (ORN 9). Composite action of the slab and beams is secured
by the use of shear connectors welded to the top flanges of the beams and cast into the
concrete. As an alternative to the solid concrete slab decks almost any bridge can be
constructed of steel universal beams (UB) with a composite concrete deck slab. The main
beams and cross members can be of standard rolled carbon steel sections (yield stress
274N/mmP2
P), with deck slab reinforcement in either mild steel (MS) or high yield steel
(HYS).
However, Steel/concrete composite deck structures have the following advantages:
The deck self weight can be less than that of an equivalent all-concrete structure The off-site prefabrication of the main load carrying elements of the bridge greatly
reduces the work necessary on site, resulting in more rapid construction.
No temporary supports are required during construction of the deck slab, since thesoffit shuttering can be supported directly from the steel beams. This can be a
particular advantage at sites with poor ground conditions, steeply sloping terrain, or
with a fast stream.
Steel is a more reliable material which is supplied with guaranteed strengthproperties, enabling the production of high and consistently reliable structure.
-
7/30/2019 Design of a Composite Bridge Deck
45/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 35 -
2.5.2. Reinforced Concrete Bridges
Reinforced concrete is particularly adoptable for use in highway bridges because of its
durability, rigidity, and economy as well as comparative ease with which a pleasing
architectural appearance can be secured. Winter (1972)
For very short spans of about 10ft (3m) to 25ft (7.5m), one way slab bridges are economical.
For somewhat longer spans, concrete girder spans may be used. Most highway spans of
medium length, from 40ft. (12m) to 90 ft. (27m), presently use steel- concrete construction
or composite pre-stressed concrete. In composite construction with structural steel, the
concrete deck is made to act integrally with supporting steel stringers by means of shear
connectors, welded to the top of thee flange of the steel section and embedded in the slab.
2.5.3 Design Standards
Among many, the design of any bridge and/or its superstructure can be in accordance with
B88110 structural use of concrete, BS 5950 structural use of steel. BSI (1979) for HA
loading and AASHTO (1985) for HS20-44 loading, Uganda Bridge Design Manual, and
Uganda Drainage Design manual
2.6 Design Detailing
2.6.1 Vertical Profile over the Bridge
The bridge should preferably be constructed either to a level profile or to a constant
longitudinal grade, if this is required by the road alignment. The steel beams can be
cambered to give some degree of hogging vertical curvature should the equipment be
available, but it may not be economical in most circumstances.
2.6.2 Shear Connectors
In order to provide more restraints to the steel beams and help attach firmly, the deck to the
tensile stress carrying steel beams, connectors are provided. These connectors are the only
links between the concrete slab, acting in compression and bending when under load, and the
steel beams, acting in tension and bending. The largest shear forces act at each end of the
-
7/30/2019 Design of a Composite Bridge Deck
46/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 36 -
deck, where the shear connectors are spaced closer together. Welded channel shear
connectors are specified, since they can be produced from readily available material and
fixed locally. The joints, however, should be of good quality welding and be protected from
corrosion both in storage and in use.
2.6.3 Protective Treatment to Steelwork
The degree of protection which the steelwork will require depends on the local environment.
However Particular care should be provided for structures in coastal locations or where there
is significant atmospheric pollution. Types of paint used and surface preparation methods
depends on the availability of materials and equipment. The designer should try to achieve
the following standard in order to ensure a reasonable life to first maintenance:
Grit blasting to remove mill scale, loose rust, welding scale etc., and produce a cleansurface for any coat of painting especially prime;
Application of a multi-coat paint system to a total dry film thickness of 0.25mm.
At least one paint coat should be applied at site after completion of construction, so that
damage to paintwork incurred during transport, steel erection and concreting can be repaired.
2.6.4 Bolts and nuts
Ordinary bolts, grade 8.8 to ISO (1982) together with grade 8 nuts, are specified for fixing
cross members. Alternatives should match the tensile strength of 80 kg/mmP2
P with a
minimum elongation at fracture of 2%.
2.6.5 Bearings
Elastomeric bearings, are specified because they are durable, inexpensive and simple to
install. These bearings consist of discrete strips of black natural rubber, extending over the
full width of the slab soffit at the support point, with a maximum width of approximately
300mm and a maximum thickness of approximately 25mm. At the free end of the span, the
bridge deck locates by friction between the rubber strip and the concrete deck, with no
-
7/30/2019 Design of a Composite Bridge Deck
47/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 37 -
positive mechanical means to develop resistance against transverse loadings. At the fixed
end, dowel bars passing through the pad at frequent intervals provide the necessary restraint,
both longitudinally and transversely. To allow rotations to occur and the deck to expand
laterally, the dowel bars are usually fitted with rubber caps where they pass into the concrete
deck slab.
