design of gas transport systems
TRANSCRIPT
-
8/17/2019 Design of Gas Transport Systems
1/46
1 - Classification: Internal 2011-02-21
Design of Gas Transport Systems
October 10, 2012
Elin Kristin Dale
TPG4140 – NATURGASS, NTNU
-
8/17/2019 Design of Gas Transport Systems
2/46
TPG4140 – NATURGASSNTNU
2 - Classification: Internal 2011-02-21
Design of gas transport systems
• Part 1:
− Intro Transport technology
− Gas/condensate fields- and infrastructure development
− System design of pipelines – terms and definitions
• Part 2:
− Design premises included examples
− System design of multiphase pipelines
− Pipeline pressure protection and leak detection
-
8/17/2019 Design of Gas Transport Systems
3/46
TPG4140 – NATURGASSNTNU
3 - Classification: Internal 2011-02-21Photo credit: Manfred Jarisch / StatoilHydro
Part 1
Intro Transport technology
-
8/17/2019 Design of Gas Transport Systems
4/46
TPG4140 – NATURGASSNTNU
4 - Classification: Internal 2011-02-21
Transport technology
“ Development of total transport solutions - from Reservoir to Market”
Responsible for Transport technology in Statoil:
• Multiphase system and flow assurance (FA)
• Transport optimisation and design (TS)
Our job is to secure and optimize transport of oiland gas in pipeline systems
-
8/17/2019 Design of Gas Transport Systems
5/46
TPG4140 – NATURGASSNTNU
5 - Classification: Internal 2011-02-21
Market
conditions
Reservoir
conditions
System definition
Hydraulic analysis
Optimisation of flow in pipeline network wrt
capacity and gas quality management
Principles for pressure control and pressure
protection
Interface management
Supervision, consultation and daily operation ofleak detection system (PM-vakt)
Transport technology
PLEM
-
8/17/2019 Design of Gas Transport Systems
6/46
6 - Classification: Internal 2011-02-21
Gas/condensate fields- and infrastructuredevelopment
-
8/17/2019 Design of Gas Transport Systems
7/46
TPG4140 – NATURGASSNTNU
7 - Classification: Internal 2011-02-21
Gas transport technology
BCM
LNG
GTL/Methanol
PIPELINE
UNECONOMIC
1000 2000 3000 4000 5000
Distance to market - Km
Floating LNG
Electricity(HVDC)
CNG
50
20
10
5
2
1
.50
Volume
(North sea)(Barents sea)
-
8/17/2019 Design of Gas Transport Systems
8/46
-
8/17/2019 Design of Gas Transport Systems
9/46
TPG4140 – NATURGASSNTNU
9 - Classification: Internal 2011-02-21
• Statoil has developed the world’s largestoffshore gas pipeline network
• Technical services are provided by Statoil forthe world's most extensive submarine gaspipeline system:
− 7800 km pipelines (30” – 44”)
− Long term transport capacity approx.
365 MSm3
/d• Statoil is the leader in the construction of
large-diameter pipelines in deep water.
• On 1st January 2002, Gassco became theoperator for most of the gas pipeline systems
from the Norwegian continental shelf.• On 1st January 2003, Gassled became the
owner for most of the gas pipeline systems(Statoil share 5%, Statoil+Petoro share 50,8%).
The Norwegian Continental Shelf
-
8/17/2019 Design of Gas Transport Systems
10/46
TPG4140 – NATURGASSNTNU
10 - Classification: Internal 2011-02-21
• Gas supply
− Production profile
− Build-up and plateau level
• Market scenarios
− Volume
− Market opportunities (and flexibility)
− Company based sales
• Existing infrastructure
− Platforms
• Tie-ins and functional
requirements
− Pipelines
• Capacity and ullage
• New infrastructure requirements
Gas/condensate fields- and infrastructure
development
-
8/17/2019 Design of Gas Transport Systems
11/46
TPG4140 – NATURGASSNTNU
11 - Classification: Internal 2011-02-21
• The pipeline between X and Y isthe main link between theproduction at A and B and the
terminal E.• Utilisation of the XY link affects the
capacity towards E, creating abottleneck and a gap between theactual delivery and the demand.
• Routing of the gas will determinethe possible transportation capacityat a given scenario.
• The sum of exit capacity in atransport system is not necessarilyequal the actual transport capacity.
• Transport capacity is dependent onvolume scenario, bottlenecks anddependencies.
