development, installation and testing of an innovative ......development, installation and testing...

137
1 Development, Installation and Testing of an Innovative Epoxy Anchored Screw Pile Thesis submitted in fulfilment of the requirements for the degree of Masters of Engineering (by Research) by John George Agius (Student Number 491824x) Department of Civil Engineering Swinburne University, Hawthorn Campus, Melbourne, Australia 2015

Upload: others

Post on 24-Mar-2020

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

1

Development, Installation and Testing of an

Innovative Epoxy Anchored Screw Pile

Thesis submitted in fulfilment of the requirements for the degree

of

Masters of Engineering (by Research)

by

John George Agius

(Student Number 491824x)

Department of Civil Engineering

Swinburne University, Hawthorn Campus, Melbourne, Australia

2015

Page 2: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

2

Abstract This thesis details the development and the installation of a new application of

foundations for cable stays that can be used in areas where ground conditions

present good to very good rock under a layer of soil either clay or sand. The Epoxy

Anchored Screw Pile presented in this work make screw piles a viable stand-alone

option in all ground conditions including early refusal on rock through the addition

of an epoxied socket. The aim is to reduce the displacement at the head of the screw

pile with the addition of an epoxied socket. This was achieved through the

development of a practical installation methodology and full scale testing which is

documented in this thesis. The results from the testing show that the socket can

provide an increase in tensile capacity and reduce the displacement by a factor of up

to 20 at similar loads to that of a screw pile without the epoxy socket. The addition

of the epoxy socket required only hand tools and can be installed rapidly.

Page 3: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

3

Acknowledgements I would like to thank and am very grateful for the encouragement, support and

assistance from the following people:

James Murray-Parkes of Engineering Innovations Group who is the innovator

responsible for the concept detailed in this thesis as one of many of his new

innovations. James supported and fought for me tirelessly to help make this thesis

possible. He introduced me to many across the industry and has helped to support

me by providing employment opportunities and introducing me to his vast network

of friends and colleagues. I am indebted to him for his friendship, endless support

and all of the opportunities he has provided me. Without James my postgraduate

studies would not have been possible. He is a brilliant engineer and physicist and I

offer him my deepest thanks for all the hard work and assistance he has given.

Professor Jay Sanjayan of Swinburne University for helping to direct and guide me

in the completion of my master’s thesis. Jay has provided many thoughtful insights

and has helped to point me in the right direction to complete this thesis. Jay has been

very supportive during the completion of this thesis.

Michael Kennedy, Dene Ward and all staff involved in the Elaine Terminal Station

from Powercor Network Services, for providing a site and a funding for the

installation and testing for this thesis. I have been very lucky to be able to work for

both Mike and Dene who have helped with my development offering kind words of

support and encouragement. I would like to add a special thanks to Mike as he was a

big factor in my decision to pursue the completion of this thesis, as the project

Page 4: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

4

manager for the Elaine Terminal Station Mike put together a great project team and

helped make the project very enjoyable.

Peter Healy and Simon Hughes of Hollow Core Concrete who provided funding for

my scholarship and encouraged me to undertake and complete this thesis.

Darren Barnett and Trident Civil Group for providing advice and staff of the highest

quality to help with the installation and construction of the Epoxy Anchored Screw

Pile.

Stewart Nipperess and SFL Piletech who helped with the development of the Epoxy

Anchored Screw Pile, installed the screw piles and provided the testing equipment

for this thesis.

Frank Albrecht, Sivanerupan Sivagnanasundram and Robert Cornish of

Engineering Innovations Group for helping with technical advice and

supporting me to expand my knowledge in the field of civil engineering.

My fellow colleges and friends for their support and encouragement during the

completion of my thesis.

I would also like to thank my family and my girlfriend Tamara for the love,

encouragement and support that they have provided me.

Page 5: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

5

Declarations This thesis contains no material that has been accepted for the award of any other

degree or diploma at any university or other institution. To the best of my

knowledge the thesis contains no material previously published or written by

another person, except where due reference is made.

John George Agius

Page 6: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

6

Contents

1. Introduction ................................................................................................................................. 9

1.1. Preface ........................................................................................................................................ 9

1.1.1. Screw Piles ....................................................................................................................... 9

1.1.2. Rock Anchors ............................................................................................................... 11

1.1.3. Bonded Rock Bolts ...................................................................................................... 13

1.1.4. Bond Strength of Cemented Grouts ........................................................................ 17

1.1.5. Bonded Chemical Anchors in Concrete ................................................................ 21

1.1.6. Tension Piles .................................................................................................................. 24

1.1.7. Load Bearing Capacity Based on Settlement ....................................................... 26

1.1.8. Drill Types and Selection ............................................................................................. 29

1.1.9. Hoek-Brown Criterion .................................................................................................. 30

1.1.10. Rock Mass Classifications ........................................................................................... 32

1.1.11. Mohr-Coulomb Strength Criterion ............................................................................ 34

1.1.12. Deflection Limits of Transmission Poles ..................... Error! Bookmark not defined.

2. Existing Tension Foundation Systems ..................................................................................... 37

2.1. Dead Man Anchors .................................................................................................................. 37

2.2. Bored Concrete Piles ............................................................................................................... 39

2.3. Helical Screw Piles .................................................................................................................. 41

2.4. Rock Anchors .......................................................................................................................... 42

2.5. Summary of Cable Stay Foundation Suitability ....................................................................... 46

2.6. Outline ..................................................................................................................................... 47

3. Innovative Epoxy Anchored Screw Pile and Installation Methodology ............................... 48

Page 7: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

7

3.1. List of Material to be installed .................................................................................................. 51

3.2. Equipment needed for the Installation ...................................................................................... 55

3.3. Method ..................................................................................................................................... 58

3.3.1. Test Installation ............................................................................................................. 58

3.3.2. Epoxy Anchor Installation Method ........................................................................... 67

3.3.3. Issues Encountered During Anchor Installation ...................................................... 89

4. Test Details of the new Epoxy Anchored Screw Pile .............................................................. 94

5. Estimation of the load capacity of the Epoxy Anchored Screw Pile ................................... 101

5.1. Failure Mechanisms................................................................................................................ 101

5.2. Screw Pile ............................................................................................................................... 102

5.3. Epoxy Anchor Failure ............................................................................................................ 104

5.3.1. Slip Failure ................................................................................................................... 104

5.3.2. Cone Failure .............................................................................................................. 109

5.3.3. Steel Failure ................................................................................................................ 113

6. Test Results .............................................................................................................................. 115

6.1. Screw Pile Only ...................................................................................................................... 115

6.2. Epoxy Anchored Screw Pile ................................................................................................... 119

7. Conclusions .............................................................................................................................. 130

8. Recommendations ................................................................................................................... 133

9. References ................................................................................................................................ 134

Page 8: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

8

Page 9: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

9

1. Introduction

Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile

1.1. Preface

The first section of this thesis details the research done into anchors, piles, rock

mechanics and rock bolts. The development of the innovative Epoxy Anchored

Screw Pile presented in this thesis came from a combination of current research into

tension piles, screw piles and bonded anchors and was adapted to suit the varying

ground conditions that were seen on the Elaine Terminal Station Transmission Line

where no singular conventional foundation system was suitable and the innovative

Epoxy Anchored Screw Pile was tested and installed.

1.1.1. Screw Piles

Screw Piles (also known as Helical Piles) are a form of deep foundation that can

provide tensile, compressive and lateral resistance to a structure. They are very cost

effective foundations for structures, as they can be installed quickly and loaded

immediately. Screw piles are a form of replacement pile generally comprising of a

steel shaft and one or more helices (bearing plates) welded to the shaft at various

spacing. Screw piles can be installed quickly using an excavator with a rotary drive

motor. They do not require dewatering nor do they generate any spoil. Screw piles

can be installed in a range of materials from soft clays and loose sands to dense

clays or extremely weathered rock. However screw piles are currently not suitable in

areas with unweathered rock as the pile cannot penetrate through a layer of rock.

Page 10: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

10

Helix

Steel Tube

Figure 1-1 - Detail of Screw Pile

Page 11: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

11

1.1.2. Rock Anchors

Tomlinson and Woodward (2008) define rock anchors as tension piles that can be

used when the overburden pressure from the soil is insufficient to develop the

required uplift capacity. Rock anchors comprise of a bored hole with either a

mechanical or bonded anchor. Drilling in hard rock can be expensive and requires

specialised machine mounted drilling equipment. The resistance of a single rock

anchor is determined by 4 key factors

β€’ Safe working stress of the steel anchor

β€’ Bond stress between the steel and the grout or bonding material

β€’ Bond stress between the grout or bonding material and rock

β€’ The dead weight of the mass of rock that may be mobilised if the bond or

anchor does not fail and rock cone failure occurs

Rock anchors can be installed in areas where a sufficient layer of rock is present to

gain the required uplift capacity through the above mechanisms.

Page 12: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

12

Figure 1-1a - Installation of Rock Anchor

Page 13: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

13

1.1.3. Bonded Rock Bolts

There are several different publications that provide guidelines for depths of resin or

epoxy grouted rock anchors in different varieties of rock. Figures 1-2 and 1-3 are

based on the results of anchor tests provide a guideline for the design and

installation of grouted or resin grouted rock bolts. Figures 1-2 and1-3 show the

results of some of these tests. The results from Schroder and Swanson (1992) were

based on very weak rock found in the Southeast region of Alaska.

Figure 1-2 - Ultimate anchor capacity vs. depth (bond length) for grouted rock anchors.

(Schroder and Swanson 1992)

kips = 4.448 kN

inches = 25.4 mm

Page 14: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

14

Figure 1-3 - - Ultimate anchor capacity vs. depth (bond length) for grouted rock anchors in

different rock. (Schroder and Swanson 1992)

kips = 4.448 kN

inches = 25.4 mm

The above figure (Figure 1-3) shows the relationship between bond length and

anchorage strength for different varieties of rock from DYWIDAG-Systems

International Canada Ltd.

Littlejohn and Bruce (1977) discussed the relationship between cement grouts and

rock. They demonstrated that when slip failure of a rock bolting system occurs it

will do so at either the grout bar interface or the grout rock interface. They

determined that the maximum strength of the grout/rock interface should be a

function of the shear strength with an appropriate safety factor (not less than 2).

Page 15: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

15

However, this was said to apply mainly to β€˜soft rocks” with a UCS (Unconfined

Compressive Strength) less than 7 MPa. Littlejohn (1972) stated that the ultimate

bond strength in massive rocks (100% core recovery) should be 10% of their

uniaxial compressive strength up to a maximum of 4.2 MPa.

