design of gas transport systems

Upload: pasquale-cutri

Post on 06-Jul-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/17/2019 Design of Gas Transport Systems

    1/46

    1 - Classification: Internal 2011-02-21

    Design of Gas Transport Systems

    October 10, 2012

    Elin Kristin Dale

    [email protected]

    TPG4140 – NATURGASS, NTNU

  • 8/17/2019 Design of Gas Transport Systems

    2/46

    TPG4140 – NATURGASSNTNU

    2 - Classification: Internal 2011-02-21

    Design of gas transport systems

    • Part 1:

    − Intro Transport technology

    − Gas/condensate fields- and infrastructure development

    − System design of pipelines – terms and definitions

    • Part 2:

    − Design premises included examples

    − System design of multiphase pipelines

    − Pipeline pressure protection and leak detection

  • 8/17/2019 Design of Gas Transport Systems

    3/46

    TPG4140 – NATURGASSNTNU

    3 - Classification: Internal 2011-02-21Photo credit: Manfred Jarisch / StatoilHydro

    Part 1

    Intro Transport technology

  • 8/17/2019 Design of Gas Transport Systems

    4/46

    TPG4140 – NATURGASSNTNU

    4 - Classification: Internal 2011-02-21

    Transport technology

    “ Development of total transport solutions - from Reservoir to Market”

    Responsible for Transport technology in Statoil:

    • Multiphase system and flow assurance (FA)

    • Transport optimisation and design (TS)

    Our job is to secure and optimize transport of oiland gas in pipeline systems

  • 8/17/2019 Design of Gas Transport Systems

    5/46

    TPG4140 – NATURGASSNTNU

    5 - Classification: Internal 2011-02-21

    Market

    conditions

    Reservoir 

    conditions

    System definition

    Hydraulic analysis

    Optimisation of flow in pipeline network wrt

    capacity and gas quality management

    Principles for pressure control and pressure

    protection

    Interface management

    Supervision, consultation and daily operation ofleak detection system (PM-vakt)

    Transport technology

    PLEM

  • 8/17/2019 Design of Gas Transport Systems

    6/46

    6 - Classification: Internal 2011-02-21

    Gas/condensate fields- and infrastructuredevelopment

  • 8/17/2019 Design of Gas Transport Systems

    7/46

    TPG4140 – NATURGASSNTNU

    7 - Classification: Internal 2011-02-21

    Gas transport technology

    BCM

    LNG

    GTL/Methanol 

    PIPELINE

    UNECONOMIC

    1000 2000 3000 4000 5000

    Distance to market - Km

    Floating LNG

    Electricity(HVDC)

    CNG

    50

    20

    10

    5

    2

    1

    .50

    Volume

    (North sea)(Barents sea)

  • 8/17/2019 Design of Gas Transport Systems

    8/46

  • 8/17/2019 Design of Gas Transport Systems

    9/46

    TPG4140 – NATURGASSNTNU

    9 - Classification: Internal 2011-02-21

    • Statoil has developed the world’s largestoffshore gas pipeline network

    • Technical services are provided by Statoil forthe world's most extensive submarine gaspipeline system:

    − 7800 km pipelines (30” – 44”)

    − Long term transport capacity approx.

    365 MSm3

    /d• Statoil is the leader in the construction of

    large-diameter pipelines in deep water.

    • On 1st January 2002, Gassco became theoperator for most of the gas pipeline systems

    from the Norwegian continental shelf.• On 1st January 2003, Gassled became the

    owner for most of the gas pipeline systems(Statoil share 5%, Statoil+Petoro share 50,8%).

    The Norwegian Continental Shelf 

  • 8/17/2019 Design of Gas Transport Systems

    10/46

    TPG4140 – NATURGASSNTNU

    10 - Classification: Internal 2011-02-21

    • Gas supply

    − Production profile

    − Build-up and plateau level

    • Market scenarios

    − Volume

    − Market opportunities (and flexibility)

    − Company based sales

    • Existing infrastructure

    − Platforms

    • Tie-ins and functional

    requirements

    − Pipelines

    • Capacity and ullage

    • New infrastructure requirements

    Gas/condensate fields- and infrastructure

    development

  • 8/17/2019 Design of Gas Transport Systems

    11/46

    TPG4140 – NATURGASSNTNU

    11 - Classification: Internal 2011-02-21

    • The pipeline between X and Y isthe main link between theproduction at A and B and the

    terminal E.• Utilisation of the XY link affects the

    capacity towards E, creating abottleneck and a gap between theactual delivery and the demand.

