design of a composite bridge deck

Upload: anonymous-jlaqis

Post on 14-Apr-2018

229 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Design of a Composite Bridge Deck

    1/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulai

    Declaration

    I declare that this project entitled Re-design of Nariamabune Bridge in Kaabong District of

    Karamoja is my own original Project work, except as cited in the references. The project has

    not been accepted for any degree and is not concurrently submitted in candidature or award of

    any other degree.

    Signature Date ..

    OKUCU ANTHONY TWENY

    (STUDENT)

  • 7/30/2019 Design of a Composite Bridge Deck

    2/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulaii

    Supervisor Approval

    Having supervised the student and read through the work herein presented, I do hereby consent

    that the project is worth the award of the Degree of Bachelor of Engineering in Civil and

    Building Engineering of Kyambogo University

    Signed Date

    DR. MICHAEL KYAKULA

    SUPERVISOR.

  • 7/30/2019 Design of a Composite Bridge Deck

    3/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulaiii

    Project Title:

    The title to this project is:

    RE-DESIGN OF NARIAMABUNE BRIDGE IN KAABONG DISTRICT

    OF KARAMOJA, UGANDA

  • 7/30/2019 Design of a Composite Bridge Deck

    4/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulaiv

    Dedication

    To Jehovah God Almighty from whom all wisdom and blessings flow. Take all the praise,

    glory and honour!

  • 7/30/2019 Design of a Composite Bridge Deck

    5/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulav

    Acknowledgements

    I must in all sincerity, thank my wife, Margaret, children: Shalom, Emmanuel, Rebecca and

    Ezra who have had to endure my absence from home during the times I had to be away in order

    to pursue this course of studies. From your patience and endurance I derived courage and

    feeling of support.

    Special thanks to my parents: Joshua J. Tweny and his dear wife Mummy Alice Tweny who

    forfeited enjoyment of their meager income in order that I may be schooled.

    To Charles Ayo, my very concerneduncle who rekindled my interest in studies when I was

    almost giving up on academics. You picked me up and helped me reach here. And to my sister,

    Dr. Atim C. Oyet, you were a challenge, an inspiration and a helping hand at the time of need.

    To my former school teacher, Mr. Ahimbisiibwe Wilson, who helped me to realize my

    engineering aptitude, and encouraged me to tow that line. Little did you know you were

    shaping this work but youve done it.

    Great appreciation to my Project Supervisor, Dr. Michael Kyakula for the guidance advice and

    positive criticisms that have shaped this project and made it such a successful and

    comprehensive design report. All my lecturers in the department of Civil and BuildingEngineering of Kyambogo University. The knowledge and skills you imparted was quite

    helpful in this project.

    To all the staff of Uganda National Roads Authority, Kotido Station for the support and

    information they provided and to my course mates for criticizing positively the works

    especially during the processes of analysis and design of the structures.

    To all the authors and authorities whose works have been cited herein

    Thank you all sincerely.

    Okucu Anthony Tweny.

  • 7/30/2019 Design of a Composite Bridge Deck

    6/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulavi

    Abstract

    Nariamabune Bridge is found in Kaabong District, Karamoja Sub-region, located at

    N03Po

    P38 57 and E34 Po

    P0209 along the Kaabong Kapedo Road link. The road link offers

    trade opportunities to the local people with other communities and neighbouring towns,

    promotes tourism industry (Kidepo Valley National Game Park) and links the Region to Kenya

    and Southern Sudan. It also facilitates humanitarian assistance and security interventions, in

    case of insurgencies.

    The existing bridge structure comprises of a Bailey bridge (steel decking) supported on stone

    masonry abutments that in turn sit on foundations observed to be sinking (a sign of settlement).

    Scouring / erosion have also been observed at the abutments and embankments pointing to an

    imminent failure.

    The problems associated with the imminent failure of the bridge are quite adverse. There is

    urgent need to prevent this imminent failure by re-designing the bridge. This project has had to

    be carried out, therefore, by using the geo-soil properties of the existing bridge site,

    determining the flood levels at the water crossings, carrying out the hydraulic design that will

    minimize scouring, determining the significant loads for analysis of the substructure and the

    superstructure and designing the decking of the bridge, the abutments (and piers) as technicallynecessary. Finally detailed drawings and appropriate recommendations will be made.

  • 7/30/2019 Design of a Composite Bridge Deck

    7/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulavii

    Table of Contents

    Pictures ....................................................................................................................................- 1 -

    Chapter 1 .................................................................................................................................- 2 -

    1. Introduction.........................................................................................................................- 2 -

    1.1. Project Title:.....................................................................................................................- 2 -

    1.2. Background:.....................................................................................................................- 2 -

    1.2.1. Bridge: ...........................................................................................................................- 4 -

    1.2.2. Bridge design:................................................................................................................- 4 -

    1.4. Project Aim: .....................................................................................................................- 5 -

    1.5. Project Objectives:...........................................................................................................- 5 -

    1.6. Scope of the Project:........................................................................................................- 6 -

    1.7. Justification:.....................................................................................................................- 6 -

    Chapter 2 .................................................................................................................................- 8 -

    2.1 Definition of a bridge; ......................................................................................................- 8 -

    2.2.1 Bridge Materials: ...........................................................................................................- 9 -

    2.2.2 Classification:...............................................................................................................- 10 -

    Steel Bridges..........................................................................................................................- 10 -Classification according to structural action:....................................................................- 13 -

    Simply supported span bridge.............................................................................................- 13 -

    Continuous span bridge .......................................................................................................- 14 -

    Cantilever bridge ..................................................................................................................- 14 -

    Rigid frame bridges..............................................................................................................- 15 -

    Classification according to Floor location..........................................................................- 15 -

    Classification based on type of connections: ......................................................................- 17 -

    Reinforced- concrete Bridges...............................................................................................- 18 -

    Types of Bridges....................................................................................................................- 18 -

    2.2.3 Requirements:..............................................................................................................- 20 -

    2.3 Site Investigation.............................................................................................................- 21 -

    2.4 Substructure and Foundations ......................................................................................- 22 -

    2.4.1 Abutments ....................................................................................................................- 24 -

  • 7/30/2019 Design of a Composite Bridge Deck

    8/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulaviii

    2.4.3. Design of Gravity and Cantilever Retaining Walls. ................................................- 24 -

    2.4.3.1. Gravity retaining walls............................................................................................- 25 -

    2.4.3.2. Cantilever Walls of reinforced cement concrete (RCC) ......................................- 25 -

    Abutment design...................................................................................................................- 25 -

    Reinforced concrete abutments...........................................................................................- 26 -

    2.4.4 Reinforced concrete retaining walls...........................................................................- 26 -

    2.4.5 Bearing Shelves............................................................................................................- 26 -

    2.4.6 Piers...............................................................................................................................- 27 -

    Reinforced Concrete Piers ...................................................................................................- 27 -

    2.4.7 Determination of allowable bearing pressure, ..........................................................- 27 -

    Non cohesive soils..................................................................................................................- 27 -

    Cohesive soils.........................................................................................................................- 28 -Presumed values....................................................................................................................- 30 -

    Table 2................................................................................................................................- 31 -

    2.4.8. Foundations on Rock..................................................................................................- 33 -

    2.4.9. Run-on Slabs ...............................................................................................................- 33 -

    2.5 Superstructure ................................................................................................................- 34 -

    2.6 Design Detailing..............................................................................................................- 35 -

    2.6.1 Vertical Profile over the Bridge..................................................................................- 35 -

    2.6.2 Shear Connectors.........................................................................................................- 35 -

    2.6.3 Protective Treatment to Steelwork ............................................................................- 36 -

    2.6.4 Bolts and nuts...............................................................................................................- 36 -

    2.6.5 Bearings ........................................................................................................................- 36 -