The shear strength can be found using the Mohr – Coulomb strength criterion as

long as the CS and internal friction angle are known. Littlejohn and Bruce (1977)

provided the following table and equation to calculate the ultimate shear strength

base on the Mohr-Coulomb Criterion.

Figure 1-4 - Relationship between shear stress and uniaxial compressive strength. (Littlejohn

and Bruce 1977)

Οƒ = axial stress; Ο„ = shear stress; Ο† = internal friction angle

Page 16: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

16

The bond strength at the rock/grout interface is, however, highly dependent on the

degree of weathering of the rock, with research of Saliman and Schaefer (1968)

showing the capacity of bond strengths in weathered rock is less than 0.1 MPa. This

makes geotechnical assessment and testing of each anchor location very important.

The assessment of the anchor location should be conducted during the drilling of

anchors to guarantee that the required bond strength will be achieved.

Page 17: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

17

1.1.4. Bond Strength of Cemented Grouts

Mechanics of load transfer between the anchor, grout and rock.

A tensile load is transferred through a steel bar bonded to rock using a grout or

epoxy. There is shear transfer between two interfaces including the rock / grout

interface or the steel / grout interface. Although the distribution of shear stress varies

depending on embedment depth and strength, simple linear models have been used

to calculate the ultimate bond strength of bonded anchors.

Aldorf and Exner (1986) used the following equation for the calculation of the

strength of grouted rock bolts:

𝑷 = 𝝅×𝒅×𝒍×π‘ͺπ’Œ

……………………………………………………………….Equation 1-1

𝑃 = Capacity

𝑑 = Diameter

𝑙 = Length

𝐢 = Bond Strength

π‘˜ = Reduction factor / Safety coefficient

Benmokrane et al. (1995) conducted a laboratory study on six different cement

based grouts and two different steel rock anchors to derive an empirical equation for

the estimation of anchor pull-out resistance.

The cementitious grouts used in the study were comprised of different combinations

of water, Portland cement, silica fume, aluminium powder, water, sand and

superplasticisers. The steel anchors used included a conventional 7 strand cable bolt

and a Dywidag threaded bar with a diameter of 15.8mm.

Page 18: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

18

Concrete samples used to emulate rock had a compressive strength of 60 MPa and a

modulus of elasticity of 30 GPa. . 38mm diameter holes were drilled using a

percussive rotary drill and varying embedment depths ranging from 7 to 20 bar

diameters.

Figures 1-5 and 1-6 from Benmokrane et al. (1995) of results from these tests show

that the superior mechanical interlock between the grout and anchor provided by the

Dywidag bar provided maximum average bond stress nearly three times greater to

that of the smooth 7 stranded cable.

Page 19: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

19

Figure 1-5 - Typical shear bond stress-slip relationship (Benmokrane et al. (1995))

Page 20: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

20

Figure 1-6 - Influence of anchored length on the load displacement behaviour.

(Benmokrane et al. (1995))

Page 21: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

21

As can be expected the relationship between anchor length (AL) and load

displacement behaviour is close to linear, with load displacement behaviour

increasing at the same rate as the increase in anchor length.

A Kilic et al. (2002) also tested the pull-out load of anchors (reinforcement bars)

bonded to basalt blocks using cement based grouts. The tests investigated the

relationship between bond strength vs. hole diameter as well as the effect of

increasing the embedment depth while hole diameter remained constant. The basalt

blocks used had a Young’s Modulus of 27.6 GPa and a UCS of 133 MPa. The

results exhibited mean bond strength of 7.73 MPa with a standard deviation of only

0.187 and all results showed a linear distribution dependant on bond area.

1.1.5. Bonded Chemical Anchors in Concrete

Failure of bonded anchor in concrete can occur in a variety of mechanisms (Cook et

al. (1998)) as shown in Figure 1-7 below.

Figure 1-7 - Failure methods of bonded anchors (Eligehausen et al. (2006))

Eligehausen et al. (2006) state that load displacement behaviour of single bonded

tension anchors is dependent on the stiffness and adhesion of the mortar. A well

selected mortar can result in elastic behaviour nearly to failure.

Page 22: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

22

Pull-out failure is dependent on the magnitude of the load, bond strength of the

mortar and the embedment depth. Failure can occur at the concrete/ mortar bond,

steel / mortar bond or a combination of the two. Spieth and Eligehausen (2002)

showed the drilling method and subsequent roughness at the interface between the

mortar and concrete can have a significant impact on the final bond strength.

Leftover dust or residue can also have an impact on the bond strength. Meszaros and

Eligenhausen (1998) showed that insufficient cleaning of holes can lead to a 40%

reduction in bond strength with the best cleaning method being a combination of

blowing with oil free pressurised air and brushing with a wire brush up to 3 times

each. Cook et al. (1994) tested 20 different mortar products showing results of 3

products under 10 MPa, 11 products between 10 and 20 MPa and 6 above 20 MPa,

concluding that epoxy product selection is a vital factor in final bond strength, and,

each product should be tested and treated differently.

Page 23: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

23

Figure 1-8 - Bond stress-displacement curves for different drilling methods. (Eligehausen et al.

(2006))

lv = embedment depth

ds = diameter

Page 24: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

24

1.1.6. Tension Piles

Vertical piles can be used to restrain uplift loads caused by swell from expansive

soils which can result in movement of between 50 mm and 100 mm, hydrostatic

pressures exceeding downward loads, structures subject to wind or overturning and

although not an issue in Australia expansion from frost can also cause uplift in piles.

Uplift is generally resisted by providing piles that are sufficiently long to withstand

all uplift forces with shaft skin friction where:

Uplift Resistance = Shaft Area x Bond Strength

Raked piles can also be used to resist uplift but are generally used when lateral

forces are also present such as thrust blocks or in conjunction with sheet piling

retaining walls with tie rods.

Failure in tension piles can occur in two modes:

1. The pull-out of the pile from the ground mass (Slip Failure)

2. Uplift of the ground containing the piles (Cone Failure)

Depending on the subsurface type the bond strength can be calculated in different

ways. O’Neil and Reese (1989) classify each subsurface into four different

classifications and give different methodologies for the design and calculation of the

bond strength between the pile and the geo-material.

The four classifications include:

Page 25: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

25

β€’ Cohesive soil [clays and plastic silts with undrained shear strength su≀0.25

MPa]

β€’ Granular soil [cohesionless geomaterial, such as sand, gravel or non-plastic

silt, with uncorrected SPT N values of 50 blows / 0.3m or less]

β€’ Intermediate geomaterial [cohesive geomaterial with undrained shear

strengths, between 0.25 MPa and 2.5 MPa (equivalent to unconfined

compression strength q, between 0.5 and 5.0 MPa); or cohesion less

geomaterials with SPT N values > 50 blows / 0.3 m]

β€’ Rock [highly cemented geomaterial with unconfined compression strength >

5.

Poulos and Davis (1980) and Tomlinson and Woodward (2008) give similar

equations for calculating the uplift capacity of piles in cohesive soils where:

𝑷𝒖 = π’Œ(𝝅 Γ— 𝒅 Γ— 𝒍 Γ— 𝜢π‘ͺ𝒖)………………………………………………………….Equation 1-2

𝑃𝑒 = Uplift Capacity

𝑑 = Pile diameter

𝑑 = Embedment depth

𝐢𝑒 = Undrained cohesion of soil

𝛼 = Adhesion factor for piles in clay (varies with clay stiffness)

π‘˜ = Reduction factor for uplift (varies with clay stiffness)

Page 26: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

26

1.1.7. Load Bearing Capacity Based on Settlement

Reese and O’Neil (1989) proposed a method for calculating load bearing capacity of

drilled piers based on settlement. The method was developed based on a database of

41 load tests of piles within the following ranges:

1. Shaft Diameter: d between 0.52 m to 1.2 m

2. Bell Depth: l between 4.7 to 30.5 m

3. Field standard penetration resistance N60 = 50 to 60

4. Concrete slump between 100mm to 225 mm

From this study Reese and O’Neil (1989) were able to develop the following plots

for normalised side load transfer for drilled shafts in cohesive and cohesionless soils

based on the settlement of the pile. Figures 1-9 and 1-9a show the relationship of

side friction based on settlement of the pile and can be used to find the ideal

allowable settlement for activation of skin friction.

Page 27: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

27

Figure 1-9 - Normalised side load transfer for drilled shafts in cohesive soil (Reese and O’Neil

(1989))

Page 28: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

28

Figure 1-9a - Normalised side load transfer for drilled shafts in cohesive soil (Reese and O’Neil

(1989))

Page 29: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

29

1.1.8. Drill Types and Selection

Littlejohn and Bruce (1977) give 6 criteria for the selection of drilling method.

i. The type and capacity of the anchor

ii. The nature of the rock and material mass

iii. The borehole surface roughness requirements

iv. The accessibility and topography of the site

v. The availability and suitability of the flushing medium

vi. The drilling rate

The application of the anchor and location will mean that several of the above

parameters will be predetermined or governed by the project application and

location. Given a specific project the main governing factors in anchor selection will

be a balance of time, cost and an associated level of risk.

The main drilling systems that are available include rotary, percussive and a

combination of rotary percussive drill bits. There are two types of rotary drill bit

available, drag drill bits and roller drill bits. The key difference between the two is

that a drag bit has no moving parts while a roller cone is made of a series of rolling

drill heads. The size, depth and rock type will have the greatest impact on drill

selection. Augers or drag bits are preferred in soft friable rock, percussive or

diamond drills for hole diameters less than 100 mm and rotary rollers for medium to

hard rocks 100-300 mm.

Page 30: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

30

1.1.9. Hoek-Brown Criterion

In 2007 Hoek published a history of the Hoek-Brown Criterion stating the failure

criterion was originally developed for the book Underground Excavations in Rock

for the design of underground excavations. (Hoek 2007) The relationship was

developed in an effort to provide engineering data on rock masses from geological

information. The equation was not unique however effort was taken to link

geological information and observations to Bieniawski’s Rock Mass Rating (RMR).

The criterion was first looking at hard rock assuming that rock mass failure was

governed by the translation and rotation of rock masses separated by jointed surfaces

and that the rock mass can be treated as isotropic. The criterion was to develop the

parameters that were currently being used in engineering practice in order to allow

for input and use in software.

The equation developed by Hoek and Brown used a modified RMR value assigning

a fixed value of 10 for the groundwater rating and setting the joint orientation at 0.

The equation did not take into account that highly jointed rock masses had a zero

tensile strength.