    • Routing of the gas will determinethe possible transportation capacityat a given scenario.

    • The sum of exit capacity in atransport system is not necessarilyequal the actual transport capacity.

    • Transport capacity is dependent onvolume scenario, bottlenecks anddependencies.

    Production scenario 1 [MSm3/d]

    Producers Exit terminals

     A B C D E

    30 40 10 15 65

     A B C

    D E

    X Y

    14,7 20 20 10

    15 49,7

    19,7

    14,7

    49,7

    Gap: ~15

    Existing infrastructure - capacity

  • 8/17/2019 Design of Gas Transport Systems

    12/46

    TPG4140 – NATURGASSNTNU

    12 - Classification: Internal 2011-02-21

    • Example of business case:

    − New field discovery Johan Sverdrup,largest finding in the world this year.

    500-1200 Mill barrels oil equivalents, 140km offshore, 112 meter depth, 1900meter below the seabed.

    − Which field architecture will yourecommend to your management ?

    Overall field architecture case – Johan Sverdrup

    • Some of the parameters to be evaluated :

    − Technical: Choice of installation (floater, fixed structure), store or transport, processing,naval architecture, sensitivity to weather/sea conditions (hurricane, waves, tide,temperature etc), fluid properties (wax, hydrates, corrosion etc.), pigging, ship transportpath, design codes, infrastructure (helicopter base, logistics, storage equipment/fluids,

    accommodation) and pressure protection and leak detection.

    − Economic analyses: availability in marked, location of construction, rent or own,distance from field to market, pipeline transport fee, country laws and regulations,personnel availability, company philosophy.

  • 8/17/2019 Design of Gas Transport Systems

    13/46

    13 - Classification: Internal 2011-02-21

    Pipeline system design

    Terms and definitions

  • 8/17/2019 Design of Gas Transport Systems

    14/46

    TPG4140 – NATURGASSNTNU

    14 - Classification: Internal 2011-02-21

    • Pipeline system

    − A pipeline with compressors or pump stations

    − Pressure reduction stations

    − Metering

    − Tankage

    −Supervisory control and data acquisition system (SCADA)

    − Safety systems

    − Corrosion protection systems

    −  And other equipment, facility or building used in the transportation of fluids

    • Pipeline

    − Those facilities through which fluids are conveyed, including pipe, pig traps,

    components and appurtenances, up to and including the isolation valve.

    Petroleum and natural gas indus tries

    Pipeline transportation systems, ISO13623

    Pipeline system design – terms and definitions

  • 8/17/2019 Design of Gas Transport Systems

    15/46

    TPG4140 – NATURGASSNTNU

    15 - Classification: Internal 2011-02-21

    • The extent of the pipeline system, its functional requirements and applicable legislation

    should be defined and documented.

    • The extent of the system should be defined by describing the system, including the

    facilities with their general locations and demarcations and interfaces with other facilities.

    • The functional requirements should define the required design life and design conditions.

    Foreseeable normal, extreme and shut-in operating conditions with their possible ranges

    in flow rates, pressures, temperatures, fluid compositions and fluid qualities should beidentified and considered when defining the design conditions.

    Petroleum and natural gas industries

    Pipeline transportation systems, ISO 13623 OS F-101: Submarine PipelineSystems

    Pipeline system design – system definition

  • 8/17/2019 Design of Gas Transport Systems

    16/46

    TPG4140 – NATURGASSNTNU

    16 - Classification: Internal 2011-02-21

    SCSSV

    PMV

    PWV

    CHOKEBRANCH

    HIPPS

    MANIFOLD

    SSIV

    SSIV

    CHECK

    LANDFALL

    PIG TRAP

    PIG TRAP

    PIG TRAP

    PLEM

    TEE

    X-MASTREE

    CHOKEMODULE

    TEMPLATE ANDMANIFOLD

    RISER BASE

    CHECK + BLOCK

    SUBSEAPROCESSING

    UNIT

    ESV

    ESV

    ESV

    Platform/Floater 

    Onshore

    SubseaProduction

    Subsea connectionPipeline Systems:Single phase; Gas, Oil, condensate

    Multiphase;

