design-refinery.pdf

Upload: djilnef

Post on 09-Oct-2015

15 views

Category:

Documents


0 download

TRANSCRIPT

  • Mid & Downstream Business Training

    ModuleHYDROCARBON PROCESSING AN OVERVIEW

    LNG

    PRO

    DU

    CED

    WA

    TER

    GA

    S

    Upstream Mid and Downstream

  • Mid & Downstream Business Training

    Module

    Plant Design Cycle

    DetailEngg.

    Pre-Commissioning& Commissioning

    Feasibility Study

    Process Design /Basic Engg.

    FEEDStable Operation& Performance

    Testing

    Trouble Shooting& Revamp

  • Mid & Downstream Business Training

    ModuleFeasibility Study: Conceptualization

    Process Simulation

    Development of Process Flow Scheme

    Cost Estimation

    Techno-Commercial Evaluation

    Basic Engineering:

    Mass and Energy Balance

    Process Control Scheme

    PFDs and Basic Process P&IDs

    Sizing and Basic Spec. for Equipments and Instruments

  • Mid & Downstream Business Training

    ModuleFront End Engineering Design (FEED):

    BEP to Project Specific Package (Residual Engineering)

    Verification of Process data for Critical items

    Preparation of Specifications

    Identification of Scope Splits

    Identification of applicable Codes & Standards

    Commissioning:

    Pre-Commissioning

    Commissioning

    Startup and Feed charging

    Performance Guarantee test run

  • Mid & Downstream Business Training

    Module

  • Mid & Downstream Business Training

    ModuleWORK FLOW DIAGRAM

    PP

    CV

    EL

    ME

    EQ

    IN

    PEBDEP BDEP

    TQTQ

    EQUIPMENT LIST

    EQUIPMENT LIST

    EQUIPMENT LIST

    EQUIPMENT LIST

    EQUIPMENT LIST

    EQ. LIST EQ. LISTUHD UHD

    UHD

    UHD

    UHD

    UHD

    UHD

    UTILITYSUMMARY

    UTILITYSUMMARY

    FLARE LOAD SUMMARY

    FLARE LOAD SUMMARY

    PROCESS D/S FOREQUIPMENTS

    PROCESS D/S FOREQUIPMENTS

    PROCESS D/S FOREQUIPMENTS

    CHEMICALSUMMARY

    CHEMICALSUMMARY

    LINE LIST LINE LIST

    LINE LIST

    REVISED P&ID REVISED P&ID

    REVISED P&ID

    REVISED P&ID

    REVISED P&ID

    REVISED P&ID

    REVISED P&ID

    UPDATED D/S FOREQUIPMENTS

    UPDATED D/S FOREQUIPMENTS

    PROCESS D/S FORMACHINERY ITEMS

    UPDATED D/S FORINSTRUMENTS

    UPDATED D/S FORINSTRUMENTS

    UPDATED D/S FORINSTRUMENTS

    PRECOMMISIONINGMANUAL

    PRECOMMISIONINGMANUAL

    OPERATINGMANUAL

    OPERATINGMANUAL

    PROCESS D/S FOREQUIPMENTS

    HAZARDOUSSOURCE LIST

    HAZARDOUSSOURCE LIST

    HAZARDOUSSOURCE LIST

    PLOT PLANREVIEW & COMMENTS

    VENDOR DOCUMENTSREVIEW & COMMENTS

    FABRICATION DWG.REVIEW & COMMENTS

    PC

    EQUIPMENT LIST

    LINE LIST

  • Mid & Downstream Business Training

    ModuleREVIEW STAGE:

    Review of Contract Documents

    Preparation of TQs

  • Mid & Downstream Business Training

    ModuleSTAGE 0:

    P&IDs mark up based on General Specifications, Standards, Amendments etc.

    Updation of Process Datasheets based on PFD and other

    documents

    Preparation of UHDs

    Sizing of Utility lines

    Preparation of Equipment list

    Preparation of Utility summary

    Preparation of Catalyst and Chemical summary

    Preparation of Tie-in summary

    Preparation of Line-list

    Preparation of Hazardous source list

  • Mid & Downstream Business Training

    Module P&IDs mark up based on General Specifications, Standards, Amendments etc.