Page 31: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

31

Giving the following

Disturbed rock masses:

π’Žπ’ƒπ’Žπ’Š

= 𝐞𝐱𝐩 (π‘Ήπ‘΄π‘Ήβˆ’πŸπŸŽπŸŽ)πŸπŸ’

………………………………..………………….Equation 1-3

𝑠 = exp (π‘…π‘€π‘…βˆ’100)6

…………………………………………………….Equation 1-4

Undisturbed or interlocking rock masses:

π‘šπ‘π‘šπ‘–

= exp (π‘…π‘€π‘…βˆ’100)28

…………………………….…………………….Equation 1-5

𝑠 = exp (π‘…π‘€π‘…βˆ’100)9

…………………………….……...……………….Equation 1-6

𝐸 = 10((π‘…π‘€π‘…βˆ’100) 40)⁄ …………………….…….............……………….Equation 1-7

mb and mi are for broken and intact rock, respectively.

Page 32: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

32

1.1.10. Rock Mass Classifications

Different methods of classifying rock masses have been in development for over a

century. The methods have been derived using case studies from civil engineering

projects and are used to gain engineering properties from geological characteristics

of information. The system used for the Hoek-Brown Criterion is the Bieniawski

(1976) Geomechanical Classification more widely know as the Rock Mass Rating

(RMR). The system has been refined over time to the 1989 version. Both systems

use six key parameters to classify a rock and find a subsequent RMR.

β€’ UCS of the Rock

β€’ Rock Quality Designation (RQD)

β€’ Spacing of discontinuities

β€’ Condition of discontinuities

β€’ Groundwater

β€’ Orientation of discontinuities

Each of the parameters is presented in a table and based on these a RMR can be

defined for an area.

Page 33: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

33

Table 1-1 - Rock Mass Rating (after Bieniawski 1989)

Page 34: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

34

1.1.11. Mohr-Coulomb Strength Criterion

The Mohr–Coulomb Strength Criterion is a linear envelope using principal stresses

from Mohr’s circle to describe the conditions under which an isotropic rock will fail.

The Mohr–Coulomb Strength Criterion can be shown as a function of the major and

minor principal stresses and shear stress. Where all stresses are compressive it has

been shown that the criterion works well with rock. The Mohr-Coulomb Criterion

came from a combination of research and laboratory tests conducted separately by

both Mohr and Coulomb.

The shear strength of Mohr-Coulomb materials can be expressed in terms of the

cohesion of the material and the internal friction angle.

𝜏 = 𝑐 + πœŽβ€² tanπœ™β€¦β€¦β€¦β€¦β€¦β€¦β€¦β€¦β€¦β€¦β€¦.……...……………….Equation 1-8

Οƒ = total normal stress; Ο„ = shear strength; Ο† = effective internal friction angle c = effective cohesive strength

For a planar, clean fracture of intact rock the cohesion will be zero and the shear

strength will be determined solely by the friction angle Wylie (1992). The friction

angle will vary depending on the type of rock and site conditions. Wylie (1992)

categorises the rocks into 3 main groups including: Low friction rocks with a

friction angle between 20 to 27 degrees including schists, shale and marl. Medium

friction rocks with a friction angle between 27 to 34 degrees including sandstone,

siltstone, chalk, gneiss and slate. High friction rocks with a friction angle between

34 to 40 degrees including basalt, granite, limestone and conglomerates.

Page 35: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

35

Οƒ = total normal stress; Ο„ = shear strength; Ο† = effective internal friction angle c = effective cohesive strength

𝜏 = 𝑐 + πœŽβ€² tanπœ™

Figure 1-6 - Mohr-Coulomb Criterion

Page 36: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

36

1.1.12. Deflection Limits of Transmission Poles

Cable guys can be used to control deflection or movement of transmission poles. AS/NZS

7000: 2010 recommends that the maximum deflection of a pole at serviceability loads shall

be 5% of the poles height above ground and the β€œdeflection shall be limited to a value that

ensures the electrical clearances will not be infringed. This condition may also be used as an

upper limit for cracking criteria in pre-stressed concrete poles.

In most cases this make deflection not a critical factor but where there are line crossings

deflection can govern the required strength of the pole to maintain safe electrical clearances

including phase to phase and phase to ground with clearance distances ranging between

0.2m and 5.2m (Table 3.1 AS/NZS 7000: 2010.)

In areas where there are tight clearances controlling the displacement of guy foundations

can become important.

Figure 1-11 - Clearances for Unattached Crossing (AS/NZS 7000: 2010)

Page 37: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

37

2. Existing Tension Foundation Systems

There are many types of foundations available for anchoring tension cables

including:

β€’ Dead Man Anchors

β€’ Drilled Shaft Piles

β€’ Helical Piles

β€’ Rock Anchors

The above foundation options can provide sufficient load capacity to resist the

imposed uplift on a structure each with their own advantages and disadvantages.

The was on the Elaine Terminal Station Transmission Line was to find a

methodology that would be suitable in all locations as the geotechnical

investigations showed hard rock at varying depths from 1 m to over 7 m with poor

access in many of the locations. This made it problematic to find one solution that

would work at all stay locations.

2.1. Dead Man Anchors

Dead man anchors use mass of concrete or bed logs combined with bearing on

backfill or pure mass in excavated pits to resist uplift. Dead man anchors were

originally proposed for use as foundations for the cable stays on the Elaine Terminal

Station Transmission Line. The access conditions and areas with high rock would

have made the installation of dead man anchors at the stay locations very expensive

Page 38: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

38

and produced large amounts of waste and spoil that would have to be removed. At

some remote poles located near the edges of valleys the installation of dead man

anchors at the required angle would have been impossible. Using a unit weight of

concrete of 2400 kg/m3 a cable stay with a 200 kN load would require a mass of

concrete over 8 m3 and produced the same amount of spoil.

Concrete Dead Man Anchor

Figure 2-1 - Dead Man Anchor

Page 39: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

39

2.2. Bored Concrete Piles

Bored concrete piles use skin friction to resist uplift and can be calculated using

equations given by Poulos and Davis (1980) or Tomlinson and Woodward (2008).

Bored piles are replacement piles and create spoil that requires disposal as well as

access for concrete trucks and reinforcement delivery. While bored piles could have

provide the required capacity within acceptable deflection limits on the Elaine

Terminal Station Transmission Line limited access at many of the pole locations and

high rock in many of the areas would have made it an expensive process. To resist a

cable stay load of 200 kN in the clay experienced in the region using a Cu of 50 kPa

a 600mm bored pile would need to reach a depth of almost 5 m creating 1.5 m3 of

spoil and require the same quantity of 32 MPa concrete.

Page 40: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

40

Figure 2-2 - Axial Capacity of Bored Pile (Tomlinson, M and Woodward, J (2008))

Axial Capacity Calculation in Clay

𝑃𝑒 = π‘˜(πœ‹ Γ— 𝑑 Γ— 𝑙 Γ— 𝛼𝐢𝑒)………………………….……...……………….Equation

2-1

𝑃𝑒 = Uplift Capacity

𝑑 = Pile diameter

𝑑 = Embedment depth

𝐢𝑒 = Undrained cohesion of soil

𝛼 = Adhesion factor for piles in clay (varies with clay stiffness)

π‘˜ = Reduction factor for uplift (varies with clay stiffness)

Page 41: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

41

2.3. Helical Screw Piles

Helical screw piles use a combination of skin friction on the shaft and bearing

resistance from large helical plates welded to the shaft. Helical screw piles are

replacement piles and are installed using a rotary motor. The use of a rotary motor

attached to an excavator means they can be installed quickly and efficiently in areas

with poor access and that they produce no spoil. Screw piles however cannot

penetrate through hard or medium hard rock meaning that on the Elaine Terminal

Station Transmission Line screw piles alone would not be suitable.

Pu

Uplift Bearing

Skin Friction

Figure 2-2 - Uplift Capacity of Screw Pile

Page 42: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

42

2.4. Rock Anchors

There are 2 main types of rock bolts readily available and used in industry each with

their own advantages and disadvantages and including a variety of mechanical and

bonded rock bolts. Each rock bolt system is quite similar with a bored hole being

drilled and filled with the chosen rock bolt system. Environmental issues and

functionality are the key factors in determining which system should be adopted.

Typical applications of rock anchors include anchoring of roof or rock formations to

protect roadways or tunnels from collapse, permanent tie downs to resist overturning

and anchors to support tensioned cables.

Rock anchors are suitable in areas with hard rock preferably close to the surface and

can be installed where access conditions are poor from tracked machinery. Although

rock anchors are a form of replacement anchor their small diameter means they can

be installed with minimal spoil created. Rock anchors would have been suitable for

use on the Elaine Terminal Station Transmission Line at many of the cable stay

locations but at some locations, however no rock was encountered at depths beyond

7 m which would require expensive casings and made rock anchors alone not a

suitable anchor type.

Page 43: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

43

Rock bolt systems include:

Mechanical/ Expansive Rock Bolts

Figure 2-4 - Expansive Shell Rock Bolt

Page 44: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

44

Cement Grouted Rock Bolts

Figure 2-5 - Cement Grouted Rock Bolt

Page 45: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

45

Polyester Resin/Epoxy Grouted Rock Bolts

Figure 2-6 - Epoxy/Resin Grouted Rock Bolt

Page 46: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

46

2.5. Summary of Cable Stay Foundation Suitability

The research work presented in this thesis used the construction of the Elaine

Terminal Station Transmission Line as the case study for the development of a new

type of anchored screw pile. It can be demonstrated that at the location where Elaine

Terminal Station Transmission Line was to be constructed one foundation

methodology alone would not be suitable. This convinced the construction team to

use a new type of anchored screw pile, which provided the opportunity to conduct

the research, and testing reported in this thesis.

The suitability of the site for various types of piles has been summarised in Table 2-

1 below.

Table 2-1 Suitability of Existing Foundations

Access Ground

Water Clay / Sand Hard Rock

Dead Man Anchor Not Suitable Not Ideal Suitable Not Ideal

Bored Pile Not Suitable Not Ideal Suitable Not Ideal

Screw Pile Suitable Suitable Suitable Not Suitable

Rock Anchor Suitable Not Ideal Not Suitable Suitable

Not Suitable

Not Ideal

Suitable

The results summarised in Table 1 show that no one option would be able to provide

a solution and suitable foundation for the cable stays at the site considered as there

Page 47: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

47

was poor access at a majority of the pole locations and the geotechnical

investigations showed areas with rock at only 1 m from the surface and other areas

with only Clay to depths of up to and beyond 7 m with groundwater likely to be

present beyond 4 m.

2.6. Outline

The thesis is comprised of three sections:

The first section details the research into previous foundation systems, anchors,

piles, rock mechanics and rock bolts. The development of the Epoxy Anchored

Screw Pile came from a combination of many of these theories and existing

products.