    2.6.6 Expansion joints...........................................................................................................- 37 -

    2.6.7 Construction joints ......................................................................................................- 37 -

    2.6.8 Slab Reinforcement .....................................................................................................- 37 -

    2.6.9 Drainage........................................................................................................................- 38 -

    2.6.10 Parapets, Surfacing and Services.............................................................................- 38 -

    2.6.11 Provision for Pedestrians and Cyclists ....................................................................- 38 -

    2.7 River Hydraulics and Hydraulic Design.......................................................................- 38 -

  • 7/30/2019 Design of a Composite Bridge Deck

    9/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulaix

    Chapter 3 ...............................................................................................................................- 44 -

    METHODOLOGY...............................................................................................................- 44 -

    3.3.1 Trial pit excavation......................................................................................................- 45 -

    3.3.2 Sampling.......................................................................................................................- 46 -

    3.3.3 Soil Testing ...................................................................................................................- 46 -

    Chapter 4 .................................................................................................................................-49-

    Analysis and Design................................................................................................................-49-

    Chapter 5 .................................................................................................................................-99-

    Recommendations...................................................................................................................-99-

    Appendices.............................................................................................................................-101-

  • 7/30/2019 Design of a Composite Bridge Deck

    10/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakulax

    L ist of F igures

    TFigure 1.1. Single span Simply supported BridgeT ..........................................................................- 13 -

    TFigure 1.2. Simply Supported Multi- span Bridge.T .........................................................................- 13 -T

    Figure 1.3 Continuous Span Bridge .................................................................................................- 14 -

    Figure 1.4 Cantilever Bridge with a Suspended Span ....................................................................- 15 -

    Figure 1.5 Solid Ribbed Arch............................................................................................................- 16 -

    Figure1.6. Braced Ribbed Arch. .......................................................................................................- 16 -

    Figure1.7. Spandrel Braced Arch Bridge.........................................................................................- 17 -

    Figure 1.8. Tied Arch Bridge ............................................................................................................- 17 -

    Figure 2.1 Slab Bridge .......................................................................................................................- 18 -

    Figure 2.2. Deck Girder Bridge ........................................................................................................- 18 -

    Figure 2.3. Composite Steel-Concrete Bridge..................................................................................- 19 -

    Figure 2.4. Composite Pre-stressed Concrete Bridge ................................................................- 19 -

  • 7/30/2019 Design of a Composite Bridge Deck

    11/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 1 -

    Pictures

  • 7/30/2019 Design of a Composite Bridge Deck

    12/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 2 -

    Chapter 1

    1 Introduction

    1.1 Project Title:

    Re-Design of Nariamabune Bridge in Kaabong District of Karamoja.

    1.2 Background:

    Nariamabune Bridge is found in Kaabong District, Karamoja Sub-region, located at N03Po

    P38

    57 and E34Po

    P0209 along the Kaabong Kapedo Road. (see Plate 1 Appendix 1)

    The history of this road link was not readily available but Kaabong Kapedo Road plays an

    important role of linking parts of Kaabong district to Pader, Kitgum and Lira districts fromwhere most of the merchandise is brought into Kaabong.

    This road link is significant not only for linking economic activities of the local people, but

    in the promotion of tourism industry. According to a UWA brochure, Kidepo Valley

    National Game Park receives tourists from various countries annually. Some of the tourists

    reach the National Park by way of Kampala Mbale Soroti Kotido Kaabong route,

    while others use the Kampala Karuma Lira Kotido Kaabong - Kidepo Route yet

    others use the Kampala Karuma Lira Pader Orom Karenga Kapedo Route. The

    former two therefore needs the bridge at Nariamabune to be safe and sound for easy

    passage.

    Most tourists from Europe, the Americas, Australia and other parts of the world land in

    Kenya and from Nairobi, they travel by road to Western Uganda to Mgahinga Gorrila

    National Park, Bwindi Impenetrable National Park, Kibale National Park, Queen Elizabeth

    National Park, Murchison Falls National Park, and others before embarking on moving to

    Kidepo National Park and finally passing along Kapedo Kaabong Kotido Soroti

    Mbale to Mt Elgon National Park from where they get back to Kenya.

    Besides the trade and commercial activities, this road link is significant in fostering

    humanitarian assistances to Karamoja region most of which lies in the arid climatic zone of

    North-eastern Uganda, often characterized by famine.

  • 7/30/2019 Design of a Composite Bridge Deck

    13/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 3 -

    Of great importance is the fact that a road link is being planned to join Kapedo to New Site

    in Southern Sudan

    Kaabong District of Karamoja is located within Latitudes 2 P0P 30 and 4 P0P 15 South and

    Longitudes 33 P0

    P 30 and 35 P0

    P 00 East in the north eastern part of Uganda.The Total area is13,208 kmP

    2P (5.47% of Ugandas total area) of which arable land coverage is 7,268 kmP

    2P and

    water coverage is 0 km P2

    P. Since arable land coverage is only 7,268 square km the cropproductivity rating is limited.

    Forestry:

    There are 12 natural forests and five plantation forests. Artificial forest coverage is 0.2 KmP

    2P

    with acassia, same and eucalyptus.

    Wild life:

    The largest Game Park in Uganda (Kideepo Valley National Game Park) has an area of

    1,442 square Km.

    Animals:

    water bucks, Jacksons hartebeest, zebras, buffalos, elands, ribi, warthogs, bush bucks,

    jackals, elephants, giraffes, lions, cheetahs, leopards, ran antelopes and ostriches. Bird life is

    in abundance.

    Minerals:

    Gold, silver, copper, iron, and mica and crude petroleum at Kathile basin.

    Sunshine and wind:

    Between December and April the Northeasterly wind usually exceed 200Km per day.

    Characterized by dust storms, desiccating and pulverizing the sparse vegetating cover.

    Average rainfall is 519mm per annum. Rainy season falls in April August with a marked

    minimum in June and marked maximum peaks in May and July. The rain is erratic in nature.

  • 7/30/2019 Design of a Composite Bridge Deck

    14/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 4 -

    Distinct wet and dry seasons are a prominent feature. The rainfall is unevenly distributed

    and unreliable and has a significant influence on the economy and life of the district.

    1.2.1. Bridge:

    Bridge, in this context, shall mean a structure that permits traffic to pass over the water

    crossing safely and conveniently.

    1.2.2. Bridge design:

    Bridge design in this context shall mean the application of scientific theories in combination

    with field data and technological knowledge to come up with a safer and an economical

    bridge structure that will permit traffic to pass safely, conveniently and comfortably above

    the river crossing.

    Almost all human activities involve problem solutions. Production of goods and services has

    always resulted from almost all the human activities. Unless the goods and services

    produced are distributed, exchanged and consumed the economic chain is not complete. In

    order, therefore, to complete the economic chain, transportation becomes a vital factor in the

    economy as the outcomes of the production process must find their ways into some market

    where exchange and consumption take place.

    Transportation involves the movement of factors of production like machinery, labour, raw

    materials, fuels, and of finished goods or services to places of utility. Traffic of various

    forms and kinds are involved in the said movement, depending on certain factors outlined

    herein as: accessibility of the places of production and markets relative to the terrain,

    existing infrastructure, drainage pattern and land use.

    Traffic form is also dependent on the economic activities, magnitude of haulage and nature

    and value of goods and services produced. In this case road transport has been considered as

    it is the most feasible and is already an existing infrastructural investment in the area of the

    project.

  • 7/30/2019 Design of a Composite Bridge Deck

    15/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 5 -

    1.3 Problem Statement:

    The existing bridge structure comprises of a Bailey bridge (steel decking) supported on

    stone masonry abutments that in turn sit on an earth foundation. It is observed that since its

    constructions in 2004, the bridge deck level is sinking. Information available from UNRA

    Kotido Station estimates the level to have sunk by about 400mm yet there are indications

    that the embankments are prone to be cut by the waters due scouring and erosion noticed at

    the site.