    Licensor P&ID

    Standard Details

  • Mid & Downstream Business Training

    Module

    Marked up P&ID

    As per the standards, the control valve assembly with block & bypass and Vent & Drain arrangement is shown in detail

  • Mid & Downstream Business Training

    Module Updation of Process Datasheets based on PFD and other documents

  • Mid & Downstream Business Training

    ModuleUpdated Process Datasheets

  • Mid & Downstream Business Training

    Module Preparation of UHDs

  • Mid & Downstream Business Training

    Module Sizing of Utility lines

  • Mid & Downstream Business Training

    Module Preparation of Equipment List

    MUMBAI

    EQUIPMENT SERVICE NO. DIMENSIONS INTERNAL EQUIPMENT ERECTION DESIGN CONDITION INSULATIONNO. REQD. (ID).X(TL-TL) TYPE THICKNESS WEIGHT PRESSURE TEMP. TYPE THICKNESS

    (m) (mm) (Tons) (kg/cm2g) (C) (mm)TOP BOTTOM TOP BOTTOM

    COLUMNSLNHT UNIT

    Top = 2.0Bott om = 2.8TL-TL = 27.9

    Top = 3.2Bott om = 4.0TL-TL = 36.9

    PENEX UNITTop =1.7

    Bott om = 3.2TL-TL=26.2

    TITLE : EQUIPMENT LISTOPERATING CONDITIONMOC + C.A

    PRESSURE (kg/cm2g)

    TEMP(C)SHELL &

    HEAD TRAYS

    125IH171 Int : 15.82Ext : FV91--DA-31701 STRIPPER KCS + 3 mm TP 4101Trays, DistributorInternal baff les, Vortex Breaker,

    DA-31702 DEPENTANIZER KCS + 3 mm TP 4101Trays, DistributorInternal baff les, Vortex Breaker,

    - - 70 119

    STABILIZERDA-32810

    DA-32811 LPG STRIPPER

    57 179

    1

    1 KCS+3mm TP 410 - -

    -TP 410CS+3mm

    Int : 4Ext : FV

    Int : 13.5Ext : FV

    Int : 13.5Ext : FV

    232171

    IH

    80

    12060

    210179

    147119

    120

    - -

    Trays, DistributorInternal baff les, Vortex Breaker,

    Trays, DistributorInternal baff les, Vortex Breaker,

    - 45 60

    ISOMERISATION PROJECT

    0.75 x 21

    IH

    Equipment list

  • Mid & Downstream Business Training

    Module

    Equipment List contains the information such as

    Equipment Number

    Service

    Dimensions

    Internals

    Material of Construction

    Operating and Design Conditions

    Insulation Details

    Other Special requirements

    Preparation of Equipment List (Continued)

  • Mid & Downstream Business Training

    ModuleSample view of Equipment list

    MUMBAI

    EQUIPMENT SERVICE NO. DIMENSIONS INTERNAL EQUIPMENT ERECTION DESIGN CONDITION INSULATIONNO. REQD. (ID).X(TL-TL) TYPE THICKNESS WEIGHT PRESSURE TEMP. TYPE THICKNESS

    (m) (mm) (Tons) (kg/cm2g) (C) (mm)TOP BOTTOM TOP BOTTOM

    COLUMNSLNHT UNIT

    Top = 2.0Bottom = 2.8TL-TL = 27.9

    Top = 3.2Bottom = 4.0TL-TL = 36.9

    PENEX UNITTop =1.7

    Bottom = 3.2TL-TL=26.2

    TITLE : EQUIPMENT LISTOPERATING CONDITIONMOC + C.A

    PRESSURE (kg/cm2g)

    TEMP(C)SHELL &

    HEAD TRAYS

    125IH171Int : 15.82Ext : FV91--DA-31701 STRIPPER KCS + 3 mm TP 4101

    Trays, DistributorInternal baff les, Vortex Breaker,

    DA-31702 DEPENTANIZER KCS + 3 mm TP 4101Trays, DistributorInternal baff les, Vortex Breaker,

    - - 70 119

    STABILIZERDA-32810

    DA-32811 LPG STRIPPER

    57 179

    1

    1 KCS+3mm TP 410 - -

    -TP 410CS+3mm

    Int : 4Ext : FV

    Int : 13.5Ext : FV

    Int : 13.5Ext : FV

    232171

    IH

    80

    12060

    210179

    147119

    120

    - -

    Trays, DistributorInternal baff les, Vortex Breaker,

    Trays, DistributorInternal baff les, Vortex Breaker,

    - 45 60

    ISOMERISATION PROJECT

    0.75 x 21

    IH

  • Mid & Downstream Business Training

    Module Preparation of Utility summary

    Utility Summary summarizes the consumption / generation of utilities in

    all equipments.