Production scenario 1 [MSm3/d]
Producers Exit terminals
A B C D E
30 40 10 15 65
A B C
D E
X Y
14,7 20 20 10
15 49,7
19,7
14,7
49,7
Gap: ~15
Existing infrastructure - capacity
-
8/17/2019 Design of Gas Transport Systems
12/46
TPG4140 – NATURGASSNTNU
12 - Classification: Internal 2011-02-21
• Example of business case:
− New field discovery Johan Sverdrup,largest finding in the world this year.
500-1200 Mill barrels oil equivalents, 140km offshore, 112 meter depth, 1900meter below the seabed.
− Which field architecture will yourecommend to your management ?
Overall field architecture case – Johan Sverdrup
• Some of the parameters to be evaluated :
− Technical: Choice of installation (floater, fixed structure), store or transport, processing,naval architecture, sensitivity to weather/sea conditions (hurricane, waves, tide,temperature etc), fluid properties (wax, hydrates, corrosion etc.), pigging, ship transportpath, design codes, infrastructure (helicopter base, logistics, storage equipment/fluids,
accommodation) and pressure protection and leak detection.
− Economic analyses: availability in marked, location of construction, rent or own,distance from field to market, pipeline transport fee, country laws and regulations,personnel availability, company philosophy.
-
8/17/2019 Design of Gas Transport Systems
13/46
13 - Classification: Internal 2011-02-21
Pipeline system design
Terms and definitions
-
8/17/2019 Design of Gas Transport Systems
14/46
TPG4140 – NATURGASSNTNU
14 - Classification: Internal 2011-02-21
• Pipeline system
− A pipeline with compressors or pump stations
− Pressure reduction stations
− Metering
− Tankage
−Supervisory control and data acquisition system (SCADA)
− Safety systems
− Corrosion protection systems
− And other equipment, facility or building used in the transportation of fluids
• Pipeline
− Those facilities through which fluids are conveyed, including pipe, pig traps,
components and appurtenances, up to and including the isolation valve.
Petroleum and natural gas indus tries
Pipeline transportation systems, ISO13623
Pipeline system design – terms and definitions
-
8/17/2019 Design of Gas Transport Systems
15/46
TPG4140 – NATURGASSNTNU
15 - Classification: Internal 2011-02-21
• The extent of the pipeline system, its functional requirements and applicable legislation
should be defined and documented.
• The extent of the system should be defined by describing the system, including the
facilities with their general locations and demarcations and interfaces with other facilities.
• The functional requirements should define the required design life and design conditions.
Foreseeable normal, extreme and shut-in operating conditions with their possible ranges
in flow rates, pressures, temperatures, fluid compositions and fluid qualities should beidentified and considered when defining the design conditions.
Petroleum and natural gas industries
Pipeline transportation systems, ISO 13623 OS F-101: Submarine PipelineSystems
Pipeline system design – system definition
-
8/17/2019 Design of Gas Transport Systems
16/46
TPG4140 – NATURGASSNTNU
16 - Classification: Internal 2011-02-21
SCSSV
PMV
PWV
CHOKEBRANCH
HIPPS
MANIFOLD
SSIV
SSIV
CHECK
LANDFALL
PIG TRAP
PIG TRAP
PIG TRAP
PLEM
TEE
X-MASTREE
CHOKEMODULE
TEMPLATE ANDMANIFOLD
RISER BASE
CHECK + BLOCK
SUBSEAPROCESSING
UNIT
ESV
ESV
ESV
Platform/Floater
Onshore
SubseaProduction
Subsea connectionPipeline Systems:Single phase; Gas, Oil, condensate
Multiphase;
Subsea isolation
Pipeline systemsSubsea Production Systems (ISO 13628) and
Pipeline Transportation Systems (ISO 13623)
-
8/17/2019 Design of Gas Transport Systems
17/46
TPG4140 – NATURGASSNTNU
17 - Classification: Internal 2011-02-21
Pipeline Project Organisation (Typical)
Project Manager
Pipeline
EngineeringSystem/RFO
Pipeline
Construction
Project Control
LandfallPreparation for
Operation
Authority
Procurement HSE
Administration EIA
Upstream
Platform/Terminal
Downstream
Platform/Terminal
-
8/17/2019 Design of Gas Transport Systems
18/46
TPG4140 – NATURGASSNTNU
18 - Classification: Internal 2011-02-21
" I draw lines, I don't move trees"
-
8/17/2019 Design of Gas Transport Systems
19/46
TPG4140 – NATURGASSNTNU
19 - Classification: Internal 2011-02-21
Thermo-
hydraulic
analysis
Internal diameter,
capacity, pressure
and temperature
profile, etc.
Functional
requirements;
gas routing,
regularity,
gas quality,
agreements
Functional
requirements,
Regularity,
Deliverability
Overall
Operational
Philosophy;
Control and
Safety
System,
Environment,
etc.