    The local scour at abutments are an indication that the width of the channel is not sufficient,

    hence a hydraulic design needs to be done, taking into account the scour and a preventive

    measures taken to minimize the same.

    Qualitative site survey has shown no protective measures taken to minimize the effects of

    scour at the abutments upstream of the water crossing, and the side drains of the

    embankments are extremely gullied, progressively leading to the embankments failure.

    1.4 Project Aim:

    The aim of this project is to design a strong and economical bridge to meet the structural and

    hydraulic requirements and improve on the level of service for a design life of 40 years.

    1.5 Project Objectives:

    The objectives are to:

    o Carry out the hydrologic and hydraulic analysis of the catchments area and the river,o Determine the flood levels at the water crossings,o Carry out the hydraulic design that will maximize flow with minimal width of

    channel and scouring effects

    o Determine the significant loads for analysis,o Design the decking of the bridgeo Use the existing soils parameter to Design the abutments, piers and the foundations.o Come up with the working and structural drawingso Make recommendations

  • 7/30/2019 Design of a Composite Bridge Deck

    16/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 6 -

    1.6 Scope of the Project:

    o Obtaining Geotechnical data / soil parameter.o Hydrologic (Flow) analysis and Hydraulic Design,o Analysis and design of Superstructure,o Analysis and design of Substructure.o Detailed drawings

    1.7 Justification:

    Kaabong Kapedo - Karenga trunk road links Pader, Kitgum, Lira and Soroti to Kaabong

    Town in the North - eastern part of Uganda. Failure of Nariamabune Bridge and therefore

    has a very significant connotation in the economic life of the four towns.

    Most of the goods and essential commodities consumed in Kaabong are sourced from

    wholesale markets as far as Kampala, Soroti, Mbale and Lira by way of Lira Abim or

    Soroti Abim routes. The same routes are used by humanitarian organizations to transport

    relief food to the district

    The same road is a link to Kidepo Valley National Game Park, therefore, very significant in

    tourism industry. The road also links this part of Uganda to Southern Sudan and North-

    western Kenya and therefore an important link for international trade. The two facts meanthe road is a foreign exchange earner in Ugandas economy.

    There is a plan by the government of the republic of Uganda to connect this road link to

    New Site in Southern Sudan through Kapedo, an investment that is anticipated to boost

    traffic on Kaabong Kapedo road.

    Kaabong District, as already noted elsewhere, is endowed with mineral resources likegold,silver, copper, iron, mica and crude petroleum at Kathile Basin. The exploitation of such

    mineral resources require explicit transportation scheme that motivate deliberate investment

    in the sector.

    Besides the economic considerations, Karamoja region, in general, is an arid area and often

    affected by famine. Food aid and humanitarian assistance will always require excellent

  • 7/30/2019 Design of a Composite Bridge Deck

    17/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 7 -

    mobility. Any slight break in mobility will lead to massive death due to famine. Other social

    services also need transportation networks that are consistent to facilitate emergency

    deliveries.

    Worth mentioning is the fact that a section of the Karamojong have firearms and are

    aggressive to passers-by. In case of failure of Nariamabune Bridge, such people will not

    hesitate to attack, loot, kill or harm the unfortunate road users that may find themselves

    trapped in the ignominy.

    The problems associated with the imminent failure of the bridge are quite adverse as has

    been seen. This project therefore is intended to offer solutions by preventing the failure

    through redesigning the bridge.

  • 7/30/2019 Design of a Composite Bridge Deck

    18/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 8 -

    Chapter 2

    2.0 LITERATURE REVIEW

    The basic concept involved in this chapter is to examine the recent and historical significantstudies that form the basis of design of a bridge.

    2.1 Definition of a bridge;

    Abridge is a structure for carrying road traffic and other moving loads over a depression orgap or obstruction such as river, canal, channel, canyon, valley, road or railways (Punmia, et

    al 1998). In other words, it's the structural system carrying the communication route and

    includes beams, girders, stringers, arches, cables and all other components above bearing

    level.

    If a bridge is constructed to carry highway traffic, it is known as a highway bridge. If,

    however, it is constructed to carry railway traffic, then it is known as a railway bridge. There

    may be a combined highway and railway bridge to carry both the highway as well as railway

    traffic. Some bridges, constructed exclusively to carry pedestrians, cycles and animals, are

    known asfoot bridges while those constructed to carry canals and for pipe lines are known as

    aqueduct bridges.

    A bridge may be a culvert, high level bridge or submersible bridge. A culvert is a bridge

    having a gross length of six metres or less between the faces of abutments or extreme

    ventway boundaries, and measured at right angles there to the direction of water flow.

    A high level bridge is a bridge which a carries the roadway above the highest floodlevel of the channel.

    Asubmersible bridge is a bridge designed to be over topped in floods. A bridge may befixedormovable type. Afixed bridge is the one which always remains in one position.

  • 7/30/2019 Design of a Composite Bridge Deck

    19/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 9 -

    A movable bridge is the one which can be opened either horizontally or vertically soas to allow river or channel traffic to pass. Such bridges are constructed over a

    navigable stream where the normal headway is not sufficient for the vehicles to pass

    through.

    A bridge may be either of deck type or through type.

    A deck type bridge is the one in which the roadway/railway floor rests on the top of the

    supporting structure.

    A through bridge is the one where the roadway/railway floor rests on the bottom of the main

    load supporting structure.

    However when the floor lies between the top and bottom of the main load supporting

    structure, it is known as half through type bridge,semi-through bridge orpony bridge.

    2.2.1 Bridge Materials:

    Bridges are made of different material such as timber, stone masonry, brick masonry,

    concrete and steel. Timber bridges are constructed only over small spans and for temporary

    purpose, to carry light loads. Masonry bridges are also constructed for shorter spans.

    Concrete bridge, both of reinforced cement concrete (RCC) as well as of prestressed cement

    concrete (PCC) are constructed over moderate to high spans, to carry all types of loads.

    Concrete arch bridges have been constructed of spans up to 200 m. Similarly, steel bridges,

    are constructed both over moderate to high spans as well as for heavy trafficular loads. In

    India, steal bridges are commonly used for railways for all types of spans. [Pumnia, et al

    (1995)]

    Abridge just like any other civil engineering structures has two component parts, namely

    Substructure Super structure

  • 7/30/2019 Design of a Composite Bridge Deck

    20/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 10 -

    2.2.2 Classification:

    (i). According to end fixity a bridge can be classified as simple or continuous bridge.(ii). According to ability to slide/move a bridge can be fixed or movable bridge.

    (iii).

    According to purpose it may be foot railway or highway Bridge.(iv). According to location of bridge floor it may be deck, through or semi-through

    bridge.

    (v). According to highest flood levels it may be submersible or non-submersible.(vi). According to construction materials it may be stone and brick (Masonry), steel,

    timber or concrete bridge

    Steel Bridges

    Classification

    Steel bridges may be classified according to the following criteria:

    1. Type of structural arrangement2. Structural action3. Floor location4. Type of connection5. Movement of structural parts

    Classification according to structural arrangement:

    Under this classification a steel bridge may be of the following types:

    (i). I-girder bridge(ii). Plate girder bridge

    (iii). Truss girder, or(iv). Suspension bridge.

  • 7/30/2019 Design of a Composite Bridge Deck

    21/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 11 -

    I-girdersmay be used for small as the main load carrying members. For this purpose, wide

    flanged I-sections are used. Such structures are suitable for spanning over crossings of

    moderate widths. There are however limitations in the maximum size of available I-sections,

    hence for longer span bridges built up plate girders are to meet the requirements of section

    modulus corresponding to the applied loads.