    Subsea isolation

    Pipeline systemsSubsea Production Systems (ISO 13628) and

    Pipeline Transportation Systems (ISO 13623)

  • 8/17/2019 Design of Gas Transport Systems

    17/46

    TPG4140 – NATURGASSNTNU

    17 - Classification: Internal 2011-02-21

    Pipeline Project Organisation (Typical)

    Project Manager

    Pipeline

    EngineeringSystem/RFO

    Pipeline

    Construction

    Project Control

    LandfallPreparation for

    Operation

    Authority

    Procurement HSE

    Administration EIA

    Upstream

    Platform/Terminal

    Downstream

    Platform/Terminal

  • 8/17/2019 Design of Gas Transport Systems

    18/46

    TPG4140 – NATURGASSNTNU

    18 - Classification: Internal 2011-02-21

    " I draw lines, I don't move trees"

  • 8/17/2019 Design of Gas Transport Systems

    19/46

    TPG4140 – NATURGASSNTNU

    19 - Classification: Internal 2011-02-21

    Thermo-

    hydraulic

    analysis

    Internal diameter,

    capacity, pressure

    and temperature

    profile, etc.

    Functional

    requirements;

    gas routing,

    regularity,

    gas quality,

    agreements

    Functional

    requirements,

    Regularity,

    Deliverability

    Overall

    Operational

    Philosophy;

    Control and

    Safety

    System,

    Environment,

    etc.

    Pipeline System

    Diagram, Process

    Flow Diagram

    Control and Safety

    Philosophy

    System design

    concept

    Boundary conditions and technical interface between platform – pipeline – terminal

    P&ID’s

    QA

    Pipeline system design – work process

  • 8/17/2019 Design of Gas Transport Systems

    20/46

    TPG4140 – NATURGASSNTNU

    20 - Classification: Internal 2011-02-21Photo credit: Manfred Jarisch / StatoilHydro

    Part 2

    Design premisesHydraulic capacity and gas quality

  • 8/17/2019 Design of Gas Transport Systems

    21/46

    TPG4140 – NATURGASSNTNU

    21 - Classification: Internal 2011-02-21

    • The objective of the system design

    − develop overall transport solutions for the gas chain from the field

    to the market which will maximize the value of the liquid- and gas

    products and without any unreasonable external conditions for

    any third party (fields or transport systems).

    − deliver gas quantities nominated by the buyers within the desired

    quality specifications.

    − ensure high availability and regularity within reasonable technical

    and economical limits and relevant agreements.

    Pipeline system design – Hydraulic analysis 1/2

  • 8/17/2019 Design of Gas Transport Systems

    22/46

    TPG4140 – NATURGASSNTNU

    22 - Classification: Internal 2011-02-21

    • The hydraulics of the pipeline system should be analysed to demonstrate that thesystem can safely transport the fluids for the design conditions specified by thesystem definition, and to identify and determine the constraints and requirements for

    its operation. This analysis should cover steady-state and transient operatingconditions.

    • Describe the function loads for the pipeline design

    − Pressure profile

    − Temperature profile

    −Density profile (fluid)

    − Velocity profile

    • Design cases:

    − Normal operation, start-up, planned shut-down, etc.

    −Not planned operation, emergency shut-down, depressurisation, etc.

    − Emergency preparedness analysis; accidents, pipe rupture, leakage etc.

    Pipeline system design – Hydraulic analysis 2/2

  • 8/17/2019 Design of Gas Transport Systems

    23/46

    TPG4140 – NATURGASSNTNU

    23 - Classification: Internal 2011-02-21

    • Pipeline Route

    − Length

    − Bathymetric profile

     Area B - Åsgard Transport, Kårstø pressure

    80

    85

    90

    95

    100

    105

    110

    115

    120

    125

    130

    66 68 70 72 74 76 78 80 82 84 86

    Hydraul ic capacity, MSm³/d

       P  r  e

      s  s  u  r  e ,

       b  a  r  g

    High Rough Likely Rough Low Rough

     Area B - Åsgard Transport, Kårstø temp.

