developing the power sector through private investment in mongolia
TRANSCRIPT
![Page 1: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/1.jpg)
Edgar Saravia
Program Manager
October 2008
Developing the
Power Sector
through Private
Investment in
Mongolia
![Page 2: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/2.jpg)
Setting the Context
Government of Mongolia (“GoM”) wishes to introduce PSP in
power generation
Benefits of PSP:
Introduce competition
Increase efficiencies
Improve reliability of electricity supply
Major form of PSP in power generation = design, construction
and capital financing for one or more new power generation
facilities under private initiative (“IPPs”)
Rationale: Alleviate existing and future electricity supply
constraints outside of state budget
![Page 3: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/3.jpg)
Agenda
Introduction to Public Private Partnerships (“PPPs”)
Best Practices in IPP Bidding
Introduction to Independent Power Projects (“IPPs”)
Project Agreements
Introduction to the International Finance Corporation
(“IFC”)
![Page 4: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/4.jpg)
Wo
rld
Ban
k
Gro
up
Multilateral Investment Guarantee Agency
The World Bank (IBRD & IDA)
International Centre for Settlement of
Investment Disputes
International Finance CorporationPrivate sector arm of the World Bank Group
![Page 5: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/5.jpg)
Lead advisor mostly to governments
Due diligence and structuring of infrastructure projects
Strategy definition for PSP-PPP
Marketing of business opportunities to selected investors
Transparent international competitive bidding
Acting as advisor to various governments to implement IPPs
through competitive bidding:
Current mandates include Vietnam, Indonesia, Philippines,
Bangladesh, Lebanon, Albania, Zambia
International Finance CorporationInfrastructure Advisory Services
![Page 6: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/6.jpg)
Agenda
Introduction to Public Private Partnerships (“PPPs”)
Best Practices in IPP Bidding
Introduction to Independent Power Projects (“IPPs”)
Project Agreements
Introduction to the International Finance Corporation
(“IFC”)
![Page 7: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/7.jpg)
What Are PPPs and How Are They
Different From Privatizations?
“PPP is a generic term for the relationships formed between
public bodies and the private sector with the aim of introducing
private sector resources and/or expertise to provide and deliver
public sector assets and services”
Public Private
Engagement Anywhere Along the Spectrum
Ultimate Goal: Ensuring Access to Reliable and Affordable
Basic Services
![Page 8: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/8.jpg)
Divestiture
Technical
Assistance
Service
Contract
Management
Contract
Lease
Contract
PPP
Concessions
3-5 yrs
8-15 yrs
1-3 yrs
25-30 yrs
State Risk
Private Sector
Risk
Options for Private Sector Participation
MOST EFFECTIVE
![Page 9: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/9.jpg)
Contrasting Public Sector Payment Profiles
of Traditional and PPP Procurement Models
Capital and operating costs are paid for
by the public sector, who take the risk of
cost overruns and late delivery.
The public sector only pays over the
long term as services are delivered. The
private sector funds itself using a large
portion of debt plus shareholder equity.
The returns on their equity will depend
on the quality of services.Source: PWC
![Page 10: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/10.jpg)
NAO Report UK’s National Audit Office report on PPP (2003)
Improved
Project
Delivery
Non PPP
Procurement (1999 Survey)
PPP
Procurement (2002 Survey)
Price
Overruns 73% 22% (mostly client
changes)
Time
Overruns 70% 24% (only 8% > 2
months)
![Page 11: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/11.jpg)
Key Benefits of PPPs
For the public sector:
Injection of private capital
Skills / know-how from the private sector result in higher quality of service
Optimized allocation of risks
Better management of public finance:
Government pays only when services are delivered
Budget certainty
More efficient use of public funds
Delivers value for money
For the private sector:
Attractive framework to enter or develop new markets
Attractive returns
Legal and financial guarantees from the Government
![Page 12: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/12.jpg)
Structuring PPPs - A Balancing Game
Private
Sector
Financial
Equilibrium
1
Appropriate
Framework
2Allocation
of Risks
4
Transparency
of Process
3
![Page 13: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/13.jpg)
Agenda
Introduction to Public Private Partnerships (“PPPs”)
Best Practices in IPP Bidding
Introduction to Independent Power Projects (“IPPs”)
Project Agreements
Introduction to the International Finance Corporation
(“IFC”)
![Page 14: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/14.jpg)
What Are IPPs?