The second section recounts the development of the installation methodology and

the testing of the Epoxy Anchored Screw Pile, including methods for calculating the

projected capacity, as well as full details of the testing. Full-scale tests were

conducted on both the screw pile and the Epoxy Anchored Screw Pile at various

depths. The results demonstrate that the Epoxy Anchored Screw Pile had sufficient

capacity to resist the loads applied and lead to a conclusion that given the limited

cost increase of the Epoxy Anchored Screw Pile it as an effective method of

foundation.

The final section concludes this masters thesis and makes recommendations for

future development and application of the Epoxy Anchored Screw Pile.

Page 48: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

48

3. Innovative Epoxy Anchored Screw Pile and

Installation Methodology

This research project is to explore the development of the innovative Epoxy

Anchored Screw Pile. The Epoxy Anchored Screw Pile allows screw piles to

become a viable stand-alone foundation solution in all ground conditions by adding

an epoxied socket where the screw pile reaches early refusal on rock without

attaining the required capacity. The installation methodology and test results show

that the Epoxy Anchored Screw Pile can be installed efficiently and provide an

increase in the required tensile capacity. The installation of the Epoxy Anchored

Screw Pile required only a small amount of additional equipment and the use of a

fast setting epoxy meant that they were ready to be loaded in just days and allowed

for the timely completion that was ideal for the transmission line for which it was

used. The addition of an epoxy socket significantly reduces the displacement at the

head of the screw pile.

The Epoxy Anchored Screw Pile comprises of a screw pile that is installed to refusal

on rock. If the screw pile does not reach the required capacity a socket was drilled

into the rock using a standard rotary hammer drill with an extension and a ReidbarTM

was bonded to the rock using an epoxy before both the ReidbarTM and the screw pile

were joined via a bolted and welded capping plate. ReidbarTM is a continuously

threaded grade 500N (500MPa) steel deformed bar.

The Epoxy Anchored Screw Pile was developed for use on The Elaine Terminal

Station Transmission Line which is a 132 kV line that runs between the Mount

Page 49: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

49

Mercer Wind Farm and the Elaine Terminal Station. It provides 131 Megawatts to

the grid which is enough energy to power the city of Ballarat located in the west side

of Victoria in Australia.

29 Stay Anchors were required for the 161 Poles on the Elaine Terminal Station

Transmission Line.

Traditionally large excavations and dead man anchors have been used to support

tension loads of this nature and scale This process is slow, expensive and the

topography of the transmission line route makes it infeasible in many of the required

locations.

Screw piles were proposed as a cost effective alternative to the dead man anchors as

they can be installed in areas of limited access and produce no spoil. But at several

locations the geotechnical investigations showed that the rock was basalt at depths

as small as 1.5 m. These site conditions meant that screw piles would not be able to

penetrate to a depth to achieve the required tensile capacity with acceptable

displacements.

At the locations where the screw pile reached early refusal (less than 3m) on rock

the Epoxy Anchored Screw Pile was installed. Of the 29 anchors, 13 reached early

refusal and an epoxy screw anchor was required. All tests conducted showed very

small displacement (<1.5mm) at the required working load.

Page 50: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

50

Rock (Basalt) Epoxy

Screw Pile

ReidbarTM and Capping Plate

Figure 3-1 - Details of Innovative Epoxy Anchored Screw Pile

Page 51: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

51

3.1. List of Material to be installed

β€’ Screw Pile – 168.3 mm Shaft Diameter with 400 mm Diameter Single Helix

β€’ Threaded Reinforcement Bar (Galvanised) – 25 mm and 32 mm Diameter

ReidbarTM

β€’ MKT Type V Epoxy

β€’ Top Capping Plate

Page 52: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

52

Figure 3-2 - Screw Pile

Page 53: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

53

Figure 3-3 - Capping Plate

Page 54: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

54

Figure 3-2 - Screw Pile Delivery

Page 55: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

55

3.2. Equipment needed for the Installation

β€’ Metabo ASR35M Dust Extractor

β€’ Metabo MHE96 SDS Max Impact Drill

β€’ Angle Grinder (To cut threaded bar)

β€’ Electrical Generator

β€’ 3 m Drill Extension

β€’ 15 mm Orange Electrical Conduit (For Vacuum Extension and to Guide

Epoxy Hose)

β€’ Cleaning Brush

β€’ Epoxy (Including Mixing Nozzle)

β€’ Clear 10 mm Extension Hose

β€’ Electrical Tape and Duct Tape

β€’ Tape Measure

β€’ Plastic

β€’ Cleaning Bucket, Water and Rags

β€’ Hose Clamp

β€’ Welding Equipment

β€’ Test Rig

β€’ Excavator

Page 56: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

56

Drill Selection for Epoxy Anchored Screw Pile

The drill selection for use in the epoxy anchored screw anchor was based on similar

parameters to those listed by Littlejohn and Brue (1977). As the required

embedment was less than 500 mm with a 40 mm diameter rotary percussive drilling

was selected as the preferred method. Tubular steel extensions were fabricated and a

standard 40 mm Hilti drill bit selected. A steel extension was heat shrunk to the drill

bit with a total length of 3 m. The use of readily available materials meant the drill

and extension could be made quickly and attached to a standard SDS max hammer

drill. Limiting the size of all equipment means that the drilling applications are

suitable when site access is very limited and with minimal training. The drilling

process requires no large plant and is a very cost effective method for socketing the

screw pile and providing an increased tensile capacity.

Figure 3-5 - Drill with extended drill bit

Page 57: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

57

Figure 3-6 - Head of drill head heat shrunk to extension

Page 58: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

58

3.3. Method

3.3.1. Test Installation

As the base of the screw pile would not be visible during the installation of the

epoxy anchor the drilling equipment was tested on some rocks at the surface. The

drill was setup using the fabricated drill extension. The drill was set to a percussive

setting and the drilling was completed using percussive drilling with no flushing

medium being used. The flights on the drill bit remove any debris from the drill hole

and allow the percussive action of the drill to break through the rock.

The debris / drill residue from the rock can be seen in the photo below (Figure 3-7).

It is also evident that the unweathered rock leaves a neat penetration. The rate at

which the drill advanced and the rate of the drill was monitored by the crew drilling

the anchors to help gauge the quality of the rock in the field. In the unweathered

basalt the drilling was quite heavy and the advancement was seen to be quite slow.

Page 59: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

59

Figure 3-7 - Drilling of test hole

Page 60: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

60

Once the drilling of the test hole was completed to 200 mm the hole was cleaned

using a dust extractor and a cleaning brush. The cleaning process was rigorous and

included repeated sequences of brushing and vacuuming any debris from the hole.

As the cleaning would be conducted at the bottom of the screw pile the cleaning

brush was revised and the brush was attached to a PVC pipe and connected to the

vacuum. The cleaning of the hole was conducted by inserting the brush and vacuum

in a rotary motion until no more debris could be seen entering the vacuum. This

process could take up to 10 minutes. Adequate cleaning of the hole removes any

debris that can interfere with the bond between the epoxy and the basalt. Meszaros

and Eligenhausen (1998) showed that insufficient cleaning of holes could lead to a

40% reduction in bond strength.

Figure 3-8 - Cleaning of test hole

Page 61: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

61

Figure 3-9 - Revised cleaning brush and vacuum

Page 62: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

62

Figure 3-10 - Cleaning brush and vacuum attachment

Page 63: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

63

Once the hole had been cleaned the epoxy and test anchor could be installed. A

standard mixing nozzle was used for the epoxy in conjunction with an extension

hose. The first injection of the epoxy was disposed as per the manufacturers

instruction prior to the extension hose being connected. It was found that beyond a

length of 1 m of extension hose, a hose clamp was required to ensure the extension

hose remained attached during the delivery of the epoxy.

Figure 3-11 - Cleaning Motion

Page 64: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

64

Figure 3-12 - Short hose extension

Figure 3-13 - Anchor installation motion

Page 65: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

65

The anchor stud must be cut at a 45-degree angle before being inserted into the wet

epoxy. The anchor is cut at 45 degrees and inserted with a slow twisting action to

evenly distribute the epoxy. This removes any piston action and the possibility of

any air bubbles forming and damaging the epoxy steel or epoxy rock bond. Once the

test anchor had been installed it was secured to ensure it did not move during the

curing process and left to cure. This was the end of the test installation and showed

that the drilling equipment was suitable to be used in the field for the installation of

the other stay anchors.

Figure 3-14 - Test anchor installed

Page 66: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

66

Figure 3-15 - Drilling of test hole

Page 67: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

67

3.3.2. Epoxy Anchor Installation Method

Step 1 – Install Screw Pile

This step was completed by SFL Piletech who are an experienced piling contractor

who operating within Australia. The screw pile was installed using an excavator

mounted rotary motor and extension arm. A Bosch DNM60L digital level was used

to install the pile at the correct angle for the cable stay. The installation of the screw

pile using a large excavator will generate sufficient force to penetrate through any

severely weathered rock but not solid rock.

In locations where screw piles were installed but reached early refusal on rock at

depths insufficient to reach the required tensile capacity the addition of a chemically

epoxied bar was socketed into the rock to help achieve the required tensile capacity.

The screw pile had an internal sleeve that acted as a guide to support the drill during

the drilling of the rock that the pile refused on. During the installation the screw pile

will also penetrate through any soft weathered rock and help to guarantee that the

rock is unweathered and a suitable material for strong bonding of the epoxy.

In total screw piles were installed at 29 locations. The final depth of the screw piles

on the project varied from 1 m to 9 m in depth with final installation torques ranging

between 24000 N-m to 45000 N-m.

Page 68: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

68

Figure 3-16 – Screw Pile after installation

Figure 3-17 – Screw Pile after installation

Figures 3-16 and 3-17 above show images of the screw pile after installation but prior to

the installation of the epoxy anchor. In areas where the anchor was not installed

immediatly the piles were covered to prevent contamination or water entering the pile and

help to givethe best possible result. Figure 3-16 shows the pile has been extended using a

bolted flange.

Page 69: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

69

Figure 3-18 - Bosch digital level used to check pile angle

Page 70: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

70

Figure 3-19 - Excavator Installing Screw Pile

Page 71: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

71

Step 2 – Site Set-Up and Initial Assessment

The drilling equipment was lightweight and only a light vehicle was required to

carry the equipment. The crew for installing the anchor included one engineer and

two workers.

Access gates for each location were marked and numbered. Once at the pole location

the equipment was unloaded and if required a crate was used to give a level surface

for the drilling team to work from.

The screw pile was examined and the depth to the bottom of screw pile was

recorded. The base of the screw pile was examined using a borescope, a steel rod

and a torch. This allowed a datum to be set up at the screw pile cut-off level and the

depth to rock was recorded. The investigation and probing also allowed us to

confirm what material the pile had refused on and the depth and properties of the

clay in the area. Field tests were done on the clay using a pocket penetrometer.