    Plate girder bri dges:This type of are quite popular with railway bridges, the advantage

    being in transportation since it can be transported in one piece. the limiting depth of plate

    girders is only 3 -4m hence when the structural requirement for depth is more than this, steel

    truss girder bridges are preferred.

    Truss girder bridges: in this arrangement, trusses are used as the main load carrying

    members. They are commonly used over spans of 20 200m

    For still longer spans, steel arch bridges or suspension bridges using high strength steelcables may be used.

  • 7/30/2019 Design of a Composite Bridge Deck

    22/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 12 -

  • 7/30/2019 Design of a Composite Bridge Deck

    23/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 13 -

    Classification according to structural action:

    According to the criteria of structural action, steel bridges may be of the following types:

    (i).

    Simply-supported-span bridges(ii). Continuous span bridges

    (iii). Cantilever bridge(iv). Arch bridges(v). Rigid Frame Bridge.

    Figure 1.1. Single span Simply supported Bridge

    (i) Simply supported span bridge

    Such types are commonly used when the width of gap is small, necessitating the use of

    single span. However, even if the width of the gap to be bridged is large, the whole widthcan be subdivided into a number of individual spans, each span being simply supported

    Figure 1.2. Simply Supported Multi- span Bridge.

    Such an arrangement is preferred specially .is those locations where there is likelyhood of

    uneven settlement of intermediate piers. The analysis of simply supported span bridge is

    very simple.

  • 7/30/2019 Design of a Composite Bridge Deck

    24/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 14 -

    (ii)Continuous span bridgeWhen the width of gap is quite large, and where there are no chances of uneven settlements,

    bridge may be continuous over two or more spans (Figure 1 (c)). Because of continuity,

    moments are developed at pier supports resulting in the reduction of stresses at the inner

    spans. This results in an economical design. Also, continuous span bridges require few

    supports, since larger spans can be used; they can also support higher loads in comparison to

    simply supported spans.

    Figure 1.3 Continuous Span Bridge

    (iii) Cantilever bridge

    In the case of a three span continuous bridge, loaded with uniformly distributed load over all

    the three spans, it is observed that these are two points of contraflexure in the central span.

    Hence if the continuous beam/girder of the middle span is cut at these two points of

    contraflexure, and shear resisting joints are made at these two points, the resulting

    configuration will be a cantileverbridge with a central suspended span between these two

    formed joints, as shown in Figure 1.4. Thus, a cantilever bridge consists of two simple

    spans, one at each end, each having an overhanging or cantilever portion along with a

    simple span (or suspended span) in between the two cantilever portions. The main

    advantage of such an arrangement is that the B.M. diagram will now not be affected by the

    settlement of supports. The suspended span is supported by the cantilever span, at each endby means of mechanical hinge. This gives rise to a statically determinate structure which can

    be analyzed very easily. Because of development of moments at the pier supports, the

    stresses in each end span is very much reduced. Another advantage of such bridge is that the

    cantilever portion and the suspended span can be erected without the use of false work or

  • 7/30/2019 Design of a Composite Bridge Deck

    25/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 15 -

    staging. Such bridges are usually provided for longer span, ranging between 200 m to 500

    m.

    Figure 1.4 Cantilever Bridge with a Suspended Span

    (i v) Arch Bridge.

    For deep gorges, arch bridges are generally used, since they offer economical and aesthetic

    solution. However, they require strong abutments to resist the thrust from the arches. The

    arches may consist of girder sections or trusses, and may be:

    Fixed arches Two hinged arches, or Three hinged arches,

    The two hinged arches are more common.

    The arch bridge may further be classified as:

    solid ribbed arches braced rib arch spandrel braced arches or Tied arches (Figure 1.8).

    Solid ribbed arch bridges are more commonly used for highways, while braced rib arch

    bridges and spandrel braced bridges are commonly used for railways.

    ( v) Rigid frame bridges

    Rigid frame bridges, comprising of single span or two to three continuous spans, are usedfor dry-over or under-crossing, for gaps between 10 to 20 m. These consist of steel columns

    and steel girders with continuity at the knee. Such bridges are quite suitable for rigid

    foundations.

    Classification according to Floor location

  • 7/30/2019 Design of a Composite Bridge Deck

    26/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 16 -

    According to the location of the floor, bridges can be classified as under:

    Deck-type bridge Through type bridge Half through-type bridge.

    In deck type bridge the floor is placed on the top flange in the case of plate girder bridge and

    on the top chord in the case of a truss bridge. No top bracing is therefore required.

    In the case ofthrough type bridge, the floor" is placed at the level of lower chord of truss

    type bridge, and the top chord is braced laterally.

    However, in the case of plate-girder bridge, the floor of the through bridge is supported on the bottom flange. In half through bridge, also known as ponny truss bridge, the floor lies

    between the top and the bottom. There are also double deck bridges constructed to carry the

    traffic of both roadways and railways. Both the decks can have through floors. Alternatively,one deck may have through floor while another deck may be kept open. The requirements of

    grade line and clearance of highways or railway track decide whether it should be through-

    type bridge or a deck type bridge. Deck type bridges are more economical than through type

    bridges, and hence they are more popular.

    Figure 1.5 Solid Ribbed Arch.

    Figure1.6. Braced Ribbed Arch.

  • 7/30/2019 Design of a Composite Bridge Deck

    27/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 17 -

    Figure1.7. Spandrel Braced Arch Bridge

    Figure 1.8. Tied Arch Bridge

    Classification based on type of connections:

    Depending upon the type of connections of the joints, bridges can be of the following types:

    (i). Riveted bridges(ii).

    Welded bridges

    (iii). Bolted (pin connected) bridges

  • 7/30/2019 Design of a Composite Bridge Deck

    28/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 18 -

    Reinforced- concrete Bridges

    Types of Bridges

    According to WinterandNilson (1972), reinforced concrete is particularly adaptable

    for use in highway bridges because of its durability, rigidity, and economy, as well

    as the comparative ease with which a pleasing architectural appearance can be

    secured. For very short spans, from about 10 to 25 ft, one-way-slab bridges (Fig. 2.1)

    are economical. For somewhat longer spans, concrete girder spans (Fig. 2.2) may be

    used.

    Probably most highway spans of medium length, from 40 to 90 ft, presently use

    composite steel-concrete construction (Fig. 2.3) or composite pre-stressed-concrete

    construction (Fig. 2.4).

    Figure 2.1 Slab Bridge

    Figure 2.2. Deck Girder Bridge

  • 7/30/2019 Design of a Composite Bridge Deck

    29/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 19 -

    Figure 2.3. Composite Steel-Concrete Bridge

    Figure 2.4. Composite Pre-stressed Concrete Bridge

    In composite construction with structural steel, the concrete deck is made to act

    integrally with supporting steel stringers by means of devices called shear connectors,

    welded to the top flange of the steel section and embedded in the slab. Although such a

    bridge is not strictly a reinforced-concrete structure, the design of this type of bridge

    will be discussed in some detail in this section because of its widespread use. Pre-

    stressed-concrete bridges frequently make use of composite section characteristics also.

    Commonly, the girders are pre-cast and placed into final location by crane, eliminating

  • 7/30/2019 Design of a Composite Bridge Deck

    30/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 20 -

    the necessity for obstructing traffic by falsework. The deck slab is then cast in place,

    bonded, and tied to the pre-cast sections by steel dowels.

    Hollow box girders, usually pre-stressed, are often used for intermediate and long-

    span concrete bridges. Spans up to about 80 ft are pre-cast in one piece and lifted into

    position. Longer spans of similar cross section, carrying two lanes of highway traffic

    as well as shoulders and walkways, have either been cast in place or pre-cast in short

    segments, which are post tensioned after positioning.

    Bridge spans as long as 320 ft have been attained using pre-stressed girders. Other

    possibilities for long-span concrete bridges are the various forms of arches, including

    the barrel arch and the three-hinged arch. [Winter and Nilson (1972)]

    2.2.3 Requirements:

    The bridge should be efficient, effective and equitable so that;

    It is economical

    It's aesthetically sound It should serve the intended function with utmost convenience, comfort and

    safety.