Pipeline System
Diagram, Process
Flow Diagram
Control and Safety
Philosophy
System design
concept
Boundary conditions and technical interface between platform – pipeline – terminal
P&ID’s
QA
Pipeline system design – work process
-
8/17/2019 Design of Gas Transport Systems
20/46
TPG4140 – NATURGASSNTNU
20 - Classification: Internal 2011-02-21Photo credit: Manfred Jarisch / StatoilHydro
Part 2
Design premisesHydraulic capacity and gas quality
-
8/17/2019 Design of Gas Transport Systems
21/46
TPG4140 – NATURGASSNTNU
21 - Classification: Internal 2011-02-21
• The objective of the system design
− develop overall transport solutions for the gas chain from the field
to the market which will maximize the value of the liquid- and gas
products and without any unreasonable external conditions for
any third party (fields or transport systems).
− deliver gas quantities nominated by the buyers within the desired
quality specifications.
− ensure high availability and regularity within reasonable technical
and economical limits and relevant agreements.
Pipeline system design – Hydraulic analysis 1/2
-
8/17/2019 Design of Gas Transport Systems
22/46
TPG4140 – NATURGASSNTNU
22 - Classification: Internal 2011-02-21
• The hydraulics of the pipeline system should be analysed to demonstrate that thesystem can safely transport the fluids for the design conditions specified by thesystem definition, and to identify and determine the constraints and requirements for
its operation. This analysis should cover steady-state and transient operatingconditions.
• Describe the function loads for the pipeline design
− Pressure profile
− Temperature profile
−Density profile (fluid)
− Velocity profile
• Design cases:
− Normal operation, start-up, planned shut-down, etc.
−Not planned operation, emergency shut-down, depressurisation, etc.
− Emergency preparedness analysis; accidents, pipe rupture, leakage etc.
Pipeline system design – Hydraulic analysis 2/2
-
8/17/2019 Design of Gas Transport Systems
23/46
TPG4140 – NATURGASSNTNU
23 - Classification: Internal 2011-02-21
• Pipeline Route
− Length
− Bathymetric profile
Area B - Åsgard Transport, Kårstø pressure
80
85
90
95
100
105
110
115
120
125
130
66 68 70 72 74 76 78 80 82 84 86
Hydraul ic capacity, MSm³/d
P r e
s s u r e ,
b a r g
High Rough Likely Rough Low Rough
Area B - Åsgard Transport, Kårstø temp.
-3
-1
1
3
5
66 68 70 72 74 76 78 80 82 84 86
Hydrauli c capacity, MSm³/d
T e m p e r a t u r e
, ° C
High Rough Likely Rough Low Rough
• Environmental Conditions
− Air temperature
− Sea bottom temperature
− Ground temperature
−Geo-technical data (soil conditions)
Pipeline system design – Design premises 1/3
-
8/17/2019 Design of Gas Transport Systems
24/46
TPG4140 – NATURGASSNTNU
24 - Classification: Internal 2011-02-21
Variation o f parameters and hyd raulic capacity compared to basis
-2 -1.5 -1 -0.5 0 0.5 1 1.5 2 2.5 3
1
2
3
4
5
Gas Compositio n
Roughness 1- 3 micron
Temperature
Leng th +/-10 Km
Trenching -200 Km
10 mic ron
Zeebru gge 69.5 MSm³/d (october)
Hydraulic capacity – Sensitivity analysis
-
8/17/2019 Design of Gas Transport Systems
25/46
TPG4140 – NATURGASSNTNU
25 - Classification: Internal 2011-02-21
• Pipeline Data
−Design pressure
− Design temperature
− Internal diameter
− Wall thickness
− Internal coating
− Concrete coating
− Insulation
− Trenching/dredging
− Gravel/rock dumping
Pipeline system design – Design premises 2/3
-
8/17/2019 Design of Gas Transport Systems
26/46
TPG4140 – NATURGASSNTNU
26 - Classification: Internal 2011-02-21
1200 km a 12m pipes:
Total pipeline steel(962 000 t)= 40 Troll A deck
Concrete coating(330 000 m3)= 1,5 Troll A GBS
Coating(25 000 t)= 3 Eiffel TowersTotal coating “wire”:(51 900km)= 1.3 timesaround the equator
Per pipe:
Ca 25 tonns
Langeled Bredero Shaw i Farsund Sept. 2004
-
8/17/2019 Design of Gas Transport Systems
27/46
TPG4140 – NATURGASSNTNU
27 - Classification: Internal 2011-02-21
Solitaire:
The worlds largest pipeline layingvessel at Nyhamna
Acergy Piper:At Sleipner T at start-up of the layingprocess
The largest laying vessels
-
8/17/2019 Design of Gas Transport Systems
28/46
TPG4140 – NATURGASSNTNU
28 - Classification: Internal 2011-02-21
• Gas properties
− Equation of state
• Gas composition
• Friction equation
− Internal roughness
• Transport specification
• Sales gas specifications
• Pressure Control System
− Pressure regulating
− Pressure safety
• Pig trap arrangement
− Pigging philosophy
• Pipeline valve philosophy• Future requirements
Pipeline system design – Design premises 3/3
-
8/17/2019 Design of Gas Transport Systems
29/46
TPG4140 – NATURGASSNTNU
29 - Classification: Internal 2011-02-21
• Double expanding gate
• Weight of valve: 80 tons (60 cars..)