Page 72: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

72

Figure 3-20 - Timber being used to provide level ground to work from

Page 73: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

73

Figure 3-21 - Pocket penetrometer tests on clay

Page 74: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

74

Step 3 – Vacuuming, Cleaning and Drilling

Once some initial measuring and setup was conducted cleaning and drilling

commenced. Initially the drilling involves removing any soft material or clay that

was caught at the bottom of the screw pile during the installation of the screw pile

but above the rock it refused on. Generally we found there was 100-200 mm of soft

material above the layer of rock that the screw pile refused on.

Drilling was conducted using rotary percussive drilling and the type of spoil, rate of

advancement and ease of drilling was used to gauge and monitor the strata and

strength of rock that was being drilled. Any change in strata was recorded on a field

check sheet and spoil was photographed, recorded and collected.

The use of handheld drill versus a machine mounted drill meant that it was possible

to gain information about the quality of rock being drilled by accessing the

difficulty/ force required to secure the drill during drilling. In some areas the initial

drilling had much less resistance than at other locations where the difficulty of

drilling was similar to that experienced when drilling the test hole. At these

locations the depth of embedment was recorded as the depth in the harder to drill

rock. While the information gained from this may not be as reliable as an intact core

sample, all tests conducted on the anchors showed that the required bond strength

and rock strength was achieved. Any change in difficulty drilling was recorded and

the drill bit was removed to check and record if the type of rock had changed. This

assessment was made by looking at the type of spoil material on the drill flights.

Page 75: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

75

This examination gave confidence in the use of a shallow epoxy socket less than that

suggested in AS 4678 – 2002. All tests confirmed the depth was sufficient.

DCP tests were conducted in the surrounding areas of the screw pile location to

ensure that the depth of rock was consistent in the area and that the screw pile had

not refused on a floating rock. The risk of floating rocks was also overcome by

offsetting the location of the screw pile during installation.

During the drilling process it is important to remove the drill after every 100 mm

and vacuum or remove any spoil that is building up in the hole or on the flights of

the drill. Removing spoil ensures that the percussive action of the drill is breaking

the rock and increases the speed and efficiency of the drilling. The drilling and

cleaning process was continued until the required depth of rock drilled has been

achieved. Once the required depth has been achieved a final clean of the hole was

completed.

The cleaning and vacuuming process required at least 5 minutes of cleaning. As we

were unable to see inside the hole it was important to use other senses to gauge how

clean the hole was. Once finished, the brush was cleaned and reinserted like a

dipstick to ensure all loose material had been removed. If the brush was still dusty

cleaning continued.

The goal of the cleaning is to remove any loose material that may later break free

and contaminate the drill hole and destroy the bond between the rock and epoxy.

Page 76: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

76

This requires rigorous brushing and can take up to 5 minutes or until no more dust

or debris was being removed.

A borescope and torch was used to view the hole that had been drilled into the basalt

rock. A clean hole could be seen in the borescope however it was difficult to tell

when changes in the drilling rate were seen. This amplified the importance of

recording data during the drilling.

Page 77: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

77

Figure 3-22 - Borescope image showing cutting in basalt rock

Page 78: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

78

Images of drilling

Final required depth

marked on drill

Figure 3-23 - Required depth

marked on drill extension

Figure 3-24 - Drilling of anchor

Figure 3-25 - Spoil from drill flights

Page 79: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

79

Images of cleaning

Figure 3-26 - Cleaning brush

Page 80: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

80

Figure 3-27- Cleaning base using vacuum

Figure 3-28 - Cleaning base using vacuum

Torch

Page 81: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

81

Step 4 – Epoxy Application

After the Hole was cleaned the epoxy was inserted using a clear 10 mm hose

extension attached to an external orange electrical conduit for added support and to

ensure the epoxy is being delivered to the correct location. The stiff electrical

conduit ensured the epoxy was being delivered to the bottom of the bored hole

where required. Prior to inserting the conduit it was measured and marked to ensure

the epoxy was being delivered to the correct depth. The connection between the hose

and conduit at the bottom of the hose was taped and closed off to ensure no epoxy

was going up the conduit.

The quantity of epoxy required was calculated using the volume of the hole and this

was the minimum amount of epoxy that was distributed to the penetration at the

base of the screw pile. The hose was slowly withdrawn from the screw pile base

while the epoxy was being installed.

The epoxy was delivered using an electric gun, as the depth that the epoxy was

being delivered would be too difficult to attain with a hand held caulking gun. At the

full depth of 3 m the electric gun was only just able to deliver enough pressure, it

would be recommended that if a greater depth is required a pneumatic gun be used

or a larger hose. We experienced several issues with the pressure of the pump

blowing the hose off the nozzle. This was affixed by the introduction of a hose

clamp.

Page 82: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

82

Figure 3-29 – Epoxy delivery hose

Figure 3-30 – Installation of epoxy

The first three trigger pulls were discarded until the colour becomes a consistent red

and then attached the mixing nozzle to the delivery hose extension. A garbage bag

was used at each location to dispose of any waste. To maintain the natural

environment any spill of epoxy to the ground was cleaned using a shovel and

disposed of in a chemical bin.

Note: The first 3 trigger pulls of the epoxy will not be properly mixed and will not

cure. Therefore it was important to ensure no unmixed epoxy goes in the extended

delivery hose.

Once removed, the extended hose can be cleaned using a wet rag and water or

discarded.

Cleaning must be done with water only. The use of detergent can contaminate the

epoxy.

Page 83: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

83

Step 5 – Install Anchor Rod

Once the epoxy had been installed the ReidbarTM could be installed. The base of the

bar was cut at 45 degrees using an angle grinder and the bar was cleaned using a wet

rag.

The anchor stud was cut at a 45-degree angle before being inserted with a slow

twisting action to evenly distribute the epoxy. This removes any piston action and

the possibility of any air bubbles forming and damaging the epoxy steel or epoxy

rock bond.

Prior to inserting the bar it was measured and the top of pile cut-off level was

marked on the bar to ensure that full embedment in the epoxy was achieved. The

bar was inserted using a slow twisting action to reduce the risk of voids forming in

the epoxy and guarantee the best bond between the rock, steel and epoxy. Once the

rod had been inserted the top of the screw pile was covered so no debris could enter

the opening at the top.

The size of ReidbarTM varied depending on the required tensile strength and both 25

mm and 32 mm diameter ReidbarTM was used.

Page 84: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

84

Figure 3-31 – Install Anchor with slow twisting action

Figure 3-32 – Base of ReidbarTM cut at 45 degrees

Page 85: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

85

Figure 3-33 - Anchor Installed and covered to avoid contamination

Page 86: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

86

Step 10 – Welding Junction Plate

Once testing had been completed the junction plate was screwed to the ReidbarTM

and welded to the top of the screw pile. A free pin and bolt was connected to the

stay of the transmission pole that could then be tightened to engage the Epoxy

Anchored Screw Pile.

Figure 34 - Junction Plate Welded to Pile

Page 87: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

87

Figure 3-35 - Details of Junction Plate

Figure 3-35 above shows the dimension and details of the junction plate that was

used. The plate used connects the top of the screw pile with the anchor rod and

eliminate the risk of any momentous energy developing as the stay remains in

tension at all times.

Page 88: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

88

Step 11– Inspection of Epoxy Anchored Screw Piles

Six months after the connection and loading of the Epoxy Anchored Screw Pile an

on-site inspection of the cable stays was conducted to make sure that there was

tension in the cables and to ensure the capacity was sufficient. This inspection

showed that there was tension in the stays and hence it was possible to again

confirm that the anchor capacity was sufficient.

Figure 3-36 - Inspection of Anchor Stay

Figure 3-37 - Junction Plate

Page 89: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

89

3.3.3. Issues Encountered During Anchor Installation

This section details the installation at the anchors at various locations and any issues

that were encountered and how they were overcome.

Issues Encountered

Issue 1. Screw Guide Not Installed

At two locations the internal guide seen below was not installed in the screw pile.

The lack of internal guide meant that the depth of topsoil and clay above the rock

increased to 600 mm as compared to 100mm-200 mm at other locations where the

guide was installed. The lack of internal guide also made the drilling of the basalt

that the pile refused on very difficult.

To ensure that the drilling could take place without the guide the 600 mm of topsoil

and clay was removed using a petrol earth auger with a 100 mm auger. This

however left a large void and it was too difficult to secure the drill and extension to

drill the basalt. To enable drilling a steel circular hollow section (CHS) with an

internal diameter of 50 mm was driven into the last 150 mm of clay at the base of

the pile and it was cleaned using the drill extension. Once the clay had been

removed the CHS was secured and the drilling of the rock could begin. Where the

guide was not installed the drilling took significantly longer as it was difficult to

begin the drilling.

Page 90: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

90

Figure 3-38 - Screw Pile with internal guide

Page 91: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

91

Figure 3-39 - Torch used to examine screw pile with no internal guide

Page 92: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

92

CHS to guide drill

Figure 3-40 - Screw Pile without internal guide but with CHS to guide drill bit.

Figure 3-41 - Petrol Auger

Page 93: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

93

Issue 2. Changes in drill advancement and drilling through rock.

The Anchor at Pole 25 showed unique ground conditions. The drilling was a little

inconsistent, initially hard rock was encountered that was typical to the other

locations but at small intervals between 50-100mm the ease of drilling changed.

This was indicative of different layers / classes of rock which differentiated the

ground conditions for Pole 25 from those for the other poles. The advancement of

the drill and spoil on the flights was used to assess the weathering of the rock. The

spoil on the flights of the drill was very consistent, which indicated that the level of

weathering in that area was more significant than in other areas or that the drill was

passing from areas of crystalline massive rock to areas of vesicular porous material. DCP

tests were conducted in the surrounding area to ensure that the screw pile had not been

obstructed by a floating rock. The DCP refused at the same depth as the screw pile showing

that the pile had refused on a shelf of rock. Because of the inconsistencies the total

embedment depth at pole 25 was increased. It was tested and under the 75% proof

load the movement experienced was less than 0.6mm.

Issue 3. No rock encountered at base of screw pile.

Drilling at one anchor showed the screw pile did not refuse on rock. The screw-

piling contractor returned and was able to install the screw pile to a depth beyond

3m that did not require an epoxy anchor. This issue flagged that while high torque

values were being recorded the pile did not actually refuse on rock and that it was

likely an obstruction such as a tree root.