    The utility data for consumption to be furnished with - ve value.

    Similarly the utility data for generation to be furnished with +ve value.

    Following are the Utilities taken into account

    Electricity

    Steam

    Condensate

    Boiler Feed Water

    Cooling Water

    Service Water and Portable Water

    Instrument Air, Plant Air and Nitrogen

    Fuel Gas and Fuel Oil

  • Mid & Downstream Business Training

    ModuleSample View of Utility summary

  • Mid & Downstream Business Training

    Module Preparation of Chemical summary

    TITLE : CHEMICAL SUMMARY Rev.: 0

    1 -- 3200 kg MRPL

    2 20% Wt 6.5 m3 MRPL

    3 100% 200 kg MRPL

    4 100% 20 kg MRPL

    5 99.9 % Min. 30 m3 MRPL

    6 -- 2500 kg MRPL

    7 20% Wt 25 m3 MRPL

    8 -- 350 kg MRPL

    Sodium Nitrate (NaNO3)

    Make-up Caustic (NaOH) for Penex unit

    Anhydrous Ammonia

    L&T-CHIYODA LIMITED BARODA, INDIADocument No.: A-317-4012

    ISOMERISATION PROJECT

    Required as corrosion inhibitor for LNHT unit

    First fill quantity required

    Scope of supply

    Chemical Identification

    Required for scrubbing of gases from stabiliser & during catalyst regeneration of naphta hydrotreating reactor.

    As a sulfiding agent during stat-up

    % Purity Chemical Service

    Required during initial start up.Anhydrous Hydrochloric Acid (HCl)

    Sr. No.

    For preparing neutralizing solution during regeneration

    For preparing neutralizing solution during regeneration

    As a promotor for penex reactor catalyst

    Required to neutraiize reactor effluent gases

    Perchloroethylene (C2Cl4)

    DMDS

    Caustic for LNHT reactor neutralisation

    Soda Ash (Na2CO3)

    This document summarizes the consumption of Chemicals for the process.

  • Mid & Downstream Business Training

    Module Preparation of Catalyst summary

    TITLE : CATALYST SUMMARY

    Bed (m3)

    Contingency 5% (m3)

    2500

    3200

    9240

    2900 9240

    UOP---- Sock 3.62

    2600 930

    11.2520 Sock2480

    6.62Sock

    UOP

    6.8--

    7 FA-32801A Puraspec 20201200Zinc oxide treater

    ADS-11

    UOP "H-8" Catalyst

    FA-32802 1800

    DC-32801

    Reactor

    Saturation Reactor

    Sulfur guard bed

    24003

    2

    1

    Equip. Tag No.Sr.No.

    Catalyst

    SockUOP "S-12" Catalyst 1065DC-31701 UOP

    Service Equip ID (mm) Bed Height (mm)

    Bulk Density(Kg /m 3)

    Type Type of Loading

    4 DC-32810 Puraspec 24431100Methanator Reactor Sock7160 UOP0.34 7.14 --

    5 DC-32811 UOP "I-8" Catalyst2900 882 Dense 61 UOP

    6 DC-32812 UOP "I-8" Catalyst 61 UOP

    3720

    Manufacturer

    19.215

    QuantityTotal

    quantity (m3)

    0.91518.3

    0.56 11.76

    UOP0.331 6.951 6464.4

    Total quantity

    (kg)

    20464.0

    64.05

    64.05

    Penex Reactor

    Penex Reactor

    3.05

    3.05882 Dense

    0.181 3.801

    6115.2

    56492.1

    56492.1

    This document summarizes the consumption of Catalyst for the process.

  • Mid & Downstream Business Training

    Module Preparation of Tie-in summary

    Battery Limit Tie-in Summary contains the following information for all ISBL & OSBL lines

    Flow rate of all process and utility streams going to B/L.