    -3

    -1

    1

    3

    5

    66 68 70 72 74 76 78 80 82 84 86

    Hydrauli c capacity, MSm³/d

       T  e  m  p  e  r  a   t  u  r  e

     ,   °   C

    High Rough Likely Rough Low Rough

    • Environmental Conditions

    −  Air temperature

    − Sea bottom temperature

    − Ground temperature

    −Geo-technical data (soil conditions)

    Pipeline system design – Design premises 1/3

  • 8/17/2019 Design of Gas Transport Systems

    24/46

    TPG4140 – NATURGASSNTNU

    24 - Classification: Internal 2011-02-21

    Variation o f parameters and hyd raulic capacity compared to basis

    -2 -1.5 -1 -0.5 0 0.5 1 1.5 2 2.5 3

    1

    2

    3

    4

    5

    Gas Compositio n

    Roughness 1- 3 micron

    Temperature

    Leng th +/-10 Km

    Trenching -200 Km

    10 mic ron

    Zeebru gge 69.5 MSm³/d (october)

    Hydraulic capacity – Sensitivity analysis

  • 8/17/2019 Design of Gas Transport Systems

    25/46

    TPG4140 – NATURGASSNTNU

    25 - Classification: Internal 2011-02-21

    • Pipeline Data

    −Design pressure

    − Design temperature

    − Internal diameter 

    − Wall thickness

    − Internal coating

    − Concrete coating

    − Insulation

    − Trenching/dredging

    − Gravel/rock dumping

    Pipeline system design – Design premises 2/3

  • 8/17/2019 Design of Gas Transport Systems

    26/46

    TPG4140 – NATURGASSNTNU

    26 - Classification: Internal 2011-02-21

    1200 km a 12m pipes:

    Total pipeline steel(962 000 t)= 40 Troll A deck

    Concrete coating(330 000 m3)= 1,5 Troll A GBS

    Coating(25 000 t)= 3 Eiffel TowersTotal coating “wire”:(51 900km)= 1.3 timesaround the equator

    Per pipe:

    Ca 25 tonns

    Langeled Bredero Shaw i Farsund Sept. 2004

  • 8/17/2019 Design of Gas Transport Systems

    27/46

    TPG4140 – NATURGASSNTNU

    27 - Classification: Internal 2011-02-21

    Solitaire:

    The worlds largest pipeline layingvessel at Nyhamna

    Acergy Piper:At Sleipner T at start-up of the layingprocess

    The largest laying vessels

  • 8/17/2019 Design of Gas Transport Systems

    28/46

    TPG4140 – NATURGASSNTNU

    28 - Classification: Internal 2011-02-21

    • Gas properties

    − Equation of state

    • Gas composition

    • Friction equation

    − Internal roughness

    • Transport specification

    • Sales gas specifications

    • Pressure Control System

    − Pressure regulating

    − Pressure safety

    • Pig trap arrangement

    − Pigging philosophy

    • Pipeline valve philosophy• Future requirements

    Pipeline system design – Design premises 3/3

  • 8/17/2019 Design of Gas Transport Systems

    29/46

    TPG4140 – NATURGASSNTNU

    29 - Classification: Internal 2011-02-21

    • Double expanding gate

    • Weight of valve: 80 tons (60 cars..)

    • 10m high including activator:

    • Total of 100 tons

    Transport of 42” subsea pipeline

    valve

  • 8/17/2019 Design of Gas Transport Systems

    30/46

    TPG4140 – NATURGASSNTNU

    30 - Classification: Internal 2011-02-21

    • Ensure interoperability /interchangeability (WI)

    • Ensure unproblematic transport of gas

    −Max/min temperature and pressure

    • Prevent corrosion and erosion of equipment

    − Water, CO2, H2S content

    • Prevent condensation of liquid (HC dew point)

    • Prevent gas hydrates (Water dew point)

    Why gas quality specifications?

    Hydrocarbon dew-point (-3 C, 69 barg)

    Water dew-point (-12 C, 69 barg)

    CO2 content (max 2.5 % mol)H2S content (5 mg/Nm3)

    GCV (Gross calorific value)

    Wobbe index (WI)Max/min pressure and temperature

  • 8/17/2019 Design of Gas Transport Systems

    31/46

  • 8/17/2019 Design of Gas Transport Systems

    32/46

    32 - Classification: Internal 2011-02-21

    System design of multiphase pipelines

  • 8/17/2019 Design of Gas Transport Systems

    33/46

    TPG4140 – NATURGASSNTNU

    33 - Classification: Internal 2011-02-21

    Technical feasibility – for how long can reservoir drive production to shore?