Page 94: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

94

4. Test Details of the new Epoxy Anchored

Screw Pile Tests were conducted on five of the twelve Epoxy Anchored Screw Piles that were

installed. The data was only recorded for four of the five tests. These tests were

conducted to exceed the working load at each stay location to verify the system. As

failure of a cable stay would lead to increased sag in the power line, deflection of the

pole is of extreme importance. The tests were conducted to verify the stiffness. Once

the cables were installed the pole line was inspected regularly during the

construction phase and a final visual inspection of the anchors was conducted six

months after the completion of construction.

A single 60 ton jack was used to carry out the short-term tension load test. The jack

sits above a spreader beam atop the Epoxy Anchored Screw Pile. The beam was

supported on two reaction points comprising of timbers to transfer the compression

loads on its ends. The timbers allow for the beam and jack to be positioned in the

correct angle to allow for testing of the Epoxy Anchored Screw Pile.

Tests that were conducted on the screw pile only were conducted on temporary piles

vertically and two reaction piles were used to support the spreader beam rather than

timbers.

The spreader beam was used to allow for the testing of the whole system as a jack

atop the pile would only test the epoxy bond and it was likely that failure would also

occur in the form of rock cone failure, with steel failures being very unlikely at the

required loads.

Page 95: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

95

The spreader beam selected comprised of two 360mm deep universal beams welded

together with a central hole to allow for the connection of the jack. We selected this

size beam so that under the test load there would be minimal deflection that would

render our results inaccurate.

Deflection of Spreader Beam

Figure 4-1 - Deflection of Spreader Beam

πœΉπ’Žπ’‚π’™ = 𝑷 Γ— π’πŸ‘

πŸ’πŸ–π‘¬π‘°= 𝟎.πŸŽπŸŽπŸ’ π’Žπ’Žβ€¦ … … … … … … … … … … … … … … … … … …Equation 4-1

𝑃 = 200,000 𝑁

𝑙 = 4000 π‘šπ‘š

𝐸𝑆𝑑𝑒𝑒𝑙 = 200 πΊπ‘ƒπ‘Ž

𝐼360π‘ˆπ΅57(2) = 2 Γ— 161 Γ— 106 = 322 Γ— 106 π‘šπ‘š4

The load was applied incrementally and each load was held for 5 minutes before

being increased. Once the maximum load was obtained the load was again decreased

incrementally and the displacement of the pile was recorded. If the testing procedure

was undertaken again it would be recommended that the pile was loaded a second

P

Page 96: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

96

time and the change in final settlement was recorded to better gauge the permanent

movement.

All tests were monitored and the pile head displacements and the test pressures on

the calibrated pump were recorded. The pile head displacements were measured

using dial gauges to the nearest 1/100th of a millimetre. Loads were increased

incrementally in two stages, loading to 75% of the ultimate load and unloading back

to zero in accordance to the Australian Piling Code AS2159:2009

Page 97: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

97

Details of the test rig setup can be seen in below:

Figure 4-2 - Test Rig Details

Page 98: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

98

Figure 4-3 - Test Rig Setup

Page 99: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

99

Figure 4-3 - Testing of Screw Pile

60t Jack

60t Jack and Power pack

Calibrated Gauge

Page 100: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

100

Figure 4-4 - Testing Screw Pile

Spreader Beam

Reaction Piles

Test Pile

Page 101: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

101

5. Estimation of the load capacity of the

Epoxy Anchored Screw Pile

5.1. Failure Mechanisms

The failure mechanisms can be seen in the flow chart below. While the skin friction

acting on the screw pile that encases the epoxied ReidbarTM may contribute there is

very limited movement allowed before failure in the epoxy socket will occur so that

the screw pile will not be allowed to deflect far enough to activate the skin friction.

This means that by the time the epoxy anchor fails the screw pile will likely not

contribute significantly to the total capacity of the system but will in fact act

independently and merely provide corrosion resistance to the ReidbarTM.

Flowchart of failure mechanisms

Epoxy Slip Failure Steel Bar Failure Rock Cone Failure

Screw Pile Failure

Page 102: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

102

5.2. Screw Pile

Screw Pile capacity calculations were conducted by SFL Piletech in accordance to

AS2159-1978 and calculated by accessing the failure of a cylinder of soil above the

single bottom helix.

The following equations were used to calculate the capacity prior to the onsite

testing.

πœ™π‘…π‘’π‘” = πœ™(πœ‹ Γ— 𝑑 Γ— 𝑙 Γ— 𝛼𝐢𝑒)………………………………………………Equation

5-1

𝑅𝑒𝑔 = Ultimate Geotechnical Uplift Capacity

πœ™ = Reduction Factor

𝑙 = Embedment depth to helix (Top 0.5m ignored)

𝑑 = Diameter of Helix

𝐢𝑒 = Undrained cohesion of soil

𝛼 = Adhesion factor for piles in clay (varies with clay stiffness as per AS2159-

1978)

Based on the geotechnical investigations conducted onsite showing very stiff clay

with the undrained cohesion of the soil of 50 kPa and as per AS2159-1978 a 𝛼 of 0.9

was used.

The helix diameter of all piles was 400mm and a πœ™ = 0.6 was adopted.

Based on these values the below table shows the capacity the screw pile achieved at

varying depths.

Page 103: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

103

Calculations for screw pile capacity can be seen in the table below, based on the

values shown.

πœ™π‘…π‘’π‘” = πœ™(πœ‹ Γ— 𝑑 Γ— 𝑙 Γ— 𝛼𝐢𝑒)………………………………………………Equation

5-2

πœ™ = Reduction Factor = 0.6

𝑙 = Embedment depth to helix (Top 0.5m ignored) = Depth

𝑑 = Diameter of Helix = 400mm

𝐢𝑒 = Undrained cohesion of soil = 50kPa

𝛼 = Adhesion factor for piles in clay = 0.9

Figure 5-1 - Calculated Screw Pile Capacity

0

50

100

150

200

250

0 1 2 3 4 5 6 7

Capa

city

(kN

)

Depth (m)

Calculated Screw Pile Capacity

Capacity

Page 104: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

104

5.3. Epoxy Anchor Failure

5.3.1. Slip Failure

Slip failure of the epoxy is likely to occur at the rock / epoxy interface prior to the

steel / epoxy interface, although in concrete the epoxy can give bond strengths of up

to 25 MPa. Bond strengths for the epoxy / rock interface have come from the

recommendations given by Littlejohn and Bruce (1977) in conjunction with

engineering rock properties given by Gu et al. (2008).

Littlejohn and Bruce give ultimate bond strengths in basalt between 5.73 to 6.37

MPa recommending a factor of safety between 1.5 and 4 depending on rock quality.

These values are quite conservative to account for the unknown factors that are

present when drilling into rock. Studies done by A Kilic et al. (2002) showed bend

strength with cementitious grouts and basalt with mean bond strengths of 7.73 MPa.

Page 105: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

105

Table 5-1 – Engineering Properties of basalt (Gu et al. (2008))

Rock Type

Weathering

Grade Moisture Content (%) qu (Mpa) n (E/qu) E (Mpa)

Basalt

EW-HW >11 4 100 400

HW 9 - 11 10 120 1250

HW-MW 7 - 9 25 160 4000

MW 5 - 7 50 200 10000

MW-SW 3 - 5 90 250 22500

SW 1 - 3 150 300 45000

SW-FR <1 250 400 100000

Page 106: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

106

Boreholes from the installation of the electrical poles exposed rock samples that

allowed for assessment of the basalt at each location to be evaluated. Samples that

were still intact from coring showed at the depths the screw pile was refusing the

level of weathering was quite low and the UCS of the basalt was greater than 100

MPa.

The ultimate bond strength of the epoxy anchor can be calculated with the following

equation. Values for the Ultimate bond strength given by Littlejohn and Bruce

(1977) have been used to give a projected capacity of the epoxy.

𝑷 = 𝝅×𝒅×𝒍×π‘ͺπ’Œ

……………………………..……………………..……Equation 5-3

𝑃 = Capacity

𝑑 = Diameter

𝑙 = Length

𝐢 = Bond Strength

π‘˜ = Factor of Safety

Page 107: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

107

Figure 5-2 – Projected Epoxy Bond Strength

**Bond strengths used are 1.43 and 4.24MPa, values from this table should be used as a guideline and should be verified with field investigations with

acceptable deflection limits.

The anchors were tested to the working load or 75% or the ultimate load and results

from these tests showed displacements less than 1.5mm in all locations.

0

100

200

300

400

500

600

0 0.2 0.4 0.6 0.8 1

Capa

city

(kN

)

Epoxy Embedment Depth

Projected Epoxy Bond Strength - 40mm Diameter

Minimum Projected BondStrength

Maximum Projected BondStrength

Page 108: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

108

Figure 5-3 - Rock sample from drilling poles

Figure 5-4 - Rock sample from drilling poles

Page 109: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

109

5.3.2. Cone Failure

As the field investigations showed good to very good rock cone failure will take

place at one of two locations depending on the level of weathering and degree of

fissure in the rock mass. For a rock mass that is soft, weathered and heavily fissured

the failure cone will be at 60 degrees and occur at the midway point of the bond and

for other rock with limited weathering or fissures failure will occur at the base of the

anchor at an angle of 90 degrees.

Figure 5-5 – Cone failure location for good rock

Figure 5-6 - Cone failure location for poor rock

Page 110: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

110

The capacity of the rock cone in good to very good rock can be calculated using the

tensile strength of the rock mass and the area of the failure cone using the following

equation which ignores the mass of the rock.

Figure 5-5 - Cone Failure

𝑸 = πˆπ’•π’ŽΓ—π…Γ—π‘³πŸ

π’„π’π’”πŸπœ½Γ—π‘­π‘Ίβ€¦β€¦β€¦β€¦β€¦β€¦β€¦β€¦β€¦β€¦β€¦β€¦β€¦β€¦.………………………Equation 5-4

𝑄 = Capacity

𝐿 = Cone Length

πœŽπ‘‘π‘š = Tensile Strength of rock mass

πœƒ = Angle of Failure

𝐹𝑆 = Factor of Safety

Page 111: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

111

Tugrul and Gurpinar (1997) conducted testing on basalt at different levels of

weathering and gave the following Table 5 -2 gives mean UCS and tensile strengths

of basalt tested. The results from these tests can be seen in Table 5 -2 below.