    Operating and Design Conditions

    Line Specifications

    Main Properties of the Streams (Optional)

  • Mid & Downstream Business Training

    ModuleSample view of Tie-in summary

    Sr. Stream Name From To Phase FlowratesNo. L/V/M Tons/hr kg/m3 (L) Visc.

    Normal MW (V) cP Pressure Temperature Pressurekg/cm2 g deg C kg/cm2 gmin/nor/max min/nor/max

    (C) INCOMING UTILITY LINES:

    1 MP Steam B/L HEADER V 36066.0 18.0 0.02 14/15/16 255/260/270 22

    2 LP Steam B/L HEADER V 33180.0 18.0 0.02 3/3.5/4 160/175/200 10

    3 HP Steam B/L HEADER V 2930.0 18.0 0.01 39/40/41 330/390/408 45

    4 Instrument Air B/L HEADER V 625.0 29.0 0.02 4.5/6.5/ - - /40/ - 10.5

    5 Cooling Water Supply B/L HEADER L 2378207.0 1000.0 0.60 - /4.5/ - - /33/ - 7

    6 Fuel Gas B/L HEADER V 1212.0 15.5 0.01 - /4.5/5 - /40/ - 6

    7 Fuel Oil B/L HEADER L 2273.0 854.0 11.50 - /13/20 - /170/ - 25

    TITLE : BATTERY LIMIT TIE-IN SUMMARY

    MUMBAI

    PropertiesOperating Conditions Design Conditions

    ISBL

  • Mid & Downstream Business Training

    Module Preparation of Line-list Line List contains the data related to process conditions

    and the data related to mechanical design and test conditions for all the lines.

    Line List is the base document utilized for verification of major deliverables of Piping department.

    Line List contains the information such as

    Line Number Line Size

    Fluid Code and Piping class

    From & To Location

    State and Nature of the fluid

    Operating (Normal&Alternative) and Design Conditions

    Steam out requirements Insulation Details Test fluid and Test pressure

  • Mid & Downstream Business Training

    ModuleSample View of Line-list

    TITLE : LINE LIST FOR LNHT UNIT

    IDENTIFICATION LOCATION STATE OPERATING (A)

    (L/V/M)

    1 10-P-3170001-A1A1 606 10 P 317 0001 A1A1 FA-31701 P-3170215 L HC

    2 6-P-3170002-A4A1 606 6 P 317 0002 A4A1 GA-31701A P-3170046 L HC

    3 10-P-3170003-A1A1 606 10 P 317 0003 A1A1 P-3170001 P-3170216 L HC

    4 6-P-3170004-A4A1 606 6 P 317 0004 A4A1 GA-31701B P-3170002 L HC

    5 0.75-P-3170005-A1A1 691 0.75 P 317 0005 A1A1 P-3170002 SN-31701 L HC

    6 0.75-P-3170006-A1A 691 0.75 P 317 0006 A1A SN-31701 FLARE L HC

    7 0.75-P-3170007-A4A1 691 0.75 P 317 0007 A4A1 SN-31701 P-3170001 L HC

    8 6-P-3170008-A4A1 606 6 P 317 0008 A4A1 P-3170002 FV-002 L HC

    9 6-P-3170009-A1A1 606 6 P 317 0009 A1A1 FV-002 FA-31701 L HC

    LINE NO. FROM TONATURE

    OFFLUID

    INSU

    LATI

    ON

    TYPE

    INSU

    LATI

    ON

    THK

    . (M

    M)

    SR. NO.

    P &

    ID N

    O.

    SIZE

    (INCH

    )

    FLU

    ID C

    OD

    E

    UNIT

    NO

    .

    LIN

    E N

    O.

    PIPI

    NG

    CLA

    SS

    MUMBAI

  • Mid & Downstream Business Training

    Module Preparation of Hazardous Source List

    Hazardous Source List is the base document utilized for hazardous area classification drawing deliverable of Electrical department.