2.6.6Expansion joints
At these relatively short deck lengths, joint movements due to temperature and live loading
are small and are readily accommodated by a simple gap joint, The joints are sealed by a
polysulphide sealant to prevent water penetration. An alternative unsealed joint, more
suitable for bridges on gravel roads, may be provided.
2.6.7Construction joints
It is always best if the deck slab can be cast in one continuous pour. If this will not be
practicable, permissible locations for construction joints should be marked on the drawings.
If a joint is unavoidable, it should be perpendicular to the centre line at a location least likely
to promote corrosion in underlying steelwork.
2.6.8Slab Reinforcement
According to Overseas Road Note 29 Section 9.2.5, the maximum length of reinforcing bar
generally available is 12m. Where a longer bar is required, e.g. for a 12m span bridge, two
bars must be lapped. The lap length should be at least 40 times the diameter of the lapped
bars and laps should be staggered both to avoid a line of weakness and to minimize
congestion of reinforcement. Main bars are positioned with the hooks at alternate ends.
Accurate positioning of the reinforcement is essential in order to maintain the minimumcover of 50mm of well compacted concrete, so that moisture and pollutants cannot penetrate
the slab to reach the reinforcing bar and corrode it.
-
7/30/2019 Design of a Composite Bridge Deck
48/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 38 -
2.6.9 Drainage
Drainage should be provided if required, generally as detailed for concrete slab bridges down
pipes must be of sufficient length to ensure that run-off water is discharged at least 150mm
clear below the beam lower flanges.
2.6.10 Parapets, Surfacing and Services
Parapet and surfacing details are the same as for concrete slab bridges. If ducts for services
are required, they can be provided
2.5.11 Provision for Pedestrians and Cyclists
The recommendations set out on pathways for pedestrians and cyclists on concrete decks
apply equally to composite decks. The addition of a 2m wide walkway to a composite deck
of the type detailed here would also require one more ''I'' beam to match those for the road
bridge.
2.7 River Hydraulics and Hydraulic Design
2.7.1 River Hydraulics
In order to secure safety from the effects of flowing water, the engineer has to ensure that the
flowing water under the bridge can pass the structure without causing damage to its parts, the
road embankment or the surrounding land. This topic thus explains how the parameters for
safe hydraulic design can be obtained. Damage can occur in a number of ways, namely:
The river may react against obstructions such as piers and abutments, and scourbeneath them causing failure.
The approach embankments may act as a dam during high floods, sustaining damageor causing more extensive flooding upstream.
A river flowing on a shifting path may bypass a bridge and cut a new channel acrossthe highway
A river may over-top a bridge if sufficient clearance is not provided.
-
7/30/2019 Design of a Composite Bridge Deck
49/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 39 -
The hydraulic characteristics of the river must be well understood and quantified so as to be
able to design a structure that avoids the above problems and unnecessary costs. The most
economical structure is usually one which is just wide and high enough to accommodate the
design flood, minimizing the total cost of abutments, piers, superstructure, approach
embankments, relief culverts and river training works.
The hydraulic data required for the design process detailed in the following sections relate to:
Design flood level DFL, flow volume and velocity. Maximum flood level, flow volume and velocity. Bed characteristics - particle size, vegetation. Channel shape and flood plain width. Sedimentation and meander characteristics. Navigational requirements and clearance of floating debris.
Using the above data, determine by calculations the:-
Geometry of waterway required at the bridge site. Backwater caused by the restriction of flow due to piers and abutments. (Scour
caused by the restriction.
River training works required.Calculating velocity using Manning's formula to estimate mean velocity
213
2
1S
P
A
nV
=
Where
V= velocity (m/sec)
A = Area of cross section of the flooded channel (mP2
P)
P= length of the wetted bed across the channel
-
7/30/2019 Design of a Composite Bridge Deck
50/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 40 -
S= gradient of the surface or bed slope
n = value of rugosity coefficient taken from the table 4.1 (ORN 9)
There are many methods of obtaining flow volume but only two are discussed here.
(i). The Area velocity methodQ =A.V
Where
Q = volume of flow (m P3
P/sec)
A= cross sectional area (mP2
P)
V= mean velocity of the water (m/sec)
Area velocity method is necessary where the river tops its banks during flood.
(ii).