Table 5-2 – UCS and Tensile Strengths of basalt

Οƒ Ultimate Compressive Strength (MPa)

Οƒ Tensile Strength (MPa)

E Young’s Modulus (MPa)

Weathering Grade Weathering Level Min. Max. Mean Min. Max. Mean Min. Max. Mean C-I Fresh Rock 105.26 136.42 120.1 8 10 8.99 44000 57700 50127

C-IIC Moderately Weathered 30 54.95 43.03 3 5 3.86 14000 26100 20073

C-IIIB Extremely Weathered 10 23.58 15.2 0.77 2.31 1.76 10500 19000 15093

B-I Fresh Rock 86.32 120 100.15 7.69 9.23 8.49 46000 81650 66101 B-IIA Faintly Weathered 60 107.79 86.03 6.43 8.15 7.42 32000 56800 48073

B-IIC Moderately Weathered 27.37 52.63 37.71 3.11 4.77 4.01 20000 36000 28039

B-IIIA Highly Weathered 21.05 36.21 28 2 3.69 2.78 6000 21700 10800

B-IIIB Extremely Weathered 4.21 16.84 7.9 - - - - - -

A-I Fresh Rock 88.42 129.05 106.19 8.08 9.54 8.79 44000 71000 56114 A-IIB Slightly Weathered 44.21 70 58.12 5 7.08 6.13 24650 42600 36506 A-IIIA Highly Weathered 15.37 31.37 22.5 2.23 4 3.13 10000 21950 15000

A-IIIB Extremely Weathered 3.69 16.26 6.9 - - - 5065 15600 8120

Page 112: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

112

Using the equation 5- 3 from above for the capacity of the rock cone and

conservatively using the tensile strength of highly weathered basalt and a 30 degree

cone at the midpoint to be conservative the uplift resistance of the cone will be:

𝑸 = πˆπ’•π’ŽΓ—π…Γ—π‘³πŸ

π’„π’π’”πŸπœ½Γ—π‘­π‘Ί= 𝟐.πŸ•πŸ–Γ—π…Γ—πŸπŸŽπŸŽπŸ

π’„π’π’”πŸπŸ‘πŸŽΓ—πŸ= 232 kN…………………………….…………Equation 5-5

𝑄 = Capacity

𝐿 = 200 mm

πœŽπ‘‘π‘š = 2.78 MPa

πœƒ = 30

𝐹𝑆 = 2

Using the input shown above and Equation 5 -4 with a factor of safety of 2 and conservative rock

strength values it would be expected that rock cone failure would occur at 232kN.

Page 113: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

113

5.3.3. Steel Failure

Steel Bar Failure Based on Calculations

The steel used within the anchor was Grade 500 N ReidbarTM, which has the

following properties.

Table 5-3 – Properties of ReidbarTM

Bar

Diameter

Min Yield

Stress (MPa)

Ultimate

Yield Stress

(MPa)

Minimum Shear

(.62 min ult)

(MPa)

Mass

(kg/m)

Nom

Area

25mm 245.5 265.1 164.4 3.95 491

32mm 402 434.4 269.2 6.47 804

The elongation of the ReidbarTM can be calculated using Hooke’s Law as the steel is

still in the elastic region. Using the equation:

𝜹 = 𝑷𝑳𝑨𝑬

mm…………………………………….……………………………………Equation 5-6

𝛿 = Deflection / Elongation of Steel (mm)

𝑃 = Force (N)

𝐿 = Free Length (mm)

𝐴 = Cross Sectional Area (mm2)

𝐸 = Young’s Modulus

The ultimate strength of the ReidbarTM is greater than the strength of the rock mass where cone

failure occurs. Due to possible bonding at the base of the pile it is difficult to predict the elongation of

the ReidbarTM and Screw Pile.

Page 114: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

114

Summary

Using the tables and formulas from section 5.3 the projected capacity can be

calculated. Section 5.3 shows that failure is likely to occur through either slip failure

at the epoxy rock interface or rock cone failure depending on the level of weathering

of the basalt and the calculated results give an ultimate tensile capacity upwards of

200 kN.

The ultimate bearing strength of the pile should not be greater that the tensile

strength as it may damage the bonded epoxy socket.

These conditions were qualified and tested by examining rock samples from the

drilling and spoil from the poles at the guy locations, recording the difficulty drilling

and the rate of advancement of the drill and examining the bored hole using a

borescope. The conclusion in the quality of the rock was verified by testing the

displacement at the head of the screw pile. The results show that the bond of the

epoxy and the rock strength are sufficient and the displacement at the pile head was

reduced by a factor of 10.

Page 115: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

115

6. Test Results

6.1. Screw Pile Only

Load displacement curves can be seen for screw piles that were tested at depth

varying from 1.8 m to 3.7 m. The screw piles had the same shaft diameter of 168.3

mm with a single 400 mm diameter helix at the base of the pile.

Load test 1 was conducted on a helical screw pile installed to a depth of 1.8 m in

stiff clay before refusal on rock. The test showed limited displacement below 75 kN

increasing to a maximum of just over 35 mm at 240 kN with almost no recovery

once the load was released.

Load test 2 was conducted on a helical screw pile installed to a depth of 2.8 m

before refusal on rock. The test showed displacement of 2 mm at 80 kN but

increased to 4-5 mm at 103 kN. Once the load was released a permanent

displacement of 4 mm was not recovered. The pile was again loaded to 206 kN and

over 22 mm of displacement was recorded with a permanent displacement of 20

mm.

Load test 3 was conducted on a helical screw pile installed to a depth of 3.7 m. The

test showed limited displacement less than 2 mm up to 90 kN, once loaded to 96 kN

4 mm of displacement was experienced with a permanent displacement of 3mm. The

pile was again loaded to 125 kN where a 16 mm displacement was seen. Once the

load was released a permanent displacement of 15 mm was seen.

Page 116: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

116

0

25

50

75

100

125

150

175

200

225

250

0 5 10 15 20 25 30 35 40

Load

(kN

)

Displacement (mm)

Load Test 1 - 1.8m Screw Pile

Figure 6-1 - Load Test 1

Page 117: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

117

0

10

20

30

40

50

60

70

80

90

100

110

120

130

140

150

160

170

180

190

200

210

220

0 3 5 8 10 13 15 18 20 23 25

Load

(kN

)

Displacement (mm)

Load Test 2 - 2.8m Screw Pile

Figure 6-2 - Load Test 2

Page 118: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

118

0

10

20

30

40

50

60

70

80

90

100

110

120

130

140

0 2 4 6 8 10 12 14 16 18

Load

(kN

)

Displacement (mm)

Load Test 3 - 3.7m Screw Pile

Figure 6-3 - Load Test 3

Page 119: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

119

6.2. Epoxy Anchored Screw Pile

Load displacement curves can be seen for screw piles with the epoxied socket. The

depth into basalt varied at each location, as did the depth of screw pile. All screw

piles has a shaft diameter of 168.3 mm with a helix diameter of 400 mm at the base

of the pile. At all recorded test locations a 25 mm ReidbarTM was installed. An

additional test was conducted at Pole 147 where a 32 mm ReidbarTM was installed.

This test was successful but unfortunately no data was recorded. The pull out tests

conducted on the epoxy screw anchor showed acceptable levels of displacement

under the required working load on the pile.

The Epoxy Anchored Screw Pile was tested within the serviceability displacement

limits of AS2159-2009 with all tests being conducted to 75% of the ultimate load

using the equation

πœΉπ’‚π’π’π’π’˜π’‚π’ƒπ’π’† = 𝑷𝑳𝑨𝑬

+ 𝟎.πŸŽπŸπ’… mm……………………………………………………….Equation 6-1

π›Ώπ‘Žπ‘™π‘™π‘œπ‘€π‘Žπ‘π‘™π‘’ = Head Displacement (mm)

𝑃 = Force (N)

𝐿 = Free Length (mm)

𝐴 = Cross Sectional Area (mm2)

𝐸 = Young’s Modulus

Page 120: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

120

Table 6-1 – Summary of Epoxy Anchored Screw Pile Results

Test Number (Location) Screw Pile

Depth (m)

Depth of

Epoxy

Socket

(mm)

Test Load

(kN)

Maximum

Displacement (mm)

Allowable

Displacement (mm)

Load Test 4 (Pole 7) 1.8 450 71 1.1 1.85

Load Test 5 (Pole 25) 1.1 500 75 0.55 1.4

Load Test 6 (Pole 54) 1.5 500 112.5 0.85 2.43

Load Test 7 (Pole 46) 1.8 600 120 0.24 2.77

Load Test 8 (Pole 147) 1.5 850 126.75 **Not Recorded **Not Recorded

Page 121: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

121

Static Load Test 4 and 5

0

10

20

30

40

50

60

70

80

0.00 0.20 0.40 0.60 0.80 1.00 1.20

Load

(kN

)

Displacement (mm)

Static Load Test 4

Figure 6-4 - Static Load Test 4

Page 122: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

122

0

10

20

30

40

50

60

70

80

0.00 0.10 0.20 0.30 0.40 0.50 0.60

Load

(kN

)

Displacement (mm)

Static Load Test 5

Figure 6-5 - Static Load Test 5

Page 123: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

123

Static load tests 4 and 5 shows some initial displacement that appears to be the

taking up of slack within the system. Once the initial movement occurred when

loaded beyond this point at the same rate the displacement seen was less than 0.1 –

0.2 mm. When unloaded the permanent displacement was between 0.35 and 0.7 mm

showing a recovery from the maximum displacement of 0.2 mm to 0.3 mm in each

case. In both case the displacement and permanent displacement was very small and

within the acceptable serviceability displacement limits of AS2159-2009.

Page 124: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

124

Static Load Test 6 and 7

0

10

20

30

40

50

60

70

80

90

100

110

120

0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90

Load

(kN

)

Displacement (mm)

Static Load Test 6

Figure 6-6 - Static Load Test 6

Page 125: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

125

0

10

20

30

40

50

60

70

80

90

100

110

120

130

0.00 0.05 0.10 0.15 0.20 0.25 0.30

Load

(kN

)

Displacement (mm)

Static Load Test 7

Figure 6-7 - Static Load Test 7

Page 126: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

126

The results from load test 6 and 7 varied a little when compared to tests 4 and 5. In

tests 6 and 7 when the load was applied it did not appear that there was any slack in

the system and both sets of results yielded very small temporary and permanent

displacements. A gauge calibrated to record measurements in the order of 1/100 of a

millimeter was used and it can be concluded that at the working load all tests

showed acceptable amount of movement. The small displacements when compared

to the results from the screw piles without the epoxy socket showed that the epoxy /

rock bond was still intact and that rock cone failure had not occurred.