    This document contains the information such as

    Inlet and Outlet streams of all equipments State and Nature of the fluid Composition

    Max. operating temperature

    Properties like Density and Molecular weight

    Flammability

    Flash point Auto-ignition temperature

  • Mid & Downstream Business Training

    ModuleSample View of Hazardous Source List

  • Mid & Downstream Business Training

    ModuleSTAGE 1:

    Hydraulic Check of Process lines

    Sizing of Vessels

    Thermal rating of Heat exchangers

    PSV Sizing & Flare hydraulics

    Preparation of Flare Load Summary

    Preparation of Equipment datasheets for new items

    Scope demarcation for Vendor items

    Updation of P&IDs based on Hydraulic results

  • Mid & Downstream Business Training

    ModuleSTAGE 1 (Continued):

    Updation of Pumps and Instruments datasheets based on Hydraulics

    Updation of Equipment list

    Development of Control and Safeguarding Narratives

  • Mid & Downstream Business Training

    Module Hydraulic Check of Process linesLoop identification in PFD

  • Mid & Downstream Business Training

    Module Hydraulic Check of Process linesCollecting Inputs required for hydraulic calculations

  • Mid & Downstream Business Training

    ModuleSample View of Hydraulic Calculation Sheet

  • Mid & Downstream Business Training

    Module Sizing of Vessels

    Sizing of vessels is carried out based on Project

    Design Criteria (Droplet size, Residence time)

    Sometimes, Sizing is governed by separation of

    fine entrained droplets using mesh pad, impact

    separators, etc.

  • Mid & Downstream Business Training

    ModuleSample view of Vessel Sizing calculation sheet

  • Mid & Downstream Business Training

    Module Thermal rating of Heat exchangers

    Designing / Rating of heat exchangers is carried

    out with the help of HTRI computer program.

    This activity enables the designer to model heat

    exchangers, allowing the designer to gauge the

    performance, geometry and inherent limitations of

    the shell and tube heat exchanger even before its

    fabrication.

    This results in lower risks of damage to the

    equipment while in service.

  • Mid & Downstream Business Training

    ModuleSample HTRI Specification Sheet

    Sample HTRI Tube Layout

  • Mid & Downstream Business Training

    Module PSV Sizing and Flare Hydraulics

    The safety of personnel and the protection of equipments due to overpressure are the basis for the design, sizing, and selection of pressure relieving systems.

    All systems and pressure relief devices shall be

    designed based on the applicable codes (API 520,

    521, etc.), industry standards and practices.

    For Flare header Sizing, first we have to determine the appropriate relief contingencies yielding maximum loads

    Flare header size has to be large enough to prevent excessive backpressure on the plant safety valves and to limit gas velocity and noise to acceptable levels.

  • Mid & Downstream Business Training

    ModuleSample view of Flare Hydraulics calculation sheet

  • Mid & Downstream Business Training

    Module Preparation of Flare Load SummaryThis document summarizes the relief load of all PSVs for the applicable relieving cases.

  • Mid & Downstream Business Training

    Module Preparation of Equipment datasheets for new items

  • Mid & Downstream Business Training

    Module Scope demarcation for Vendor items

    Vendor scope of supply has to be identified and to be clearly marked in the P&IDs.

  • Mid & Downstream Business Training

    Module Updation of P&IDs based on Hydraulic results

    Licensor P&ID

  • Mid & Downstream Business Training

    Module Updated P&ID based on Hydraulics

    Compressor Suction line is increased to 6 from 4 as per hydraulic calculations

  • Mid & Downstream Business Training

    Module Updation of Pumps and Instruments datasheets based on Hydraulics

    Licensor Datasheet

  • Mid & Downstream Business Training

    ModuleUpdated Pumps datasheets based on Hydraulics

  • Mid & Downstream Business Training

    Module Development of Control Narratives

    This narrative describes the plant control systems by instrumentation.

    The purpose of this document are as follows :

    (1) To explain control systems to those who may not be familiar with instrumentation symbols or functional logic diagrams.

    (2) To define purpose and algorithm of each control system.

    Pump auto start systems will be also covered in this

    document.

  • Mid & Downstream Business Training

    Module Development of Safeguarding Narratives

    The purpose of this narrative is to thoroughly

    explain the safeguarding scheme and its

    significance. Based on the same it is possible to

    understand how safeguarding scheme works and

    how it will be depicted in Cause and Effect

    diagram or Safeguarding Matrix.

  • Mid & Downstream Business Training

    ModuleSample of Cause and Effect Diagram

    P-5105B HP STEAM VAL

    VE

    P-5105A HP BFW PUMP

    P-51203 HP BFW PUMP

    P-51402A MP BFW PUMP

    P-51206A HP BFW PUMP

    P-51206B HP BFW PUMP

    P-51206C HP BFW PUMP

    P-51206D HP BFW PUMP

    COMMON TRIP ALARM

    CAUSE CLOSE TRIP TRIP TRIP TRIP TRIP TRIP TRIP ALARM ACTION

    TAG NO. DESCRIPTION PEFS NO.