• 10m high including activator:
• Total of 100 tons
Transport of 42” subsea pipeline
valve
-
8/17/2019 Design of Gas Transport Systems
30/46
TPG4140 – NATURGASSNTNU
30 - Classification: Internal 2011-02-21
• Ensure interoperability /interchangeability (WI)
• Ensure unproblematic transport of gas
−Max/min temperature and pressure
• Prevent corrosion and erosion of equipment
− Water, CO2, H2S content
• Prevent condensation of liquid (HC dew point)
• Prevent gas hydrates (Water dew point)
Why gas quality specifications?
Hydrocarbon dew-point (-3 C, 69 barg)
Water dew-point (-12 C, 69 barg)
CO2 content (max 2.5 % mol)H2S content (5 mg/Nm3)
GCV (Gross calorific value)
Wobbe index (WI)Max/min pressure and temperature
-
8/17/2019 Design of Gas Transport Systems
31/46
-
8/17/2019 Design of Gas Transport Systems
32/46
32 - Classification: Internal 2011-02-21
System design of multiphase pipelines
-
8/17/2019 Design of Gas Transport Systems
33/46
TPG4140 – NATURGASSNTNU
33 - Classification: Internal 2011-02-21
Technical feasibility – for how long can reservoir drive production to shore?
• Minimize pressure drop large pipe diameter
Operational acceptability – will system availability be high enough?
• Minimize liquid inventory in pipeline small pipe diameter
0
1000
2000
3000
4000
5000
6000
7000
8000
24 26 28 30 32 34Gas rate (MSm3/d)
L
i q u i d c o n t e n t ( m
3 )
Designrate
20
30
40
50
20 22 24 26 28 30 32 34
Gas rate (MSm3/d)
P
r e s s u r e d r o p ( b a
r a )
LargeID
SmallID
Designrate
SmallID
Large
ID
The diameter dilemma of long gas-condensate
pipelines
-
8/17/2019 Design of Gas Transport Systems
34/46
TPG4140 – NATURGASSNTNU
34 - Classification: Internal 2011-02-21
Pipeline diameter: small
• Minimize liquid inventory
Accept moderate/high pressure drop
Slug-catcher size set by:
• Rate increase:From maximum turndown to designrate
• Pigging
Liquid inventory prior to pigging
20
30
40
50
20 22 24 26 28 30 32 34
Gas rate (MSm3/d)
P r e s s u r e d r o p ( b a r a )
Design pressuredrop
Designrate
Maximumturndown
0
1000
2000
3000
4000
5000
60007000
8000
24 26 28 30 32 34Gas rate (MSm3/d)
L i q u i d c o n t e n t ( m 3 )
Design
rate
Steady state
liquid contentMaximumturndown
S l u g - c a t c
h e r
v o l u m e
Troll slug-catcher
Conventional design of gas-condensate pipelines
-
8/17/2019 Design of Gas Transport Systems
35/46
TPG4140 – NATURGASSNTNU
35 - Classification: Internal 2011-02-21
Pipeline diameter: large
• Minimize pressure drop
Accept relatively large liquid inventory
• If possible, alleviate liquid load
Multi-diameter pipelines/dual lines
• Exploit pipeline’s slow response to transients
Operational procedures
Slug-catcher design
• Exploit pipeline’s slow response to transients
Reduce slug-catcher size
• Onshore reception system routes liquid to
off-spec tank
Optimise slug-catcher design
Liquid flow into slug-catcher
0 2 4 6 8 10 12 14Time (days)
300
200
100
0 V o l u m e
r a t e ( m 3 / h )
20
30
40
50
20 22 24 26 28 30 32 34
Gas rate (MSm3/d)
P r e s s u
r e d r o p ( b a r a )
LargeID
SmallID
New design of gas-condensate pipelines
-
8/17/2019 Design of Gas Transport Systems
36/46
36 - Classification: Internal 2011-02-21
Pipeline integrity and leak detection
Deepwater horizon
-
8/17/2019 Design of Gas Transport Systems
37/46
TPG4140 – NATURGASSNTNU
37 - Classification: Internal 2011-02-21
Pipeline integrity and leak detection
Robust
design
Safe
operation
Emergency
response
Integrity
management
Leak
detection
Probability reduction Consequence reduction
-