    • Minimize pressure drop large pipe diameter 

    Operational acceptability – will system availability be high enough?

    • Minimize liquid inventory in pipeline small pipe diameter 

    0

    1000

    2000

    3000

    4000

    5000

    6000

    7000

    8000

    24 26 28 30 32 34Gas rate (MSm3/d)

       L

       i  q  u   i   d  c  o  n   t  e  n   t   (  m

       3   )

    Designrate

    20

    30

    40

    50

    20 22 24 26 28 30 32 34

    Gas rate (MSm3/d)

       P

      r  e  s  s  u  r  e   d  r  o  p   (   b  a

      r  a   )

    LargeID

    SmallID

    Designrate

    SmallID

    Large

    ID

    The diameter dilemma of long gas-condensate

    pipelines

  • 8/17/2019 Design of Gas Transport Systems

    34/46

    TPG4140 – NATURGASSNTNU

    34 - Classification: Internal 2011-02-21

    Pipeline diameter: small

    • Minimize liquid inventory

    Accept moderate/high pressure drop

    Slug-catcher size set by:

    • Rate increase:From maximum turndown to designrate

    • Pigging

    Liquid inventory prior to pigging

    20

    30

    40

    50

    20 22 24 26 28 30 32 34

    Gas rate (MSm3/d)

       P  r  e  s  s  u  r  e   d  r  o  p   (   b  a  r  a   )

    Design pressuredrop

    Designrate

    Maximumturndown

    0

    1000

    2000

    3000

    4000

    5000

    60007000

    8000

    24 26 28 30 32 34Gas rate (MSm3/d)

       L   i  q  u   i   d  c  o  n   t  e  n   t   (  m   3   )

    Design

    rate

    Steady state

    liquid contentMaximumturndown

       S   l  u  g  -  c  a   t  c

       h  e  r

      v  o   l  u  m  e

    Troll slug-catcher

    Conventional design of gas-condensate pipelines

  • 8/17/2019 Design of Gas Transport Systems

    35/46

    TPG4140 – NATURGASSNTNU

    35 - Classification: Internal 2011-02-21

    Pipeline diameter: large

    • Minimize pressure drop

    Accept relatively large liquid inventory

    • If possible, alleviate liquid load

    Multi-diameter pipelines/dual lines

    • Exploit pipeline’s slow response to transients

    Operational procedures

    Slug-catcher design

    • Exploit pipeline’s slow response to transients

    Reduce slug-catcher size

    • Onshore reception system routes liquid to

    off-spec tank

    Optimise slug-catcher design

    Liquid flow into slug-catcher

    0 2 4 6 8 10 12 14Time (days)

    300

    200

    100

    0   V  o   l  u  m  e

      r  a   t  e   (  m   3   /   h   )

    20

    30

    40

    50

    20 22 24 26 28 30 32 34

    Gas rate (MSm3/d)

       P  r  e  s  s  u

      r  e   d  r  o  p   (   b  a  r  a   )

    LargeID

    SmallID

    New design of gas-condensate pipelines

  • 8/17/2019 Design of Gas Transport Systems

    36/46

    36 - Classification: Internal 2011-02-21

    Pipeline integrity and leak detection

    Deepwater horizon

  • 8/17/2019 Design of Gas Transport Systems

    37/46

    TPG4140 – NATURGASSNTNU

    37 - Classification: Internal 2011-02-21

    Pipeline integrity and leak detection

    Robust

    design

    Safe

    operation

    Emergency

    response

    Integrity

    management

    Leak

    detection

    Probability reduction Consequence reduction

  • 8/17/2019 Design of Gas Transport Systems

    38/46

    TPG4140 – NATURGASSNTNU

    38 - Classification: Internal 2011-02-21

    PPS and PPC

  • 8/17/2019 Design of Gas Transport Systems

    39/46

    TPG4140 – NATURGASSNTNU

    39 - Classification: Internal 2011-02-21

    Allocations of risk reducing measures

    Frequency of

    overpressure

    Frequency of 

    overpressure

    Without risk reduction

    Acceptable risk 

    (Frequency of 

    overpressure )