    It is durable

  • 7/30/2019 Design of a Composite Bridge Deck

    31/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 21 -

    2.3 Site Investigation

    The soils supporting the abutments and pier foundations always carry the weight of the

    traffic, superstructure, abutments and piers. In order to design for the best suitable

    foundations, the designer has to determine the nature and location of the different soil typesoccurring at the site of the bridge and its approaches, to depths containing strata sufficiently

    strong to support the bridge and embankments without failure.

    This information is obtained by analyzing samples taken from a grid of bore-holes or test pits

    covering the whole of the proposed site, and by testing the samples for density, shear

    strength, plasticity and penetration, in order to provide quantitative data for foundation

    design.

    2.3.1 Methods of site investigation

    Test pits Hand auger boring Cable percussion boring Rotary drilling Geophysical surveying.

    2.3.2 Sampling

    The choice of sampling technique depends on the purpose for which the sample is required

    and the character of the ground.

    There are four main techniques for obtaining samples:

    Taking disturbed samples from drill tools or from excavating equipment in the courseof boring or excavation

    Drive sampling in which a tube or split tube sampler with a sharp cutting edge at itslower end is forced into the ground, either by static thrust or by dynamic impact

    Rotary sampling, in which a tube with a cutter at its lower end is rotated into theground, so producing a core sample

  • 7/30/2019 Design of a Composite Bridge Deck

    32/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 22 -

    Taking block samples cut by hand from a trial pit, shaft or heading.Samples obtained by the last three techniques will be sufficiently intact to enable the ground

    structure within the sample to be examined. However, the quality of these samples can vary

    considerably, depending on the sampling technique and ground conditions, and most sampleswill exhibit some degree of disturbance. Table 2.1 indicates the mass of sample required for

    identification purposes, Atterburg tests, moisture content, sieve analysis and sulphate tests.

    Care should be taken to ensure that samples are as pure and undisturbed as possible.

    Table1. Required Sample Mass

    2.3.3 Aggressive Chemicals

    The ground or ground water may contain chemicals capable of causing damage to concrete

    or steel. These chemicals may emanate from nearby industrial processing or may occur

    naturally. Total sulphate content of more than 0.2% by weight in soil and 300 ppm in ground

    water are potentially aggressive (BRF 1981). There are often difficulties in specifying

    ground condition before the excavation for constructions are complete. For this reason the

    engineer should be prepared to review his plan, both during construction, if evidence is

    found of unexpected soil conditions.

    2.4 Substructure and Foundations

    This is a support for the super structure and comprises of; abutments, piers, wing walls and

    any part below bearing level i.e. the foundation.

    Soil typeMass required

    (kg)

    Cla , silt, sand 2Fine and medium gravel 5

    Coarse gravel 30

  • 7/30/2019 Design of a Composite Bridge Deck

    33/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 23 -

    The substructure can be made of materials such as mass concrete, reinforced concrete, steel,

    timber and ifexperience is available in structural masonry it can be an economical substitute

    for concrete. However, the engineer must be certain of the strength of materials used,

    particularly when they are submerged in flowing water.

    All concrete decks must have rigid substructures like those detailed in this booklet, because

    uneven settlement of either abutment or pier can result in unacceptably high stresses in the

    materials of the decks. The positioning of the abutment and pier foundations is critically

    important.

    Because the most likely cause of bridge failure is scour, a bridge designer should pay careful

    attention to the estimation of general and local scour. Pier foundation depths are specified

    according to foundation type and protection method. However when dealing with

    substructures and foundation, there are two important issues to consider:-

    The general scour area must not be obstructed or the flow will be impeded meaningmore scour damage.

    Local scour is caused by turbulence and may be reduced by armouring the bed.Abutments also fail when the soil under the foundation is not strong enough to carry the

    combined forces from the bridge structure and the embankment. It's recommended that

    spread foundations be used wherever possible, but if adequate support is unavailable, a piled

    foundation is required.

    If a satisfactorily strong soil is found not too far below preferred foundation level, caisson

    support may be considered. The technique is simple if the caissons are short, but the engineer

    must take care that:-

    The maximum soil reaction at the sides does not exceed the maximum passivepressure at any depth,

    The soil pressure at the base remains compressive throughout and the maximumpressure does not exceed the allowable pressure.

  • 7/30/2019 Design of a Composite Bridge Deck

    34/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 24 -

    2.4.1 Abutments

    Besides carrying the dead load of the superstructure, it's imperative that the abutments of a

    bridge must:

    Resist the vertical and horizontal live loads exerted on them by vehicles and otherelements.

    Retain the approach embankments and the live loads (or surcharge) applied to them. Provide a smooth transition from the road surface to the deck running surface.

    The essentials features of abutments are:-

    A foundation slab, which transmits the weight of the abutment and the superstructureand its loads directly to the supporting soil, or which forms a capping slab to a system

    of load bearing piles.

    A front wall with bearing shelf that supports the superstructure and usually retains thesoil of the embankment.

    Wing walls or retaining walls which may be separate from the abutments or, if theyare short, may be built integrally with them. These walls retain the road embankment

    or river bank adjacent to the abutment and are usually built so as to bisect the angle

    between the road and the river bank, though they can be set at any angle to the

    abutments and may be built parallel to the road or perpendicular to it.

    2.4.3. Design of Gravity and Cantilever Retaining Walls.

    A gravity retaining wall is that which resists the lateral earth pressure by its own weight;

    whereas, a cantilever retaining wall is that which resists the lateral earth pressure by bending

    action. Garg (2005)

  • 7/30/2019 Design of a Composite Bridge Deck

    35/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 25 -

    2.4.3.1. Gravity retaining walls

    Gravity retaining walls are, therefore, thicker in section, and are made of stone or brick

    masonry or sometimes plain cement concrete (PCC).

    2.4.3.2. Cantilever Walls of reinforced cement concrete (RCC)

    The cantilever walls of reinforced cement concrete (RCC) are more economical, because the

    backfill itself is employed to provide most of the dead weight to counteract the lateral thrust.

    Both types of walls are liable to rotational turning or translational sliding movements, and

    the lateral pressure for the design is computed by Rankines or Coulomb,s theories.

    The design of retaining wall should be such that the wall as a whole must satisfy the two

    basic conditions: The base pressure at the toe of the wall must not exceed the allowable bearing

    capacity of the soil.

    The Factor of safety against sliding between the base and the underlying soil must beadequate; value of 1.5 being usually required.

    Unyielding retaining walls, such as the bridge abutments, restrained by the deck structure,

    do not deform. In such cases, therefore, active or passive pressures would not be developed;

    rather, the lateral pressures should be computed as equal to rest value using the coefficient

    KBRB (also represented byKBOB).

    This value ofKBRB is also very high when the backfill is compacted artificially; say as high as

    0.8 or so. It has, thus, been noticed that in such unyielding walls, compaction caused by the

    flow of sewers, etc. may lead to residual lateral pressures, considerably higher than the

    corresponding values for the uncompacted soil.

    (i)Abutment design

    While designing the abutment, there is need to carefully analyze and take into account all the

    individual characteristics of the site and the superstructure, e.g. foundation conditions, deck

    thickness, expansion joints etc. Specifications for the concrete and steel are also important.

  • 7/30/2019 Design of a Composite Bridge Deck

    36/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 26 -

    (ii)Reinforced concrete abutments

    For small span bridges of (span not exceeding 12m) abutments are provided with a standard

    width of 1200mm at the top but the front and rear faces are vertical. This structure is

    considerably lighter than its mass concrete counterpart. The bearing shelf is an integral partof the stem. The widths of the toe and heel, and the thickness of the foundation for various

    heights, span and bearing pressures are suggested in ORN9.

