detector decommissioning related activities at dØ george ginther fermilab and university of...

18
Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

Upload: cassandra-christina-watson

Post on 06-Jan-2018

214 views

Category:

Documents


0 download

DESCRIPTION

More Recent Events Blown fuse in ODH system closes valves on calorimeter during the early morning of Saturday 24 December LCW pumps off and system drained Disconnected solenoid and toroid power supplies Powered down Silicon Track Trigger Collision hall permit (intentionally) dropped –Transition to supervised access mode Configured detector to allow access to pump down vacuum jackets on liquid argon transfer lines Power down lumi system 3

TRANSCRIPT

Page 1: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

Detector Decommissioning Related Activities at DØ

George GintherFermilab and University of Rochester 23 January 2012

Page 2: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

Secure and StabilizeRecent Events

• Routine recording of cosmics ended before 0730 on Thursday 22 December

• Began warm-up of Silicon Microstrip Tracker – Raised chiller setpoint to 16C– Recording IV curves and monitoring annealing of Layer 0 sensors

• Ramped down muon chamber high voltages• Shutdown of muon chamber gas systems• Powered down Level 1 Calorimeter Trigger system• North dry engine failed during the early morning of

Friday 23 December– East dry engine not able to keep up with demand– Liquid helium inventory dwindling– Started warm-up of solenoid early to reduce demand on helium

2

Page 3: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

More Recent Events• Blown fuse in ODH system closes valves on

calorimeter during the early morning of Saturday 24 December

• LCW pumps off and system drained• Disconnected solenoid and toroid power supplies• Powered down Silicon Track Trigger• Collision hall permit (intentionally) dropped

– Transition to supervised access mode• Configured detector to allow access to pump down

vacuum jackets on liquid argon transfer lines• Power down lumi system

3

Page 4: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

Even More Recent Events• Ramped down calorimeter high voltages and terminated

calorimeter bias current monitoring• Transferred 11100 gallons for liquid argon to

underground storage tank• Recondensing residual argon as it evaporates from the

calorimeters• Drained liquid helium inventory• Shutdown liquid helium plant• Began warm-up of Visible Light Photon Counter cryostats

(readout for Central Fiber Tracker)– Turn off VLPC bias and temperature control

• Turned off VLPC cryostat lid heaters• Powered down Level 1 Muon and Central Track Trigger

systems4

Page 5: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

Next Steps• Start purge on VLPC cryostats

– Verify cold block above dewpoint– Extract a cassette from the east cryostat and install a blank

with purge inlet– Replace a blank on west cryostat with a blank equipped

with purge inlet• Power down Central Fiber Tracker readout• Power down Calorimeter readout

• Complete rad survey of collision hall to update postings

5

Page 6: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

As conditions (and resources) permit

• Power down rack infrastructure• Continue preparations of online computing cluster

for transition to offline cluster– Identify, backup and archive critical information

• Shut down silicon chiller and purge system• Drain Deionized Chilled Water detector systems and

purge• Decommission Trane Chiller• Secure halon fire suppression systems• Continue high bay preparations• Continue harvesting components for re-use• Continue preparations for basic exhibit

6

Page 7: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

Clean Out and Harvest• The mechanical crew is well into the process of

preparing the DØ Assembly Building high bay to accommodate MicroBooNE TPC assembly

7

Page 8: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

High Bay 22-Nov-2011

8

Page 9: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

High Bay 9-Dec-2011

9

Page 10: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

High Bay 19-Dec-2011

10

Page 11: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

High Bay 16-Jan-2012

11

Page 12: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

Preparing the Basic Exhibit• Cleared north sidewalk area and moved current

collection of artifacts into that area

• Next steps– Prepare for dismantling of concrete shield block wall

• Clear top of wall and dismount bus work as needed• Support helium cryo lines• Disconnect air handling units

– Take down much of concrete block wall– Install barriers to control access to collision hall– Configure detector for exhibit

• Move north toroid onto sidewalk and open west central iron and move north end calorimeter back to expose gap

– Aim to be ready with basic exhibit prior to Tevatron symposium in early June 2012

12

Page 13: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

13

Page 14: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

14

Page 15: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

15

Page 16: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

Detector Decommissioning Summary

• DØ successfully collected supporting data samples during the post-collider operations period

• The detector is in the process of warming, being stabilized and secured• Monitoring of SMT annealing in progress

• Making significant progress in preparing the Assembly Building to accommodate additional operations– High bay was ready for installation of MicroBooNE TPC assembly clean room

well in advance of the project’s required milestone• Anticipate resources will be sufficient to secure the detector and

provide the basic detector exhibit in 2012– Constraints generated by broader lab plans are being integrated into the

decommissioning effort may impact the schedule• This flexible plan should provide the opportunity to maximize the

productivity of the lab’s staff while ensuring that the DØ detector is put into a safe and secure state and transitions into a valuable educational exhibit

16

Page 17: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

DØ Mechanical Operations Team

Page 18: Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012

DØ Operations SupportTeams

PPD Electrical Engineering Department members Mike Cherry,

Victor Martinez, Tim Martin, Mike Matulik, and Bruce Merkel also provide essential support

Russ Rucinski

Pete Simon

Bob Barger

John Najdzion

Bob Kubinski

Mike Sarychev

Bryan Johnso

n

Pat Healey

Bill Frank