    1 times pr year1x10 -5

    Achieved freq of 

    overpressure

    Required risk reduction

    Achieved risk reduction from safety functions

    PPS -2 PPS -1 PPCManuel

    actions

    •Facilities regulation §33•ISO 10418 (API 14 C)

    •IEC 61508

    •IEC 61511

    Actual risk reduction

    PPC: Independent of the PSS

    PPS: Two independent systems activated at different pressure levels, and

    with a redundant and fail safe instrumentation and signal transfer system

    Risk reduction

  • 8/17/2019 Design of Gas Transport Systems

    40/46

    TPG4140 – NATURGASSNTNU

    40 - Classification: Internal 2011-02-21

    Shut down of receiving facility

    Kollsnes export is stopped 0.5 hour later 44" Den Helder. SOP at 2% Opflex. October 

    90

    100

    110

    120

    130

    140

    150

    160

    170

    180

    190

    200

    210

    0 100 200 300 400 500 600 700 800 900

    Distance, km

       P  r  e  s  s  u  r  e

     ,   b  a  r  g

    0 2 4 6 8 10 12 14 16 18Time, hrs

    203 barg (+10m)

    156.8 barg (+10m)

    Den Helder

    Kollsnes

    Norwegiansector 

    Danishsector  Germansector  Dutchsector 

  • 8/17/2019 Design of Gas Transport Systems

    41/46

    TPG4140 – NATURGASSNTNU

    41 - Classification: Internal 2011-02-21

    Normal pressure profile

    Low utilisation of pipe material

    PD

    Upstream end Downstream end

    Normal Design

    Settle out pressure

    Normal pressure profile

    PD2

    PD1

    PD3

    Multi Design Pressure

    • The settle out pressure in a “normal” shut-in situation shall not exceed the lower design

    pressure

    • The pipeline hydraulics during normal, upset and packing conditions are analysed to

    demonstrate that the pressure control and pressure protection system will act satisfactory

    • Cost saving material

    Multi design pressure concept

  • 8/17/2019 Design of Gas Transport Systems

    42/46

    TPG4140 – NATURGASSNTNU

    42 - Classification: Internal 2011-02-21

    EV

    PPS-1 PPS-2

    PT PT

    Pipeline

    EV

    Upstream

    Plant

    Downstream

    Plant

    PT PT

    PPS-1 PPS-2

    Triple redundant

    Fiberoptic and

    telemetry

    EVEVEV

    PPS-1 PPS-2PPS-1 PPS-2

    PT PTPT PTPTPT PTPT

    Pipeline

    EV

    Upstream

    Plant

    Downstream

    Plant

    PT PTPT PTPTPT PTPT

    PPS-1 PPS-2PPS-1 PPS-2

    Triple redundant

    Fiberoptic and

    telemetry

    Pipeline pressure protection

  • 8/17/2019 Design of Gas Transport Systems

    43/46

    TPG4140 – NATURGASSNTNU

    43 - Classification: Internal 2011-02-21

    Pipeline integrity and leak detection

    Robust

    design

    Safe

    operation

    Emergency

    response

    Integrity

    management

    Leak

    detection

    Probability reduction Consequence reduction

    need

    protecting

    what?

    pipeline or

    zone? sensitivity

    robustness

    reliability

    technology

    solution

    mass balance

    pressure loss

    point sensor 

    acoustic

  • 8/17/2019 Design of Gas Transport Systems

    44/46

    TPG4140 – NATURGASSNTNU

    44 - Classification: Internal 2011-02-21

    The risk picture…

    Probability

    Consequence

     Acceptable risk, but extrabarriers?

    30” Kvitebjørn gas pipeline damage and leak, 2007

  • 8/17/2019 Design of Gas Transport Systems

    45/46

    TPG4140 – NATURGASSNTNU

    45 - Classification: Internal 2011-02-21

    • Complexity of field architecture development

    • Parameters influencing pipeline infrastructure development

    • Pipeline design premises

    • How the hydraulic of the pipeline system influence pipeline design

    • Pressure protection and leak detection of pipeline systems

    Key learning points

  • 8/17/2019 Design of Gas Transport Systems

    46/46