Page 127: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

127

0

50

100

150

200

250

0 2 4 6 8 10 12 14 16 18 20 22 24

Load

(kN

)

Displacement (mm)

Load vs Displacement - Screw Pile vs Epoxy Anchored Screw Pile

Plot 4

Plot 5

Plot 6

Plot 7

Plot 1 Screw Pile Only

Plot 3 Screw Pile Only

Figure 6-8 - Combined load test results

Page 128: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

128

Figure 6-9 - Combined load test results

0

25

50

75

100

125

150

0 2 4 6 8 10

Load

(kN

)

Displacement (mm)

Load vs Displacement - Screw Pile vs Epoxy Anchored Screw Pile

Plot 4 Plot 5 Plot 6

Plot 7 Plot 1 Screw Pile Only Plot 3 Screw Pile Only

Page 129: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

129

The previous two charts show results from load displacement tests on the screw pile

and also the Epoxy Anchored Screw Pile. The results show that the displacements

experienced by the screw pile versus the Epoxy Anchored Screw Pile are

significantly larger at similar loads. If failure were to occur in the Epoxy Anchored

Screw Pile in either the form of rock / epoxy failure or rock cone failure it would be

expected that the displacement would be similar to that of the screw pile alone. As

this is not the case it can be concluded that this failure has not occurred and that the

basalt is not fissured and the level of weathering allows the epoxy bond to achieve

the required capacity.

Page 130: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

130

7. Conclusions

The Epoxy Anchored Screw Pile can be used to provide additional capacity and

reduce the displacement of the screw piles that refuse on rock. The installation

method showed it is not always necessary to spend expensive resources drilling,

cutting or excavating large areas of rock to provide the required tensile capacity

within acceptable displacement limits in areas where rock with limited weathering

or fissures are present. The use of the Epoxy Anchored Screw Pile produces limited

to no spoil and allows screw piles to be a viable option in all conditions with only

the addition of some minor equipment. The use of tracked machinery to install the

screw pile makes the Epoxy Anchored Screw Pile suitable even in areas with poor

access without the need to build expensive access roads and removing the need for

heavy tired vehicles such a concrete agitators.

The use of a hand held rotary percussive drill was inexpensive, quickly implemented

and allowed for rapid installation of the epoxy socket. As shown by Spieth and

Eligehausen (2002) rotary percussive drilling gives a rough cut on the drilled hole

and increases the possible bond strength at the epoxy / rock interface. The hand held

drilling meant that it was possible to gauge the quality of the rock that the pile

refused on through monitoring the speed and difficulty in advancement. In addition

to this a soil report, DCP tests and an assessment of the spoil from the pole

installation gave confidence in the bond that would be achieved by the epoxy. This

was confirmed by the testing of the Epoxy Anchored Screw Pile. Installation of the

Page 131: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

131

Epoxy Anchored Screw Pile was quick and the use of a fast setting epoxy allowed

for the system to be loaded after only 24 hours including testing.

The testing of the Epoxy Anchored Screw Pile was conducted at a rate of two to

three tests per day and all tests conducted showed acceptable amounts of

displacement up to 20 times less than the screw pile alone. However, if the tests had

failed due to the underlying rock being highly fissured or weathered it may have

been difficult to install a replacement anchor using the same methodology. While all

tests concluded that in the given situation the epoxy socket was sufficient, if the

process was implemented again it would be recommended that a non-situation

Epoxy Anchored Screw Pile is tested to failure. The values used to calculate the

capacity in the results section have used conservative bond strength values and Cook

et al. (1994) have shown that the epoxy concrete bond strength can be greater than

20 MPa and the Young’s Modulus of both concrete and basalt are very similar. The

low displacements also make the Epoxy Anchored Screw Pile suitable in areas

where long term displacement under sustained load needs to be controlled and could

be used for socketing screw piles in areas of expansive soils.

Failure of the Epoxy Anchored Screw Pile would most likely be either epoxy / rock

bond failure or rock cone failure both of which are non-elastic.

The Epoxy Anchored Screw Pile provided an innovative solution for the foundations

of the cable stays on the Elaine Terminal Station Transmission Line. The installation

was quick and cost effective as it reduced the need for expensive access roads to be

constructed and the additional equipment required was procured using items that are

readily available. The short curing time means that stringing of the cables can be

conducted prior to that of concrete dead man anchor. Though not suitable in all

Page 132: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

132

locations where appropriate the Epoxy Anchored Screw Pile makes screw piles a

valid foundation solution in a range of ground conditions where conventional screw

piles alone would not be suitable.

Page 133: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

133

8. Recommendations

To improve the system in the future de-bonding the ReidbarTM and the screw pile

through the use of a bolted top pile instead of a welded top plate and allowing the

screw pile to move independently would allow for part of the load to be resisted by

the screw pile and reduce the load on the epoxied socket. The testing done by Reese

and O’Neil (1988) and also the testing conducted on the screw pile with the epoxy

socket showed that with only 5 mm of movement the screw pile could resist up to 75

kN and reduce the load on the epoxy socket and create better synergy between the

screw pile and epoxy socket.

It would be recommended that if future applications are adopted significant

geotechnical investigations be undertaken prior to adopting the Epoxy Anchored

Screw Pile and that prior to commitment to a full installation program a test

installation is conducted. Current bond strengths given for rock anchors are very

conservative and the development of a site-specific testing regime of the Epoxy

Anchored Screw Pile would be required. Further testing of the Epoxy Anchored

Screw Pile to failure would be very useful and help for the future development of

this application. Adapting the system to induce failure in the steel and not the

chemical bond or rock cone would allow for ductile failure of the system and can be

achieved by increasing the embedment depth and testing as required.

Page 134: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

134

9. References

Aldorf, J and Exner, R. 1986. Mine Openings: Stability and Support. Elsevier

Science Publishers. Amsterdam, The Netherlands.

Benmokrane, B, Chennouf, A and Mitri, H. 1995. β€œLaboratory Evaluation of

Cement-Based Grouts and Grouted Rock Anchors”. Int. J. Rock Mech. Min. Sci.

and Geomech. Abstr. Vol. 32, NO. 7, pp. 633-642.

Balmer, G., 1952. A general analytical solution for Mohr’s envelope. Am. Soc.

Test. Mat. 52, 1260-1271.

Bieniawski, Z.T. 1976. Rock mass classification in rock engineering. In

Proceeding of the Symposium on Exploration of Rock Engineering (ed. Z.T.

Bieniawski), 1, 97-106. Cape Town, Balkema.

Cook, R. Bishop, M. Hagedorn, H. Sikes, D. Richardson, D. Adams, T. De Zee, D.

1994. Adhesive Bonded Anchors: Bond Properties and Effects of In Service and

Installation Conditions. Report No.94-2A, University of Florida, Department of

Civil Engineering, College of Civil Engineering, Gainsville

Eligehausen, R, MallΓ©e, R and Silva, J. 2006. Anchorage in Concrete

Construction. Ernst & Sohn Verlag fΓΌr Architektur und technische

Wissenschaften GmbH & Co. KG. Berlin, Germany

Gu, D. X. Tamblyn, W. Lamb, I and Ramsey, N. 2008. Effect of Weathering on

Strength and Modulus of Basalt and Siltstone. American Rock Mechanics

Association. The 42nd U.S. Rock Mechanics Symposium (USRMS), 29 June-2

July, San Francisco, California

Page 135: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

135

Hoek, E. and Brown, E.T. 1988. The Hoek-Brown failure criterion - a 1988

update. In Rock engineering for underground excavations, proc. 15th Canadian

rock mech. symp., (ed. J.C. Curran), 31-38. Toronto: Dept. Civ. Engineering,

University of Toronto.

Hoek E. 2007. β€œA brief history of the development of the Hoek-Brown failure

criterion ”. Brazilian Journal of Soil and Rocks, No. 2, November 2007, Sao

Paulo, Brazil

Kilic, A, Yasar, E, and Celik A. (2002). Effects of grout properties on the pull-out

load capacity of fully grouted rock bolt. Elsevier Science Publishers. Tunneling

and Underground Space Technology. Vol. 17, No. 4, pp. 355-362.

Labuz, J and Zang, A 2012. Mohr-Coulomb Failure Criterion. Rock Mechanics

and Rock Engineering, 45, pp.975-979.

Littlejohn, S . Bruce, B. 1977. Rock Anchors – State of the Art. Foundation

Publications. Brentwood, Essex

Meszaros, J. Eligehausen, R. 1998: Einfluss der Bohrlochreinigung und von

feuchtem Beton auf das Tragvehalten von Injektions- dubeln (Influence of hole

cleaning and of humid concrete on the load-bearing behaviour of injection

anchors), Report No. 98/2- 2/2, Institut fur Werkstoffe im Bauwesen.

Universitat Stuttgart

Poulos, H and Davis, E. 1980. Pile Foundation Analysis and Design. New York :

Wiley.

Ronald A. Cook, Jacob Kunz, Werner Fuchs, and Robert C. Konz. 1998. Behavior

and Design of Single Adhesive Anchors under Tensile Load in Uncracked

Concrete. Structural Journal. 1 (95), 9-26.

Page 136: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

136

Reese, L. C. and O’Neill, M.W. 1989 β€œNew Design Method for Drilled Shafts from

Common Soil and Rock Tests. Proceedings, Foundation Engineering: Current

Principles and Practices, American Society of Civil Engineers, Vol. 2, pp.1026-

1039

Saliman, R. & Schaefer, R. 1968. "Anchored footings for transmission towers",

ASCE Annual Meeting and National Meeting on Structural Engineering,

Pittsburgh, PA, Sept. 3-Oct. 4, Preprint 753, pp. 15-38

Schroeder, W.L. and D.N. Swanston. 1992. Installation and Use of Epoxy-

Grouted Rock Anchors for Skyline Logging in - Southeast Alaska. Portland,

Oregon 97208: United States Department of Agriculture.

Serafim, J.L. and Pereira, J.P. 1983. Consideration of the Geomechanics

Classification of Bieniawski. Proc. Intnl. Symp. Engng. Geol. And Underground

Construction, Lisbon, Portugal, 1133-44.

Spieth, H.A., Eligehausen, R. 2002 : Bewehrungsnschlusse mit nachtraglich

eingemortelten bewehrungstaben (Starter bars with post installed rebars),

Beton und Stahlebetonbau 97, No. 9, pp. 445-459, Berlin,

Standards Australia, (2002), β€œEarth – retaining structures”, Australian

Standards AS 4678

Standards Australia, (2009), β€œPiling - Design and Installation”, Australian

Standards AS 2159

Standards Australia, (2010), β€œOverhead Line Design – Detailed procedures”,

Australian Standards AS 7000

Tomlinson, M and Woodward, J. 2008. Pile Design and Construction Practice.

Taylor and Francis. London and New York

Page 137: Development, installation and testing of an innovative ......Development, Installation and Testing of an innovative Epoxy Anchored Screw Pile 1.1. Preface The first section of this

137

Tugrul, A., GΓΌrpinar, O. 1997. The effect of chemical weathering on the

engineering properties of eocene basalts in Northeastern

Turkey. Environmental and Engineering Geoscience, 3 (2), pp. 225-234.

Wyllie, Duncan. 1992. Foundations on Rock. E and FN Spon. Melbourne,

Australia