8/17/2019 Design of Gas Transport Systems
38/46
TPG4140 – NATURGASSNTNU
38 - Classification: Internal 2011-02-21
PPS and PPC
-
8/17/2019 Design of Gas Transport Systems
39/46
TPG4140 – NATURGASSNTNU
39 - Classification: Internal 2011-02-21
Allocations of risk reducing measures
Frequency of
overpressure
Frequency of
overpressure
Without risk reduction
Acceptable risk
(Frequency of
overpressure )
1 times pr year1x10 -5
Achieved freq of
overpressure
Required risk reduction
Achieved risk reduction from safety functions
PPS -2 PPS -1 PPCManuel
actions
•Facilities regulation §33•ISO 10418 (API 14 C)
•IEC 61508
•IEC 61511
Actual risk reduction
PPC: Independent of the PSS
PPS: Two independent systems activated at different pressure levels, and
with a redundant and fail safe instrumentation and signal transfer system
Risk reduction
-
8/17/2019 Design of Gas Transport Systems
40/46
TPG4140 – NATURGASSNTNU
40 - Classification: Internal 2011-02-21
Shut down of receiving facility
Kollsnes export is stopped 0.5 hour later 44" Den Helder. SOP at 2% Opflex. October
90
100
110
120
130
140
150
160
170
180
190
200
210
0 100 200 300 400 500 600 700 800 900
Distance, km
P r e s s u r e
, b a r g
0 2 4 6 8 10 12 14 16 18Time, hrs
203 barg (+10m)
156.8 barg (+10m)
Den Helder
Kollsnes
Norwegiansector
Danishsector Germansector Dutchsector
-
8/17/2019 Design of Gas Transport Systems
41/46
TPG4140 – NATURGASSNTNU
41 - Classification: Internal 2011-02-21
Normal pressure profile
Low utilisation of pipe material
PD
Upstream end Downstream end
Normal Design
Settle out pressure
Normal pressure profile
PD2
PD1
PD3
Multi Design Pressure
• The settle out pressure in a “normal” shut-in situation shall not exceed the lower design
pressure
• The pipeline hydraulics during normal, upset and packing conditions are analysed to
demonstrate that the pressure control and pressure protection system will act satisfactory
• Cost saving material
Multi design pressure concept
-
8/17/2019 Design of Gas Transport Systems
42/46
TPG4140 – NATURGASSNTNU
42 - Classification: Internal 2011-02-21
EV
PPS-1 PPS-2
PT PT
Pipeline
EV
Upstream
Plant
Downstream
Plant
PT PT
PPS-1 PPS-2
Triple redundant
Fiberoptic and
telemetry
EVEVEV
PPS-1 PPS-2PPS-1 PPS-2
PT PTPT PTPTPT PTPT
Pipeline
EV
Upstream
Plant
Downstream
Plant
PT PTPT PTPTPT PTPT
PPS-1 PPS-2PPS-1 PPS-2
Triple redundant
Fiberoptic and
telemetry
Pipeline pressure protection
-
8/17/2019 Design of Gas Transport Systems
43/46
TPG4140 – NATURGASSNTNU
43 - Classification: Internal 2011-02-21
Pipeline integrity and leak detection
Robust
design
Safe
operation
Emergency
response
Integrity
management
Leak
detection
Probability reduction Consequence reduction
need
protecting
what?
pipeline or
zone? sensitivity
robustness
reliability
technology
solution
mass balance
pressure loss
point sensor
acoustic
-
8/17/2019 Design of Gas Transport Systems
44/46
TPG4140 – NATURGASSNTNU
44 - Classification: Internal 2011-02-21
The risk picture…
Probability
Consequence
Acceptable risk, but extrabarriers?
30” Kvitebjørn gas pipeline damage and leak, 2007
-
8/17/2019 Design of Gas Transport Systems
45/46
TPG4140 – NATURGASSNTNU
45 - Classification: Internal 2011-02-21
• Complexity of field architecture development
• Parameters influencing pipeline infrastructure development
• Pipeline design premises
• How the hydraulic of the pipeline system influence pipeline design
• Pressure protection and leak detection of pipeline systems
Key learning points
-
8/17/2019 Design of Gas Transport Systems
46/46