    2.4.4 Reinforced concrete retaining walls

    Considerations here are just as in the abutments with reinforced concrete stems. If the

    retaining wall is not long, weep holes can usually be ignored. These details apply to thetypical case of walls set at 45 to the abutments supporting road embankments with slopes of

    1 in 2.

    2.4.5Bearing Shelves

    These designs are generally suitable for concrete, composite or timber decks, though the

    bearing details will be specific to the deck type. The dowel and bearing pad details are

    required for concrete and composite decks. Good drainage and the facility for removal ofdebris are important requirements on all bearing shelves. The road approaches should be

    built to prevent water draining onto the bridge, but some water falling on the deck will

    penetrate expansionjointseals and leak through to the bearing shelves. This is particularly

    likely to occur when no seal at all is provided. A number of drainage configurations are

    available, Hambly (1979), but the two main principles to be observed are:-

    Slope horizontal surfaces to direct water away from the bearing pads. Provide good access for the removal of stones, vegetation, bird nests and other

    debris.

  • 7/30/2019 Design of a Composite Bridge Deck

    37/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 27 -

    2.4.6 Piers

    Just like abutments, piers perform a support function by transmitting vertical and horizontal

    loads from the superstructure via the bearing shelf, stem and foundation slab to the

    supporting soil. In most cases, piers stand on saturated soils for most or all of the year: theydo not retain soil embankments but are designed to withstand hydraulic pressures and impact

    loads. Piers are often more affected by scour damage than abutments and need to be

    orientated carefully with respect to flow direction. Their foundations should be located well

    below maximum scour depth.

    Reinforced Concrete Piers

    Though piers may be built using masonry or mass concrete, reinforced concrete has severaladvantages, notably a more slender stem presenting less interference to flow and hence

    causing less induced scour. Superstructure spans are sometimes designed to be simply

    supported at the abutments and at the piers. Each span should have one fixed and one free

    end. It is usual practice, though not essential, to provide one fixed bearing and one free

    bearing on the bearing shelf of each pier. Pier foundations are even more susceptible to

    damage by erosion than abutment foundations. They must be constructed on soils of well

    established allowable bearing pressure

    2.4.7 Determination of allowable bearing pressure,

    a) Non cohesive soils

    The allowable bearing pressure under foundation in non cohesive soils is governed by the

    permissible settlement of the structure due to consolidation of the soils under the appliedloading.

    If standard penetration tests have been performed in bore holes, the values of N can be used

    to obtain allowable bearing pressure for various foundation dimensions.

  • 7/30/2019 Design of a Composite Bridge Deck

    38/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 28 -

    The allowable bearing pressure is that which causes 25mm of settlement under the given

    breadth of foundation front to back, B BrB i.e. measured perpendicular to water flow direction on

    the assumption that the water table always remains at the depth of at least B BrB below the

    foundation level. If the water table can be higher than this, then the allowable pressure is

    halved. At a shallow depth, the test seriously under-estimates the relative densities of

    cohesionless soils thus the engineer may need to correct the standard penetration values

    measured in boreholes before applying the relationships

    To allow for this, a correction factor should be applied to the measured values

    Where the N values of a fine or silty sand below the water table is greater than 15, the

    density of the soil should be assumed to be equal to that of sand having the N value of

    )15(2

    115 + N

    Very loose uniformly graded sands with N equal to 5 or less and subject to rapid changes of

    water level are liable to suffer large settlements under load. In these circumstances, either the

    sand should be dug out and thoroughly re-compacted or the foundation should be supported

    on piles.

    b)Cohesive soils

    Most cohesive soils at the foundation level are saturated and have an angle of shearing

    resistance equal to zero. Provided that no water is expelled from the soil as the load is

    applied. This is accepted as the basis for calculating the ultimate bearing capacity of

    foundations where the load is applied relatively quickly.

    The ultimate bearing capacity of cohesive soils can be calculated from the following

    formula.

    Ultimate bearing capacity, qBfB = CBuBNBeB = P

    Where

  • 7/30/2019 Design of a Composite Bridge Deck

    39/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 29 -

    Cu = untrained shear strength (kN/m P2

    P)

    NBeB = bearing capacity factor

    P = total overburden pressure at foundation level kN/mP2

    P

    = D

    Where

    = density of soil above foundation level kN/m P3

    P

    D = depth of foundation level below ground surface.

    Values of the bearing capacity factor N BcB for square or circular foundations can be read from

    the graph inFigure 8.6 ORN9

    For rectangular foundations

    NBc(rectangular) B=BB cr N

    L

    B

    + 16.084.0

    Where

    BBrB = breadth of the foundation front to back

    L = length of the foundation

    The undrained shear strength CBuB of soft clays can be measured by means of field vane tests

    but the results need to be corrected because the soil is sheared in the horizontal direction.

    The value of CBuB to be used in the bearing capacity formula is the vane shear strength

    multiplied by the correction factor read from the graph in figure 8.7 ORN 9. This factor is

    dependent on the plasticity index of the soil.

  • 7/30/2019 Design of a Composite Bridge Deck

    40/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 30 -

    The allowable bearing pressure is one third of the calculated ultimate bearing capacity.

    c)Presumed values

    Sometimes at the preliminary stage of design there may be no measured values of soil

    density or field strengths available. For purposes of estimation, Table 2.2 below lists

    approximate values of allowable bearing pressures for different soil types.

  • 7/30/2019 Design of a Composite Bridge Deck

    41/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 31 -

    Table 2. Presumed Bearing Capacities

    (a) Foundations beadng on ROCK, width not exceeding

    3m and the length not more than 10 times width.

    Description of rockPresumed

    bearing

    valuekN/mPzPMassive strong igneous and

    metamorphic rocks and limestones10,000

    Unweathered medium to fine grained

    sandstones4,000

    Schists and slates 3,000Hard shales, mudstones and soft

    sandstones1,500

    Soft limestones 600

    (b) Foundations in non cohesive soils at a minimum

    depth of 1m below ground level

    Presumed bearing

    value,kN/mPz

    P

    Foundation widthDescription of soil

    1m 2m 3m

    Very dense sands and gravels 600 500 400

    Dense sands and gravels 500 400 300

    Medium dense sands and gravels 250 200 150

    Loose sands and gravels 100 75 75

    (c) Foundations in cohesive soils at a minimum depth of

    1m below ground level

    Presumed bearing

    value,kN/mPz

    P

    Foundation widthDescription of soil

    1m 2m 3m

    Hard boulder clays, hard fissured

    clays, weathered shales and

    weathered mudstones800 600 400

    Very stiff boulder clays, very stiff

    marls600 400 200

    stiff boulder clays, stiff fissured clays

    and stiff marls300 200 100

    Firm clays 150 100 75Soft alluvial clays 75 35 0

    Source: Table 8.1 ORN 9

  • 7/30/2019 Design of a Composite Bridge Deck

    42/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 32 -

  • 7/30/2019 Design of a Composite Bridge Deck

    43/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 33 -

    2.4.8. Foundations on Rock

    The foundation designs presented in the preceding sections are for soils readily excavated by

    hand or mechanical digger. Modifications may be required to suit individual site conditions,

    particularly when bedrock is encountered. Where foundations are set on rock at ground levelor on the river bed, substantial keying will be necessary in the form of steel dowels and

    notching.

    2.4.9.Run-on Slabs

    Almost all earth embankments are subject to settlement. The amount they settle will depend

    on the height, the degree of compaction of the material and the strength of the sub-grade.