The Rational Formula
)/(6.3
3 smCIA
Q =
Where
Q = volume of flow (mP3
P/sec)
C= Catchment coefficient
I = Rainfall intensity (mm/hr)
A = Area of the watershed/ catchment.
-
7/30/2019 Design of a Composite Bridge Deck
51/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 41 -
In design of any bridge structure, much as excessive rainfall is unpredictable, it should be
carefully designed for. Meteorological data should be used carefully to narrow or remove the
range of uncertainty in river hydrology.
Every designer needs to select a Design Flood Level (DFL), a design discharge or flowvolume and a design velocity, on which to base calculations of waterway geometry,
foundation depths, scour protection and vertical clearance.
The design flood is the maximum flow that can pass through the bridge without:-
Unacceptable disruptions to traffic. Endangering the pier and abutment foundations with respect to scour Damaging approach embankments Causing flood damage on the upstream side of embankment.
It should however be noted that the design flood is not necessarily the highest flood. The
highest flood is a rarely occurring flow that it's uneconomical to include in the design flood
but which may be considered when designing superstructure and piers of the bridge.
Where the river is narrow enough, it can be bridged with a single span. The abutments are
built clear of the level of the design flood and hence there is no restriction to river flow i.e.
no river training, no backwater or additional scour is expected as a result of the bridge
presence. For a wide flood channel, the superstructure is longer and will be very expensive if
piers are not used. Both pier and abutment foundations are below DFL and thus require
protection from scour.
The abutment walls and piers will sabotage the design flood. This restriction causes
backwater and additional scour of bed which must be considered while designing the
foundation.
(i) The Hydraulic Design Process.
The steps involved in the design process include:-
1. Establish the height of the infrastructure i.e. clearance above the DFL
-
7/30/2019 Design of a Composite Bridge Deck
52/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 42 -
2. Establish trial positions for the abutments according to the bed shape at the proposedcrossing.
3. Make a provisional decision concerning the number of piers that will result in thelowest overall cost of the superstructure, piers and abutments.
4. Calculate the general and local scours due to the abutments and piers and draw theworst case profiles in the cross sections.
5. Check that the backwater caused by the restriction to flow doesn't cause damage tosurrounding land upstream of the bridge or affect the height set for the superstructure.
6. Prepare preliminary designs of abutments and piers.7. Check scour and backwater effects and make adjustments as required, reclaiming the
effects of any changes to the waterway.
8.
Calculate the cost of the superstructure once its length is decided and the cost of thesubstructures, embankments, river training works and relief culverts.
9. In order to obtain the most economical design, or to compare the cost of the structures catering for the different design floods, it may be necessary to repeat the above
procedure on the basis of alternative waterway conditions.
(ii) Bridge Height.
The waterway below the superstructure must be designed to pass the design flood and thefloating debris carried on it Table 5.1 below shows recommended vertical clearance at DFL
minimum measurements for a vertical clearance between the lowest part of the
superstructure and the DFL, taking in to account backwater effects. This clearance should be
increased on rivers with a history of unusually large floating items or navigational
requirement
-
7/30/2019 Design of a Composite Bridge Deck
53/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 43 -
Discharge
(mP3
P/sec)
Vertical clearance
(mm)
300 1200
(iii) Positioning of Abutment
Choose a position bearing in mind the guidelines at the beginning of hydraulic design then
check for scour using flow charts and spacing of abutments and piers.
(iv). Scour
Scour is the erosive effect of water flow on the river bed or banks. Bridge works may alter
the existing scour pattern by restricting the free flow of the stream and/or causing local
changes to the current. Approximately half of all river bridge failures are due to scour alone
(ORN 9)
However, there are four types of scour and they include:
natural scour and channel shifting on alluvial rivers scour caused by changes to the river upstream or downstream of the bridge site General" scour caused by reduction in the channel width at the bridge works . "Local" scour at the base of piers, abutments and river training works where these
divert the general flow.
At the bridge site provide estimates for general and local scour.
-
7/30/2019 Design of a Composite Bridge Deck
54/121
Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE
By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 44 -
Chapter 3
METHODOLOGY
A bridge just like any other structure must be designed to resist all loads and forces that mayreasonably be exerted on it during its design life. The methodology used here was meant to
address and aim at achieving the objectives outlined in section 1.4 above in a way that will
appropriately solve the identified problem. And consider the design to take into account the
cost implications and environment impact of the bridge structure. In this chapter, procedures
to obtain which parameters are likely to occur and the magnitudes and combination of loads
that produce maximum stress are listed.
This project starte