IPPs are PPPs in the power generation sector
Private investors build and operate independent power plants
and supply electricity according to long-term power purchase
agreements (PPAs) – typically 15 to 30 years
Under the terms of a PPA, the project company typically agrees
on an exclusive basis to make available to the offtaker the
plant’s entire generating capacity and, to the extent dispatched
by the offtaker or the relevant transmission authority, supply
electricity up to the plant capacity
VERY DIFFERENT FROM A CONSTRUCTION CONTRACT
WITH GOVERNMENT AS OWNER
![Page 15: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/15.jpg)
Sustainable IPP Investments
Simple hypothesis
“Sustainable IPP investments depend on a balance between investment
and development outcomes”
___________________________
Investment outcome:
Adequate return on investment
Prospects for expanded investments
Development outcomes
Reliable power
Competitively priced power
Timely power
![Page 16: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/16.jpg)
Agenda
Introduction to Public Private Partnerships (“PPPs”)
Best Practices in IPP Bidding
Introduction to Independent Power Projects (“IPPs”)
Project Agreements
Introduction to the International Finance Corporation
(“IFC”)
![Page 17: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/17.jpg)
Best Practices in IPP Bidding
Two stage tender
Stage 1: Pre-qualification
Pre-qualification (PQ): to narrow down (ideally) 5-6 qualified sponsor /
consortium of sponsors
PQ on pass-fail basis based on objective and quantifiable criteria
Criteria to test financial strength, IPP development experience,
construction experience, O&M experience
Stage 2: Tender
Technical proposal – on pass-fail basis
Includes legal statement, bid bond, technical proposal, accepted final
project agreements (PPA, etc.)
Only those proposals that pass have their financial proposals opened
Financial proposal – single number, usually lowest levelized tariff wins
Occasionally PQ is merged with Tender by including qualification
criteria in the Technical Proposal
![Page 18: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/18.jpg)
Best Practices in IPP Bidding (cont.)
Advantages of this approach
Transparency and Objectivity
PQ criteria based on objective, quantifiable criteria – no room for
dispute
Pass-fail system in PQ ensures that all bidders have level playing
field and are equally qualified
Pass-fail system in Tender (technical proposal) ensures that there
are no deviations to the bid (difficult to evaluate)
Single number for evaluation of financial proposals – easy to
evaluate, no room for dispute
If project agreements/terms vary between bidders, not comparing
“apples to apples”
Most multilateral financial institutions look for transparent
competitive procurement when providing financing
![Page 19: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/19.jpg)
Best Practices in IPP Bidding (cont.)
Advantages of this approach (cont.)
Speed
Project agreements “pre-negotiated” with pre-qualified bidders
prior to bid
Bidders must accept final project agreements in tender with no
material deviations – minimizes post-bid negotiations and time to
PPA signing
Assurance
Bid security ensures that winning bidder has a high stake in
ensuring financial close
![Page 20: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/20.jpg)
Agenda
Introduction to Public Private Partnerships (“PPPs”)
Best Practices in IPP Bidding
Introduction to Independent Power Projects (“IPPs”)
Project Agreements
Introduction to the International Finance Corporation
(“IFC”)
![Page 21: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/21.jpg)
Best Practices in Project Agreements
Sponsors and lenders invest/lend to a project after close scrutiny of
project agreements
Power Purchase Agreement
Between winning bidder’s project company and offtaker
Sets out the rights and responsibilities of each party and allocation of
project risks
Risk allocation should be based on which party is best able to manage the
relevant risk and on market precedent
Eg. project company usually takes construction risk, financing risk,
operating risk and risk of “natural force majeure”. May also take
market risk and fuel supply and price risk depending on type of
contract
Eg. offtaker or Government usually takes political risk, FX risk. May
take market and fuel supply and price risk depending on type of
contract
Specifies default, termination events and consequence of termination
![Page 22: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/22.jpg)
Best Practices in Project Agreements
Power Purchase Agreement
PPA must specify tariff structure – typically two-part tariff
Capacity payment covering fixed costs of financing (debt and
equity) and fixed O&M costs
Energy payment covering fuel cost and variable O&M
If plant is not dispatched due to fault of offtaker/Government,
capacity payments must be made
Other agreements may include
Implementation Agreement between Gov and project company
where Gov assures an enabling environment
Gov guarantee of the offtaker’s payment obligations
The above are standard requirements for IPPs in IDA countries
May include a Land Lease Agreement, fuel supply agreement
![Page 23: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/23.jpg)
Energy Conversion Agreement
Two possible structures:
Energy Conversion Agreement (“ECA”)
• Power purchaser or off-taker (Gov entity) bears responsibility for
fuel supply to the power producer (including quantities, costs,
delivery and quality)
• Power producers agrees to convert fuel into electricity and deliver