    Relatively uniform settlement can be expected from most embankments until a cause of

    uneven compaction is met, such as a bridge or a box culvert with little fill above it. It is

    difficult to compact fully the embankment material close to the bridge abutments or the

    culvert walls, and the result of poor compaction is more pronounced settlement. The

    resulting longitudinal profile is uncomfortable for road users and causes impact loads on the

    structure, owing to vehicle bounce. These local depressions in the carriageway close to

    drainage structures may be bridged using run-on slabs. They are more easily constructed at

    the same time as the structure, rather than afterwards as a remedial measure, and they span

    the fill material susceptible to settlement. One end of the slab rests on a small shelf cast onto

    the culvert wall or on the abutment ballast wall, while the other rests on well compacted

    material several meters away.

    Run-on slabs are usually between 3 and 6 meters long. The concrete and reinforcement

    details may be abstracted from the culvert detailing, assuming that the slab is resting on good

    support for one third of its length, i.e. a 6m slab will have similar details to a 4m wide

    culvert lid. Run-on slabs are usually made wide enough to support the kerbs on the approach

    roads.

    Run-on slabs should not be required where efficient maintenance facilities are readily

    available (Hambley 1979).

  • 7/30/2019 Design of a Composite Bridge Deck

    44/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 34 -

    2.5 Superstructure

    2.5.1Steel/concrete Composite Superstructures

    Because they are easy to erect, more durable if well maintained and are light in weight, steel

    beams with concrete decking are often a good solution for structures intended to have a long

    service life. Through regular maintenance painting can prevent deterioration of the beam

    webs and bottom flanges. Where structures are intended to be permanent, the durability of

    the steel over a service life of 50 years or more can be achieved more readily by the use of a

    cast in situ concrete deck slab (ORN 9). Composite action of the slab and beams is secured

    by the use of shear connectors welded to the top flanges of the beams and cast into the

    concrete. As an alternative to the solid concrete slab decks almost any bridge can be

    constructed of steel universal beams (UB) with a composite concrete deck slab. The main

    beams and cross members can be of standard rolled carbon steel sections (yield stress

    274N/mmP2

    P), with deck slab reinforcement in either mild steel (MS) or high yield steel

    (HYS).

    However, Steel/concrete composite deck structures have the following advantages:

    The deck self weight can be less than that of an equivalent all-concrete structure The off-site prefabrication of the main load carrying elements of the bridge greatly

    reduces the work necessary on site, resulting in more rapid construction.

    No temporary supports are required during construction of the deck slab, since thesoffit shuttering can be supported directly from the steel beams. This can be a

    particular advantage at sites with poor ground conditions, steeply sloping terrain, or

    with a fast stream.

    Steel is a more reliable material which is supplied with guaranteed strengthproperties, enabling the production of high and consistently reliable structure.

  • 7/30/2019 Design of a Composite Bridge Deck

    45/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 35 -

    2.5.2. Reinforced Concrete Bridges

    Reinforced concrete is particularly adoptable for use in highway bridges because of its

    durability, rigidity, and economy as well as comparative ease with which a pleasing

    architectural appearance can be secured. Winter (1972)

    For very short spans of about 10ft (3m) to 25ft (7.5m), one way slab bridges are economical.

    For somewhat longer spans, concrete girder spans may be used. Most highway spans of

    medium length, from 40ft. (12m) to 90 ft. (27m), presently use steel- concrete construction

    or composite pre-stressed concrete. In composite construction with structural steel, the

    concrete deck is made to act integrally with supporting steel stringers by means of shear

    connectors, welded to the top of thee flange of the steel section and embedded in the slab.

    2.5.3 Design Standards

    Among many, the design of any bridge and/or its superstructure can be in accordance with

    B88110 structural use of concrete, BS 5950 structural use of steel. BSI (1979) for HA

    loading and AASHTO (1985) for HS20-44 loading, Uganda Bridge Design Manual, and

    Uganda Drainage Design manual

    2.6 Design Detailing

    2.6.1 Vertical Profile over the Bridge

    The bridge should preferably be constructed either to a level profile or to a constant

    longitudinal grade, if this is required by the road alignment. The steel beams can be

    cambered to give some degree of hogging vertical curvature should the equipment be

    available, but it may not be economical in most circumstances.

    2.6.2 Shear Connectors

    In order to provide more restraints to the steel beams and help attach firmly, the deck to the

    tensile stress carrying steel beams, connectors are provided. These connectors are the only

    links between the concrete slab, acting in compression and bending when under load, and the

    steel beams, acting in tension and bending. The largest shear forces act at each end of the

  • 7/30/2019 Design of a Composite Bridge Deck

    46/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 36 -

    deck, where the shear connectors are spaced closer together. Welded channel shear

    connectors are specified, since they can be produced from readily available material and

    fixed locally. The joints, however, should be of good quality welding and be protected from

    corrosion both in storage and in use.

    2.6.3 Protective Treatment to Steelwork

    The degree of protection which the steelwork will require depends on the local environment.

    However Particular care should be provided for structures in coastal locations or where there

    is significant atmospheric pollution. Types of paint used and surface preparation methods

    depends on the availability of materials and equipment. The designer should try to achieve

    the following standard in order to ensure a reasonable life to first maintenance:

    Grit blasting to remove mill scale, loose rust, welding scale etc., and produce a cleansurface for any coat of painting especially prime;

    Application of a multi-coat paint system to a total dry film thickness of 0.25mm.

    At least one paint coat should be applied at site after completion of construction, so that

    damage to paintwork incurred during transport, steel erection and concreting can be repaired.

    2.6.4 Bolts and nuts

    Ordinary bolts, grade 8.8 to ISO (1982) together with grade 8 nuts, are specified for fixing

    cross members. Alternatives should match the tensile strength of 80 kg/mmP2

    P with a

    minimum elongation at fracture of 2%.

    2.6.5 Bearings

    Elastomeric bearings, are specified because they are durable, inexpensive and simple to

    install. These bearings consist of discrete strips of black natural rubber, extending over the

    full width of the slab soffit at the support point, with a maximum width of approximately

    300mm and a maximum thickness of approximately 25mm. At the free end of the span, the

    bridge deck locates by friction between the rubber strip and the concrete deck, with no

  • 7/30/2019 Design of a Composite Bridge Deck

    47/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 37 -

    positive mechanical means to develop resistance against transverse loadings. At the fixed

    end, dowel bars passing through the pad at frequent intervals provide the necessary restraint,

    both longitudinally and transversely. To allow rotations to occur and the deck to expand

    laterally, the dowel bars are usually fitted with rubber caps where they pass into the concrete

    deck slab.

    2.6.6Expansion joints

    At these relatively short deck lengths, joint movements due to temperature and live loading

    are small and are readily accommodated by a simple gap joint, The joints are sealed by a

    polysulphide sealant to prevent water penetration. An alternative unsealed joint, more

    suitable for bridges on gravel roads, may be provided.

    2.6.7Construction joints

    It is always best if the deck slab can be cast in one continuous pour. If this will not be

    practicable, permissible locations for construction joints should be marked on the drawings.

    If a joint is unavoidable, it should be perpendicular to the centre line at a location least likely

    to promote corrosion in underlying steelwork.

    2.6.8Slab Reinforcement

    According to Overseas Road Note 29 Section 9.2.5, the maximum length of reinforcing bar

    generally available is 12m. Where a longer bar is required, e.g. for a 12m span bridge, two

    bars must be lapped. The lap length should be at least 40 times the diameter of the lapped

    bars and laps should be staggered both to avoid a line of weakness and to minimize

    congestion of reinforcement. Main bars are positioned with the hooks at alternate ends.

    Accurate positioning of the reinforcement is essential in order to maintain the minimumcover of 50mm of well compacted concrete, so that moisture and pollutants cannot penetrate

    the slab to reach the reinforcing bar and corrode it.

  • 7/30/2019 Design of a Composite Bridge Deck

    48/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 38 -

    2.6.9 Drainage

    Drainage should be provided if required, generally as detailed for concrete slab bridges down

    pipes must be of sufficient length to ensure that run-off water is discharged at least 150mm

    clear below the beam lower flanges.