    51UZA-2103

    51UZA-2102

    51UZA-2104

    51UZA-2100

    51UZA-2105

    51UZA-2106

    51UZA-2107

    51UZA-2108

    51UZA-2100

    TAG NO.

    51LZA-2008 D-0098-51-25-0006 X X X X X 51LZA-2008

    51LZA-2011 D-1651-51-50-0018 X X X X X 51LZA-2011

    51LZA-2008 D-0098-51-25-0006 X X X X X X X X X 51LZA-2008

    51LZA-2011 D-1651-51-50-0018 51LZA-2011

    51LZA-2008 D-0098-51-25-0006 51LZA-2008

    51LZA-2011 D-1651-51-50-0018 X X X X X X X X X 51LZA-2011

    V-51203 LEVEL LOW LOW

    V-51210 LEVEL LOW LOW

    V-51203 LEVEL LOW LOW

    V-51210 LEVEL LOW LOW

    EFFECT 51UZA-2100 V-51203 / V-51201 SGS

    DESCRIPTION

    SAFE GUARDING MATRIX UNIT 51

    V-51210 LEVEL LOW LOW

    V-51203 LEVEL LOW LOW

    Cause Section

    Effect Section

  • Mid & Downstream Business Training

    ModuleSTAGE 2:

    Interface Activities

    Updation of Control & Safeguarding narratives and issue

    for HAZOP Study

    Updation of Utility summary

    Updation of Line list

  • Mid & Downstream Business Training

    Module Interface Activities

    Vendor Document Review

    Review of Engineering Drawings

    Review of Plot Plan

    3D-Model Review

    Review of DCS Graphics

  • Mid & Downstream Business Training

    Module Vendor Document Review

    Some of the Critical points to be reviewed in Engineering Drawings are:

    Consistency of Process data as per process datasheets such as Operating & Design Conditions, MOC, Special service requirements, etc.

    Review of other technical aspects

    (a) Meeting all Specifications as per requirement.

    (b) Expected Utility consumption figures.

    (c) Guarantee figures, if any.

    (d) Other technical requirements specified in the requisition.

    (e) Fulfilment of Scope of Supply.

  • Mid & Downstream Business Training

    Module Review of Engineering Drawings

    Some of the Critical points to be reviewed in Engineering Drawings are:

    Consistency of Process data as per process datasheets such as Operating & Design Conditions, MOC, Special service requirements, etc.

    Number of Nozzles

    Sizes of Nozzles

    Checking location and orientation of all nozzles

    especially nozzles for Temperature, Pressure and

    Level Instruments as per Project requirements

  • Mid & Downstream Business Training

    Module Review of Plot PlanSome of the Critical points to be reviewed in Plot plan are:

    Consistency of equipments shown in plot plan with Equipment List, PFD and P&IDs.

    Are the distances between equipment kept minimum with respect to pressure drop?

    Are the height of Towers and vessels enough to provide NPSH of pumps?

    Are the equipment located symmetrically such as column and reboilers?

    Is there enough space around columns, towers and reactors for removal of internals?

    Is there enough space to remove tube bundle of heat exchangers?

    Are the equipments arranged considering safety aspects especially for Fired heaters, Compressors and Tanks?

  • Mid & Downstream Business Training

    Module 3D-Model Review

    Some of the Critical points to be considered in 3D-model review are:

    Is piping arranged to provide straight run requirement such as inlet of tower?

    Are CV sets placed as per Project requirements such as closeness to equipment, at high or low level, etc., if

    any?

    Are symmetrical piping considered for AFCs?

    Are the valves located at operable location from the nearest platform or grade?

    Is piping arranged to keep special bending radius requirements, if any?