power to purchaser
Power Purchase Agreement (“PPA”)
• Power producer responsible for fuel supply
• Power producer recovers fuels costs through tariff paid by power
of taker
ECA
Provides needed certainty to investors
Better financing/bankability perspective for lenders
![Page 24: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/24.jpg)
Market Reforms
We understand that GoM is planning to transition from Single
Buyer Model to Competitive Markets
Bidders/lenders will be concerned about weakening of take-or-
pay provision typical in PPAs
To satisfy bidder/lender concerns, typically
Retain take-or-pay levels in PPA – i.e., “grandfather” the PPA
since it would have been signed before the reforms and priced on
that basis (in un-tested markets)
Provide in the PPA that any restructuring would preserve equity
returns and debt service capability (still voluntary on part of
investor) AND provide that any successor offtaker obligations be
guaranteed
Provide for gradual lowering of take-or-pay provision (unlikely to be
accepted except in mature markets)
![Page 25: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/25.jpg)
Providing Credit Enhancement
Improve credit worthiness of offtaker
For IDA countries, state guarantee from Gov may not be sufficient
How to provide comfort to investors and lenders:
• Escrow account arrangements to cover payment risk
• Capital subsidies to the Project by using the grants and subsidized
loans available to GoM
• Partial financing by ECAs and multilaterals
• World Bank Partial Risk Guarantee (“PRG”) or similar guarantee to
cover residual termination risks
• MIGA Political Risk Insurance (“PRI”) to cover residual risks
Once track record is established (one or two successful IPPs with a stable
payment record), investors/lenders will become more comfortable and
need for guarantees may reduce for future projects
Guarantee and all other credit enhancements must also be “pre-
negotiated” with bidders
![Page 26: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/26.jpg)
The End
THANK YOU
![Page 27: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/27.jpg)
Key Challenges of PPPs
For the public sector:
Select the right partner (expertise, capacity, commitment etc)
Select the right structure (PPPs = wide variety of models)
Potential high procurement costs
Define the optimal risk allocation
Risks should be borne by the party that controls them
Project contracts are used as a means to mitigate these risks
Residual risks, such as political force majeure and regulatory risks, are mitigated through guarantees and insurance
Long term commitment
For the private sector:
Define the optimal risk allocation
Lack of protections to guarantee sufficient return on investment
Long term commitment
![Page 28: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/28.jpg)
Typical Risk Allocation
Risks
State: Operator:
Technical
Assistance
Market Risk
O & M
Invest. Renewal
New Assets
Financing: Access
Debt Service
Full
DivestitureConcessionManagement
& Services
Lease/
Affermage
![Page 29: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/29.jpg)
Cost covering tariff-
Actual tariff
Time
User Contribution
Trans. Subsidy
Time
User Contribution
Trans.
Subsidy
Subsidies
Time
Example: A Possible PPP Setup
Type of Subsidies
Capital Subsidies
Transition
Subsidies
Ongoing
Subsidies
(targeted poor
population)
![Page 30: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/30.jpg)
IFC deals only in private sector projects
IFC operates on a commercial basis.
It invests exclusively in for-profit projects, fully shares risks with
its partners, and charges market rates for its products and
services.
Products cover three broad areas:
• Financial products: IFC provides loans, equity finance,
quasi-equity and financial risk management products.
• Advisory services: IFC is the only multilateral which
provides advice and technical assistance to private
businesses and governments. Areas include
privatization, business-related public policy, and industry-
specific issues.
• Resource mobilization: IFC helps companies to tap into
international capital markets via syndicated loans.
IFC Products and Services
![Page 31: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/31.jpg)
IPP Investments Best Practices
Investment process
and support
1. Economic and political sustainability of the
investment enhanced by a competitive selection
process
2. Government responsive to needs and time frames of
investors
3. Presence of government guarantee of state-
enterprise performance and revenue sufficiency
4. Availability of limited recourse financing
Revenue factors 1. Cash flow sustainability: retail tariff levels and
collection discipline adequate to meet cash flow
needs of sector
2. Demand growth was in line with projects, no
oversupply or capacity utilization problems
![Page 32: Developing the Power Sector through Private Investment in Mongolia](https://reader035.vdocument.in/reader035/viewer/2022071601/613d4771736caf36b75b71b6/html5/thumbnails/32.jpg)
IPP Investments Best Practices (continued)
Operational factors 1. Public-private partnerships facilitated success of
investment
2. Ability to exercise effective management and
operational control of the investment
Regulatory factors 1. Regulatory commitment sustained through long-term
contract
2. Regulatory process allowed for satisfactory and non-
arbitrary adjudication of tariff adjustments and
dispute resolutions
Government
support and
performance
1. Government met all commitments of state-enterprise
performance and exchange conversion
2. Laws and contracts were enforced