    2.6.10 Parapets, Surfacing and Services

    Parapet and surfacing details are the same as for concrete slab bridges. If ducts for services

    are required, they can be provided

    2.5.11 Provision for Pedestrians and Cyclists

    The recommendations set out on pathways for pedestrians and cyclists on concrete decks

    apply equally to composite decks. The addition of a 2m wide walkway to a composite deck

    of the type detailed here would also require one more ''I'' beam to match those for the road

    bridge.

    2.7 River Hydraulics and Hydraulic Design

    2.7.1 River Hydraulics

    In order to secure safety from the effects of flowing water, the engineer has to ensure that the

    flowing water under the bridge can pass the structure without causing damage to its parts, the

    road embankment or the surrounding land. This topic thus explains how the parameters for

    safe hydraulic design can be obtained. Damage can occur in a number of ways, namely:

    The river may react against obstructions such as piers and abutments, and scourbeneath them causing failure.

    The approach embankments may act as a dam during high floods, sustaining damageor causing more extensive flooding upstream.

    A river flowing on a shifting path may bypass a bridge and cut a new channel acrossthe highway

    A river may over-top a bridge if sufficient clearance is not provided.

  • 7/30/2019 Design of a Composite Bridge Deck

    49/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 39 -

    The hydraulic characteristics of the river must be well understood and quantified so as to be

    able to design a structure that avoids the above problems and unnecessary costs. The most

    economical structure is usually one which is just wide and high enough to accommodate the

    design flood, minimizing the total cost of abutments, piers, superstructure, approach

    embankments, relief culverts and river training works.

    The hydraulic data required for the design process detailed in the following sections relate to:

    Design flood level DFL, flow volume and velocity. Maximum flood level, flow volume and velocity. Bed characteristics - particle size, vegetation. Channel shape and flood plain width. Sedimentation and meander characteristics. Navigational requirements and clearance of floating debris.

    Using the above data, determine by calculations the:-

    Geometry of waterway required at the bridge site. Backwater caused by the restriction of flow due to piers and abutments. (Scour

    caused by the restriction.

    River training works required.Calculating velocity using Manning's formula to estimate mean velocity

    213

    2

    1S

    P

    A

    nV

    =

    Where

    V= velocity (m/sec)

    A = Area of cross section of the flooded channel (mP2

    P)

    P= length of the wetted bed across the channel

  • 7/30/2019 Design of a Composite Bridge Deck

    50/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 40 -

    S= gradient of the surface or bed slope

    n = value of rugosity coefficient taken from the table 4.1 (ORN 9)

    There are many methods of obtaining flow volume but only two are discussed here.

    (i). The Area velocity methodQ =A.V

    Where

    Q = volume of flow (m P3

    P/sec)

    A= cross sectional area (mP2

    P)

    V= mean velocity of the water (m/sec)

    Area velocity method is necessary where the river tops its banks during flood.

    (ii).

    The Rational Formula

    )/(6.3

    3 smCIA

    Q =

    Where

    Q = volume of flow (mP3

    P/sec)

    C= Catchment coefficient

    I = Rainfall intensity (mm/hr)

    A = Area of the watershed/ catchment.

  • 7/30/2019 Design of a Composite Bridge Deck

    51/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 41 -

    In design of any bridge structure, much as excessive rainfall is unpredictable, it should be

    carefully designed for. Meteorological data should be used carefully to narrow or remove the

    range of uncertainty in river hydrology.

    Every designer needs to select a Design Flood Level (DFL), a design discharge or flowvolume and a design velocity, on which to base calculations of waterway geometry,

    foundation depths, scour protection and vertical clearance.

    The design flood is the maximum flow that can pass through the bridge without:-

    Unacceptable disruptions to traffic. Endangering the pier and abutment foundations with respect to scour Damaging approach embankments Causing flood damage on the upstream side of embankment.

    It should however be noted that the design flood is not necessarily the highest flood. The

    highest flood is a rarely occurring flow that it's uneconomical to include in the design flood

    but which may be considered when designing superstructure and piers of the bridge.

    Where the river is narrow enough, it can be bridged with a single span. The abutments are

    built clear of the level of the design flood and hence there is no restriction to river flow i.e.

    no river training, no backwater or additional scour is expected as a result of the bridge

    presence. For a wide flood channel, the superstructure is longer and will be very expensive if

    piers are not used. Both pier and abutment foundations are below DFL and thus require

    protection from scour.

    The abutment walls and piers will sabotage the design flood. This restriction causes

    backwater and additional scour of bed which must be considered while designing the

    foundation.

    (i) The Hydraulic Design Process.

    The steps involved in the design process include:-

    1. Establish the height of the infrastructure i.e. clearance above the DFL

  • 7/30/2019 Design of a Composite Bridge Deck

    52/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 42 -

    2. Establish trial positions for the abutments according to the bed shape at the proposedcrossing.

    3. Make a provisional decision concerning the number of piers that will result in thelowest overall cost of the superstructure, piers and abutments.

    4. Calculate the general and local scours due to the abutments and piers and draw theworst case profiles in the cross sections.

    5. Check that the backwater caused by the restriction to flow doesn't cause damage tosurrounding land upstream of the bridge or affect the height set for the superstructure.

    6. Prepare preliminary designs of abutments and piers.7. Check scour and backwater effects and make adjustments as required, reclaiming the

    effects of any changes to the waterway.

    8.

    Calculate the cost of the superstructure once its length is decided and the cost of thesubstructures, embankments, river training works and relief culverts.

    9. In order to obtain the most economical design, or to compare the cost of the structures catering for the different design floods, it may be necessary to repeat the above

    procedure on the basis of alternative waterway conditions.

    (ii) Bridge Height.

    The waterway below the superstructure must be designed to pass the design flood and thefloating debris carried on it Table 5.1 below shows recommended vertical clearance at DFL

    minimum measurements for a vertical clearance between the lowest part of the

    superstructure and the DFL, taking in to account backwater effects. This clearance should be

    increased on rivers with a history of unusually large floating items or navigational

    requirement

  • 7/30/2019 Design of a Composite Bridge Deck

    53/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 43 -

    Discharge

    (mP3

    P/sec)

    Vertical clearance

    (mm)

    300 1200

    (iii) Positioning of Abutment

    Choose a position bearing in mind the guidelines at the beginning of hydraulic design then

    check for scour using flow charts and spacing of abutments and piers.

    (iv). Scour

    Scour is the erosive effect of water flow on the river bed or banks. Bridge works may alter

    the existing scour pattern by restricting the free flow of the stream and/or causing local

    changes to the current. Approximately half of all river bridge failures are due to scour alone

    (ORN 9)

    However, there are four types of scour and they include:

    natural scour and channel shifting on alluvial rivers scour caused by changes to the river upstream or downstream of the bridge site General" scour caused by reduction in the channel width at the bridge works . "Local" scour at the base of piers, abutments and river training works where these

    divert the general flow.

    At the bridge site provide estimates for general and local scour.

  • 7/30/2019 Design of a Composite Bridge Deck

    54/121

    Re-design of Nariamabune Bridge in Kaabong District of Karamoja, Uganda 2009 B.Eng.CBE

    By: Okucu Anthony Tweny (07/U/2032/ECE/PE) Supervised by Dr . M ichael Kyakula- 44 -

    Chapter 3

    METHODOLOGY

    A bridge just like any other structure must be designed to resist all loads and forces that mayreasonably be exerted on it during its design life. The methodology used here was meant to

    address and aim at achieving the objectives outlined in section 1.4 above in a way that will

    appropriately solve the identified problem. And consider the design to take into account the

    cost implications and environment impact of the bridge structure. In this chapter, procedures

    to obtain which parameters are likely to occur and the magnitudes and combination of loads

    that produce maximum stress are listed.

    This project starte