  • Mid & Downstream Business Training

    Module Review of DCS GraphicsReview of Control logics as per Control & Safeguarding narratives

  • Mid & Downstream Business Training

    ModuleSTAGE 2 (Continued):

    Updation of Control & Safeguarding narratives and issue

    for HAZOP Study

    Updation of Utility summary

    Updation of Line list

  • Mid & Downstream Business Training

    ModuleSTAGE 3:

    Safety Studies / Analysis

    Updation of P&IDs based on Safety Studies

    recommendation

    Preparation of Precommisioning manual

    Preparation of Operating manual

  • Mid & Downstream Business Training

    Module Safety Studies / Analysis

    HAZOP Study

    SIL Study

    FIREPRAN Study

  • Mid & Downstream Business Training

    Module

    HAZard and OPerability study is a technique to examine a

    system, part by part, in a very systematic manner, to find

    out the cause and consequence of every conceivable

    deviation in the normal operation of the system as well

    as during emergencies, start-ups and shutdowns. The

    method enables prediction of all possible ways in which a

    hazard or an operating problem could arise, whether the

    design takes preventive care of them and if not,

    recommends changes (Action) as may be necessary.

    HAZOP Study

  • Mid & Downstream Business Training

    ModuleSIL Measurement of confidence level for performance of safety function is called the Safety Integrity Level(SIL)

    Safety integrity of a system can be defined as The probability (likelihood) of a safety-related system

    performing the required safety function under all the stated conditions within a stated period of time

    SIL is a measure of the reliability of the safety function performing to specification.

    The SIL is based on the accepted risk level and ranges from 1 to 4

    Probability of Failure Safety

    Integrity Level (SIL)

    Mode of Operation On demand (average probability of failure to perform

    its design function upon demand)

    Mode of Operation continuous (probability of dangerous failure per

    hour) 4 > 10-5 to < 10-4 > 10-9 to < 10-8 3 > 10-4 to < 10-3 > 10-8 to < 10-7 2 > 10-3 to < 10-2 > 10-7 to < 10-6 1 > 10-2 to < 10-1 > 10-6 to < 10-7

  • Mid & Downstream Business Training

    Module FIREPRAN studyFIRE PRotection & ANalysis is a new technique employed at the design phase of a facility or installation to achieve the following objectives

    Overview the role of the facility and its significance to the overall operation.

    Review the facilitys Fire and Explosion Strategy (FES) in the context of the role of the facility and its significance to the overall company.

    Analyze threats to loss of containment or other potential sources of combustion events.

    Assess release event consequences and explosion scenarios

    Review and assess adequacy of threat control measures, mitigation and recovery measures.

    Make recommendation for risk reduction measures to achieve levels as low as reasonably practicable (ALARP).

  • Mid & Downstream Business Training

    ModuleExample for Firepran StudyColumn middle cut pool fire and isopleths is analyzed as shown below in case of possible explosion due to oil leakage above its Auto Ignition Temperature.

    Heat Flux kW/m2

    Effects on Human Effects on Property

    4

    Sufficient to cause pin to personnel if unable to reach cover within 20 seconds.

    No damage

    12.5

    This level of radiation will cause a 30% chance of fatality for a prolonged exposure.

    Minimum energy required for piloted ignition of wood, melting of plastic tubing

    37.5

    Sufficient to cause damage to process equipment. Exposure to this level of radiation is assumed to give rise to a 100% chance of fatality

    Failure of steel structures within 30 minutes

  • Mid & Downstream Business Training

    ModuleCritical Area identification

    Area in red needs to be given extensive consideration for fire protection systems

  • Mid & Downstream Business Training

    Module

    Updation of P&IDs based on Safety Studies

    recommendation

    Preparation of Precommisioning manual

    Preparation of Operating manual

    STAGE 3 (Continued):

  • Mid & Downstream Business Training

    Module

    Slide 1Slide 2Slide 3Slide 4Slide 5Slide 6Slide 7Slide 8Slide 9Slide 10Slide 11Slide 12Slide 13Slide 14Slide 15Slide 16Slide 17Slide 18Slide 19Slide 20Slide 21Slide 22Slide 23Slide 24Slide 25Slide 26Slide 27Slide 28Slide 29Slide 30Slide 31Slide 32Slide 33Slide 34Slide 35Slide 36Slide 37Slide 38Slide 39Slide 40Slide 41Slide 42Slide 43Slide 44Slide 45Slide 46Slide 47Slide 48Slide 49Slide 50Slide 51Slide 52Slide 53Slide 54Slide 55Slide 56Slide 57Slide 58Slide 59Slide 60Slide 61Slide 62Slide 63Slide 64Slide 65